RERA projects past their possession deadline
11,770 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 57 of 59
- ACHARYA ASHRAM SAHAKARI GRIHA RACHANA SANSTHA MARYADIT4 mo overdueVASTU DARSHAN DEVELOPERS LLP · OPP DON BOSCO SCHOOL, VAZIRA, BORIVALI WEST, Mumbai SuburbanP51800027379· filed Oct 2023 → now Mar 2026· 90.9% built
- ATHARVA NEST4 mo overdueATHARVA ENGINEERS AND DEVELOPERS · E WARD, KolhapurP53000045232· 90.9% built
- Sunrise Apartment4 mo overduePurushottam Naran Patel · Mane Nagar, NashikP51600047549· 81.8% built
- Kalpataru Magnus4 mo overdueKalpataru Properties Pvt. Ltd. · Andheri, Mumbai SuburbanP51800004029· filed Jun 2024 → now Mar 2026· 83.9% built· 64 complaints
- Supreme Villagio II4 mo overdueTurquoise Housing LLP · Somatne, PuneP52100049506· 53.9% built
- PHOENIX4 mo overdueNEMINATH CORP · Borivali, Mumbai SuburbanP51800029237· filed Mar 2025 → now Mar 2026· 90.9% built
- EMPIRE TOWERS4 mo overdueLAKHANI REALTY LLP · Naupada Thane, ThaneP51700005215· filed Jul 2024 → now Mar 2026· 38.2% built· 1 complaint
- ROYAL HEIGHTS4 mo overdueUTTAM MAROTRAO KHADGI · MOUZA BORGAON, NagpurP50500051087· 89.4% built
- LEO GALAXY-044 mo overdueMahendra Rishabhchand Jain · BORGAON, NagpurP50500048415· 90.9% built
- UMIYA VIJAY APARTMENT4 mo overdueIMPERIAL REALTY · NEAR BALI MANDIR, PANCHAVATI, NashikP51600047270· 49.1% built
- ATHARVED-III4 mo overdueAIR DEVELOPERS · DIXIT NAGAR NARI-56/1, NagpurP50500054313· 72.7% built
- Sukoon Heights4 mo overdueVIRANI CONSTRUCTION COMPANY · Thane, ThaneP51700004837· 97% built
- 24 HIGH4 mo overdueDREAM APEX REALTIES LIMITED · OPP DY PATIL STADIUM, ThaneP51700025150· 60.9% built· 1 complaint
- Mahalakshmi Heights4 mo overdueParth Infra · Mustafabad, AurangabadP51500028095· 63.6% built
- DEVGIRI ROW BUNGALOWS4 mo overduePERFECT BUILDERS AND DEVELOPERS · -, SataraP52700080506· 89.5% built
- JANKI LEGACY4 mo overdueMihir Nandkumar papaiya · Mira Road East, ThaneP51700020239· 42.7% built
- Euphoria Pride Building A West Side3 mo overdueSwastik Vastu Private Limited · North Shivaji Nagar, SangliP53100047641· filed Jul 2025 → now Apr 2026· 81.8% built· 2 complaints
- The crown3 mo overdueElite Associates · Kurla, Mumbai SuburbanP51800048225· 86.8% built
- Signature3 mo overdueSignature · Kurla, Mumbai SuburbanP51800052112· 61.2% built
- Snehsagar Apartment3 mo overdueSagar Mahadev Jarad · Shirwal, Shirke Colony, SataraP52700045366· 90.9% built
- Shreenath Residency3 mo overdueChandrakant Gulab Jamdade · Jamdade Estate, PuneP52100052917· filed May 2025 → now Apr 2026· 81.8% built
- NAV CHETNA3 mo overdueForishna Developers LLP · Andheri, Mumbai SuburbanP51800048061· 42.7% built
- SEAPLAZA3 mo overdueSEAPLAZA · Kurla, Mumbai SuburbanP51800054646· 45.5% built· 1 complaint
- ROONGTA FUTUREX APARTMENT3 mo overdueROONGTA LANDMARKS LLP · NASHIK, NashikP51600029167· 81.8% built· 18 complaints
- GANGA DHAM TOWER B..3 mo overdueLegends County Landmark Pvt Ltd · Pune City, PuneP52100000212· 60% built
