RERA projects past their possession deadline
11,768 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 48 of 59
- TOWER E OF BUILDING NO 3-PHASE OF PROJECT NAMED VIVAREA BEING CONSTRUCTED ON PORTION OF PROJECT LAND2.1 yr overdueGENEXT HARDWARE & PARKS PRIVATE LIMITED · Ward E, Mumbai CityP51900019931· 99.7% built
- OM SAI HOME2.1 yr overdueM/S. INFINI DEVELOPERS · TEMGHAR, ThaneP51700019911· 87.3% built
- KUMAR PALAASH B2.1 yr overdueKUMAR & POTNIS ASSOCIATES · NEAR KUMAR PRIMAVERAP52100027406· 96.4% built
- ACORN PARK PHASE I2.1 yr overduePANTHEON ASSOCIATES LLP · wakad, PuneP52100028087· 86.4% built
- SHAMBHAVI PRESTIGE2.1 yr overdueN K COMPANY · pune ahmednagar roadP52100027341· 90.9% built
- SHREE KRISHNA AVENUE2.1 yr overdueHemant Enterprises · KATHE GALLI, NashikP51600025635· 60.9% built
- SAI SHILP RESIDENCY- BHAKTI2.1 yr overdueOM SAI BUILDCON · Nashik (M Corp.), NashikP51600011886· 90.9% built
- EXPRESS ZONE B WING2.1 yr overdueCELLO SONAL CONSTRUCTION · Andheri, Mumbai SuburbanP51800005634· 54.5% built
- RACHNA HOUSES2.1 yr overdueDNYANESHWAR KACHARU ILAG · SAPTASHRUNGI NAGAR SINNAR, NashikP51600029873· 90.9% built
- OMKAR CHS LTD2.1 yr overdueLAKSHMI BUILDERS AND DEVELOPERS · Andheri, Mumbai SuburbanP51800003558· filed Jul 2023 → now Jun 2024· 90.9% built
- Gagan Utopia2.1 yr overdueGAGAN BUILDSCAPES LLP · Mundhwa, PuneP52100005074· filed Dec 2019 → now Jun 2024· 63.3% built· 2 complaints
- AMAR SAHAVAS APARTMENT2.1 yr overdueAMAR INFRASTRUCTURES · SHIVAJI NAGAR, NashikP51600027690· 90.9% built
- AMEY2.1 yr overdueRanjekar Realty LLP · Kothrud, Pune, PuneP52100026733· 89.1% built
- SAI SHRUSHTI APARTMENT2.1 yr overdueSHREE VYANKTESH CONSTRUCTIONS · MAKHMALABAD SHIWAR, NashikP51600027386· 90.9% built
- DESTINATION EL PROGRESO2.1 yr overdueEL PROGRESO VENTURES · MOSHI PRADHIKARAN, PuneP52100026761· 57.6% built
- Mangalam homes2.1 yr overdueYashashree Group · Dudulgoan Moshi, PuneP52100021772· 61.4% built
- Morning Star2.1 yr overdueM/s. Star Enterprises · Bhabhola, PalgharP99000027877· 51.8% built
- SPECTRUM2.1 yr overdueJOSHI BUILDCON LANDMARKS · Shivajinagar, PuneP52100032621· 68.2% built
- RADHE HARMONY2.1 yr overdueSTAR PROPERTIES · NEAR STAR CITYP52100021137· 90.9% built
- Mahavir Kalp2.1 yr overdueRAJESH BUILDERS · Palghar, PalgharP99000021428· 90.9% built
- Yashwin Orizzonte - Phase I2.1 yr overdueVILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP · Opposite Panchashil TowerP52100026213· 90.2% built
- 127 UPPER EAST2.1 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Andheri, Mumbai SuburbanP51800000454· filed Dec 2019 → now Jun 2024· 56.4% built· 1 complaint
- MALOO MARVEL2.1 yr overdueRAJIV MOHANLAL MALOO · TUNGARESHWAR PHATA, PalgharP99000027988· 81.8% built
- PALAASH SADAPHULI2.1 yr overdueGS ASSOCIATES · Varale, PuneP52100003228· filed Apr 2018 → now Jun 2024· 90.9% built· 21 complaints
- SHIV-GOVIND ORCHID2.1 yr overdueR B CONSTRUCTION CO. · ZINGABAI TAKLI, NagpurP50500027140· 90.9% built
