RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 42 of 61
- SAI PRASAD3.4 yr overdueUNITY CONSTRUCTIONS · ERANDWANA, PuneP52100026161· 59.1% built
- THE SPRINGS3.4 yr overdueSMS STAR DEVELOPERS LLP ·P99000005347· filed Sept 2019 → now Jun 2023· 81.3% built
- SHRI MARYAMBI VANSH PARK3.4 yr overdueNARENDRA NAMDEO DHADVE · Shringartali, RatnagiriP52800013301· filed Dec 2019 → now Jun 2023· 35.5% built
- Rosalia Apartments3.4 yr overdueKusum Associates · Andheri, Mumbai SuburbanP51800005568· filed Jul 2020 → now Jun 2023· 72.7% built· 5 complaints
- MADHULATA RESIDENCY3.4 yr overdueMANISH MADHUSUDAN AGRAWAL · Near old bus stand, YavatmalP51000011182· 29.7% built
- PALAVA ESTELA H, I, J3.4 yr overduePalava Dwellers Private Limited · Palava, ThaneP51700013145· 81.8% built
- MARVEL TANISHQ3.4 yr overdueMARVEL PROPERTIES · Nashik, NashikP51600012755· 19.5% built
- SHREE VASTUPURAM3.4 yr overdueShivdatta Associates · Varnali, Vishrambag, SangliP53100021231· 69.1% built
- Goodwill Unique Zest County Phase 23.4 yr overdueZENITH BUILDCON · Lohegaon, PuneP52100023942· 90.9% built
- VYANKTESH HEIGHTS3.4 yr overdueReliable Construction · VYANKATESH COLONY, SataraP52700026443· 73.2% built
- PADMAVATI DARSHAN BUILDING NO 23.4 yr overduePADMAVATI CONSTRUCTION · NANDIMAL NAKA, RaigarhP52000026108· 18.2% built
- Ananta3.4 yr overdueNDG Projects LLP · Right Bhusari Colony, PuneP52100031934· filed Dec 2022 → now Jun 2023· 72.7% built
- YASHODA AANGAN3.4 yr overdueKONARK ASSOCIATES · Thergaon, PuneP52100006664· filed Dec 2019 → now Jun 2023· 76.6% built· 1 complaint
- HAVA MAHAL CHS LTD3.4 yr overdueH RISHABRAJ PROJECTS · MALAD EAST MUMBAI, Mumbai SuburbanP51800027606· 90.9% built
- JACOB SKYLINE APARTMENT3.4 yr overdueJACOB DANIEL CHARUVILA · BH EXPRESS INN HOTEL, NashikP51600025583· 90.9% built
- DELTA CENTRAL3.4 yr overdueBALAJI CORPORATION · Panvel, RaigarhP51800001613· 97.3% built· 2 complaints
- Maxima3.4 yr overdueOberoi Constructions Limited · Andheri, Mumbai SuburbanP51800017154· 99.6% built· 1 complaint
- ROONGTA BELLAVISTA APARTMENT3.4 yr overdueROONGTA HOMES LLP · GOVIND NAGAR, NashikP51600019713· 81.8% built
- OM SAI HEIGHTS II3.4 yr overdueCREATIVE ENTERPRISES · Palghar, PalgharP99000012565· filed Dec 2022 → now Jun 2023· 90.7% built
- STAR GLORIOUS3.4 yr overdueSTARLITE CONSTRUCTIONS · Vasai-Virar City (M Corp), PalgharP99000008579· filed Dec 2019 → now Jun 2023· 90% built
- Tulas3.4 yr overdueRajesh Raka · WANJOLA ROAD, JalgaonP49900026363· 81.8% built
- PARAG COMPLEX PHASE 13.4 yr overdueMALOO CONSTRUCTION · NEAR SANT GADGE BABA AMRAVATI UNIVERSITY, AmravatiP50300023712· 9.1% built
- GIRIRAJ DARSHAN3.4 yr overdueKISHORE S. DUBE · Palghar, PalgharP99000009715· filed Mar 2019 → now Jun 2023· 81.8% built
- AMAR ORNATE-II3.4 yr overdueMALOJI AND SONS · HADAPSAR, PuneP52100027186· 81.8% built
- Varun Flora Township - Lotus Bldg3.4 yr overdueVertex Developers · Ujalaiwadi, KolhapurP53000025421· 79.5% built
