RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 47 of 61
- Majestique City D Building2.6 yr overdueMANISH DWARKADAS MAHESHWARI · Pune-Nagar Road, PuneP52100019947· 90.9% built
- Neelkanth Valley II2.6 yr overdueNeelkanth Properties · Khalapur, RaigarhP52000016470· 90.9% built
- SARA CITY C82.6 yr overdueJagrutsara Structures LLP · KHARABWADI, PuneP52100015654· 90.9% built
- The Courtyard Phase II2.6 yr overdueMarc Developers · TARAKPUR, AhmednagarP52200022201· 90.9% built
- Maruti Bhuvan2.6 yr overdueSuresh Prabhushankar Sharma · Mogra, Mumbai SuburbanP51800005335· filed Mar 2019 → now Mar 2024· 72.7% built
- Godrej Rejuve2.6 yr overdueOXFORD REALTY LLP · Keshavnagar, PuneP52100018720· 90.9% built· 11 complaints
- Sadanand Residency2.6 yr overdueBhavani Builders · Oras Bk., SindhudurgP52900007520· filed Mar 2019 → now Mar 2024· 89.5% built
- SILVER OAK PHASE 22.6 yr overdueBHASKAR RAMGONDA PATIL · NEAR RELIANCE PETROL PUMP, KolhapurP53000025215· 90.9% built
- SWARAJYA2.6 yr overdueKaumudi Builders and Developers · Behind TV Tower, RatnagiriP52800016000· 90.9% built
- ROHAN ABHILASHA 2 WING A2.6 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · Wagholi, PuneP52100025655· 80% built
- ROYAL RESIDENCY2.6 yr overdueS J BUILDER & DEVELOPERS · PIMPRI CHINCHWAD, PuneP52100045783· 81.8% built
- PAVILION2.6 yr overdueCERATEC GARIMA · KIWALE, PuneP52100047319· 72.7% built
- Orchid Plaza2.6 yr overdueA J Associates · Jawahar Nagar, AkolaP50100052054· 81.8% built
- VRINDAVAN HEIGHTS2.6 yr overdueSACHIN SUBHASH GAIKWAD · DINDORI, NashikP51600030455· 72.7% built
- YASHWANT PANDHARI2.6 yr overdueSHREE DATTA ENTERPRISES · NALLASOPARA, PalgharP99000032419· 90.9% built
- Arunya2.6 yr overdueGM Buildcon · Haveli, PuneP52100014346· filed Dec 2020 → now Mar 2024· 45.5% built· 1 complaint
- SUPER MARKET2.6 yr overdueVSI BUILDERS AND DEVELOPERS · BHOR TOWNSHIP, NashikP51600034814· 18.2% built
- DIVINE HEIGHTS2.6 yr overdueDIVINE ASSOCIATES · Bandra West, Mumbai CityP51900034314· 90.9% built· 1 complaint
- VRUNDAVAN APARTMENT2.6 yr overdueSHREE ASSOCIATES · PANCHAVATI, NashikP51600030779· 90.9% built
- Prem Zephyr2.6 yr overdueAshwin Enterprises · Mulund West, Mumbai SuburbanP51800029011· 90.9% built
- AASHIYANA RESIDENCY2.6 yr overdueIMRAN PAPAMIYA MULLA · OPP SURYA HOTEL, SangliP53100046552· 29.1% built
- SAMARTH VILLA2.6 yr overdueD.A.BORADE & SONS · VISHAL NAGAR, PuneP52100050168· 81.8% built
- PROBITAS GLORY2.6 yr overdueMAHESH BHAGWANRAO SALUNKHE · BHADKAMKARNAGAR, SataraP52700031402· 63.6% built
- PREETI SANGAM CHS2.6 yr overdueKANDIVALI PRITI SANGAM CO-OP HOS SOC LTD · Borivali, Mumbai SuburbanP51800011235· filed Jul 2022 → now Mar 2024· 30.2% built· 3 complaints
- VALENCIA2.6 yr overdueSHETE PATIL DEVELOPERS · GANESH VIHAR COLONY, AhmednagarP52200029222· filed Apr 2023 → now Mar 2024· 76.8% built
- Revati Imperia2.6 yr overdueRevati Infra Engineers · Gangapur Road, NashikP51600029905· 36.4% built