- Yes Residency2.1 yr overdueYemul& Sancheti Associates · Hadapsar, PuneP52100010630· filed Dec 2018 → now Jun 2024· 79.5% built· 2 complaints
- Supreme Evana2.1 yr overdueSupreme Mega Constructions LLP · Bandra West, Mumbai SuburbanP51800033931· 90% built
- GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED2.1 yr overdueDILIP DOSHI · Borivali, Mumbai SuburbanP51800028730· 91.8% built
- BHALCHANDRA PROSPERA2.1 yr overdueN B BHONDAVE PROMOTERS · RAVET, PuneP52100031692· 89.2% built· 1 complaint
- GOKHALE SERENITY2.1 yr overdueSUDHIR MAHADEV GOKHALE · DHAYRI, PuneP52100028814· 73.3% built
- FLORENZA VILLAS2.1 yr overdueMahesh Vithalrao Labhshetwar · Golwadi Village, AurangabadP51500002341· filed Dec 2019 → now Jun 2024· 56.6% built
- Guardian Cityscapes Phase 12.1 yr overdueGuardian Homes Private Limited · Dattawadi, PuneP52100003214· 75.2% built· 4 complaints
- KRUSHNA PRIDE - 12.1 yr overdueNAMDEO GOVIND BORHADE · Pathardi Shivar, NashikP51600027619· 35.1% built
- Bhoomi Samarth B Wing2.1 yr overdueSamarth Erectors & Developers · Borivali, Mumbai SuburbanP51800026289· 50.9% built
- EXPRESS ZONE MALL2.1 yr overdueCELLO SONAL CONSTRUCTION · Andheri, Mumbai SuburbanP51800002490· 81.8% built· 3 complaints
- JIGAR CONSTRUCTION VENUS2.1 yr overduePRAFUL HARIBHAI SENJALIA · Kalyan, ThaneP51700003962· filed Mar 2019 → now Jun 2024· 90.9% built
- VIJAY ANNEX2.1 yr overdueJAY DEVELOPERS · Nashik (M Corp.), NashikP51600012034· filed Dec 2018 → now Jun 2024· 90.9% built
- SAI BABA NAGAR2.1 yr overdueSai Developers · Mahim, PalgharP99000008318· filed Dec 2019 → now Jun 2024· 46.8% built
- ZIPRYA GOVIND TOWER2.1 yr overdueShivshkati Builders and Developers · Near Kopar Railway Station, ThaneP51700027822· filed Jun 2023 → now Jun 2024· 63.6% built
- ROYAL MIRAJ ARCADE2.1 yr overdueVishwas Bajirao Patil · Opp. Railway Station, KolhapurP53000002279· filed Dec 2022 → now Jun 2024· 75.9% built
- Splendid Lake view2.1 yr overdueYASHADA HOMES · PASHAN, PuneP52100021727· 90.9% built
- Swapnalok Nagari Commercial Building2.1 yr overdueSWAPNALOK DEVELOPERS · Bhor, PuneP52100017103· 81.8% built
- SPRING GARDENS PHASE - I2.1 yr overdueAchalare Realtors Private Limited · BORHADEWADI, PuneP52100026121· 90.9% built
- DEVRAJ NISSARG2.1 yr overdueDEVRAJ BUILDERS AND DEVELOPERS · Baramati (M Cl), PuneP52100010031· filed Feb 2021 → now Jun 2024· 79.5% built· 1 complaint
- SAI SHILP RESIDENCY-POOJA2.1 yr overdueOM SAI BUILDCON · Nashik, NashikP51600012032· 90.9% built
- Yazarina One2.1 yr overdueKEYSTONE REALTORS LIMITED · Ward FNorth, Mumbai CityP51900000287· 90.9% built
- KRISHNA VIHAR2.1 yr overdueKRISHNA CONSTRUCTION CO. · Zingabai Takli, NagpurP50500027765· 46.4% built
- MORYA HEIGHTS2.1 yr overdueD B REALTY · DIGHIP52100028711· 81.8% built
- SARVESHWAR CO-OP HSG SOC2.1 yr overdueDALAL BUILDSCAPE · TALUKA AMBERNATH, ThaneP51700031253· 71.8% built· 1 complaint
- MILESTONE RKD DEVELOPERS2.1 yr overdueRKD DEVELOPERS · BANER, PuneP52100030844· 75.9% built
- SUKHWANI NYSA2.1 yr overdueSUKHWANI LANDMARK · RAVET, PuneP52100026493· 81.6% built
