RERA projects past their possession deadline
11,768 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 47 of 59
- Arunya2.4 yr overdueGM Buildcon · Haveli, PuneP52100014346· filed Dec 2020 → now Mar 2024· 45.5% built· 1 complaint
- AASHIYANA RESIDENCY2.4 yr overdueIMRAN PAPAMIYA MULLA · OPP SURYA HOTEL, SangliP53100046552· 29.1% built
- ELEGANCE PARK2.4 yr overdueM/S RAMOLI SRUSHTI DEVELOPERS · near Sarpanch Vasti, PuneP52100013441· filed Sept 2023 → now Mar 2024· 75.2% built· 3 complaints
- MAYAANK HEIGHTS2.4 yr overdueN. K. LIFESTYLE · Borivali, Mumbai SuburbanP51800030223· 90.9% built
- ROMELL CORNERSTONE2.4 yr overdueROMELL REAL ESTATE PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800032709· 90.9% built
- Revati Imperia2.4 yr overdueRevati Infra Engineers · Gangapur Road, NashikP51600029905· 36.4% built
- VRINDAVAN HEIGHTS2.4 yr overdueSACHIN SUBHASH GAIKWAD · DINDORI, NashikP51600030455· 72.7% built
- SAI DWARKA PHASE 22.4 yr overdueMAA SANKALP BUILDCON · YAWALEWADI, PuneP52100004883· filed Dec 2019 → now Mar 2024· 42.3% built· 8 complaints
- YASHWANT PANDHARI2.4 yr overdueSHREE DATTA ENTERPRISES · NALLASOPARA, PalgharP99000032419· 90.9% built
- SHREE SANKET EMPIRE2.4 yr overdueSHREE SANKET DEVELOPERS · -, NashikP51600007618· filed Dec 2017 → now Mar 2024· 90.9% built
- DIVINE HEIGHTS2.4 yr overdueDIVINE ASSOCIATES · Bandra West, Mumbai CityP51900034314· 90.9% built· 1 complaint
- ACCORD CLASSIC2.4 yr overdueSUYOJANA IMPEX PVT. LTD · Borivali, Mumbai SuburbanP51800007765· filed Mar 2022 → now Mar 2024· 81.8% built
- SACHINAM CO OP HSG SOCIETY2.4 yr overdueSHREEKANTH DEVELOPERS · KULGAON, ThaneP51700033985· 63.6% built
- PAVILION2.4 yr overdueCERATEC GARIMA · KIWALE, PuneP52100047319· 72.7% built
- PREETI SANGAM CHS2.4 yr overdueKANDIVALI PRITI SANGAM CO-OP HOS SOC LTD · Borivali, Mumbai SuburbanP51800011235· filed Jul 2022 → now Mar 2024· 30.2% built· 3 complaints
- SAMARTH VILLA2.4 yr overdueD.A.BORADE & SONS · VISHAL NAGAR, PuneP52100050168· 81.8% built
- CHINTAMANI2.4 yr overdueSANKET BUILDTECH · NEAR RAMLEELA LAWNS, NashikP51600006246· filed Jul 2019 → now Mar 2024· 90.9% built
- KANAKMANGALA - GAJANAN2.4 yr overdueKanakmangala Properties · Haveli, PuneP52100034371· 31.8% built
- MILLENNIUM PACIFIC2.4 yr overdueMillennium Developers · TATHAWADE, PuneP52100027204· 89.1% built
- SHILP TULSI APARTMENT2.4 yr overdueKaran Hemant Gaikwad · Jai Bhavani Road, Nashik Road, NashikP51600030620· 81.8% built
- SIDDHIVINAYAK2.4 yr overdueSANKET BUILDTECH · Near Ramleela Lawns, NashikP51600007408· filed Dec 2018 → now Mar 2024· 90.9% built
- SUKHMANI NIWAS2.4 yr overdueM/S PREETAM ASSOCIATES · PIMPRI, PuneP52100048054· 9.1% built
- DWARKAMAI HEIGHTS2.4 yr overdueDWARKAMAI ASSOCIATES · CHARHOLI BUDRUK, PuneP52100046861· filed Mar 2023 → now Mar 2024· 63.5% built
- SHUBHASHREE2.4 yr overdueKotibhaskar Infrastructures &Developers Pvt.Ltd. · PUNE, PuneP52100045350· 99.1% built