- ACCORD CLASSIC2.6 yr overdueSUYOJANA IMPEX PVT. LTD · Borivali, Mumbai SuburbanP51800007765· filed Mar 2022 → now Mar 2024· 81.8% built
- ROMELL CORNERSTONE2.6 yr overdueROMELL REAL ESTATE PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800032709· 90.9% built
- SHREE DATT GLORY2.6 yr overdueVILAS DATTATRAY KHAIRNAR · MHASRUL NASHIK, NashikP51600034624· 81.8% built
- CHINTAMANI2.6 yr overdueSANKET BUILDTECH · NEAR RAMLEELA LAWNS, NashikP51600006246· filed Jul 2019 → now Mar 2024· 90.9% built
- Swarajya Apartment2.6 yr overdueKalash Developers Associates · Nashik, NashikP51600033621· 72.7% built
- SHILP TULSI APARTMENT2.6 yr overdueKaran Hemant Gaikwad · Jai Bhavani Road, Nashik Road, NashikP51600030620· 81.8% built
- TRINITY ARCADE2.6 yr overdueSURESH NAMDEO GAYKHE · PANCHAWATI, NashikP51600030716· 90.9% built
- Govind Leela Niketan2.6 yr overdueNiketan Construction · Powainaka, SataraP52700030353· 81.8% built
- ELEGANCE PARK2.6 yr overdueM/S RAMOLI SRUSHTI DEVELOPERS · near Sarpanch Vasti, PuneP52100013441· filed Sept 2023 → now Mar 2024· 75.2% built· 3 complaints
- AARAMBH2.6 yr overdueA TO Z CONSTRUCTION · ABHAY NAGAR, AhmednagarP52200031478· 90.9% built
- LABH SAMARTH HEIGHT2.6 yr overdueM.V. LABH ASSOCIATES · Andheri, Mumbai SuburbanP51800011676· filed Dec 2018 → now Mar 2024· 90.9% built
- SHUBHASHREE2.6 yr overdueKotibhaskar Infrastructures &Developers Pvt.Ltd. · PUNE, PuneP52100045350· 99.1% built
- SAMARTH SADAN2.6 yr overdueMODEL DEVELOPERS AND GENGAJE ASSOCIATES · SHANIWAR PETH SATARA, SataraP52700029437· 81.8% built
- Laxmi Pooja Multi Family Residential Unit on Plot No 68-69 Part and 70-69 Part Kh no 1372.6 yr overduePOOJA CONSTRUCTIONS · Chinchbhawan, NagpurP50500047883· 90.9% built
- ZEAL REGENCY2.6 yr overdueBLUE BARON REALTORS · Vasai, PalgharP99000003182· filed Dec 2018 → now Mar 2024· 81.8% built· 14 complaints
- SAI DWARKA PHASE 22.6 yr overdueMAA SANKALP BUILDCON · YAWALEWADI, PuneP52100004883· filed Dec 2019 → now Mar 2024· 42.3% built· 8 complaints
- DRUMADAL2.6 yr overdueRanjekar Realty LLP · Shivajinagar, Bhamburda, PuneP52100026105· filed Sept 2023 → now Mar 2024· 55.5% built
- Ace Courtyard2.6 yr overdueAce Signature Homes LLP · Mogharpada, ThaneP51700033813· 90.9% built
- CHANDRA-TARA2.6 yr overdueNIRMAAN ENGINEERS AND CONTRACTORS · CHURCH GATE, NashikP51600034999· 12.7% built
- SUKHMANI NIWAS2.6 yr overdueM/S PREETAM ASSOCIATES · PIMPRI, PuneP52100048054· 9.1% built
- MAYA HARMONY2.6 yr overdueMAYA DEVELOPERS · Kurla, Mumbai SuburbanP51800009358· filed Nov 2020 → now Mar 2024· 74.1% built
- MILLENNIUM PACIFIC2.6 yr overdueMillennium Developers · TATHAWADE, PuneP52100027204· 89.1% built
- JAMDAR ERA2.6 yr overdueYogesh Suresh Dudhal · Baramati, PuneP52100048521· 90.9% built· 1 complaint
- Motivilla2.6 yr overdueAAKAR SHIV INFRA VENTURE · Goregaon West, Mumbai SuburbanP51800033793· 90.9% built
