RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 58 of 61
- ISHWAR SARASWATI PALACE5 mo overdueISHWAR REALITY · KANSAI, ThaneP51700051501· filed May 2025 → now May 2026· 72.3% built
- JUBILATE COUNTY5 mo overdueJUBILATE COUNTY · Mulshi, PuneP52100027501· 28.2% built
- Phase 15 mo overduePhase 1 · Sudhagad, RaigarhP52000017655· 4.5% built· 4 complaints
- HIRANI VILLA5 mo overdueAMI INFRA PROJECTS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800026708· filed Mar 2023 → now May 2026· 90.9% built· 1 complaint
- Sigma Pearl5 mo overdueAshapura Shelters Private Limited · Andheri, Mumbai SuburbanP51800050197· filed May 2025 → now May 2026· 90.9% built
- Central Park Residences C15 mo overdueSRI KALPATRU REALTY PVT. LTD. · Borhadewadi, PuneP52100054901· 72.7% built
- ISHWAR NEW AMIT5 mo overdueISHWAR DEVELOPERS · VADAVALI, ThaneP51700050877· filed May 2025 → now May 2026· 81.4% built
- Sarthi Emrald5 mo overdueSarthi Developers · Dombivli, ThaneP51700049548· filed May 2024 → now May 2026· 90.9% built
- Garnet Paladium5 mo overdueGarnet Construction Limited · Andheri, Mumbai SuburbanP51800005369· filed Dec 2018 → now May 2026· 90.9% built· 2 complaints
- Godrej Green Vistas5 mo overdueMahalunge Township Developers Private Limited · Mahalunge, PuneP52100028117· filed Jun 2025 → now May 2026· 79.7% built· 23 complaints
- ONELLA TOWER5 mo overdueSAHARA CONSTRUCTIONS · Haveli, PuneP52100029869· filed May 2024 → now May 2026· 90.9% built· 1 complaint
- HANISHA RESIDENCY5 mo overdueGURUDARSHAN REALTORS · RAMWADI PEN, RaigarhP52000046792· 90.9% built
- INFINITY PLANET E WING5 mo overdueTULIP PROPERTIES · Haveli, PuneP52100034091· filed Dec 2025 → now May 2026· 90.9% built
- AARAMBH5 mo overdueR M S Developers · Haveli, PuneP52100050419· filed Dec 2024 → now May 2026· 54.5% built
- Skyi Manas Lake Phase VIII5 mo overdueEnerrgia Skyi Ventures LLP · Mulshi, PuneP52100052033· 48.1% built
- SHRIHARI DARSHAN5 mo overdueMANGALMURTI DEVELOPERS · Vasai, PalgharP99000028981· filed Dec 2024 → now May 2026· 90.9% built
- Navkamal Pushpa CHS5 mo overdueDream Realtors · Naupada, Thane West, ThaneP51700056041· 27.3% built
- Chandraprabha5 mo overdueManisha Supreme Realty LLP · Kurla, Mumbai SuburbanP51800048875· 87.3% built
- Sai Ganesh Co-Operative Housing Society Ltd5 mo overdueShree Vyankatesh Enterprises · Dombivli West, ThaneP51700051405· 59.1% built
- RAGHAV HEALTH STAR5 mo overdueCONCRETE DEVELOPERS · RAMDASPETH, NagpurP50500051632· 54.1% built
- BHOSALE EMPIRE5 mo overdueBHOSALE DEVELOPERS · DINANATH CHOWK, SangliP53100053023· 70.9% built
- MIDAS-BHAKTI MEADOWS5 mo overdueIRENE EDWYN DMELLO · Kurla, Mumbai SuburbanP51800013457· filed Jun 2019 → now May 2026· 76.4% built· 19 complaints
- INFINITY CUBE5 mo overdueSNEHMANGAL TULIP DEVELOPERS · Mulshi, PuneP52100029887· filed Mar 2024 → now May 2026· 90.9% built