- ALPINE ASTONIA3 mo overdueALPINE LANDMARKS LLP · Mawal, PuneP52100047595· 80.9% built
- 42 EAST PARK3 mo overdueMADHUPURI HOMES · Mumbai City, Mumbai CityP51900048224· 97.3% built
- LA VISTA3 mo overdueDARSHANRAJ REALITY · BHOSALE NAGAR, SHIVAJI NAGAR, PuneP52100052539· 78.2% built
- GLOBE BUSINESS SQUARE3 mo overdueGLOBE REALTY · Kalyan, ThaneP51700020338· 72.7% built
- GANGA DHAM TOWER A..3 mo overdueLegends County Landmark Pvt Ltd · Pune City, PuneP52100000393· 69.7% built· 5 complaints
- SHUBH LABH HEIGHTS3 mo overdueBhuvi Landmarks LLP · GARKHEDA, AurangabadP51500026771· 72.7% built
- KUSH AVENUEE3 mo overdueKUSH AVENUEE · Kurla, Mumbai SuburbanP51800052873· 68.2% built
- YASHOMATI CHSL3 mo overdueSAMRAT ENTERPRISE · Kurla, Mumbai SuburbanP51800023057· filed Dec 2022 → now Apr 2026· 92.3% built
- MITHILA RESIDENCY3 mo overdueSHREEYASH ASSOCIATES · Plot No 3, Gat No 187/2/A, Jalochi, Baramati, PuneP52100051051· 79.1% built
- YASH SHRINE3 mo overdueYASHWANT SAMPATRAJ GANDHI · Borivali, Mumbai SuburbanP51800027389· 9.1% built
- Usha Enclave3 mo overdueKalash Developers · Mangalmurti Colony, Sangli, SangliP53100050076· filed Dec 2025 → now Apr 2026· 62.3% built
- VILLA 793 mo overdueMehta Jaising Builders LLP · Andheri, Mumbai SuburbanP51800052707· 63.6% built
- KUKREJA GARDENS WING B3 mo overdueTOLARAM AND CO · Kurla, Mumbai SuburbanP51800021344· 32.5% built· 1 complaint
- ATLANTA SQUARE3 mo overdueUTTAM ASSOCIATE · Mawal, PuneP52100054714· filed Dec 2025 → now Apr 2026· 78.2% built
- NAVRANG NAVKAR3 mo overdueOXFORD NAVRANG REALTY LLP · Borivali, Mumbai SuburbanP51800047342· filed Oct 2025 → now Apr 2026· 81.8% built
- Sai Kuteer3 mo overdueShree Mahalaxmi Enterprises · Vasai, PalgharP99000020537· filed Apr 2025 → now Apr 2026· 96.8% built
- Indira3 mo overdueSugee Developers Pvt. Ltd. · Shivaji Park, Dadar, Mumbai CityP51900048976· 50.9% built
- A.N. HEIGHTS3 mo overdueH SQUARE BUILDERS · Borivali, Mumbai SuburbanP51800005739· filed Jun 2021 → now Apr 2026· 90.5% built· 2 complaints
- Vanu Heights3 mo overdueVanu Developers Private Limited · Ward FNorth, Mumbai CityP51900023322· filed Dec 2025 → now Apr 2026· 95% built
- PITTIE PARADISE3 mo overdueVICTORIA ENTERPRISES LIMITED · Mumbai City, Mumbai CityP51900033030· 68.7% built
- PALAASH OAK PRIME3 mo overdueBhakti Sagar Developers · -, PuneP52100047171· filed Dec 2025 → now Apr 2026· 90.9% built
- NIRMAN ADI3 mo overdueNIRMAN DEVELOPERS · Pune City, PuneP52100051655· 59.1% built· 1 complaint
- Saraswati Niwas3 mo overdueSugee Twenty Three Developers LLP · Ward GNorth, Mumbai CityP51900048130· 81.8% built
- Trupti Park3 mo overdueDhanraj Baburao Patwari · Aurangabad, AurangabadP51500046390· 77.7% built
- GIRDHARI HEIGHTS3 mo overdueSHREE KRISHNA DEVELOPERS · Vasai, PalgharP99000029298· filed Dec 2024 → now Apr 2026· 80.5% built
- YashONE Eternitee Phase 13 mo overdueVilas Javdekar Infinitee Developers Pvt. Ltd. · Maan, PuneP52100046122· 89.5% built· 1 complaint