- SIDDHIVINAYAK2.6 yr overdueSANKET BUILDTECH · Near Ramleela Lawns, NashikP51600007408· filed Dec 2018 → now Mar 2024· 90.9% built
- SHREE SANKET EMPIRE2.6 yr overdueSHREE SANKET DEVELOPERS · -, NashikP51600007618· filed Dec 2017 → now Mar 2024· 90.9% built
- IMPERIAL PRIDE2.6 yr overdueIMPERIAL REALTY · PANCHAVATI, NashikP51600029696· 72.7% built
- MAYAANK HEIGHTS2.6 yr overdueN. K. LIFESTYLE · Borivali, Mumbai SuburbanP51800030223· 90.9% built
- Tirupati Royal Homes2.6 yr overdueTIRUPATI CONSTRUCTION PROMOTERS & DEVELOPERS · KBP College Chowk, SolapurP52600047849· 90.9% built
- VEDANT PRIDE2.6 yr overdueVEDANT CONSTRUCTIONS · OPP OJASWI APARTMENT, PuneP52100033002· 81.8% built
- REDEVELOPMENT OF SILVERENE CHSL2.6 yr overduePRANAV CONSTRUCTIONS LIMITED · MUMBAI, Mumbai SuburbanP51800031840· 90.9% built
- ICHHAMANI2.6 yr overdueSANKET BUILDTECH · NEAR RAMLEELA LAWNS, NashikP51600004120· filed Dec 2018 → now Mar 2024· 90.9% built
- Mai Kripa Co. Op. Hsg. Soc.2.6 yr overdueOJASS CONSTRUCTIONS · Thane, ThaneP51700033561· 90.9% built
- JAYSHREE BLISS2.6 yr overdueJAYSHREE INFRA PROJECTS · PANCHAVATI, NashikP51600047741· 81.8% built
- Vidya Nidhi2.6 yr overdueLaxmi Aakar Realty · Goregaon West, Mumbai SuburbanP51800033588· 90.9% built
- Yamuna Arcade2.6 yr overdueMarvel Trinity Infra LLP · Infront of Kotak Hospital, AkolaP50100029100· 90.9% built
- CASTLE O CLIFF2.6 yr overdueNASHIK, NashikP51600045924· 81.8% built
- THE JAMBLI GALLI CHS LTD2.6 yr overdueMAHAVIR CORPORATIONS · BORIVALI WEST, Mumbai SuburbanP51800045335· 81.8% built
- ACE AURUM COMMERCIAL2.6 yr overdueAALIA HOMES · OPP. SENTOSA RESORT, NEAR MUKAI CHOWK RAVET, PuneP52100030450· 90.9% built
- KANAKMANGALA - GAJANAN2.6 yr overdueKanakmangala Properties · Haveli, PuneP52100034371· 31.8% built
- SARA SANGAM GANGA BLDG2.6 yr overdueJAGRUT SARA ASSOCIATES · BAJAJNAGAR, AurangabadP51500030505· 90.9% built
- DWARKAMAI HEIGHTS2.6 yr overdueDWARKAMAI ASSOCIATES · CHARHOLI BUDRUK, PuneP52100046861· filed Mar 2023 → now Mar 2024· 63.5% built
- KRUPA2.6 yr overdueAASAMANTA REALTY · GOREGAON EAST, Mumbai SuburbanP51800032389· 90.9% built
- SHREE SIDDHI BLDG NO 692.6 yr overdueHIRANIMANTHAN BUILDERS AND DEVELOPERS · Kurla, Mumbai SuburbanP51800003413· filed Mar 2020 → now Mar 2024· 90.9% built
- SACHINAM CO OP HSG SOCIETY2.6 yr overdueSHREEKANTH DEVELOPERS · KULGAON, ThaneP51700033985· 63.6% built
- Shikhar2.6 yr overduePTR Universal · Andheri, Mumbai SuburbanP51800020732· 97.3% built
- SIGNATURE PARK C AND D BUILDING2.6 yr overdueSHREE SONIGARA REALCON · THERGAON, PuneP52100020943· 42.3% built· 66 complaints
- KUMAR PEBBLE PARK KHUSHI 2- D22.6 yr overdueKumar Construction and Properties Pvt Ltd · HANDEWADI, PuneP52100020421· 49.1% built
- SIGNATURE PARK G AND H BUILDING2.6 yr overdueSHREE SONIGARA REALCON · THERGAON, PuneP52100019960· 45.5% built· 89 complaints
- Ganganagar2.6 yr overdueSanjay Chandrakant Bafana · Shirur, PuneP52100022015· 90.9% built