- Mai Kripa Co. Op. Hsg. Soc.2.4 yr overdueOJASS CONSTRUCTIONS · Thane, ThaneP51700033561· 90.9% built
- JAYSHREE BLISS2.4 yr overdueJAYSHREE INFRA PROJECTS · PANCHAVATI, NashikP51600047741· 81.8% built
- SIGNATURE PARK G AND H BUILDING2.3 yr overdueSHREE SONIGARA REALCON · THERGAON, PuneP52100019960· 45.5% built· 89 complaints
- Ganganagar2.3 yr overdueSanjay Chandrakant Bafana · Shirur, PuneP52100022015· 90.9% built
- SIGNATURE PARK C AND D BUILDING2.3 yr overdueSHREE SONIGARA REALCON · THERGAON, PuneP52100020943· 42.3% built· 66 complaints
- KUMAR PEBBLE PARK KHUSHI 2- D22.3 yr overdueKumar Construction and Properties Pvt Ltd · HANDEWADI, PuneP52100020421· 49.1% built
- Shikhar2.3 yr overduePTR Universal · Andheri, Mumbai SuburbanP51800020732· 97.3% built
- VYANKATESH HEIGHTS2.3 yr overdueSANGALEJI GROUP · MHASRUL, NashikP51600045621· 72.7% built
- SWANANDI RESIDENCY2.3 yr overdueAMIT SANJAY CHAKANKAR · DHAYARI, PuneP52100031935· filed Dec 2023 → now Apr 2024· 97.7% built
- SAI KIRAN2.3 yr overdueRAVI KIRAN HOMES · VADGHAR, RaigarhP52000051736· filed Dec 2023 → now Apr 2024· 62.7% built
- BALEWADI 372.3 yr overduenitin shamrao patil · BALEWADI, PuneP52100028844· 72.7% built
- ASIL PARADISE2.3 yr overdueASIL INFRATECH LLP · TALOJA, RaigarhP52000024129· filed Dec 2022 → now Apr 2024· 87.7% built
- VEDANT DEVELOPERS2.3 yr overdueVEDANT DEVELOPERS · TAL- HAVELI, DISTRICT PUNE, PuneP52100048105· filed Dec 2023 → now Apr 2024· 36.8% built
- SHEETAL DHARMARAJ2.3 yr overdueD.G.LAND DEVELOPERS PRIVATE LIMITED · MARVE ROAD, Mumbai SuburbanP51800027915· 0% built· 1 complaint
- Vtp Beaumonde- Nation R2 Tower52.3 yr overdueAshdan Developers Private Limited · Manjri, PuneP52100007384· filed Jul 2022 → now Apr 2024· 90.9% built· 33 complaints
- Boulevard part of Towers Phase 12.3 yr overdueBramhacorp Limited · Pune City, PuneP52100004150· 81.8% built· 1 complaint
- Kumar Prospera - A3, A4 and A52.3 yr overdueKumar Agro Products Pvt Ltd - Kumar Company (Now known as Kumar Construction and Properties Pvt Ltd) JV · Magarpatta, PuneP52100022619· 88.1% built· 1 complaint
- SANSKRUTI PHASE IV2.3 yr overdueSAI ENTERPRISES · Kherdi (CT), RatnagiriP52800003822· filed Dec 2020 → now Apr 2024· 40% built
- GLOBE PRATHAM2.3 yr overdueGLOBE CORP · Palghar, PalgharP99000032857· 68.2% built
- SHAMROCK RESIDENCY2.3 yr overdueSHantee Homes Realty LLP · Vasai, PalgharP99000020998· 80.9% built
- SHREE DREAMS2.3 yr overdueRAFIK AKBAR MULLA · Shirur, PuneP52100001844· filed Feb 2020 → now Apr 2024· 90.9% built
- Shakambari Centro2.3 yr overdueSushilkumar Ratanlal Khowal · Ram Nagar, AkolaP50100049359· 81.8% built
- EKTA VERVE2.3 yr overdueEKTA WORLD PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800021089· 87% built· 2 complaints
- NYATI ELAN SOUTH I2.3 yr overduePSQUARE BUILDERS LLP · WAGHOLI, PuneP52100029008· 86.4% built
- JB PEARL2.3 yr overdueJB HOUSING LLP · CHAIYANYA GARDEN, BEHIND SYNERGY MULTISPECIALTY HOSPITAL, CHANDANWADI, MIRAJ, SangliP53100024812· filed Mar 2024 → now Apr 2024· 90.9% built