- Rite Amor3 mo overdueRite Pragati Developers · Mumbai, Mumbai SuburbanP51800034921· filed Aug 2023 → now Apr 2026· 80.9% built
- Navlabh3 mo overdueBorivali, Mumbai SuburbanP51800034406· filed Sept 2025 → now Apr 2026· 71.8% built
- Gangawas3 mo overdueArchway Estates DB Gangawas LLP · Erandawane, PuneP52100034138· filed Dec 2024 → now Apr 2026· 80.8% built
- RAY3 mo overdueManish Builders & Developers · Borivali, Mumbai SuburbanP51800031492· filed Oct 2025 → now Apr 2026· 81.1% built· 1 complaint
- J.K. PRIDE3 mo overdueJ.K.INFRACON · PUSHPAK NODE, RaigarhP52000051271· 80.7% built
- MY HOME KIWALE3 mo overdueRAVET LAND DEVELOPERS LLP · KIWALE, PuneP52100026833· 63.6% built· 3 complaints
- SWOJAS ADVAIT3 mo overdueSWOJAS REALTORS LLP · Pune City, PuneP52100045710· filed Oct 2025 → now Apr 2026· 81.8% built
- HOLIDAY MAIYAAN KARJAT3 mo overdueB QUBES · Karjat, RaigarhP52000000477· filed Apr 2019 → now Apr 2026· 72.7% built
- Bluegrass Residences Tower II3 mo overdueSagitarius Ecospaces LLP · Pune City, PuneP52100024441· 81.8% built
- SDPL Om3 mo overdueSANDEEP DWELLERS PVT. LTD. · Small Factory Area, NagpurP50500026827· 93.2% built
- YOGI NIWAS3 mo overdueELITE INFRASTRUCTURE · AMBERNATH, ThaneP51700015565· 1.8% built
- Ventures ALTA MONTE3 mo overdueVENTURES KUBER REALITY LLP · Andheri, Mumbai SuburbanP51800007794· filed Dec 2018 → now May 2026· 47.5% built
- Jeevan Anand3 mo overdueReal Buildcon · Mhasrul, NashikP51600045594· 81.8% built
- SAI WORLD LEGEND3 mo overdueParadise Lifestyles Private Limited · Ulhasnagar, ThaneP51700025002· 45.8% built
- VRUNDAVAN CITY PHASE-2A3 mo overdueKalyani Associates · AGASHIVNAGAR, SataraP52700054596· 9.1% built
- 24 ELEMENTS3 mo overdueS.P. BUILDERS AND DEVELOPERS · Ambegaon, PuneP52100052370· 71.8% built
- Terraform K - Residences3 mo overdueMoney Magnum Constructions · Thane, ThaneP51700002673· filed Sept 2023 → now May 2026· 90.9% built
- BHAGIRATHI HEIGHTS3 mo overdueGAURAV VISHVANATH AWATI · AGARKAR MALA, AhmednagarP52200076748· 90.9% built
- ALI TOWER3 mo overdueALAMDAR INFRASTRUCTURE PVT LTD · Ward ABCD, Mumbai CityP51900028809· 65% built
- SAHYADRI PRIDE3 mo overdueSAHYADRI DEVELOPERS · KUPWAD ROAD, SangliP53100020127· 97.7% built
- PadmaVishwa BusinessHub2 mo overdueSiddhi Construction · Adwait Colony, NashikP51600027405· 90.9% built
- GOODWILL CO OPERATIVE HOUSING SOCIETY LTD2 mo overdueTRIMURTI BUILDCON BUILDERS AND DEVELOPERS · Mumbai, Mumbai SuburbanP51800049604· filed May 2025 → now May 2026· 71.8% built
- Godrej Green Vistas2 mo overdueMahalunge Township Developers Private Limited · Mahalunge, PuneP52100028117· filed Jun 2025 → now May 2026· 79.7% built· 14 complaints
- Garnet Paladium2 mo overdueGarnet Construction Limited · Andheri, Mumbai SuburbanP51800005369· filed Dec 2018 → now May 2026· 90.9% built· 2 complaints
- Sigma Pearl2 mo overdueAshapura Shelters Private Limited · Andheri, Mumbai SuburbanP51800050197· filed May 2025 → now May 2026· 90.9% built