- VYANKATESH HEIGHTS2.6 yr overdueSANGALEJI GROUP · MHASRUL, NashikP51600045621· 72.7% built
- SWANANDI RESIDENCY2.6 yr overdueAMIT SANJAY CHAKANKAR · DHAYARI, PuneP52100031935· filed Dec 2023 → now Apr 2024· 97.7% built
- SAI KIRAN2.6 yr overdueRAVI KIRAN HOMES · VADGHAR, RaigarhP52000051736· filed Dec 2023 → now Apr 2024· 62.7% built
- BALEWADI 372.6 yr overdueNitin Shamrao Patil · BALEWADI, PuneP52100028844· 72.7% built
- VEDANT DEVELOPERS2.6 yr overdueVEDANT DEVELOPERS · TAL- HAVELI, DISTRICT PUNE, PuneP52100048105· filed Dec 2023 → now Apr 2024· 36.8% built
- ASIL PARADISE2.6 yr overdueASIL INFRATECH LLP · TALOJA, RaigarhP52000024129· filed Dec 2022 → now Apr 2024· 87.7% built
- SHEETAL DHARMARAJ2.6 yr overdueD.G.LAND DEVELOPERS PRIVATE LIMITED · MARVE ROAD, Mumbai SuburbanP51800027915· 0% built· 1 complaint
- Vtp Beaumonde- Nation R2 Tower52.6 yr overdueAshdan Developers Private Limited · Manjri, PuneP52100007384· filed Jul 2022 → now Apr 2024· 90.9% built· 33 complaints
- Boulevard part of Towers Phase 12.6 yr overdueBramhacorp Limited · Pune City, PuneP52100004150· 81.8% built· 1 complaint
- Kumar Prospera - A3, A4 and A52.5 yr overdueKumar Agro Products Pvt Ltd - Kumar Company (Now known as Kumar Construction and Properties Pvt Ltd) JV · Magarpatta, PuneP52100022619· 88.1% built· 1 complaint
- SANSKRUTI PHASE IV2.5 yr overdueSAI ENTERPRISES · Kherdi (CT), RatnagiriP52800003822· filed Dec 2020 → now Apr 2024· 40% built
- GLOBE PRATHAM2.5 yr overdueGLOBE CORP · Palghar, PalgharP99000032857· 68.2% built
- Arihant Residency2.5 yr overdueAditya Deepak Karnawat · Dahanu East, PalgharP99000032477· 74.1% built
- SHAMROCK RESIDENCY2.5 yr overdueSHantee Homes Realty LLP · Vasai, PalgharP99000020998· 80.9% built
- Shakambari Centro2.5 yr overdueSushilkumar Ratanlal Khowal · Ram Nagar, AkolaP50100049359· 81.8% built
- KRISHNAs BLISS2.5 yr overdueSHREYA CONSTRUCTION · NR PATIDAR BHAVAN GENERAL VAIDYA NAGAR DWARKA, NashikP51600029447· 90.9% built
- Poorti2.5 yr overdueRahul Ramesh Shah · Gultekadi, PuneP52100032542· 90.9% built
- Annapurna Smruti2.5 yr overdueGokhale Empires LLP · Shukrawar Peth, PuneP52100026504· 81.8% built· 1 complaint
- BLUE ROOF SERA2.5 yr overdueRainbow Construction · SUS, PuneP52100024232· 72.9% built
- KAMGAR PANCH GANGA SRAPHASE 1 CHSPROPOSED2.5 yr overduePAYAL J SHAH · Borivali, Mumbai SuburbanP51800008400· filed Aug 2018 → now Apr 2024· 99.1% built· 1 complaint
- NYATI ELAN SOUTH I2.5 yr overduePSQUARE BUILDERS LLP · WAGHOLI, PuneP52100029008· 86.4% built
- Mayuri Infinity2.5 yr overdueMAYURI LANDMARKSLLP · TATA inora park, PuneP52100015703· filed Apr 2021 → now Apr 2024· 66.7% built· 1 complaint
- EKTA VERVE2.5 yr overdueEKTA WORLD PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800021089· 87% built· 3 complaints
- FLORA CASA2.5 yr overdueSynergy Infra · Solapur (M Corp.), SolapurP52600007672· filed Oct 2023 → now Apr 2024· 90.9% built