- FORTUNE SHUBHAN PHASE 2 BUILDING D2.3 yr overdueFORTUNE COPORATION · Pune (M Corp.), PuneP52100006125· filed Jun 2019 → now Apr 2024· 90.9% built
- Mont Vert Grande Bldg Type G plot 22.3 yr overdueNiraj Kumar Associates Pvt Ltd · Pashan, PuneP52100020880· 90.9% built
- KRISHNAs BLISS2.3 yr overdueSHREYA CONSTRUCTION · NR PATIDAR BHAVAN GENERAL VAIDYA NAGAR DWARKA, NashikP51600029447· 90.9% built
- Annapurna Smruti2.3 yr overdueGokhale Empires LLP · Shukrawar Peth, PuneP52100026504· 81.8% built· 1 complaint
- Poorti2.3 yr overdueRahul Ramesh Shah · Gultekadi, PuneP52100032542· 90.9% built
- RAJYOG RESIDENCY2.3 yr overdueRajyog Developers · Marutimandir, RatnagiriP52800029325· 90.9% built
- KUKREJA GARDENS WING A2.3 yr overdueTOLARAM AND CO · BHANDUP WEST, Mumbai SuburbanP51800020817· 73.3% built· 1 complaint
- BALKRUSHNA AND NANDALAL2.3 yr overdueVAINATEYA BUILD PRIVATE LIMITED · PUNE, PuneP52100004293· filed Dec 2019 → now Apr 2024· 90.9% built
- NYATI ELAN CENTRAL I2.3 yr overduePSQUARE BUILDERS LLP · WAGHOLI, PuneP52100029005· 86.4% built· 1 complaint
- Mayuri Infinity2.3 yr overdueMAYURI LANDMARKSLLP · TATA inora park, PuneP52100015703· filed Apr 2021 → now Apr 2024· 66.7% built· 1 complaint
- SURYADARSHAN CHS LTD2.3 yr overdueH&D PROJECTS · Borivali, Mumbai SuburbanP51800046756· 70.5% built
- BLUE ROOF SERA2.3 yr overdueRainbow Construction · SUS, PuneP52100024232· 72.9% built
- FLORA CASA2.3 yr overdueSynergy Infra · Solapur (M Corp.), SolapurP52600007672· filed Oct 2023 → now Apr 2024· 90.9% built
- Rachayati Crown2.3 yr overdueRachayati Realtors and Developers pvt ltd · Amravati, AmravatiP50300028865· 88.5% built
- Arihant Residency2.3 yr overdueAditya Deepak Karnawat · Dahanu East, PalgharP99000032477· 74.1% built
- SAI SPARSH2.3 yr overdueVIKAS LAXMAN CHAUDHARY · ITKHEDA AURANGABAD, AurangabadP51500016484· 90.9% built
- SHREE CHARAN APARTMENT2.3 yr overdueSHREE MANGALMURTI ENTERPRISES · MURBAD, ThaneP51700034064· 52.8% built
- KAMGAR PANCH GANGA SRAPHASE 1 CHSPROPOSED2.3 yr overduePAYAL J SHAH · Borivali, Mumbai SuburbanP51800008400· filed Aug 2018 → now Apr 2024· 99.1% built· 1 complaint
- DHOLE COMPLEX2.3 yr overdueGAURAV VISHVANATH AWATI · OPP. VYAPARI MANGAL KARYALAY, WARD NO. 5, AhmednagarP52200050319· 90.9% built
- PC RESIDENCY PRIDE2.3 yr overdueSHUBHAM SURENDRA CHECHANI · JALNA, JalnaP51400045717· 90.9% built
- Iora2.3 yr overdueVerain Commercials LLP · Tardeo, Mumbai CityP51900004714· filed Jun 2022 → now May 2024· 99% built· 1 complaint
- Laxmi Pushp2.3 yr overdueJOSHI PARANJAPE DEVELOPERS · Swapna Nagari, SangliP53100030453· 90.9% built
- TRIDENT2.2 yr overdueDEU ASSOCIATES · PIMPLE NILKH, PuneP52100026732· 36.4% built
- Studio High 5 Phase 3 Wing E Luxe2.2 yr overdueRamshiromani Lurkhur Yadav · DHAMOTE, RaigarhP52000047178· 90.4% built
- AKAR VISHWA PHASE 22.2 yr overdueAKAR INFRASTRUCTURE · BEHIND CHIRAYU HOSPITAL, RatnagiriP52800016360· 90.9% built