- ONELLA TOWER2 mo overdueSAHARA CONSTRUCTIONS · Haveli, PuneP52100029869· filed May 2024 → now May 2026· 90.9% built· 1 complaint
- ISHWAR NEW AMIT2 mo overdueISHWAR DEVELOPERS · VADAVALI, ThaneP51700050877· filed May 2025 → now May 2026· 81.4% built
- Central Park Residences C12 mo overdueSRI KALPATRU REALTY PVT. LTD. · Borhadewadi, PuneP52100054901· 72.7% built
- SHUBHARAMBH PARADISE2 mo overdueM/s Shubharambh Realty · Panvel, RaigarhP52000028587· 43.2% built
- Phase 12 mo overduePhase 1 · Sudhagad, RaigarhP52000017655· 4.5% built· 4 complaints
- JUBILATE COUNTY2 mo overdueJUBILATE COUNTY · Mulshi, PuneP52100027501· 28.2% built· 7 complaints
- HIRANI VILLA2 mo overdueAMI INFRA PROJECTS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800026708· filed Mar 2023 → now May 2026· 90.9% built· 1 complaint
- ISHWAR SARASWATI PALACE2 mo overdueISHWAR REALITY · KANSAI, ThaneP51700051501· filed May 2025 → now May 2026· 72.3% built
- Vardhan Royale2 mo overdueVardhan Associates · Borivali, Mumbai SuburbanP51800024821· filed May 2024 → now May 2026· 90.9% built
- VAISHNAVI CITY PHASE 2 SECTOR 22 mo overdueVAISHNAVI CITY PHASE 2 SECTOR 2 · Haveli, PuneP52100076657· 81.2% built
- HANISHA RESIDENCY2 mo overdueGURUDARSHAN REALTORS · RAMWADI PEN, RaigarhP52000046792· 90.9% built
- AARAMBH2 mo overdueR M S Developers · Haveli, PuneP52100050419· filed Dec 2024 → now May 2026· 54.5% built
- Pote Solitaire2 mo overdueVishwas Gajanan Pote · Panvel, RaigarhP52000051249· 80% built
- Celestial City Phase II Building I, J, K2 mo overdueRAMA SYNERGY SPACES · Haveli, PuneP52100028977· filed Jun 2024 → now May 2026· 99.9% built
- Chandraprabha2 mo overdueManisha Supreme Realty LLP · Kurla, Mumbai SuburbanP51800048875· 87.3% built
- Mangal Varsha2 mo overdueMangal Varsha · Andheri, Mumbai SuburbanP51800054491· 58.2% built· 1 complaint
- Navkamal Pushpa CHS2 mo overdueDream Realtors · Naupada, Thane West, ThaneP51700056041· 27.3% built
- VRINDAVAN2 mo overdueSHIVRAJ DEVELOPERS · Kalyan, ThaneP51700020946· filed Jul 2024 → now May 2026· 86.4% built
- Riverside2 mo overdueShristhi Developers · Koyanavele Panvel, RaigarhP52000045602· 75.9% built· 3 complaints
- METRO CORNER2 mo overdueMOHD ARIF ABDUL LATIF PATEL · TALOJA PHASE 1, RaigarhP52000052919· 81.4% built
- BLOSSOM GARDEN2 mo overdueM S ASSOCIATES · Haveli, PuneP52100008745· filed Jun 2019 → now May 2026· 12.7% built· 1 complaint
- Sadanand Condominium2 mo overdueRajendra balakrushna Chaphalkar · Pune City, PuneP52100048959· filed Mar 2025 → now May 2026· 60.5% built
- INFINITY PLANET E WING2 mo overdueTULIP PROPERTIES · Haveli, PuneP52100034091· filed Dec 2025 → now May 2026· 90.9% built
- WESTWINDS Wing A2 mo overdueShreeram Sankalp Associates · Haveli, PuneP52100005189· filed Dec 2021 → now May 2026· 67.3% built
- UMA KUNJ COOPERATIVE HOUSING SOCIETY LIMITED2 mo overduePravin Arvind Apte · Badlapur, ThaneP51700033015· filed Dec 2025 → now May 2026· 90.9% built