- BALKRUSHNA AND NANDALAL2.5 yr overdueVAINATEYA BUILD PRIVATE LIMITED · PUNE, PuneP52100004293· filed Dec 2019 → now Apr 2024· 90.9% built
- FORTUNE SHUBHAN PHASE 2 BUILDING D2.5 yr overdueFORTUNE COPORATION · Pune (M Corp.), PuneP52100006125· filed Jun 2019 → now Apr 2024· 90.9% built
- Mont Vert Grande Bldg Type G plot 22.5 yr overdueNiraj Kumar Associates Pvt Ltd · Pashan, PuneP52100020880· 90.9% built
- SHREE DREAMS2.5 yr overdueRAFIK AKBAR MULLA · Shirur, PuneP52100001844· filed Feb 2020 → now Apr 2024· 90.9% built
- SURYADARSHAN CHS LTD2.5 yr overdueH&D PROJECTS · Borivali, Mumbai SuburbanP51800046756· 70.5% built
- JB PEARL2.5 yr overdueJB HOUSING LLP · CHAIYANYA GARDEN, BEHIND SYNERGY MULTISPECIALTY HOSPITAL, CHANDANWADI, MIRAJ, SangliP53100024812· filed Mar 2024 → now Apr 2024· 90.9% built
- Rachayati Crown2.5 yr overdueRachayati Realtors and Developers pvt ltd · Amravati, AmravatiP50300028865· 88.5% built
- RAJYOG RESIDENCY2.5 yr overdueRajyog Developers · Marutimandir, RatnagiriP52800029325· 90.9% built
- SAI SPARSH2.5 yr overdueVIKAS LAXMAN CHAUDHARY · ITKHEDA AURANGABAD, AurangabadP51500016484· 90.9% built
- KUKREJA GARDENS WING A2.5 yr overdueTOLARAM AND CO · BHANDUP WEST, Mumbai SuburbanP51800020817· 73.3% built· 1 complaint
- SHREE CHARAN APARTMENT2.5 yr overdueSHREE MANGALMURTI ENTERPRISES · MURBAD, ThaneP51700034064· 52.8% built
- NYATI ELAN CENTRAL I2.5 yr overduePSQUARE BUILDERS LLP · WAGHOLI, PuneP52100029005· 86.4% built· 1 complaint
- DHOLE COMPLEX2.5 yr overdueGAURAV VISHVANATH AWATI · OPP. VYAPARI MANGAL KARYALAY, WARD NO. 5, AhmednagarP52200050319· 90.9% built
- PC RESIDENCY PRIDE2.5 yr overdueSHUBHAM SURENDRA CHECHANI · JALNA, JalnaP51400045717· 90.9% built
- Iora2.5 yr overdueVerain Commercials LLP · Tardeo, Mumbai CityP51900004714· filed Jun 2022 → now May 2024· 99% built· 1 complaint
- Laxmi Pushp2.5 yr overdueJOSHI PARANJAPE DEVELOPERS · Swapna Nagari, SangliP53100030453· 90.9% built
- TRIDENT2.5 yr overdueDEU ASSOCIATES · PIMPLE NILKH, PuneP52100026732· 36.4% built
- AKAR VISHWA PHASE 22.5 yr overdueAKAR INFRASTRUCTURE · BEHIND CHIRAYU HOSPITAL, RatnagiriP52800016360· 90.9% built
- Studio High 5 Phase 3 Wing E Luxe2.5 yr overdueRamshiromani Lurkhur Yadav · DHAMOTE, RaigarhP52000047178· 90.4% built
- KRISHNA KOYNA2.5 yr overdueJKD ENGINEERS AND INFRASTRUCTURE PRIVATE LIMITED · SHIMPOLI, Mumbai SuburbanP51800027749· 20.6% built
- Zenith Enclave2.5 yr overdueZenith Enterprises · Hirawadi, NashikP51600029766· 90.9% built
- Avani II2.5 yr overdueKamal Promoters & Builders. · Mohammadwadi chowk, PuneP52100015958· 51.8% built· 1 complaint
- AROHI HEIGHTS2.5 yr overdueROHINI SUBHASH PAWAR · PANCHAVATI, NashikP51600046183· 72.7% built
- Chinmay Pride2.5 yr overdueChinmay Pride · Mahavir Nagar, PuneP52100031331· 63.6% built
- ABHINAV SUPER MARKET2.5 yr overdueRAMESH NANDLAL SODANI · ambad, JalnaP51400010132· 81.4% built
- KHUSHI PRIDE2.4 yr overdueKASIM MOHAMED MANER · NEAR FATIMA MASJID, SangliP53100028957· 82.6% built