- MADHUSHREE5 mo overdueKPL BUILD CON LLP · Dhayari, PuneP52100051809· 81.8% built
- Rajas Leela5 mo overdueNakhye's Everest Estate Private Limited · Navagaon, ThaneP51700050538· 81.8% built
- METRO CORNER5 mo overdueMOHD ARIF ABDUL LATIF PATEL · TALOJA PHASE 1, RaigarhP52000052919· 81.4% built
- Pote Solitaire5 mo overdueVishwas Gajanan Pote · Panvel, RaigarhP52000051249· 80% built
- Mangeshi Royale5 mo overdueMangesh Dashrath Gaikar · Kalyan West, ThaneP51700034444· 0% built
- CONTENDRE ENCLAVE5 mo overdueCONTENDRE ENCLAVE · Kurla, Mumbai SuburbanP51800053218· 72.7% built
- JASMIN PARADISE5 mo overdueJASMIN DEVELOPERS · PALGHAR, PalgharP99000051425· filed May 2025 → now May 2026· 77.7% built
- Mangeshi Marvel5 mo overdueMangesh Dashrath Gaikar · Kalyan West, ThaneP51700034332· 63.2% built
- GOKUL GRAND - 1, 2 & 35 mo overdueGOKUL GRAND - 1, 2 & 3 · Palghar, PalgharP99000006400· filed Dec 2019 → now May 2026· 87.6% built· 1 complaint
- VRINDAVAN5 mo overdueSHIVRAJ DEVELOPERS · Kalyan, ThaneP51700020946· filed Jul 2024 → now May 2026· 86.4% built
- Arunya A Wing5 mo overdueGM Buildcon · Haveli, PuneP52100027329· filed Jun 2024 → now May 2026· 79.1% built
- UMA KUNJ COOPERATIVE HOUSING SOCIETY LIMITED5 mo overduePravin Arvind Apte · Badlapur, ThaneP51700033015· filed Dec 2025 → now May 2026· 90.9% built
- THE SIGNET5 mo overdueKRISHNA POOJA BUILDCON · GAIKWAD NAGAR, NashikP51600029475· 49.1% built
- Akruti Co-operative Housing Society Limited5 mo overdueSPITI CONSTRUCTION PRIVATE LIMITED · Nashik, NashikP51600052998· 73.6% built
- Saibaba Complex5 mo overdueKESHAV PREMLAL CHINDHALORE (HUF) · Tumsar, BhandaraP50600052219· 72.7% built
- WESTWINDS Wing A5 mo overdueShreeram Sankalp Associates · Haveli, PuneP52100005189· filed Dec 2021 → now May 2026· 67.3% built
- SAI SHARADA CHS LTD5 mo overdueM SQUARE DEVELOPERS · GANESH NAGAR, ThaneP51700051917· 75% built
- Riverside5 mo overdueShristhi Developers · Koyanavele Panvel, RaigarhP52000045602· 75.9% built
- VARAD VINAYAK5 mo overdueVIRAT AND SANSKAR GROUP · PUSHPAK NODE, NAVI MUMBAI, PANVEL, RaigarhP52000056210· 61.8% built
- TULSI NIRVANA APARTMENT5 mo overdueTULSI CONSTRUCTION · NASHIK, NashikP51600034546· 68.2% built
- Nilay5 mo overdueANGAL & CO · Shivajinagar (Bhamburda), PuneP52100052245· 63.2% built
- ABHISHEK CO OPERATIVE HOUSING SOCIETY LIMITED5 mo overdueFORTUNE DEVELOPERS · Pune City, PuneP52100053895· 68.2% built
- SEVEN HILLS5 mo overdueSHRI HARIPRIYA BUILDERS AND DEVELOPERS LLP · NEMINATHNAGAR, SangliP53100027570· 90.9% built
- YOGESHWAR VANDAN5 mo overdueYOGESHWAR PROPERTIES · Nashik Road, NashikP51600004876· 90.9% built
- CHARKOP JEEVAN MANGAL C.H.S. LTD5 mo overdueSANDHYA KSHITIJ BUILDERS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800034943· filed Oct 2024 → now Jun 2026· 90.9% built
- Royal Plaza5 mo overdueRoyal Group · Taloja, RaigarhP52000052277· 76.2% built