- BLISS2.1 yr overduePRAMUKH REALTY · NR PRAMUKH VIHAR, Dadra & Nagar HaveliP49600000090· 90.9% built
- LAXMI KIRAN2.1 yr overdueKIRAN ENTERPRISES · KARJAT, RaigarhP52000027810· 54.5% built
- ISHAN SQUARE2.1 yr overdueADHIRAJBUILDERSANDDEV · RING ROAD, LaturP52400028717· 9.1% built
- ACE AVENUE2.1 yr overdueAce properties · MULUND WEST, Mumbai SuburbanP51800033494· 90.9% built
- Annapurna Avenue2.1 yr overdueANNAPURNA BUILDCON INFRA PRIVATE LIMITED · THANE, ThaneP51800000876· filed Jun 2019 → now Jun 2024· 90.9% built
- Ajit Mulund CHS2.1 yr overdueYug Developers · Mulund, Mumbai SuburbanP51800032940· filed Mar 2024 → now Jun 2024· 64% built
- SAPTASHRUNGI VANDAN2.1 yr overduePRAGATI DEVELOPERS · NEAR EKTA GREEN VALLEY, NashikP51600027711· 72.7% built
- SIYARAM PHASE II2.1 yr overdueMadhumalti Costruction Pvt Ltd · SAVEDI, AhmednagarP52200027000· 90.9% built
- PARASNATH NAGARI BUILDING NO. 12.1 yr overdueSHREE PARASNATH BUILDERS · Vasai, PalgharP99000009841· filed Jun 2018 → now Jun 2024· 80% built· 6 complaints
- SAMRUDDHI PARK2.1 yr overdueSANSKAR BUILDERS AND DEVELOPERS · PATHARDI SHIVAR NEAR PANDAVLENI, NashikP51600027831· 90.9% built
- DOSTI PLANET NORTH - PHASE 3 -DOSTI ONYX2.1 yr overdueCHALAMA INFRAPROPERTIES PRIVATE LIMITED · SHIL, ThaneP51700020162· 99.5% built
- PRIYADARSHANI CHS LIMITED2.1 yr overdueANIRUDDHA GROUP SHILPALI PROJECT · Thane, ThaneP51700016267· filed Dec 2021 → now Jun 2024· 81.8% built
- GOLDEN WINDS Building D Phase 52.1 yr overdueGOLDEN BRICKS DEVELOPERS · Opposite D Y Patil Knowledge City Off Porwal Road, PuneP52100027754· 81.8% built
- SAPPHIRE TOWERS2.1 yr overdueCHAURANG VENTURES · CHOVISAWADI, PuneP52100027242· 89.5% built
- REDEVELOPMENT OF KHATRI APARTMENTS COOPERATIVE HOUSING SOCIETY LIMITED2.1 yr overdueSRP REALTORS PRIVAYE LIMITED · Borivali, Mumbai SuburbanP51800009333· filed Dec 2019 → now Jun 2024· 90.9% built
- Swapnalok Nagari, Building No -32.1 yr overdueSWAPNALOK DEVELOPERS · Bhor, PuneP52100017102· 81.8% built
- SAPTSHRUNGI KRUPA APARTMENT2.1 yr overduePRAKASH AMBADAS DAGALE(HUF) · NARHARI NAGAR, NashikP51600025426· 90.9% built
- KASTURI2.1 yr overdueMORYA LANDMARKS · BEHIND SEASONS HOTEL NEAR CROMA MALL AUNDH, PuneP52100048116· filed Jan 2024 → now Jun 2024· 63.6% built
- Saraswati Sadan2.1 yr overdueLAKSHMI BUILDERS AND DEVELOPERS · Vile Parle East, Mumbai SuburbanP51800026655· 90.9% built
- Acharat Baug2.1 yr overdueAnkur Premises Developers LLP · Andheri, Mumbai SuburbanP51800034682· 39.1% built
- 41 EVOKE PHASE 12.1 yr overdueKRIASLA ASSOCIATES · KOHALI GAS SERVICE, PuneP52100026277· 45.2% built· 2 complaints
- MANTRA CITY 360 PHASE042.1 yr overdueMANTRA ISLAND HOMES TALEGAON LLP · TALEGAON, PuneP52100001457· filed Oct 2019 → now Jul 2024· 90.9% built· 5 complaints
- atlantis2.1 yr overdueZASH CONSTRUCTIONS · Mamdapur, RaigarhP52000006994· 90.9% built
- PRIDE2.1 yr overdueMOHIT DILIP KHIVASARA · ICCHAMANI COLONY, NASIK, NashikP51600033498· 72.7% built
- Prem Belaire2.1 yr overdueM/s Aryan Infra · Kurla, Mumbai SuburbanP51800003675· filed Feb 2019 → now Jul 2024· 90.8% built· 1 complaint