- Zenith Enclave2.2 yr overdueZenith Enterprises · Hirawadi, NashikP51600029766· 90.9% built
- KRISHNA KOYNA2.2 yr overdueJKD ENGINEERS AND INFRASTRUCTURE PRIVATE LIMITED · SHIMPOLI, Mumbai SuburbanP51800027749· 20.6% built
- AROHI HEIGHTS2.2 yr overdueROHINI SUBHASH PAWAR · PANCHAVATI, NashikP51600046183· 72.7% built
- Avani II2.2 yr overdueKamal Promoters & Builders. · Mohammadwadi chowk, PuneP52100015958· 51.8% built· 1 complaint
- Chinmay Pride2.2 yr overdueChinmay Pride · Mahavir Nagar, PuneP52100031331· 63.6% built
- ABHINAV SUPER MARKET2.2 yr overdueRAMESH NANDLAL SODANI · ambad, JalnaP51400010132· 81.4% built
- Suraj Co.Op.HSG.SOC.Ltd2.2 yr overdueASD ENTERPRISES · Sarvodaya Nagar, ThaneP51700017984· 27.5% built
- HIGHLAND SPRINGS B4- A WING2.2 yr overdueSIDDHI REAL ESTATE DEVELOPERS · Thane, ThaneP51700005338· filed Jun 2023 → now May 2024· 90.9% built· 1 complaint
- NAVRANG CHS LTD2.2 yr overdueADITYARAJ DEVELOPERS · SARDAR NAGARP51900024861· 90.9% built
- SATYAM CRESCENT2.2 yr overdueSATYAM GROUP · PUSHPAK NODE PANVEL, RaigarhP52000050486· 72.7% built
- RAGHUNANDAN KASTURI/ KAMTHE PATIL BUSINESS CENTER2.2 yr overdueRAGHUNANDAN ASSOCIATES · KONDHWA BK, PuneP52100020129· 81.8% built
- VENKATESH GRAFFITI ELAN PHASE 12.2 yr overdueSHREE VENKATESH BUILDCON PVT LTD · Keshav Nagar, Mundhwa, PuneP52100023431· 90.9% built
- KHUSHI PRIDE2.2 yr overdueKASIM MOHAMED MANER · NEAR FATIMA MASJID, SangliP53100028957· 82.6% built
- HIGHLAND SPRINGS B4- B WING2.2 yr overdueSIDDHI REAL ESTATE DEVELOPERS · Thane, ThaneP51700007745· filed Jun 2023 → now May 2024· 90.9% built· 4 complaints
- SAWALI APARTMENTS2.2 yr overduePARMAR REALTY · PARVATI, PuneP52100032232· 53.6% built
- iNDRAPRASTHA PHASE 2 INCLUDES BUILDING NO 72.2 yr overdueINDRAPRASTHA ASSOCIATES · Gondhalpada, RaigarhP52000035138· 64.5% built
- SAINATH HEIGHTS2.2 yr overdueDHRUVED CONSTRUCTION · ANANDWALI, NashikP51600046125· 0.7% built
- SHREE VARAD APARTMENT2.2 yr overdueSHREE RENUKA BUILDERS · HAGWANE MALA, NashikP51600047143· 72.7% built
- WESTBROOK2.2 yr overdueTara Constructions · AMBEGAON, PuneP52100003178· filed Sept 2020 → now May 2024· 68% built· 14 complaints
- RISHABRAJ SURAJ2.2 yr overdueH RISHABRAJ REALTY · BORIVALI WEST, Mumbai SuburbanP51800029277· 90.9% built
- Bhagwati Ashish2.2 yr overduePritesh Damji Savla · Andheri, Mumbai SuburbanP51800010515· filed Nov 2020 → now May 2024· 88.6% built· 4 complaints
- SAIKUNJ CO-OPERATIVE HSG SOCIETY2.2 yr overdueROYAL ENTERPRISES · 52 BUNGLOW, RaigarhP52000045864· 90.9% built
- MUKUND2.2 yr overdueKotibhaskar Infrastructures &Developers Pvt.Ltd. · MAHARSHI KARVENAGAR, PuneP52100045860· 90% built
- Dreamsville2.2 yr overdueParadiso Builders Private Limited · Borivali, Mumbai SuburbanP51800046670· 81.8% built
- Ten X Vibes2.2 yr overdueTen X Vibes · Thane, ThaneP51700052442· 90.9% built
- PALM RESIDENCY2.2 yr overdueFIRDAUS DINSHAW IRANI · LONIPADA, PalgharP99000028359· 90.9% built