- Suraj Co.Op.HSG.SOC.Ltd2.4 yr overdueASD ENTERPRISES · Sarvodaya Nagar, ThaneP51700017984· 27.5% built
- HIGHLAND SPRINGS B4- B WING2.4 yr overdueSIDDHI REAL ESTATE DEVELOPERS · Thane, ThaneP51700007745· filed Jun 2023 → now May 2024· 90.9% built· 4 complaints
- SAWALI APARTMENTS2.4 yr overduePARMAR REALTY · PARVATI, PuneP52100032232· 53.6% built
- RAGHUNANDAN KASTURI/ KAMTHE PATIL BUSINESS CENTER2.4 yr overdueRAGHUNANDAN ASSOCIATES · KONDHWA BK, PuneP52100020129· 81.8% built
- HIGHLAND SPRINGS B4- A WING2.4 yr overdueSIDDHI REAL ESTATE DEVELOPERS · Thane, ThaneP51700005338· filed Jun 2023 → now May 2024· 90.9% built· 1 complaint
- SATYAM CRESCENT2.4 yr overdueSATYAM GROUP · PUSHPAK NODE PANVEL, RaigarhP52000050486· 72.7% built
- NAVRANG CHS LTD2.4 yr overdueADITYARAJ DEVELOPERS · SARDAR NAGARP51900024861· 90.9% built
- VENKATESH GRAFFITI ELAN PHASE 12.4 yr overdueSHREE VENKATESH BUILDCON PVT LTD · Keshav Nagar, Mundhwa, PuneP52100023431· 90.9% built
- Dreamsville2.4 yr overdueParadiso Builders Private Limited · Borivali, Mumbai SuburbanP51800046670· 81.8% built
- SAIKUNJ CO-OPERATIVE HSG SOCIETY2.4 yr overdueROYAL ENTERPRISES · 52 BUNGLOW, RaigarhP52000045864· 90.9% built
- Felicia2.4 yr overdueAryavedant promoters & builders · Balewadi, PuneP52100046927· 89.5% built
- iNDRAPRASTHA PHASE 2 INCLUDES BUILDING NO 72.4 yr overdueINDRAPRASTHA ASSOCIATES · Gondhalpada, RaigarhP52000035138· 64.5% built
- SAINATH HEIGHTS2.4 yr overdueDHRUVED CONSTRUCTION · ANANDWALI, NashikP51600046125· 0.7% built
- SHREE VARAD APARTMENT2.4 yr overdueSHREE RENUKA BUILDERS · HAGWANE MALA, NashikP51600047143· 72.7% built
- Ten X Vibes2.4 yr overdueTen X Vibes · Thane, ThaneP51700052442· 90.9% built
- Bhagwati Ashish2.4 yr overduePritesh Damji Savla · Andheri, Mumbai SuburbanP51800010515· filed Nov 2020 → now May 2024· 88.6% built· 4 complaints
- MUKUND2.4 yr overdueKotibhaskar Infrastructures &Developers Pvt.Ltd. · MAHARSHI KARVENAGAR, PuneP52100045860· 90% built
- WESTBROOK2.4 yr overdueTara Constructions · AMBEGAON, PuneP52100003178· filed Sept 2020 → now May 2024· 68% built· 14 complaints
- RISHABRAJ SURAJ2.4 yr overdueH RISHABRAJ REALTY · BORIVALI WEST, Mumbai SuburbanP51800029277· 90.9% built
- SOHAM GALAXY2.4 yr overdueNANDU NARHARI JAGTAP · PUNE, PuneP52100029013· filed Dec 2023 → now Jun 2024· 10% built
- PALM RESIDENCY2.4 yr overdueFIRDAUS DINSHAW IRANI · LONIPADA, PalgharP99000028359· 90.9% built
- Blue Ridge Project E Land T24 and T252.4 yr overdueParanjape Schemes (Construction) Ltd. · Hinjewadi, PuneP52100016328· 99.9% built· 1 complaint
- SHIV ORCHID2.4 yr overdueSIDDHIVINAYAK CONSTRUCITONS · NASHIK ROAD, NashikP51600032776· 89.1% built
- SRUSHTI HEIGHTS2.4 yr overduePUNDLIK VILAS ADSUL · NEAR MALI THEATHER, OPP ARCHITECTURE HALL, SangliP53100025217· 90.9% built
- TILANG APARTMENTS2.4 yr overdueGOKHALE INFRADEVELOPERS PVT LTD · SHIVAJINAGAR, SangliP53100019409· 90.9% built· 1 complaint