- Laxmi Krupa CHS Ltd.3.4 yr overdueM/s. Shreepad Developers · Borivali, Mumbai SuburbanP51800011532· filed Dec 2019 → now Jun 2023· 68.2% built· 2 complaints
- PALAVA MARVELLA B,C,D,E,F,G3.4 yr overduePalava Dwellers Private Limited · ., ThaneP51700013462· 76.7% built· 4 complaints
- Rajal - Veer Abhimanyu CHS Ltd3.4 yr overdueNisar Properties Private Limited · Borivali West, Mumbai SuburbanP51800006097· 90.9% built· 2 complaints
- YASHRAJ PRADAKSHINA3.4 yr overdueRAJENDRA MURLIDHAR GODBOLE · Haveli, PuneP52100000633· filed Jan 2021 → now Jun 2023· 90.9% built
- RGS ANANTYA3.4 yr overdueSINGH HOLDING PVT LTD · CHEMBUR, Mumbai SuburbanP51800032255· 90.9% built
- NAKSHATRA3.4 yr overduePADMAVATI LANDMARKS · Pune City, PuneP52100030557· 9.1% built
- DARSHAN3.4 yr overdueArkade Developers Private Limited · VILE PARLE EAST, Mumbai SuburbanP51800027271· 67% built
- Kalpataru Phase-43.4 yr overdueAshoka Infraways Limited · Near Indian Oil Petrol Pump, Chunchale Shiwar, NashikP51600028206· 9.1% built
- JEEVAN ANAND3.4 yr overdueSUYOG DEVELOPERS · Kurla, Mumbai SuburbanP51800007491· filed Jun 2021 → now Jun 2023· 90.9% built
- KAKADE- SANJEEVANI3.4 yr overdueBMK PROPERTIES PRIVATE LIMITED · NEAR BALADOR, PuneP52100028898· 70.5% built· 3 complaints
- Konark Virtue3.4 yr overdueKonark Builders · kESHAVNAGAR, PuneP52100001587· filed Dec 2022 → now Jun 2023· 78.5% built· 4 complaints
- UNIMONT EMPIRE3.4 yr overdueRSM ENTERPRISES · Khalapur, RaigarhP52000002714· 87.6% built
- Laxmi Plaza3.4 yr overdueR. M. Realtor · Dabhole Bk., RatnagiriP52800010111· 90.9% built
- SAMRAJYA3.4 yr overdueGARVE PATIL CONSTRUCTION COMPANY · Haveli, PuneP52100014056· filed Dec 2019 → now Jun 2023· 60% built· 1 complaint
- MARATHON NEXTOWN CORAL3.4 yr overdueMARATHON ENER-GEN LLP · Thane, ThaneP51700000952· filed Dec 2021 → now Jun 2023· 72.7% built· 3 complaints
- JUHU ACROPOLIS3.4 yr overdueBHARAT REALTY VENTURE PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800017864· 90.9% built
- 24 SILVER SPRING3.4 yr overdueMARUTI BUILDCON · Talegaon Dabhade (M Cl), PuneP52100009224· 27.3% built
- Grace Iconic Wing A-B3.4 yr overdueGrace Property Development Ventures · Andheri, Mumbai SuburbanP51800007207· filed Oct 2019 → now Jun 2023· 38.9% built
- EKA PHASE III - F BUILDING3.4 yr overdueAmit Builders · Pathardi, NashikP51600008507· filed Dec 2019 → now Jun 2023· 90.9% built· 3 complaints
- SAI VIDHATA3.4 yr overdueSAI SHRADDHA ASSOCIATES · Ulhasnagar, ThaneP51700030832· 81.8% built
- SWAMI HIGHT3.4 yr overdueBASAVESHWAR MAHALINGAYYA SWAMI · EAST SIDE OF NEW COURT BUILDING, SangliP53100022143· 81.8% built
- OMKAR COMPLEX - PHASE 13.4 yr overdueShree Omkar developers · SHRIRAM GOGATE HIGH SCHOOL, SindhudurgP52900018151· filed Jun 2021 → now Jun 2023· 27.3% built
- Rahul Residency3.4 yr overdueSiddh Construction and Developers · Parvati, PuneP52100019158· filed Sept 2020 → now Jun 2023· 81.8% built
- AUDUMBER WING B3.4 yr overdueGPL SANKALP ASSOCIATES · Pune City, PuneP52100032612· 90.9% built