- SOHAM GALAXY2.2 yr overdueNANDU NARHARI JAGTAP · PUNE, PuneP52100029013· filed Dec 2023 → now Jun 2024· 10% built
- Blue Ridge Project E Land T24 and T252.2 yr overdueParanjape Schemes (Construction) Ltd. · Hinjewadi, PuneP52100016328· 99.9% built· 1 complaint
- SHIV ORCHID2.2 yr overdueSIDDHIVINAYAK CONSTRUCITONS · NASHIK ROAD, NashikP51600032776· 89.1% built
- SRUSHTI HEIGHTS2.2 yr overduePUNDLIK VILAS ADSUL · NEAR MALI THEATHER, OPP ARCHITECTURE HALL, SangliP53100025217· 90.9% built
- TILANG APARTMENTS2.2 yr overdueGOKHALE INFRADEVELOPERS PVT LTD · SHIVAJINAGAR, SangliP53100019409· 90.9% built· 1 complaint
- MANERI RESIDENCY2.1 yr overdueNatasha Dcosta · Maneri, SindhudurgP52900013413· filed Jun 2023 → now Jun 2024· 81.8% built
- THE HORIZON2.1 yr overdueNILCON INFRABUILDERS PRIVATE LIMITED · DEOPUR, DhuleP49800046176· 90.9% built
- SHIVPRASAD HEIGHTS2.1 yr overduePRINCE DEVELOPERS · VIDHYANAGAR, SataraP52700027045· 63.6% built
- KUTUMB PRIME2.1 yr overdueNAIKNAVARE BUILDCON PVT LTD · Mawal, PuneP52100002348· filed Jun 2019 → now Jun 2024· 60.5% built
- Arya Sapphire2.1 yr overdueVAASTUDEAL DEVELOPERS PVT. LTD. · Asade Golavali, kalyan, ThaneP51700021439· filed Dec 2022 → now Jun 2024· 12.3% built
- Shreeraj Darshan2.1 yr overdueShreeraj Developers · Raje Shiv Chatrapati Nagar, NashikP51600029841· 90.9% built
- MARATHON NEXWORLD AURA-22.1 yr overdueMATRIX ENCLAVES PROJECTS DEV. PVT. LTD · Thane, ThaneP51700000507· filed Jun 2023 → now Jun 2024· 26.3% built· 3 complaints
- Three Jewels2.1 yr overdueSnowflower Properties Private Limited · Kondhwa, PuneP52100006160· filed Dec 2023 → now Jun 2024· 71.8% built
- MONTESOUTH-32.1 yr overdueSWAYAM REALTORS & TRADERS LLP · Ward E, Mumbai CityP51800001681· filed Jun 2023 → now Jun 2024· 43.6% built
- MARATHON NEXTOWN SAPPHIRE2.1 yr overdueMARATHON ENER-GEN LLP · OFF KALYAN SHIL ROAD, ThaneP51700001265· filed Dec 2021 → now Jun 2024· 85.9% built
- PLATINUM TOWERS2.1 yr overdueLaxman Sopanrao Nimhan · wakad, PuneP52100016501· 90.9% built
- Aldea Espanola Phase VI2.1 yr overduePuranik Buildcon Private Limited · Mahalunge, PuneP52100000537· 90.6% built· 1 complaint
- PRAYEJA CITY2.1 yr overduePRAYEJA CITY · Wadgaon Budruk, PuneP52100010668· filed Nov 2018 → now Jun 2024· 85.5% built· 11 complaints
- BALI LAXMI2.1 yr overdueBALI SPACES LLP · Borivali, Mumbai SuburbanP51800027818· 90.9% built
- SIDDHAKALA HEIGHTS2.1 yr overdueRushabh Developers · Thane, ThaneP51700027126· 90.9% built
- Skyline viha Wing B2.1 yr overdueAnkit Overseas · Kurla, Mumbai SuburbanP51800002495· filed Dec 2018 → now Jun 2024· 82.6% built· 1 complaint
- SUDARSHAN HEIGHTS2.1 yr overdueDEEPAK VENKATRAO KULKARNI · ROSHAN HOUSING SOCIETY, AurangabadP51500027497· 69.5% built
- GREENVILLE BUILDING A12.1 yr overdueVision Realtors · Hadapsar, PuneP52100028126· 90% built· 1 complaint