- Sai Ganesh Co-Operative Housing Society Ltd2 mo overdueShree Vyankatesh Enterprises · Dombivli West, ThaneP51700051405· 59.1% built
- JASMIN PARADISE2 mo overdueJASMIN DEVELOPERS · PALGHAR, PalgharP99000051425· filed May 2025 → now May 2026· 77.7% built
- Skyi Manas Lake Phase VIII2 mo overdueEnerrgia Skyi Ventures LLP · Mulshi, PuneP52100052033· 48.1% built
- BHOSALE EMPIRE2 mo overdueBHOSALE DEVELOPERS · DINANATH CHOWK, SangliP53100053023· 70.9% built
- Wadhwa 723 Avenue2 mo overdueHarshvardhan Constructions · Andheri, Mumbai SuburbanP51800050698· 27.7% built
- BORIVALI VEER DHAVAL2 mo overdueSHREE DURGA VASTU MAKERS LLP · Borivali, Mumbai SuburbanP51800034441· filed May 2024 → now May 2026· 90.9% built
- Akruti Co-operative Housing Society Limited2 mo overdueSPITI CONSTRUCTION PRIVATE LIMITED · Nashik, NashikP51600052998· 73.6% built
- Arunya A Wing2 mo overdueGM Buildcon · Haveli, PuneP52100027329· filed Jun 2024 → now May 2026· 79.1% built
- MIDAS-BHAKTI MEADOWS2 mo overdueIRENE EDWYN DMELLO · Kurla, Mumbai SuburbanP51800013457· filed Jun 2019 → now May 2026· 76.4% built· 19 complaints
- Vaastu Shreya2 mo overdueVaastu Shreya · Andheri, Mumbai SuburbanP51800077215· 51.8% built
- SHRIHARI DARSHAN2 mo overdueMANGALMURTI DEVELOPERS · Vasai, PalgharP99000028981· filed Dec 2024 → now May 2026· 90.9% built
- Amaresha2 mo overdueInconel Developers & Builders Private Limited · Ward GNorth, Mumbai CityP51900046922· 10.9% built
- EMERALD HEIGHTS2 mo overdueM/S. RIDDHISIDDHI DEVELOPERS · Mawal, PuneP52100076755· 67.3% built
- INFINITY CUBE2 mo overdueSNEHMANGAL TULIP DEVELOPERS · Mulshi, PuneP52100029887· filed Mar 2024 → now May 2026· 90.9% built
- GOKUL GRAND - 1, 2 & 32 mo overdueGOKUL GRAND - 1, 2 & 3 · Palghar, PalgharP99000006400· filed Dec 2019 → now May 2026· 75.9% built· 1 complaint
- SAFAL TRADEMARK2 mo overdueJAI MATA DI HOME CONSTRUCTION PVT LTD · Kurla, Mumbai SuburbanP51800003754· filed Dec 2023 → now May 2026· 85.5% built· 34 complaints
- CONTENDRE ENCLAVE2 mo overdueCONTENDRE ENCLAVE · Kurla, Mumbai SuburbanP51800053218· 72.7% built
- THE SIGNET2 mo overdueKRISHNA POOJA BUILDCON · GAIKWAD NAGAR, NashikP51600029475· 49.1% built
- Saibaba Complex2 mo overdueKESHAV PREMLAL CHINDHALORE (HUF) · Tumsar, BhandaraP50600052219· 72.7% built
- MANRAJ VIEW2 mo overdueEkta Developers · Kurla, Mumbai SuburbanP51800011821· filed Jun 2021 → now May 2026· 40.9% built
- RAGHAV HEALTH STAR2 mo overdueCONCRETE DEVELOPERS · RAMDASPETH, NagpurP50500051632· 54.1% built
- VARAD VINAYAK2 mo overdueVIRAT AND SANSKAR GROUP · PUSHPAK NODE, NAVI MUMBAI, PANVEL, RaigarhP52000056210· 61.8% built
- SHANTAI CLASSIC2 mo overdueSHANTAI GROUP · Haveli, PuneP52100023007· filed Dec 2024 → now Jun 2026· 70.8% built
- TULSI NIRVANA APARTMENT2 mo overdueTULSI CONSTRUCTION · NASHIK, NashikP51600034546· 68.2% built
- Nilay2 mo overdueANGAL & CO · Shivajinagar (Bhamburda), PuneP52100052245· 63.2% built
- ABHISHEK CO OPERATIVE HOUSING SOCIETY LIMITED2 mo overdueFORTUNE DEVELOPERS · Pune City, PuneP52100053895· 81.8% built