- SIMPLICITY G BUILDING3.4 yr overdueASCENTVENTURES · Fattepur, AurangabadP51500005615· filed Dec 2017 → now Jun 2023· 90.9% built
- USHA JOSHI PARK PHASE B3.4 yr overdueJ K T BUILDERS & DEVELOPERS · Khadavali, ThaneP51700012148· filed Dec 2021 → now Jun 2023· 18.6% built
- SEA GRAPES3.4 yr overdueNINE REALTY BUILDERS · Vasai, PalgharP99000002584· filed Dec 2019 → now Jun 2023· 90.7% built
- Florida Water Color II3.4 yr overdueONE EARTH · MUNDHAWA, PuneP52100000946· 63.6% built
- UDYAM BIZBAY3.4 yr overdueKADU REALTY · Saswad, PuneP52100026686· 90.9% built
- SHUBHAM PARADISE3.4 yr overdueARHAM REALTORS · Vasai-Virar City (M Corp), PalgharP99000008958· 90.5% built
- BALAJI HIGHTS3.4 yr overduePANDURANG WAMAN KHARE · VISHRAMBAG, SangliP53100027265· 90.9% built
- Swaraj Phase IV TUV3.4 yr overdueSim Realty · Borhadewadi Moshi, PuneP52100015606· 93.9% built
- SAI SPRING3.4 yr overdueMOHAN KEDARNATH KRISHNAVANSHI · KALYAN, ThaneP51700009813· 90% built
- VRAJ VILLA3.4 yr overdueSHREE INFRA PROJECT · CANAL ROAD, NashikP51600025502· 93.6% built
- VARAD VIRAJ3.4 yr overdueSHRIKANT HIRALALJI UNECHA · DHAYARI PUNE, PuneP52100025846· 90% built
- Acciano-Aurelia No. 13.4 yr overdueM/s Ideal Enterprises · Vasai, PalgharP99000019904· 32.7% built
- Sunteck Icon, Kolekalyan, CST Road, Kalina, Santacruz East, Mumbai3.4 yr overdueSunteck Realty Limited · Andheri, Mumbai SuburbanP51800014845· 81.8% built
- Ekdant Wing D3.4 yr overdueHemant Thombare · kothrud, PuneP52100015134· 33.6% built
- APEX ADDRESS3.4 yr overdueAPEX BUILDCON · NODE PUSHPAK, RaigarhP52000021012· 81.8% built
- Hillside Apartment 4th Floor3.4 yr overduePratik Chandrakant Bhide · Talegaon Dabhade, PuneP52100027682· 94.5% built
- VARAD MORYA3.4 yr overdueSRUSHTI DEVELOPERS · NEAR KELKAR PETROL PUMP ROAD, SangliP53100026871· 81.8% built
- MESACON JEWEL WING C3.4 yr overdueMESACON PROJECTS · Andheri, Mumbai SuburbanP51800023909· 79.5% built
- Sai Aangan3.4 yr overdueVIR Enterprises · Panvel, RaigarhP52000004701· filed Mar 2020 → now Jun 2023· 90.9% built· 1 complaint
- SHIV GANGA3.4 yr overdueANJANI KUMAR COMPANY PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800017043· 90.9% built
- OMKAR HEIGHTS3.4 yr overdueANIKET TANAJI CHAVAN · PUSHPAK NODE, RaigarhP52000027718· 27.3% built
- VISTA VALLEY3.4 yr overdueM/s IQRA REALTY · Kausa, ThaneP51700016240· 87.2% built
- UNIVERSE I PHASE II3.4 yr overdueSAHYADRI GRIH NIRMAN · Thane (M Corp.), ThaneP51700006220· 15.5% built
- Avika Periwinkle3.4 yr overdueM/S Avika Buildcon Pvt Ltd · Baner, PuneP52100029015· 90.9% built
- vedant imperial D phase 33.4 yr overdueMOHAN HARDASMAL THARWANI · Badlapur (M Cl), ThaneP51700007549· 63.2% built
- KRISHNAI GALAXY3.4 yr overduePRATAP LAXMAN SONAWANE · SONAWANE MALA, NashikP51600019478· 90.9% built
- Spring Field3.4 yr overdueSoham Developers · Haveli, PuneP52100027261· 90% built
- THE CENTRUM3.4 yr overdueMANSION CREATORS · OPP SKYSCRAPER, PuneP52100027662· 30.5% built