- Swastick Heights2.1 yr overdueShree Swastick Builders · Vasai, PalgharP99000011121· filed Jan 2019 → now Jun 2024· 90.9% built· 3 complaints
- Barsana2.1 yr overdueVedbhumi Builders & Developers Pvt. Ltd. · Nagpur, NagpurP50500013341· filed Jul 2018 → now Jun 2024· 75% built
- Megapolis Saffron - A3 to A92.1 yr overduePegasus Properties Pvt. Ltd. · Rajiv Gandhi Infotech Park, Phase 3, PuneP52100018779· 89.1% built
- AMBIKA HEIGHTS2.1 yr overdueRAJESH MAVJI CHHEDA · AMRAI CHOWK, ThaneP51700033336· 90.9% built· 1 complaint
- KENISHA HOLIDAY HOMES - CLUSTER E-J-K2.1 yr overdueKUNAL AVINASH KUMTHEKAR · Sudhagad, RaigarhP52000000966· filed Dec 2018 → now Jun 2024· 72.4% built
- NL TAKSASILA2.1 yr overdueNAHALCHAND LALOOCHAND PVT. LTD. · KANDIVALI (WEST), Mumbai SuburbanP51800025643· 90.9% built
- OYSTER MARINA2.1 yr overdueSUDHIR RAMCHANDRA THAKUR · ULWE, RaigarhP52000003462· 64.5% built
- LAXMI AVENUE2.1 yr overdueLAXMAN SAIBANA MEHETRE · NEAR PRISTINE PROLIFE PHASE III, PuneP52100024445· 86.4% built
- GVC SHAGUN CITY PHASE III2.1 yr overdueSHAGUN ASSOCIATES · KAUTHA, NandedP51100026123· 78.2% built
- Laxmi Homes2.1 yr overduePokar Realty · Haveli, PuneP52100025463· filed Jul 2023 → now Jun 2024· 72.7% built
- Savannah2.1 yr overdueSim Properties · wagholi, PuneP52100027297· 51.5% built
- VAGISHWARI RESIDENCY2.1 yr overdueRasika Constructions · Near Tiwari Hospital, RaigarhP52000026526· 90.9% built
- SAMYEKDARSHAN2.1 yr overdueDARSHAN BUILDERS & DEVELOPERS · NAVALI, PalgharP99000028611· 25.9% built
- Sukhniwas2.1 yr overdueAmol Ajit Ravetkar · Shivajinagar, PuneP52100009654· filed Feb 2021 → now Jun 2024· 90.9% built
- SRUSHTI RESIDENCY BUILDING E2.1 yr overduePappu Developers & Group · KANCHANGAON THAKURLI, ThaneP51700028176· 90.9% built
- BHALCHANDRA VIHAR PHASE - IV/M32.1 yr overdueN B BHONDVE BUILDERS · RAVET, PuneP52100047005· 81.8% built
- PALAASH SADAPHULI PHASE 2 A1 WING2.1 yr overdueGS ASSOCIATES · Varale, PuneP52100005853· filed Apr 2018 → now Jun 2024· 81.8% built· 20 complaints
- SAI SOLITARE2.1 yr overdueSamrudhi Associates · Kurla, Mumbai SuburbanP51800006560· filed Jun 2021 → now Jun 2024· 89.5% built· 1 complaint
- UNNATHI WOODS PHASE VII-B2.1 yr overdueUNNATHI ESTATES · KAVESAR, ThaneP51700015800· 89.8% built· 9 complaints
- VIRKUD PLAZA2.1 yr overdueSANJARI BUILDERS · Palghar, PalgharP99000025589· 90.9% built
- OM PARADISE2.1 yr overduePATADE PROPERTIES · Gadhinglaj, KolhapurP53000008750· filed Dec 2017 → now Jun 2024· 90.9% built
- Guruprasad Residency2.1 yr overdueHRISHIKESH SHRIPAD DESHPANDE · SHIVAJI COLONY, SangliP53100030791· 99.1% built
- Arkade Serene2.1 yr overdueArkade Developers Private Limited · Sunder Nagar Malad West, Mumbai SuburbanP51800029961· 74.5% built
- AURORA2.1 yr overdueMagnum Developers · GAT NO.927 PART, PuneP52100030790· 81.8% built
- AND ROSE2.1 yr overdueANANTNATH DEVELOPERS · Diva East, ThaneP51700019146· 90.9% built
- SANJEEVANI HEIGHTS2.1 yr overdueOSWAL CREATIVE · Sudhagad, RaigarhP52000027812· 90.9% built