- SPLENDOUR COUNTY WAGHOLI5 mo overduePS DEVELOPERS · Haveli, PuneP52100021548· filed Jun 2024 → now Jun 2026· 86.4% built· 1 complaint
- SHREE GOVIND KRUPA5 mo overdueMAMTORA FOUNDATION · Borivali, Mumbai SuburbanP51800046222· filed Dec 2024 → now Jun 2026· 81.8% built
- PRIME PRESTIGE5 mo overduePRIME CONSTRUCTION · Junnar, PuneP52100052709· 81.8% built
- Navkar Suchit5 mo overdueFOUR PILLARS · Chinchwad Gaon, Pune, PuneP52100053413· filed Dec 2025 → now Jun 2026· 45.9% built
- Matrubhumi Heights5 mo overdueShree Ganesh Developers · Vadghar, Panvel, RaigarhP52000048341· 81.8% built
- AJANTA COMPLEX5 mo overdueKAVITA RAMCHANDRA PAWAR · DATTANAGAR, SangliP53100048987· filed Jun 2025 → now Jun 2026· 80% built
- Chandrasmit4 mo overdueMetricon Builders Private Limited · Pune City, PuneP52100047222· filed Jun 2025 → now Jun 2026· 64.1% built
- VTP ALTAIR4 mo overdueIntegrated Business Ecosystem Private Limited · Haveli, PuneP52100030521· filed Jun 2025 → now Jun 2026· 94.2% built· 33 complaints
- SUN SUMIT JEEVAN MANGAL4 mo overdueSUN SUMIT VENTURE · Borivali, Mumbai SuburbanP51800046062· filed Jun 2025 → now Jun 2026· 81.8% built
- Phase VI - Buildings O1 and P14 mo overduePhase VI - Buildings O1 and P1 · Khed, PuneP52100012061· filed Dec 2019 → now Jun 2026· 27.7% built
- SARA SWAPNODAY4 mo overdueJagrutsara Structures LLP · Khed, PuneP52100029638· filed Jun 2025 → now Jun 2026· 90.9% built
- GAURI EXCELLENCY NX4 mo overdueM/S GAURI LAND DEVELOPERS LLP · Borivali, Mumbai SuburbanP51800029939· filed Dec 2023 → now Jun 2026· 80.2% built· 1 complaint
- AMAIRA RESIDENCY4 mo overdueAMAIRA RESIDENCY · Andheri, Mumbai SuburbanP51800046422· 29.1% built
- Gurudeep Apartment4 mo overdueANUP BUILDCON · NASHIK ROAD, NashikP51600053395· 84.1% built
- GOMANT KUTIR CHSL4 mo overdueJBR HOUSECON LLP · Borivali, Mumbai SuburbanP51800052397· filed Dec 2025 → now Jun 2026· 81.8% built
- DPS NAKSHATRA HEIGHTS4 mo overdueDPS NAKSHATRA HEIGHTS · Borivali, Mumbai SuburbanP51800052649· 90.9% built
- DEVRAJ RESIDENCY4 mo overdueSHAMS ENTREPRISES · Malad - West, Mumbai SuburbanP51800051682· filed Jun 2024 → now Jun 2026· 89.1% built
- Vanraj Flora4 mo overdueABHIJIT VAMANRAO PATIL · Gangapur Road, NashikP51600033720· 72.7% built
- Om Gopal - Floor 3 to 94 mo overdueOmkar Realtors and Developers Private Limited · Ward GNorth, Mumbai CityP51900012360· filed Dec 2020 → now Jun 2026· 90.9% built· 9 complaints
- AVIRO4 mo overdueKrishna Vision · Haveli, PuneP52100045561· filed Jun 2025 → now Jun 2026· 90.9% built
- SARANG PILLARS BELLVIEW4 mo overdueAAGAM BUILDTECH · SECTOR 8, RaigarhP52000018499· filed Dec 2024 → now Jun 2026· 56.5% built· 1 complaint
- GAURI EXCELLENCY4 mo overdueM/S GAURI LAND DEVELOPERS LLP · Borivali, Mumbai SuburbanP51800004832· filed Dec 2020 → now Jun 2026· 82.8% built· 10 complaints