- AABIEL HEIGHTS2.1 yr overdueDAICHI INFRA LLP · Meera Hospital, ThaneP51700006603· filed Aug 2022 → now Jul 2024· 90.9% built
- V M RESIDENCY2.1 yr overdueV M DEVELOPERS · PLOT NO 25/1, CTS NO 1665 AND 1668. S NO 54/2 AND 57/2, RaigarhP52000029118· 86.8% built
- DEVCHHAYA2.1 yr overdueHARSHAL ENTERPRISES · RAWALPADA DAHISAR EAST, Mumbai SuburbanP51800015406· filed Mar 2024 → now Jul 2024· 90.9% built
- Vtp Cygnus- Nation R1-Tower 82.1 yr overdueAshdan Developers Private Limited · Manjri, PuneP52100007722· filed Jul 2023 → now Jul 2024· 90.9% built· 23 complaints
- LOTUS PARK2.1 yr overdueSARTHAK CONSTRUCTIONS THROUGH PROPRIETOR RAJENDRA KESHERCHAND BORA · GOVIND NAGAR, NashikP51600028602· 90.9% built
- TATHASTU2.1 yr overdueASHA DEVELOPERS · VITA, SangliP53100030808· 25.9% built
- SHYAM KUNJ2.1 yr overdueBASONS CONSTRUCTIONS · Andheri, Mumbai SuburbanP51800046209· 90.9% built
- Saarrthi Swadesh2.1 yr overdueSiddharth Properties · Mawal, PuneP52100003849· filed Sept 2018 → now Jul 2024· 90.9% built· 3 complaints
- SIDHARTH APARTMENT2.0 yr overdueNIRMITI DEVELOPERS · NEAR CHINTAMANI SOCIETY, SangliP53100051440· 81.8% built
- MANALI DWARKAPURAM2.0 yr overdueSSD BUILDERS AND DEVELOPERS · Waluj Mahnagar 1, AurangabadP51500030314· 25% built
- Anmol Nayantara City Two phase 22.0 yr overdueBafna Realtors Pvt Ltd · Karmayogi nagar, NashikP51600000215· filed Jun 2021 → now Jul 2024· 81.8% built
- Metro Life Bizz Bay2.0 yr overdueRAMA SYNERGY SPACES · Next to Indira College of Commerce and Science, PuneP52100022156· filed Jul 2023 → now Jul 2024· 90.9% built· 2 complaints
- TRIDENT2.0 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Wakad, PuneP52100004511· filed Jul 2023 → now Jul 2024· 92.5% built· 2 complaints
- Sanghavi Paradise A Building2.0 yr overdueSanjay Walchand Sanghavi · Sanghavi Nagar, PuneP52100017993· filed Sept 2023 → now Jul 2024· 90.9% built
- VIJAY SNEH2.0 yr overdueJAYDEVELOPERS · Nashik, NashikP51600008562· filed Dec 2018 → now Jul 2024· 90.9% built
- SAIRAJ PHASE 2 WING-B2.0 yr overdueSUMAN VISHWANATH KOLHE · LAXMINAGAR, AhmednagarP52200030975· 72.7% built
- Gandharv Pearl Project I2.0 yr overdueVinayak Pandharinath Bhongale · DighiP52100046690· 79.5% built
- ALPHA 312.0 yr overduePARIKH REALTY · BEHIND VOLKSWAGEN SHOWROOM, OPP. AKASHWANI SANGLI, SangliP53100027305· filed Jun 2024 → now Jul 2024· 90.9% built
- Vidya Residency2.0 yr overdueSukhkarta Builders · Gangapur Shivar, NashikP51600030109· 90.9% built
- Shree Vaishnavi Heights2.0 yr overdueShree Vaishnavi Gold Homes · Thane, ThaneP51700006741· filed Dec 2022 → now Jul 2024· 90% built
- Anmol Oasis2.0 yr overdueM/s Ekdant Housing · Bhaskar colony, ThaneP51700023557· 90.9% built
- NALINI VASANT VIHAR2.0 yr overdueDinesh Mohanlal Jain · NIVKHOL, RatnagiriP52800026079· 90.9% built
- Vaikunth Cluster 4A2.0 yr overduePEPL Developers Pvt Ltd · Balkum, ThaneP51700005256· 85.5% built
- VIJAY ANAND2.0 yr overduePRASAD VYANKTESH KANT · GOKUL NAGARI, NashikP51600032715· 82.5% built