- MANERI RESIDENCY2.4 yr overdueNatasha Dcosta · Maneri, SindhudurgP52900013413· filed Jun 2023 → now Jun 2024· 81.8% built
- THE HORIZON2.4 yr overdueNILCON INFRABUILDERS PRIVATE LIMITED · DEOPUR, DhuleP49800046176· 90.9% built
- SHIVPRASAD HEIGHTS2.4 yr overduePRINCE DEVELOPERS · VIDHYANAGAR, SataraP52700027045· 63.6% built
- KUTUMB PRIME2.4 yr overdueNAIKNAVARE BUILDCON PVT LTD · Mawal, PuneP52100002348· filed Jun 2019 → now Jun 2024· 60.5% built
- Shreeraj Darshan2.4 yr overdueShreeraj Developers · Raje Shiv Chatrapati Nagar, NashikP51600029841· 90.9% built
- Arya Sapphire2.4 yr overdueVAASTUDEAL DEVELOPERS PVT. LTD. · Asade Golavali, kalyan, ThaneP51700021439· filed Dec 2022 → now Jun 2024· 12.3% built
- Three Jewels2.4 yr overdueSnowflower Properties Private Limited · Kondhwa, PuneP52100006160· filed Dec 2023 → now Jun 2024· 71.8% built
- MARATHON NEXTOWN SAPPHIRE2.4 yr overdueMARATHON ENER-GEN LLP · OFF KALYAN SHIL ROAD, ThaneP51700001265· filed Dec 2021 → now Jun 2024· 85.9% built
- MONTESOUTH-32.4 yr overdueSWAYAM REALTORS & TRADERS LLP · Ward E, Mumbai CityP51800001681· filed Jun 2023 → now Jun 2024· 43.6% built
- MARATHON NEXWORLD AURA-22.4 yr overdueMATRIX ENCLAVES PROJECTS DEV. PVT. LTD · Thane, ThaneP51700000507· filed Jun 2023 → now Jun 2024· 26.3% built· 3 complaints
- Aldea Espanola Phase VI2.4 yr overduePuranik Buildcon Private Limited · Mahalunge, PuneP52100000537· 90.6% built· 1 complaint
- Guardian Cityscapes Phase 12.4 yr overdueGuardian Homes Private Limited · Dattawadi, PuneP52100003214· 75.2% built· 4 complaints
- SAI SHILP RESIDENCY- BHAKTI2.4 yr overdueOM SAI BUILDCON · Nashik (M Corp.), NashikP51600011886· 90.9% built
- Sai Sanskruti2.4 yr overdueHORIZON REALTY · Kharadi, PuneP52100025975· 90.9% built
- Samraat Apna Ghar Phase-III2.4 yr overdueM/S Shweta Infrastructure & Housing (I) Pvt. Ltd. · Satpur Link Road, NashikP51600029928· 41.3% built
- SPRING GARDENS PHASE - I2.4 yr overdueAchalare Realtors Private Limited · BORHADEWADI, PuneP52100026121· 90.9% built
- AND ROSE2.4 yr overdueANANTNATH DEVELOPERS · Diva East, ThaneP51700019146· 90.9% built
- NINE STAR PRIDE II BUILDING NO. 072.4 yr overdueNINE HOME REALTORS · Palghar, PalgharP99000026194· 45.5% built
- SHIV-GOVIND ORCHID2.4 yr overdueR B CONSTRUCTION CO. · ZINGABAI TAKLI, NagpurP50500027140· 90.9% built
- BALI LAXMI2.4 yr overdueBALI SPACES LLP · Borivali, Mumbai SuburbanP51800027818· 90.9% built
- SUKHWANI NYSA2.4 yr overdueSUKHWANI LANDMARK · RAVET, PuneP52100026493· 81.6% built
- SIDDHAKALA HEIGHTS2.4 yr overdueRushabh Developers · Thane, ThaneP51700027126· 90.9% built
- Laxmi Homes2.4 yr overduePokar Realty · Haveli, PuneP52100025463· filed Jul 2023 → now Jun 2024· 72.7% built
- HIBISCUS HEIGHTS2.4 yr overdueMOHAN DINESH SINGH · THANE, ThaneP51700017046· 63.6% built
- KRUSHNA PRIDE - 12.4 yr overdueNAMDEO GOVIND BORHADE · Pathardi Shivar, NashikP51600027619· 35.1% built