- Mangalam Breeze4 mo overdueMetro Buildcon · Dudulgoan Moshi, PuneP52100026808· 57.7% built
- ALAG ANANTA4 mo overdueAlag Square LLP · Kurla, Mumbai SuburbanP51800045309· filed Sept 2024 → now Jun 2026· 90.9% built
- NITIN ENCLAVES4 mo overdueNITIN ENCLAVES · Thane, ThaneP51700004830· filed Jun 2018 → now Jun 2026· 90.9% built· 8 complaints
- Magnolia4 mo overdueMadhumalti Costruction Pvt Ltd · savedi, AhmednagarP52200028201· 81.8% built
- GINI ARIA - PHASE 24 mo overdueGini Construction Pvt Ltd · Yevlewadi, PuneP52100054760· 81.8% built
- KESAR VALLEY4 mo overdueBANSAL RIVERVIEW · Haveli, PuneP52100027291· 87.9% built
- TRISHALA4 mo overdueRAINBOW PROPERTIES · Gultekadi, PuneP52100077604· filed Dec 2025 → now Jun 2026· 90.9% built
- GRAZIA4 mo overdueSBM SPACE REALTY LLP · KOTHRUD, PuneP52100052712· filed Dec 2025 → now Jun 2026· 80% built
- 19 DEGREE NORTH4 mo overdueARUNIS EDIFICE PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800050846· 66.8% built
- Central Tower - Tower 24 mo overdueGlider Buildcon Realtors · Mumbai City, Mumbai CityP51900016482· 90.9% built· 10 complaints
- Vista 3A4 mo overdueSamsara Fund Advisors Pvt. Ltd. · Mouza, NagpurP50500051699· 18.4% built
- SHASHWAT PARK Z-5 A and B WING APARTMENT4 mo overdueSHASHWAT HOMES · BADLAPUR WEST, ThaneP51700050263· filed Jun 2025 → now Jun 2026· 90.9% built
- Revati4 mo overduePIONEER CONSTRUCTIONS · Haveli, PuneP52100053317· filed Dec 2025 → now Jun 2026· 80% built
- Nasar Enclave Sale Building A and B Wing4 mo overdueM/s. Nasar Associates · Andheri, Mumbai SuburbanP51800028733· 81.9% built
- Sudarshan CHS Ltd4 mo overdueSUDARSHAN CO-OPERATIVE HOUSING SOCIETY LIMITED · Ghatkopar - East, Mumbai SuburbanP51800032217· 90.9% built
- NB TOWERS4 mo overdueSHEKHAR INFRATECH · NEAR TULSI LANDMARK, PuneP52100052677· 79.8% built
- CLUSTER RESIDENCY4 mo overdueCLUSTER REALITY · WAHAL, RaigarhP52000076600· filed Dec 2025 → now Jun 2026· 77.2% built
- Tatkare Mall4 mo overdueAshraf Karim Fakir · Bazarpeth, RatnagiriP52800026098· 81.8% built
- Sunrise Tower4 mo overdueAkshay Vinod Tatiya And Pratik Prakash Badgujar · Nashik, NashikP51600045705· filed Dec 2025 → now Jun 2026· 72.7% built
- GOVIND SOLITAIRE4 mo overdueSHANKH DEVELOPERS LIMITED LIABILITY PARTNERSHIP · Kurla, Mumbai SuburbanP51800030555· filed Jul 2024 → now Jun 2026· 71.8% built
- Yashwin NuovoCentro4 mo overdueVilas Javdekar Lifestyle Developers Pvt. Ltd. · Wakad, PuneP52100034523· 95.8% built· 1 complaint
- SMITA APARTMENT4 mo overdueSMITA DEVELOPERS · RUKMINI NAGAR, KolhapurP53000047738· filed Sept 2025 → now Jun 2026· 89.1% built
- AZAD RESIDENCY4 mo overdueDUDHWALA CONSTRUCTION · Byculla, Mumbai CityP51900011568· filed Dec 2025 → now Jun 2026· 99.7% built
- RAKHI TOWER PHASE 3 12TH TO 15TH FLOOR PART4 mo overdueRAKHI TOWER PHASE 3 12TH TO 15TH FLOOR PART · Borivali, Mumbai SuburbanP51800027354· 36.4% built