- AMARDEEP ALLIANCE2.0 yr overdueALLIANCE CITY DEVELOPERS REALTORS PVT LTD · St. Pius Church Mulund West, Mumbai SuburbanP51800024225· 90.9% built· 2 complaints
- Shravan Corner2.0 yr overdueSuraj Buildcon · Pimpri Chinchawad (M Corp.), PuneP52100013651· filed Oct 2018 → now Jul 2024· 60% built
- SWAPNA GANESHA APARTMENT2.0 yr overdueSWAPNAPURTI BUILDERS and DEVELOPERS · DUBERE NAKA, NashikP51600030412· 90.9% built
- Neelkanth Alpine2.0 yr overdueNeelkanth Infracon · Thane, ThaneP51700021881· 81.8% built
- Altavista - Phase 12.0 yr overdueSPENTA ENCLAVE PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800001050· filed Dec 2019 → now Jul 2024· 90.9% built· 18 complaints
- LOTUS AVENUE2.0 yr overdueMAULI DEVELOPERS · CHOVISWADI, PuneP52100022298· 81.4% built
- SAI BALAJI COMPLEX2.0 yr overdueSAI BALAJI COMPLEX · TONDLIKAR NAGAR, ThaneP51700030544· 90.9% built
- YASHVANT SRUSTI2.0 yr overdueINSTACROISSANCE LIMITED · Palghar, PalgharP99000007915· 90.9% built
- AMBER VISTA2.0 yr overdueGURUKRUPA ENTERPRISES · Kalyan, ThaneP51700000456· 90.9% built
- SHREE RENUKA SANKUL2.0 yr overdueYOGESH YASHVANT MAHAJAN · NEAR GOL NAKA, AurangabadP51500051201· 45% built
- NIDHI TOWERS2.0 yr overdueRAJAN KUMAR MANCHANDA · Andheri, Mumbai SuburbanP51800008893· filed Jul 2022 → now Jul 2024· 90.9% built· 3 complaints
- NYATI EMBRACE I2.0 yr overdueNITIN DWARKADAS NYATI · UNDRI, PuneP52100002290· 39.4% built
- Charms City A122.0 yr overdueCharms Developers · Titwala, ThaneP51700034654· 2.3% built
- LEGACY IVY2.0 yr overdueLEGACY LIFESPACES LLP · Punawale, PuneP52100029412· 77% built
- SATYAM TULIP2.0 yr overdueOMSATYAM BUILDCONS PRIVATE LIMITED · Godhani (Rly), NagpurP50500030292· 90.9% built· 3 complaints
- UPPER THANE -SERENO A12.0 yr overdueLODHA DEVELOPERS LIMITED · ., ThaneP51700020191· 81.8% built
- Sun-Srushti Greens2.0 yr overdueSRUSHTI DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100009844· filed Dec 2019 → now Aug 2024· 80% built
- PEARL RESIDENCY - WING-B, RESIDENTIAL PHASE - III2.0 yr overdueGIRIRAJ ENTERPRISES · Andheri, Mumbai SuburbanP51800006592· 52.7% built
- Eden Spaces Phase 22.0 yr overdueElysian Realty · Kiwale, PuneP52100025591· filed Jun 2023 → now Aug 2024· 86.4% built
- Kartikya Paradise - Building No.12.0 yr overdueKartikya Spaces · Karjat, RaigarhP52000017158· filed Dec 2022 → now Aug 2024· 85% built
- Pradnyaraj Buds2.0 yr overduePradnyaraj Properties · Munurwar Housing SocietyP52100024131· filed Dec 2023 → now Aug 2024· 67.7% built
- SANJEEVANI HOSPITAL2.0 yr overdueSHRADHA INFRAPROJECTS LIMITED · GOKULPETH, NagpurP50500045280· filed Mar 2024 → now Aug 2024· 81.8% built
- DEOGIRI VRINDAVAN2.0 yr overdueCITI HOMES · HARSUL, AurangabadP51500004708· 66.7% built
- DOLPHIN GARIMA2.0 yr overdueDOLPHIN VASTU · RAVET, PuneP52100030737· filed Dec 2023 → now Aug 2024· 81.8% built
- mauli plaza2.0 yr overdueMAULI ASSOCIATES · yashomangal colony, AmravatiP50300018935· 81.8% built
- NANDADEEP2.0 yr overdueM R Group · Karvanchiwadi, RatnagiriP52800008933· 38.6% built