- GOLDEN WINDS Building D Phase 52.4 yr overdueGOLDEN BRICKS DEVELOPERS · Opposite D Y Patil Knowledge City Off Porwal Road, PuneP52100027754· 81.8% built
- RACHANA ROHINI2.4 yr overdueRachana Developers · BESIDE FIRE ENGINEERING INSTITUTE JAGDISH NAGAR NAGPUR, NagpurP50500033105· 76.8% built
- Skyline viha Wing B2.4 yr overdueAnkit Overseas · Kurla, Mumbai SuburbanP51800002495· filed Dec 2018 → now Jun 2024· 82.6% built· 1 complaint
- SAI SOLITARE2.4 yr overdueSamrudhi Associates · Kurla, Mumbai SuburbanP51800006560· filed Jun 2021 → now Jun 2024· 89.5% built· 1 complaint
- GREENVILLE BUILDING A12.4 yr overdueVision Realtors · Hadapsar, PuneP52100028126· 90% built· 1 complaint
- Kakad Paradise Phase 22.4 yr overdueKakad Housing Corporation · Thane, ThaneP51700006750· 90.9% built· 4 complaints
- VIRESHWAR DARSHAN CHS LTD2.4 yr overdueVIRESHWAR DARSHAN CHS LTD · VILE PARLE EAST, Mumbai SuburbanP51800049312· 70% built
- Gauri Lila2.4 yr overdueM/S Nashte Associates · E Ward Kolhapur, KolhapurP53000008365· filed Dec 2022 → now Jun 2024· 49.1% built
- SAPPHIRE TOWERS 22.4 yr overdueCHAURANG VENTURES · CHARHOLI PHATA, CHOVISAWADI, PuneP52100031392· 89.5% built
- OYSTER MARINA2.4 yr overdueSUDHIR RAMCHANDRA THAKUR · ULWE, RaigarhP52000003462· 64.5% built
- EXPRESS ZONE MALL2.4 yr overdueCELLO SONAL CONSTRUCTION · Andheri, Mumbai SuburbanP51800002490· 81.8% built· 3 complaints
- Bhoomi Samarth B Wing2.4 yr overdueSamarth Erectors & Developers · Borivali, Mumbai SuburbanP51800026289· 50.9% built
- SOSAR SOLITAIRE2.4 yr overdueSOSAR ENTERPRISES · Andheri, Mumbai SuburbanP51800025925· 81.8% built
- MILESTONE RKD DEVELOPERS2.4 yr overdueRKD DEVELOPERS · BANER, PuneP52100030844· 75.9% built
- Kanchan Sheila CHS2.4 yr overdueYug Developers · Mulund West, Mumbai SuburbanP51800033242· filed Mar 2024 → now Jun 2024· 64.6% built
- TRUSHNA CHS LTD2.4 yr overdueMahesh Shriram Borkar · PANCHPAKHADI, ThaneP51700023568· 77.5% built
- GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED2.4 yr overdueDILIP DOSHI · Borivali, Mumbai SuburbanP51800028730· 91.8% built
- AAKASH TOWER2.4 yr overdueAAKASH ASSOCIATES INFRASTRUCTURE ·P51900012769· filed Jun 2021 → now Jun 2024· 40% built
- KENISHA HOLIDAY HOMES - CLUSTER E-J-K2.4 yr overdueKUNAL AVINASH KUMTHEKAR · Sudhagad, RaigarhP52000000966· filed Dec 2018 → now Jun 2024· 72.4% built
- PALAASH SADAPHULI2.4 yr overdueGS ASSOCIATES · Varale, PuneP52100003228· filed Apr 2018 → now Jun 2024· 90.9% built· 21 complaints
- PARASNATH NAGARI BUILDING NO. 12.4 yr overdueSHREE PARASNATH BUILDERS · Vasai, PalgharP99000009841· filed Jun 2018 → now Jun 2024· 80% built· 6 complaints
- Borawake Shilp2.4 yr overdueUrban Creations · Satavvadi, PuneP52100028860· 77.3% built
- EXPRESS ZONE B WING2.4 yr overdueCELLO SONAL CONSTRUCTION · Andheri, Mumbai SuburbanP51800005634· 54.5% built
- ACE AVENUE2.4 yr overdueAce properties · MULUND WEST, Mumbai SuburbanP51800033494· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.