- Platinum Tower3.4 yr overdueHaware's Housing Development Finance Corporation Ltd. · Thane, ThaneP51700000549· filed Sept 2022 → now Jun 2023· 72.7% built
- VIJAYSHRUSHTI3.4 yr overdueJAY DEVELOPERS · Nashik (M Corp.), NashikP51600011620· filed Dec 2018 → now Jun 2023· 86.4% built
- Joyville Hinjawadi - I, Phase 23.4 yr overdueJoyville Shapoorji Housing Private Limited · Man Village, PuneP52100016252· 90.9% built
- PTK Heights3.4 yr overdueSantosh Ramchandra Tadsare · pagmala chiplun, RatnagiriP52800006399· 67.6% built
- WINSPACE AMELIO3.4 yr overdueBINI BUILDERS PRIVATE LIMITED · -, Mumbai SuburbanP51800010932· filed Jun 2021 → now Jun 2023· 90.9% built
- AMBER ELLANCE A-13.4 yr overdueAAKASH CORPORATION · Thane, ThaneP51700013692· 90.9% built
- Kanakshree Apartments3.4 yr overdueKanak Developments · undri, PuneP52100003928· filed Dec 2018 → now Jun 2023· 90.9% built
- AYESHA PLANET3.4 yr overdueANISA SUBHAN PATEL · TALOJA, RaigarhP52000027819· 81.8% built
- Samraat Apna Ghar Phase-I3.4 yr overdueM/S Shweta Infrastructure & Housing (I) Pvt. Ltd. · Someshwar -Satpur link Road near DJ Reva Meadows, NashikP51600020299· 89.1% built
- RAVIRAJ APARTMENT3.4 yr overdueRAJENDRA GHORPADE · GANESH NAGAR, ThaneP51700020559· filed Dec 2022 → now Jun 2023· 72.7% built
- V N RESIDENCY APARTMENT3.4 yr overdueCENTURY BUILDERS AND DEVELOPERS · PANCHVATI, NashikP51600023215· 90.9% built
- MALATI- MANOHAR APT3.4 yr overdueSATISH MANOHAR DESHPANDE · Nashik (M Corp.), NashikP51600003147· filed Dec 2018 → now Jun 2023· 81.8% built
- HILTON ENCLAVE WING A, B, B-13.4 yr overdueBHAVANI DEVELOPERS PVT LTD · Kurla, Mumbai SuburbanP51800012042· filed Jun 2021 → now Jun 2023· 90% built· 4 complaints
- SUMEET ANAND3.4 yr overdueGhansham jivandas Ahuja · DAHIVALI, RaigarhP52000007287· filed Dec 2018 → now Jun 2023· 90.9% built
- Florida Water Color I3.4 yr overdueONE EARTH · Mundhawa, PuneP52100000870· 90.9% built
- Shreeji Aura3.4 yr overdueSHREEJI REALTORS · Karjat, RaigarhP52000005330· filed Jun 2019 → now Jun 2023· 90.9% built· 2 complaints
- BALAJI COMPLEX - PLOT NO 5, 6, 7 AND 83.4 yr overdueBALAJI INFRA · Khalapur, RaigarhP52000007536· filed Dec 2021 → now Jun 2023· 90.9% built
- SAMARTH PLAZA APARTMENT3.4 yr overdueSHREE SAMARTH BUILDERS AND DEVELOPERS · Nashik (M Corp.), NashikP51600009652· filed Dec 2020 → now Jun 2023· 90.9% built
- Altura3.4 yr overdueSigma Housing · Baner, PuneP52100028192· 60.6% built
- Joyville Hinjawadi - I, Phase 13.4 yr overdueJoyville Shapoorji Housing Private Limited · Man Village, PuneP52100016131· 90.9% built
- SUKHADEV NAGAR PHASE I PART 13.4 yr overdueRAJENDRA SUKHADEV MIRGANE · Barshi, SolapurP52600006417· 75.5% built
- VASANT SHILP3.4 yr overdueS S INFRA · WANLESSWADI, SangliP53100021959· 81.8% built
- SWAPNASHILP3.4 yr overdueUday Pandurang Dalvi · GHORPADI, PuneP52100020665· filed Dec 2022 → now Jun 2023· 43.4% built