- Samraat Apna Ghar Phase-III2.1 yr overdueM/S Shweta Infrastructure & Housing (I) Pvt. Ltd. · Satpur Link Road, NashikP51600029928· 41.3% built
- IPSIT NAVODAY PHASE 52.1 yr overdueIPSIT ENTERPRISE · Palghar, PalgharP99000003777· filed Mar 2019 → now Jun 2024· 60.5% built
- BRAMHA CITY2.1 yr overdueBHAGWAN PARASHARAM DHOOT · SHEVGAON, AhmednagarP52200045756· 36.4% built
- DAHISAR SHIVANGAN WING A2.1 yr overdueYASH ENTERPRISES · DAHISAR EAST, Mumbai SuburbanP51800028519· 40% built· 3 complaints
- Dmellos Residency2.1 yr overdueM/s Ideal Properties · Manikpure Circle, PalgharP99000025569· 76.1% built
- ARCHANA PARADISE WING A2.1 yr overdueKANIFNATH REALITY · MOHAMMADWADI, PuneP52100026701· 51.4% built
- Ganadhish Park2.1 yr overdueM/S. Ravindra Developers Pvt. Ltd. · Ambad Khurd, NashikP51600030411· 81.8% built
- GREENVILLE BUILDING A42.1 yr overdueVision Realtors · HADAPSAR, PuneP52100052689· 90.9% built
- NINE STAR PRIDE II BUILDING NO. 062.1 yr overdueNINE HOME REALTORS · Palghar, PalgharP99000026178· 45.5% built
- Borawake Shilp2.1 yr overdueUrban Creations · Satavvadi, PuneP52100028860· 77.3% built
- SAPPHIRE TOWERS 22.1 yr overdueCHAURANG VENTURES · CHARHOLI PHATA, CHOVISAWADI, PuneP52100031392· 89.5% built
- KANCHAN BUSINESS CENTER2.1 yr overdueNOVEL BUILDCON · PALGHAR, PalgharP99000020390· 90.9% built
- TRUSHNA CHS LTD2.1 yr overdueMahesh Shriram Borkar · PANCHPAKHADI, ThaneP51700023568· 77.5% built
- ADDRESS 8172.1 yr overdueDESHPANDE INFRA · SAI BABA COLONY, KARANDEMALA, KASBA BAVADE, KOLHAPUR., KolhapurP53000032216· 90.9% built
- VISHNUPUSHP KUTIR2.1 yr overdueL P DEVELOPERS · GOKHIVARE, PalgharP99000050499· 90.9% built
- Oshi2.1 yr overdueSahyog Homes Limited · Oshiwara, Mumbai SuburbanP51800002965· filed Dec 2022 → now Jun 2024· 92.7% built· 7 complaints
- TULSA PARK2.1 yr overdueSHREE SHIVAM DEVELOPERS · Kalyan, ThaneP51700005797· filed Jun 2021 → now Jun 2024· 57.4% built
- SOSAR SOLITAIRE2.1 yr overdueSOSAR ENTERPRISES · Andheri, Mumbai SuburbanP51800025925· 81.8% built
- NIDHAAN CLOVER - A2.1 yr overdueNIDHAAN BUILDCON PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800019932· 86.4% built
- Sai Sanskruti2.1 yr overdueHORIZON REALTY · Kharadi, PuneP52100025975· 90.9% built
- CASA ABRIGO2.1 yr overdueTECHSTONE CONSTRUCTIONS LLP · HADAPSAR, PuneP52100026227· 90.9% built
- Gauri Lila2.1 yr overdueM/S Nashte Associates · E Ward Kolhapur, KolhapurP53000008365· filed Dec 2022 → now Jun 2024· 49.1% built
- KAILASH HEIGHTS2.1 yr overdueKAILASH DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000008653· filed Dec 2019 → now Jun 2024· 90% built
- GAYATRREE LEGACY2.1 yr overdueGAYATRREE PROPERTIES · Chikhali, PuneP52100013335· filed Dec 2018 → now Jun 2024· 69.7% built· 5 complaints
- ADI AVENTURA2.1 yr overdueADI HOMES · RAVET, PuneP52100016461· 87.9% built
- ELITE HOMES2.1 yr overdueCRYSTAL HOMES · NALASOPARA WEST, PalgharP99000026203· 90.9% built