- Aaraadhy Imperial2.0 yr overdueNirmaan Realty · Tilak Nagar, ThaneP51700047256· 41.8% built
- Shree Swami Samarth Krupa2.0 yr overdueShoreline Builders Pvt Ltd · Kurla, Mumbai SuburbanP51800018673· 19.8% built· 3 complaints
- Gayatri Complex2.0 yr overdueKanubhai Mohanbhai Lakkad · Kalyan, ThaneP51700009950· filed Dec 2019 → now Aug 2024· 81.6% built
- SHRI SHIVANAND CHS2.0 yr overdueTrimity Constructions · BHASKAR COLONY, ThaneP51700024183· filed Jun 2023 → now Aug 2024· 81.4% built· 1 complaint
- Bhakti Park2.0 yr overduePravin Haibatrao Shinde · Ambegaon, PuneP52100024924· filed Dec 2023 → now Aug 2024· 28.2% built
- MARIGOLD1.9 yr overdueSHRIJEEKRUPA REALTORS LLP · Navali Village, PalgharP99000033174· filed Jul 2024 → now Aug 2024· 78.2% built
- VENTURE CITY A AND D WING1.9 yr overdueVENTURE GROUP · DUDULGAON, PuneP52100019311· filed Dec 2022 → now Aug 2024· 90.9% built· 1 complaint
- ANANDAM WORLD CITY PART OF TOWER A B AND D1.9 yr overdueGOLDBRICKS INFRASTRUCTURE PVT LTD · Nagpur (M Corp.), NagpurP50500004568· 90.9% built· 2 complaints
- URICH MALL1.9 yr overdueSAWRABH BUILDERS · AARTI TALKIES, WardhaP50400022199· 32.7% built
- REAL DREAM HOMES WING A AND B1.9 yr overdueREAL BUILDCON BUILDERS AND DEVELOPERS · GANESH NAGAR, PuneP52100021993· 99.5% built
- SHRI JYOTIDARSHAN1.9 yr overdueDHANRAJ BABURAO PATWARI · AURANGABAD, AurangabadP51500022102· 95.5% built
- BALAJI AURA1.9 yr overdueRELIABLE REALTIES · TALOJA, RaigarhP51700003428· filed Sept 2022 → now Aug 2024· 97.7% built· 1 complaint
- SANTACRUZ ANURAG MANDIR CHSL1.9 yr overdueS M CONSTRUCTIONS · SANTACRUZ, Mumbai SuburbanP51800050095· 90.9% built· 1 complaint
- MARATHA COMMERCIAL COMPLEX1.9 yr overdueDHANLAKSHMI BUILDERS AND DEVELOPERS · RISOD NAKA, WashimP50200051851· 81.8% built
- Chaitanya Anand - Lunkhod CHSL1.9 yr overdueChaitanya Developers · Andheri West, Mumbai SuburbanP51800029553· filed May 2024 → now Aug 2024· 90.9% built
- SHUBHARAMBH1.9 yr overdueJAIKUMAR CONSTRUCTIONS LTD · PANCHAVATI ANNEX, NashikP51600030396· 85.5% built
- Supreme Elenor1.9 yr overdueSupreme Mega Constructions LLP · Kurla, Mumbai SuburbanP51800030270· 70.9% built
- OM TRIMURTI1.9 yr overdueJE AND VEE INFRASTRUCTURE · OPP OBEROI MALL, Mumbai SuburbanP51800020394· filed Dec 2023 → now Aug 2024· 85.5% built· 1 complaint
- MAKSKAP CENTRE1.9 yr overdueDILIP ESTATE & TOWN PLANNERS PVT LTD · Mumbai City, Mumbai CityP51900009030· filed Dec 2019 → now Aug 2024· 89.2% built· 2 complaints
- Kinjal Nine1.9 yr overdueHi Rock Construction Pvt Ltd · Ward E, Mumbai CityP51900004158· filed Oct 2020 → now Aug 2024· 90.9% built· 5 complaints
- GOVINDA PRIDE1.9 yr overdueRADHE DEVELOPERS · BEHIND INOX CINEMA,WADALA SHIVAR, NashikP51600031509· 57.3% built
- ACE FLORENCE1.9 yr overdueAce properties · MULUND WEST, Mumbai SuburbanP51800034518· 90.9% built
- Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade1.9 yr overduePUNE HOUSING AND AREA DEVELOPMENT BOARD · Joshiwada, PuneP52100019009· filed Jun 2022 → now Aug 2024· 86.8% built
- RISHABRAJ AGNEL1.9 yr overdueRISHABRAJ ESTATE DEVELOPERS PVT LTD · Borivali, Mumbai SuburbanP51800030530· 90.9% built