- SHIV SIDDHI3.4 yr overdueKEDAR CONSTRUCTION · mharal, ThaneP51700010414· 90% built
- MOHINI CASTLE3.4 yr overdueMOHINI SHELTORS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800005492· filed Jun 2021 → now Jun 2023· 90.9% built
- VISHNU KRUPA3.4 yr overdueA S ASSOCIATES · Uravade, PuneP52100004048· filed Jul 2020 → now Jun 2023· 58.2% built
- NANDANVAN3.4 yr overdueKOSMOS DEVELOPERS · BORIVALI, Mumbai SuburbanP51800012073· filed Jun 2021 → now Jun 2023· 23.6% built
- CRYSTAL SPIRES3.4 yr overdueLUXORA REALTORS PRIVATE LIMITED · Chitalsar Manpada, ThaneP51700009216· filed Jan 2021 → now Jun 2023· 84.8% built· 9 complaints
- SWAPNPURTI3.4 yr overdueUDAYRAJ DEVELOPERS · PUIKHADI, KolhapurP53000021379· 90.9% built
- Rachana Corner3.4 yr overdueShree Construction Builders and Developers · Bhama nagar, AhmednagarP52200032268· 90.9% built
- Dynamic Oasis3.4 yr overdueRajeev Shivnath Sonkar · Undri, PuneP52100001931· 64.1% built· 3 complaints
- TRIDENT BUSINESS CENTER3.4 yr overdueSHIRISH BHASKAR JADHAV · Haveli, PuneP52100008007· filed Jul 2020 → now Jun 2023· 81.8% built
- YASH3.4 yr overdueRANJEKAR REALTY · Kothrud, PuneP52100030981· 81.8% built
- Joyville Hinjawadi - I, Phase 43.4 yr overdueJoyville Shapoorji Housing Private Limited · Man Village, PuneP52100016786· 90.9% built· 1 complaint
- Akshara Platinum3.4 yr overdueGARVE DEVELOPERS · Mulshi, PuneP52100023153· 90.9% built· 3 complaints
- THE EVOQ3.4 yr overdueFUTURISTIC HOMES · ASHOK THEATRE, PuneP52100027486· 81.8% built
- SAI ENCLAVE3.4 yr overdueASHOKKUMAR BHANJIBHAI LADANI · PANCHAVATI, OPP MANE NAGAR, NashikP51600030111· 81.8% built
- MAHALAXMI DHAM CO-OP HOUSING SOCIETY LIMITED TYPE C3.4 yr overdueMAHALAXMIDHAM CO-OP HSG SOCIETY LIMITED · Jail Road, NashikP51600009470· 90.9% built
- Business Index3.4 yr overdueROONGTA INFRASPACE LLP · Makhamalabad, NashikP51600021649· 99.5% built
- REDEVLOPMENT OF SUN AND MOON CHS LTD. BLDG NO. 12 AND 133.4 yr overdueKaustubh Construction Private Limited · Borivali, Mumbai SuburbanP51800007374· filed Dec 2019 → now Jun 2023· 81.8% built
- SUKRUTAM APARTMENT3.4 yr overdueMAKARAND KRISHNAJI DESHPANDE · NEAR MHASKE MEDICAL COLLEGE, AhmednagarP52200028127· 90.9% built
- BHALCHANDRA VIHAR PHASE - II / C3.4 yr overduePOLITE BUILDTECH · RAVET, PuneP52100029204· 74.5% built
- Borivali Nirmala Sadan CHS LTD3.4 yr overdueShreenath Realty LLP · Borivali East, Mumbai SuburbanP51800029552· 60% built
- PARADISE GRANDEUR3.4 yr overduePARIKH INVESTMENT AND DEVELOPMENT PVT. LTD. · Vasai, PalgharP99000004547· filed Dec 2020 → now Jun 2023· 36.4% built
- Kalpataru Ph-33.4 yr overdueAshoka Infraways Limited · Near Indian Oil Corporation Petrol Pump, Chunchale Shiwar, NashikP51600025437· 45.5% built
- GANADHISH SANKUL B WING3.4 yr overdueM.S.PATIL AND ASSOCIATES · Pune City, PuneP52100021788· 90.9% built
- PANORAMA3.4 yr overdueEKTA SHUBHAM VENTURE · Kurla, Mumbai SuburbanP51800001112· filed Dec 2019 → now Jun 2023· 90.9% built· 2 complaints