- SEVEN HILLS2 mo overdueSHRI HARIPRIYA BUILDERS AND DEVELOPERS LLP · NEMINATHNAGAR, SangliP53100027570· 90.9% built
- VATIKA SUDARSAN2 mo overdueVATIKA SUDARSAN · Andheri, Mumbai SuburbanP51800056335· 81.8% built
- Paradise - B2 and B32 mo overdueKEVIN PROPERTIES · Haveli, PuneP52100049914· 79.5% built· 1 complaint
- YOGESHWAR VANDAN2 mo overdueYOGESHWAR PROPERTIES · Nashik Road, NashikP51600004876· 90.9% built
- CHARKOP JEEVAN MANGAL C.H.S. LTD2 mo overdueSANDHYA KSHITIJ BUILDERS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800034943· filed Oct 2024 → now Jun 2026· 90.9% built
- Navkar Suchit2 mo overdueFOUR PILLARS · Chinchwad Gaon, Pune, PuneP52100053413· filed Dec 2025 → now Jun 2026· 45.9% built
- Royal Plaza2 mo overdueRoyal Group · Taloja, RaigarhP52000052277· 76.2% built
- PRIME PRESTIGE2 mo overduePRIME CONSTRUCTION · Junnar, PuneP52100052709· 81.8% built
- SHREE GOVIND KRUPA2 mo overdueMAMTORA FOUNDATION · Borivali, Mumbai SuburbanP51800046222· filed Dec 2024 → now Jun 2026· 81.8% built
- SPLENDOUR COUNTY WAGHOLI2 mo overduePS DEVELOPERS · Haveli, PuneP52100021548· filed Jun 2024 → now Jun 2026· 86.4% built· 1 complaint
- AJANTA COMPLEX2 mo overdueKAVITA RAMCHANDRA PAWAR · DATTANAGAR, SangliP53100048987· filed Jun 2025 → now Jun 2026· 80% built
- AKASH CHSL1 mo overdueAKASH CHSL · Borivali, Mumbai SuburbanP51800077950· 48.2% built
- SARVODAY AANAND1 mo overdueOM SAI LAND DEVELOPERS · Kalyan, ThaneP51700000725· filed Dec 2020 → now Jun 2026· 56.8% built
- RAM KANTA APARTMENTS1 mo overduePHADTARE BUILDCON · Haveli, PuneP52100048674· filed Jun 2025 → now Jun 2026· 62.3% built
- PRISMA HOMES1 mo overdueprisma realty pvt ltd · Haveli, PuneP52100046647· filed Jun 2025 → now Jun 2026· 75.5% built
- VIVA CITY - A41 mo overdueVIVA WINNER VENTURE RELATORS LLP · Vasai, PalgharP99000003476· filed Jun 2022 → now Jun 2026· 73% built· 5 complaints
- Phase VI - Buildings O1 and P11 mo overduePhase VI - Buildings O1 and P1 · Khed, PuneP52100012061· filed Dec 2019 → now Jun 2026· 27.7% built
- SHRADHA RESIDENCY1 mo overdueKONARK SHRADHA REALTORS · Andheri, Mumbai SuburbanP51800027190· filed Jun 2023 → now Jun 2026· 57.7% built
- Chandrasmit1 mo overdueMetricon Builders Private Limited · Pune City, PuneP52100047222· filed Jun 2025 → now Jun 2026· 64.1% built
- SUN SUMIT JEEVAN MANGAL1 mo overdueSUN SUMIT VENTURE · Borivali, Mumbai SuburbanP51800046062· filed Jun 2025 → now Jun 2026· 81.8% built
- SARA SWAPNODAY1 mo overdueJagrutsara Structures LLP · Khed, PuneP52100029638· filed Jun 2025 → now Jun 2026· 90.9% built
- VERDANT1 mo overdueVERDANT · Andheri, Mumbai SuburbanP51800054425· filed Jun 2025 → now Jun 2026· 51.8% built
- VTP ALTAIR1 mo overdueIntegrated Business Ecosystem Private Limited · Haveli, PuneP52100030521· filed Jun 2025 → now Jun 2026· 94.2% built· 30 complaints
- Prime Avenue1 mo overdueM/s Prasad Developers · Haveli, PuneP52100047879· filed Jun 2025 → now Jun 2026· 81.8% built