- Sai Sparsh-A1, A22.1 yr overdueJalan Associates · Bhor, PuneP52100003561· filed Dec 2018 → now Jun 2024· 99.1% built
- Vista 3C2.1 yr overdueLuxora Infrastructure Private Limited · Mauza, NagpurP50500007884· filed Dec 2019 → now Jun 2024· 80% built· 4 complaints
- TRIMURTI RESIDENCY2.1 yr overdueTRIMURTI CONSTRUCTIONS · SAVEDI, AhmednagarP52200030627· 86.4% built
- Dynamic Grandeur2.1 yr overdueDYNAMIC REALTY ENTERPRISES · Undri, PuneP52100005396· 85% built
- NANDANVAN2.1 yr overduePENTAGON PROPERTIES · Haveli, PuneP52100008374· filed Sept 2021 → now Jun 2024· 95.5% built
- NYATI ELITE2.1 yr overdueNITIN DWARKADAS NYATI · UNDRI VILLAGE, PuneP52100045651· 83.5% built
- RACHANA ROHINI2.1 yr overdueRachana Developers · BESIDE FIRE ENGINEERING INSTITUTE JAGDISH NAGAR NAGPUR, NagpurP50500033105· 76.8% built
- NINE STAR PRIDE II BUILDING NO. 072.1 yr overdueNINE HOME REALTORS · Palghar, PalgharP99000026194· 45.5% built
- HIBISCUS HEIGHTS2.1 yr overdueMOHAN DINESH SINGH · THANE, ThaneP51700017046· 63.6% built
- Kanchan Sheila CHS2.1 yr overdueYug Developers · Mulund West, Mumbai SuburbanP51800033242· filed Mar 2024 → now Jun 2024· 64.6% built
- VIRESHWAR DARSHAN CHS LTD2.1 yr overdueVIRESHWAR DARSHAN CHS LTD · VILE PARLE EAST, Mumbai SuburbanP51800049312· 70% built
- SHERLYN AVENUE2.1 yr overdueSHARAD SOPAN SHENDE · Pisoli, PuneP52100001087· filed Feb 2021 → now Jun 2024· 66.1% built
- GAYATRI APARTMENT2.1 yr overdueSANTOSH RAMESH RAUT · Karjat, RaigarhP52000005736· filed Dec 2019 → now Jun 2024· 81.8% built
- VELSONS HEIGHTS2.1 yr overdueVELSONS DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000006958· filed Dec 2019 → now Jun 2024· 90.7% built
- VENKATESH GRAFFITI ELAN PHASE 22.1 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAVNAGAR MUNDHWA, PuneP52100026737· 90.9% built
- Green park2.1 yr overdueAnishka Developers Pvt. Ltd. · Kondhwa Bk, PuneP52100000501· filed Dec 2022 → now Jun 2024· 98.2% built
- Malpani Arcade2.1 yr overdueHEMANT VISHWANATH MALPANI · Tidke Colony, NashikP51600023448· 90.9% built
- Satyabhama CHS LTD2.1 yr overdueMahesh Shriram Borkar · GHANTALI, ThaneP51700032055· 90.9% built
- YAHAVI-TOWER-1-OAK2.1 yr overdueIMAGE REALTY PRIVATE LIMITED · OXFORD GOLF COURSE, PuneP52100028031· 81.8% built· 1 complaint
- Kakad Paradise Phase 22.1 yr overdueKakad Housing Corporation · Thane, ThaneP51700006750· 90.9% built· 4 complaints
- AAKASH TOWER2.1 yr overdueAAKASH ASSOCIATES INFRASTRUCTURE ·P51900012769· filed Jun 2021 → now Jun 2024· 40% built
- GANDHI TOWERS2.1 yr overdueJAYSHREE SATISH GANDHI · DAUND, PuneP52100016096· 36.4% built
- BRAHMAND RESIDENCY2.1 yr overdueBHAVI REALITY LLP · MASOLI, PalgharP99000002353· 90.9% built
- RAJAN DINAKAR PHATAK AND OTHERS2.1 yr overdueWESTIN SANKALP DEVELOPERS · Borivali, Mumbai SuburbanP51800028236· 89.1% built
- BALAJI VIBHA2.1 yr overdueANNASAHEB KALLAPPA UPADHYE · CHINTAMANI NAGAR, SangliP53100028397· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.