- United Athashri1.9 yr overdueTen Corner Developers LLP · Lohegaon, PuneP52100033894· filed Mar 2024 → now Aug 2024· 65.5% built
- Dixit Sneh Sankul Phase 11.9 yr overdueSahasrabudhe & Kanitkar Associates · Nene Ghat, PuneP52100032280· filed Apr 2024 → now Aug 2024· 83.9% built
- JENNY PARK1.9 yr overdueDEEPAK POPATLAL OSWAL · DHARMAPURI, SataraP52700031500· 78.2% built
- HARSH AVENUE1.9 yr overdueSHREE SWAMI BUILDCON · PANCHAK, NashikP51600048030· 38.6% built
- THE VILE PARLE MEGHALAYA CHSL1.9 yr overdueDHRUV INFRASTRUCTURE · VILE PARLE EAST, Mumbai SuburbanP51800033919· 90.9% built
- RISHABRAJ RAMESHWAR1.9 yr overdueH RISHABRAJ REALTY · Borivali, Mumbai SuburbanP51800030723· 90.9% built
- RISHABRAJ SUJAI1.9 yr overdueRISHABRAJ ESTATE DEVELOPERS PVT LTD · MALAD EAST, Mumbai SuburbanP51800031075· 90.9% built
- 52 PARK AVENUE1.9 yr overdueDAN KUTIR CHSL · Andheri, Mumbai SuburbanP51800032136· 90.9% built
- SHIVAJI SANKUL41.9 yr overdueSUBHASH DEVIDAS BHARSAKALE · AMRAVATI, AmravatiP50300010756· 26.5% built
- Legacy Celestia1.9 yr overdueLegacy Lifespaces LLP · Wakad, PuneP52100030612· 90.9% built
- SIDDHIVINAYAK1.9 yr overdueSAACHI DEVELOPERS · KUPWAD, SangliP53100047420· filed Jul 2024 → now Sept 2024· 81.8% built
- OM RESIDENCY1.9 yr overdueOM CONSTRUCTION · NEAR VINAYAK PLAZA, CHURCH ROAD, KolhapurP53000045425· 90.9% built
- Nakshatra1.9 yr overdueANGAL & CO · Nimhan Mala, PuneP52100019074· 90.9% built· 5 complaints
- AADIGURU APARTMENT1.9 yr overdueRAJENDRA BUILDERS and DEVELOPERS · MAUJE GANGAPUR SHIWAR DHRUVA NAGAR NR MOTIWALA MEDICAL COLLEGE NASHIK, NashikP51600028773· 90.9% built
- Earth Darshan1.9 yr overdueM/s. Earth Graphics · GirgaonP51900008314· filed Jun 2021 → now Sept 2024· 79.5% built
- SHIVSHAKTI HEIGHTS1.9 yr overdueNEHA BHAVANI DUBEY · ADGAON SHIWAR, NashikP51600031897· 90.9% built
- ASHWA LUXORA1.9 yr overdueASHWAMEDH PRODUCTION · Near Kankavali Depot, SindhudurgP52900000637· filed Jun 2022 → now Sept 2024· 90.9% built
- DAHISAR GULISTAN CHS1.9 yr overdueDAHISAR GULISTAN CO OPERATIVE HOUSING SOCIETY LIMITED · DAHISAR EAST, ThaneP51700006563· filed Jun 2021 → now Sept 2024· 90.7% built
- Mi Casa1.9 yr overdueMarimagnum Constructions · UNDRI, PuneP52100009650· filed Mar 2020 → now Sept 2024· 96.4% built
- INDUS ROYAL1.9 yr overdueRAJIV SURESHRAO NAIK NIMBALKAR · KOLKI, SataraP52700028696· 81.8% built
- Rustomjee Virar Avenue L1-L2 and L4 Wing K1.9 yr overdueKEYSTONE INFRASTRUCTURE PRIVATE LIMITED · Avenue L4, PalgharP99000020235· filed Sept 2023 → now Sept 2024· 50% built
- ANANT CORNER1.9 yr overdueASHAPURA DEVELOPERS · SECTOR 50, RaigarhP52000018083· filed Sept 2023 → now Sept 2024· 92.1% built
- TROVE1.9 yr overdueKALASH PROPERTIES · BANER, PuneP52100031289· filed Sept 2023 → now Sept 2024· 95.5% built
- Megapolis Saffron - A10 to A141.9 yr overduePegasus Properties Pvt. Ltd. · Rajiv Gandhi Infotech Park Phase 3, PuneP52100021609· 90.7% built
- HILL CREST1.9 yr overdueUNIVERSAL INFRA · ULHASNAGAR, ThaneP51700030982· 59.5% built