- Royal Fantasy Phase III1 mo overdueRoyal Fantasy Constructions Private Limited · Andheri, Mumbai SuburbanP51800009920· filed Dec 2019 → now Jun 2026· 65.3% built
- ARCADIA1 mo overdueACME SAWANT VENTURES · Haveli, PuneP52100013508· filed Dec 2022 → now Jun 2026· 49.8% built· 2 complaints
- NB TOWERS1 mo overdueSHEKHAR INFRATECH · NEAR TULSI LANDMARK, PuneP52100052677· 79.8% built
- SWAMIPUSHPA1 mo overdueNUTAN DEVELOPPERS · Pune City, PuneP52100034641· filed Sept 2025 → now Jun 2026· 70.5% built
- Aarambh - C1 mo overdueM/s. Annapurna Lifespaces LLP · Thane, ThaneP51700000940· 90.9% built
- Nakshatra i-Land Phase 41 mo overdueEllora Homemakers Pvt. Ltd. · Haveli, PuneP52100046743· 23.6% built
- ENSO SANZA1 mo overdueSai Aastha Developers · Borivali, Mumbai SuburbanP51800013955· filed Dec 2023 → now Jun 2026· 82.5% built· 31 complaints
- SARA SWAPNAVIHAR1 mo overdueJagrutsara Structures LLP · Khed, PuneP52100019508· 81.5% built
- APEX GREEN WOOD1 mo overdueAPEX INFRATEC · Borivali, Mumbai SuburbanP51800047381· 72.7% built
- BHOOMI ICON1 mo overdueFORNAX REALTY · Thane, ThaneP51700026412· filed Jun 2024 → now Jun 2026· 81.8% built
- CRYSTAL PRIDE1 mo overdueCRYSTAL CONSTRUCTION COMPANY · Borivali, Mumbai SuburbanP51800009735· filed Dec 2019 → now Jun 2026· 78.6% built
- Revati1 mo overduePIONEER CONSTRUCTIONS · Haveli, PuneP52100053317· filed Dec 2025 → now Jun 2026· 80% built
- GAURI EXCELLENCY1 mo overdueM/S GAURI LAND DEVELOPERS LLP · Borivali, Mumbai SuburbanP51800004832· filed Dec 2020 → now Jun 2026· 82.8% built· 10 complaints
- VARDHAN HEIGHTS1 mo overdueVARDHAN HOUSING · Kurla, Mumbai SuburbanP51800014198· filed Dec 2022 → now Jun 2026· 58% built· 9 complaints
- PANACHE AURA1 mo overdueSHREE BHAGWATI GROUP · DUDULGAON, PuneP52100052013· filed Dec 2025 → now Jun 2026· 81.8% built
- Majestique Towers East Phase 31 mo overdueM/s. Sharad Shree Enterprises, Sachin Date, Jayshree Date · Haveli, PuneP52100028815· 65% built
- SHASHWAT PARK Z-5 A and B WING APARTMENT1 mo overdueSHASHWAT HOMES · BADLAPUR WEST, ThaneP51700050263· filed Jun 2025 → now Jun 2026· 90.9% built
- JADE AVENUE-Residential Wing1 mo overdueJAIRAJHAPPYHOMES · Mumbai City, Mumbai CityP51900033215· 89.7% built
- SHREE DATTATRAYA SAHANIWAS1 mo overdueRaghukul Integrity Constructions LLP · Shivaji Nagar, NagpurP50500031956· 85.5% built
- Gayatri Heights1 mo overdueGayatri Properties · Andheri, Mumbai SuburbanP51800049323· 90.2% built
- Eon One1 mo overdueFirstlight Properties Private Limited · Ward GNorth, Mumbai CityP51900011726· filed Dec 2023 → now Jun 2026· 93.8% built· 1 complaint
- A.R VINTAGE1 mo overdueA.R ASSOCIATES · Mumbai City, Mumbai CityP51900007503· filed May 2022 → now Jun 2026· 81.8% built
- Om Gopal - Floor 3 to 91 mo overdueOmkar Realtors and Developers Private Limited · Ward GNorth, Mumbai CityP51900012360· filed Dec 2020 → now Jun 2026· 90.9% built· 7 complaints