- Mahalaxmi Nivara3.4 yr overdueMAHALAXMI BUILDTECH LLP · Mangaon, RaigarhP51900007332· filed Jun 2021 → now Jun 2023· 77.1% built
- Shivam Complex Phase - 13.4 yr overdueManoj Ramanand Prajapati · Lodhivali, RaigarhP52000015165· filed Dec 2020 → now Jun 2023· 90.9% built
- Anil3.4 yr overdueGokhale Housing LLP · Subhash Nagar Shukrawar Peth, PuneP52100022240· 81.8% built
- Green Valley Phase 33.4 yr overdueH M DEVELOPERS · Jaysingpur, KolhapurP53000025545· 81.8% built
- NEW LAXMI CHHAYA3.4 yr overduePARMAR AND SM CONSTRUCTION · Andheri, Mumbai SuburbanP51800009399· filed Jul 2019 → now Jun 2023· 90.9% built
- MAHALAXMI DHAM CO-OP HOUSING SOCIETY LIMITED BUILDING A AND B3.4 yr overdueMAHALAXMIDHAM CO-OP HSG SOCIETY LIMITED · Jail Road, NashikP51600009997· 90.9% built
- ROYAL NEST3.4 yr overdueDHANASHREE DEVELOPERS · Ambarnath(M Cl), ThaneP51700003909· filed Dec 2020 → now Jun 2023· 99.1% built
- JAGAJJIVAN HEIGHTS3.4 yr overdueAavishkar Realtors · Kolhapur (M Corp.), KolhapurP53000001291· filed Dec 2019 → now Jun 2023· 81.8% built
- Revanta3.4 yr overdueP4 PROPERTIES · RAVET, PuneP52100014793· 77.3% built
- SAI PAVITRA RESIDENCY3.4 yr overdueSAILAVKIK REALTY PRIVATE LIMITED · Thane, ThaneP51700021480· 81.8% built
- Lunawat Apex3.4 yr overdueNavya Prem Developers LLP · Aundh, PuneP52100025503· 81.8% built
- CHAITANYA KOHINOOR3.4 yr overdueCHAITANYA DEVELOPERS · Borivali, Mumbai SuburbanP51800024570· 90.9% built
- RKL Anand ph13.4 yr overdueLUNKAD GRUH NIRMAN COMPANY · Tathawade, PuneP52100023493· 90.9% built
- SHREE SAMARTH KRUPA APARTMENT3.4 yr overdueL P DEVELOPERS · VIRAR WEST, PalgharP99000027447· 28.6% built
- Mohan Skyville3.4 yr overdueMOHAN LIFESPACES LLP · Kalyan, ThaneP51700003607· filed Jun 2019 → now Jun 2023· 81.8% built
- LINEA3.4 yr overdueRajeev Shivnath Sonkar · Hadapsar, PuneP52100002743· 45.8% built· 1 complaint
- STERLING BLOOMS3.4 yr overdueYASHADA GOVIND CITY CORPORATION · Pimpri Chinchawad (M Corp.), PuneP52100003148· filed Jun 2022 → now Jun 2023· 97% built
- Royal Residency3.4 yr overdueRoyal Eterprises · Krupasinndhu Park, PuneP52100033743· 90.9% built
- PRABHAT DARSHAN3.4 yr overdueSHIVALIK VENTURES PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800002608· 89.5% built
- Shree Datta Samartha CHSL3.4 yr overdueShree Sai Swami Enterprises · Near Railway Station, ThaneP51700034066· 90.9% built
- KUL Utsav Phase I -Building G3.4 yr overdueKumar Builders · kondhwa BK, PuneP52100003489· filed May 2019 → now Jun 2023· 49.3% built
- Parmarth Niketan - Redevelopment of Mani Bhuvan3.4 yr overdueJ V Constructions & Developers · Borivali, Mumbai SuburbanP51800001745· filed Dec 2019 → now Jun 2023· 90.9% built
- VARAD PAVAN3.4 yr overdueBHALCHANDRA VISHWANATH DESAI · NEAR HUMAN MANDIR, SangliP53100028118· 90.9% built
- BASERA CHS LTD3.4 yr overdueLAKSHMI BUILDERS AND DEVELOPERS · Andheri, Mumbai SuburbanP51800001959· 90.9% built
- ZAHRA LAND3.4 yr overdueZAHRA LAND DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000005947· 36.9% built