- REDEVELOPMENT OF POPULAR TERRACE CHSL1.9 yr overduePRANAV CONSTRUCTIONS LIMITED · BORIVALI WEST MUMBAI, Mumbai SuburbanP51800029351· 90.9% built
- School View Shreyas CHS Ltd1.9 yr overdueMAJESTIC ROYALE DEVELOPERS · MUMBAI, Mumbai SuburbanP51800046219· 54.5% built
- VJ IndiLife1.9 yr overdueVILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP · Pashan, PuneP52100028030· 86.8% built· 2 complaints
- REDEVELOPMENT OF GALA APARTMENTS CHSL1.9 yr overduePRANAV CONSTRUCTIONS LIMITED · MALAD EAST, Mumbai SuburbanP51800029415· 90.9% built· 1 complaint
- NYATI EVOLVE I1.9 yr overdueNYATI GEETA ASSOCIATES · MUNDHWA, PuneP52100022030· 93.5% built
- Parshuram Krupa Apartment1.9 yr overdueSukruti Constructions · Madhli Galli, Tiwanda Chowk, NashikP51600045453· filed Dec 2023 → now Sept 2024· 81.8% built
- KRISHNA HEIGHTS1.9 yr overdueSHRI SANT LAHANUJI DEVELOPERS · GANESHPETH, NagpurP50500024678· 90.9% built
- THE SILVER CREST1.9 yr overdueHI TECH ULTRA HOMES AND INFRASTRUCTURE PRIVATE LIMITED · Panvel, RaigarhP52000004729· filed Mar 2023 → now Sept 2024· 70% built
- NYATI EVOLVE II1.9 yr overdueNYATI GEETA ASSOCIATES · MUNDHWA, PuneP52100022029· 85.1% built
- PARLE NIMESH CO-OP. HSG. SOC. LTD.1.9 yr overdueCHINTAMANI COMMERCIAL VENTURES · VILE PARLE EAST, Mumbai SuburbanP51800030964· 90% built
- AIM Avenue1.9 yr overdueAIM REALTORS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800028763· 77.7% built
- Avenue Park - I1.9 yr overdueCB Enterprises · pathanwadi, Mumbai SuburbanP51800005425· filed Jun 2022 → now Sept 2024· 73.5% built· 1 complaint
- Green City 41.9 yr overdueGREEN SPACE INFRA VENTURES · Mouza Gotal Panjari, NagpurP50500025013· 97% built
- REHMAT APARTMENT1.9 yr overduePARVIN GAMIR SHAIKH · MAUJE NASHIK - 4 SHIWAR, NashikP51600031833· 90.9% built
- MOONSTONE-WING A1.9 yr overdueB. J. ENTERPRISE · Vasai, PalgharP99000018357· 39.1% built
- United Courtyard Phase 21.9 yr overdueUnited Builders · Behind INOX, NashikP51600026084· 76.4% built
- Ramanand Residency1.9 yr overduePhadke Pradeep Shridhar HUF · Vidyanagar, SangliP53100030929· 65% built
- PRISM CITY-INDIGO1.9 yr overdueSWASTIK DIAMOND REALTY · CHARHOLI, PuneP52100030026· 88.2% built
- AMAR VIJAY CHS LTD1.9 yr overdueJ.V. ENTERPRISES · STATION ROAD, ThaneP51700024853· 82.5% built
- Lodha Splendora - River View1.9 yr overdueLODHA DEVELOPERS LIMITED · BHAYANDERPADA, ThaneP51700016375· 81.8% built· 4 complaints
- VENKATESH GRAFFITI GLOVER PHASE 11.9 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAV NAGAR MUNDHWA, PuneP52100025621· 90.9% built
- SARA VATIKA1.9 yr overdueSAKAMBARI BUILDCON · NEAR PROPOSED ISKON TEMPLE, AurangabadP51500025439· 90.9% built
- Sukhwani Araya1.9 yr overdueSukhwani Associates · Rahatani, PuneP52100031415· 81.8% built
- Paramount F1.9 yr overdueKalpataru Homes Private Limited · Thane, ThaneP51700050624· 72.5% built
- AAKANKSHA RESIDENCY1.9 yr overdueSHARVIN BUILDERS LLP · KATRAJ, PuneP52100033307· filed Dec 2023 → now Sept 2024· 58.2% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.