- GHATKOPAR AVENUE AARADHYA ONE EARTH I PHASE V1 mo overdueMAN REALTORS AND HOLDINGS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800027922· 63.6% built
- RUKHMINI HEIGHTS1 mo overdueSPRING SHELTERS · Pachora (M Cl), JalgaonP49900011699· 72.7% built
- TULSI POOJA1 mo overdueSHREE SAMARTH BUILDCOM · Uran, RaigarhP52000005441· filed Jun 2021 → now Jun 2026· 90.9% built
- Abundanttiafull - By Bholas1 mo overdueSandeep Dalchand Jain · Borivali, Mumbai SuburbanP51800052704· 67.7% built
- CITY PLAZA1 mo overdueBharat Builders and Developers · CHAKAN, PuneP52100023832· 90.9% built
- D SOLITAIRE1 mo overdueKRISHNAN AND KAMAL ASSOCIATES · Borivali, Mumbai SuburbanP51800031850· filed Mar 2023 → now Jun 2026· 64.7% built
- Asya1 mo overdueMOIRA SPACES OPC PRIVATE LIMITED · Pune City, PuneP52100066499· filed Dec 2025 → now Jun 2026· 64.2% built
- SONIGARA SUNVIEW1 mo overdueSONIGARA SUNVIEW · Haveli, PuneP52100079565· 72.7% built
- TULSI CHAMBER PHASE II1 mo overdueSURANA CONSTRUCTION (CHEMBUR ) · Kurla, Mumbai SuburbanP51800027210· filed Jun 2024 → now Jun 2026· 85.9% built
- Unique Youtopia Phase II1 mo overdueUnique Associates · Haveli, PuneP52100046003· 90.9% built
- EMERALD TOWERS1 mo overdueSamruddhi Developers · Haveli, PuneP52100032827· filed Jun 2025 → now Jun 2026· 99.1% built
- THAPAR LE PARC1 mo overdueTHAPAR LE PARC · Kurla, Mumbai SuburbanP51800052495· 81.8% built
- ARV Newtown Phase III1 mo overdueVedant Infracon · Haveli, PuneP52100027214· 90.3% built· 1 complaint
- MINT1 mo overdueMINT · Andheri, Mumbai SuburbanP51800053816· 90.9% built
- ALAG ANANTA1 mo overdueAlag Square LLP · Kurla, Mumbai SuburbanP51800045309· filed Sept 2024 → now Jun 2026· 90.9% built
- Sunrise Tower1 mo overdueAkshay Vinod Tatiya And Pratik Prakash Badgujar · Nashik, NashikP51600045705· filed Dec 2025 → now Jun 2026· 72.7% built
- SKY GARDENS1 mo overdueAPK LANDMARKS LLP · Haveli, PuneP52100016753· filed Dec 2024 → now Jun 2026· 75.9% built· 3 complaints
- MARVEL ISOLA J BUILDING1 mo overdueMARVEL LANDMARKS PVT LTD · Haveli, PuneP52100001843· filed Jun 2021 → now Jun 2026· 78.6% built· 40 complaints
- Kohinoor Eden B61 mo overdueKGI REALTY PRIVATE LIMITED · Kalyan East, ThaneP51700052179· 57.3% built
- addressOne - Phase 61 mo overduePeninsula Land Limited · Mawal, PuneP52100018788· filed Jun 2024 → now Jun 2026· 67.3% built· 25 complaints
- Kush Pride1 mo overdueKush Housing LLP · Borivali, Mumbai SuburbanP51800033962· filed Dec 2025 → now Jun 2026· 77.4% built
- The Terraces Phase 21 mo overdueRashmi Commercial Company Limited · Balewadi, PuneP52100004039· 87.7% built
- Manan Jijai1 mo overdueRanjana Prakash Jagnade · Panvel, RaigarhP52000053367· 81.8% built
- SHUBHAM ATHENA1 mo overdueSHUBHAM ATHENA · Kurla, Mumbai SuburbanP51800054167· 38.5% built
- PRIME AURA1 mo overduePRIME GROUP · Borivali, Mumbai SuburbanP51800046359· filed Dec 2025 → now Jun 2026· 90.9% built
- SPARKLE SPLENDOR1 mo overdueSPARKLE BUILDER · SR NO.79P52100030178· 72.7% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.