- ASHTALAXMI ANNEX3.4 yr overdueSHIVAJI GHAMJI DADAS · Near Cummins India, SataraP52700000099· 81.8% built
- GLOBAL RESIDENCY3.4 yr overdueGLOBAL HOUSING VENTURES · Borivali, Mumbai SuburbanP51800009478· 27.6% built· 2 complaints
- SHUBHAMKROTI SAHANIWAS3.4 yr overdueSAMBHAJI SHANKAR DESHMUKH · NEAR JAIN MANDIR, SangliP53100030364· 90.9% built
- Atharva Patson Phinix PH II3.4 yr overdueM/S SAMRAT ATHARVA PATSON BUILDERS AND DEVELOPERS · Chakan (CT), PuneP52100006867· 7.9% built
- SKYSCRAPER PHASE 13.3 yr overdueVISHAL PROPERTIES · Tathwade, PuneP52100008605· 90.9% built· 1 complaint
- SRISHTI AANGAN3.3 yr overdueNEERAJ MOHAN DESAI HUF · SALAIWADA, SindhudurgP52900007953· 45.5% built
- Pranav Pushkaram3.3 yr overduePranav Builders · Tuljainagar, SangliP53100024862· 81.8% built
- Proposed Redevelopment of Vaid Mahal3.3 yr overdueLulu Enterprise · Ward ABCD, Mumbai CityP51900009905· 71.4% built
- AASHIRWAD AVENUE3.3 yr overdueRACHANA BUILDERS AND DEVELOPERS KUDAL · Kudal, SindhudurgP52900007098· 72.3% built
- KUMKUM Sector 7 Building 23 Wing F3.3 yr overdueKalash Developers · Vasai-Virar City (M Corp), PalgharP99000007366· filed Dec 2019 → now Jul 2023· 90.9% built
- EKTA PARKSVILLE PHASE I3.3 yr overdueEKTA PARKSVILLE HOMES PVT. LTD. · Vasai, PalgharP99000000116· filed Dec 2019 → now Jul 2023· 98.9% built· 34 complaints
- MAHALAXMI NAGAR3.3 yr overdueMAHALAXMI HOMEMAKERS PRIVATE LIMITED · Chandrapada, PalgharP99000013575· 40.5% built
- BROOKLYN PARK PHASE III3.3 yr overdueEKTA PARKSVILLE HOMES PVT. LTD. · Vasai, PalgharP99000000148· filed Feb 2020 → now Jul 2023· 88.6% built· 18 complaints
- Vyankatesh City 43.3 yr overdueVYANKATESHA BUILDERS AND DEVELOPERS · Kalamana, NagpurP50500007447· 25.3% built· 2 complaints
- NALINI - SUMANT3.3 yr overdueVINOD SUMANT UGEMUGE · Wardha (M Cl), WardhaP50400010094· filed Jan 2021 → now Jul 2023· 90.9% built· 1 complaint
- Princetown Tower - C33.3 yr overdueManikchand Kumar Properties · Undri, PuneP52100009077· 90.9% built
- SAI KUNJ3.3 yr overdueCHOULWAR CONSTRUCTION · BAVDHAN, PuneP52100025939· filed Jan 2023 → now Jul 2023· 56.4% built
- METRO LIFE MAXIMA RESIDENCES PHASE I3.3 yr overdueRAMA SYNERGY SPACES · Next to Indira College of Commerce and Science, PuneP52100022178· 90.9% built· 26 complaints
- HEERA PALACE3.3 yr overdueM/S. OMKAR DEVELOPERS · WAI, SataraP52700023041· 81.8% built
- RAGHUNATH VIHAR PHASE 13.3 yr overdueTRUST BUILDCON · Khalapur, RaigarhP52000008988· 30.3% built
- Lodha Patel Estate - Tower A, B3.3 yr overdueMACROTECH DEVELOPERS LIMITED · Borivali, Mumbai SuburbanP51800014891· 81.8% built· 2 complaints
- THARWANI MILLENNIUM CITY PHASE I3.3 yr overdueTHARWANI REALTORS · BADLAPUR, ThaneP51700023974· 95.9% built
- Lodha Patel Estate - Tower C, D3.3 yr overdueMACROTECH DEVELOPERS LIMITED · Borivali, Mumbai SuburbanP51800014860· 81.8% built· 5 complaints
- Rachana Samruddhi3.3 yr overdueRachana Developers · Pipla, NagpurP50500008630· 20.5% built
- SAHAKAR PREMIER3.3 yr overduePREMIER REALTY · Thane, ThaneP51700002452· 27.3% built
- RATHI PLANET3.3 yr overdueRATHI CONSRUCTION · Aurangabad (M Corp.), AurangabadP51500003407· 90.9% built
- Waterfront Tower3.3 yr overdueSea Kunal Corporation Pvt. Ltd. · Ward ABCD, Mumbai CityP51900006784· 90.9% built
- SAISH HEIGHTS3.3 yr overdueSAISH BUILDERS AND DEVELOPERS · Satara, SataraP52700013112· 90.9% built
- VENKATESH PRIME3.3 yr overdueVENKATESH PROMOTERS AND BUILDERS · JADHAVWADI PHALTAN, SataraP52700022254· 90.9% built
- KALYANJI ASHRAYA3.3 yr overdueB.Kalyanji Realty · VEENANAGAR, RaigarhP52000028681· 90.9% built
- YASHASWATI CHS LTD3.3 yr overdueLAKSHMI BUILDERS AND DEVELOPERS · Kurla, Mumbai SuburbanP51800001279· 90.9% built
- Dipti SkyCity Building 1 and 33.3 yr overdueDipti Home Makers Pvt Ltd · Ambarnath, ThaneP51700008856· 95.5% built
- Phoenix Ribereno IJBK3.3 yr overduePhoenix Realtors · Shirwal, SataraP52700006704· 90.9% built
- Atharva Heights3.3 yr overdueAtharva Developers · INFRONT MARKET YARD, PuneP52100007912· 73.1% built
- 75 WESTGATE3.3 yr overdueSIDDHARTH RAMESH BANSAL · RAVET, PuneP52100021442· 1.8% built
- PEBBLES MARINA APARTMENTS3.3 yr overduePEBBLES INFRA PROJECTS LTD · Andheri, Mumbai SuburbanP51800012288· 56.4% built
- NEW SAHARA APARTMENT3.3 yr overduePARVIN GAMIR SHAIKH · KHODE NAGAR, NashikP51600021896· 90.9% built
- SRUSHTI COMPLEX3.3 yr overdueAAKAR DEVELOPERS · Bhingaloli, RatnagiriP52800005132· 9.3% built
- Hubtown Countrywoods Building 53.3 yr overdueHubtown Limited · Tilekar Nagar Kondhwa Budruk, PuneP52100002695· 51.5% built
- VISION STARWEST PHASE - 13.3 yr overdueVISION CREATIVE INFRA · TATHAWADE, PuneP52100024346· 90.9% built
- RAGHU-NARAYANA RESIDENCY3.3 yr overdueD.S DEVELOPERS & BUILDERS · aurangabad, AurangabadP51500004562· 90.9% built
- INDRAPRASTHA-Phase-23.3 yr overdueM/s Apte Reality · Salgarwasti, SolapurP52600009835· 72.3% built
- KALINA MARKET3.3 yr overdueKRISHNA ASSOCIATES · Mumbai, Mumbai SuburbanP51800005221· filed Jun 2018 → now Jul 2023· 51.8% built
- 74DownTown3.3 yr overdueAura Realtors · Baner Shroff Road Pune 411045, PuneP52100025327· 90.9% built
- Velentine Apartment 1 Wing D3.3 yr overdueVelentine Properties Private Limited · Andheri, Mumbai SuburbanP51800002036· 7.3% built
- Vikrant3.3 yr overduePate P Square Developers LLP · Navi Peth, PuneP52100021513· 90.9% built
- INDRADHANU Phase-33.3 yr overdueM/S Ganesh Ramchandra Apte · Solapur (M Corp.), SolapurP52600009419· 48.2% built
- SHREE ROYAL HEIGHT3.3 yr overdueROYAL'S RELATORS · Borivali, Mumbai SuburbanP51800022042· 81.8% built
- RKH Blessings B andd C building3.3 yr overdueRKH DEVELOPERS · Moshi, PuneP52100006496· 21.1% built
- KRISHNA ENCLAVE3.3 yr overdueASHA DEVELOPERS · Andheri, Mumbai SuburbanP51800000004· 66.7% built
- MADHUKOSH HEIGHTS3.3 yr overdueGAURAV VISHVANATH AWATI · NEAR VIJAY HOTEL, AhmednagarP52200022069· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.