- FINE HEIGHTS4 mo overdueFINE HEIGHTS · Borivali, Mumbai SuburbanP51800055299· filed Dec 2025 → now Jun 2026· 70.9% built
- The Terraces Phase 24 mo overdueRashmi Commercial Company Limited · Balewadi, PuneP52100004039· 87.7% built
- Kingston Atlantis A1 and A2 Building4 mo overdueVedant Landmarks · MOHAMMADWADI, PuneP52100005525· filed Jun 2022 → now Jun 2026· 95.5% built· 25 complaints
- TULSI POOJA4 mo overdueSHREE SAMARTH BUILDCOM · Uran, RaigarhP52000005441· filed Jun 2021 → now Jun 2026· 90.9% built
- GAGAN ALLURE PHASE 24 mo overdueGAGAN ALLURE PHASE 2 · Haveli, PuneP52100027825· 47.5% built
- Neelyog Aashiyana II4 mo overdueNeelyog Construction Pvt Ltd · KANDIVALI WEST, Mumbai SuburbanP51800034106· 90.9% built
- SANGHVIS SHRI PARRSSSVA CITY 15-164 mo overdueSANGHVI PREMISES PRIVATE LIMITED · Atgaon, ThaneP51700007140· filed Dec 2019 → now Jun 2026· 16.4% built
- NEHA GALAXY4 mo overdueSHISHIR MANGEH SHIVAPURKAR · Ward GSouth, Mumbai CityP51900010851· filed May 2021 → now Jun 2026· 51.4% built· 1 complaint
- Bhavya Elite4 mo overdueNewlook Constructions Pvt. Ltd · Ward FNorth, Mumbai CityP51900027909· filed Jun 2025 → now Jun 2026· 81.8% built· 1 complaint
- BSC IT PARK4 mo overdueBansal Steel Corporation · Thane, ThaneP51700045736· filed Jun 2024 → now Jun 2026· 90.9% built
- VRINDASHREE4 mo overdueABHIJIT SHRIPAD DESHPANDE · -, KolhapurP53000049252· filed Dec 2025 → now Jun 2026· 90.9% built
- Pruthvi Pushpanjali4 mo overdueFlying Earth LLP · Andheri, Mumbai SuburbanP51800046070· 82.4% built
- Mantra Mirari Phase 24 mo overdueMANTRA RESIDENCES MUNDHWA PRIVATE LIMITED · MUNDHWA, PuneP52100032842· 99.5% built
- OSIAN ONE AND ONLY PHASE I4 mo overdueAHURA BUILDERS · MUNDHWA, PuneP52100030568· 92.7% built
- Gokul Heights4 mo overdueGokul Heights · Panvel, RaigarhP52000052367· filed Jun 2025 → now Jun 2026· 76.4% built
- NAKSHATRA RESIDENCY4 mo overdueSHREE SAIRAJ DEVELOPERS · Haveli, PuneP52100046154· filed Jun 2025 → now Jun 2026· 71.8% built
- Vraj Vatika4 mo overdueVraj Vatika · Thane, ThaneP51700025676· 36.4% built
- ISHWAR BLOSSOM4 mo overdueISHWAR LIFESPACE · KANSAI SECTION, ThaneP51700049361· filed Dec 2024 → now Jun 2026· 72.3% built
- SHREE DATTATRAYA SAHANIWAS4 mo overdueRaghukul Integrity Constructions LLP · Shivaji Nagar, NagpurP50500031956· 85.5% built
- Imperial Exotica4 mo overdueIMPERIAL DEVELOPERS · Vasai West, PalgharP99000033077· 44.5% built
- Gandharv Nagari A64 mo overdueVinayak Pandharinath Bhongale · Haveli, PuneP52100047726· filed Oct 2024 → now Jun 2026· 69.5% built
- VIDULA APARTMENTS4 mo overdueHINDUSTAN BUILDERS · Kothrud, PuneP52100076729· 73.6% built
- BASIL SERENITY4 mo overdueBASIL DEVELOPERS · CHARHOLI BK, PuneP52100051897· 89.1% built
- THAKUR SKYNEST4 mo overdueSky Homes · WAHAL, RaigarhP52000053156· filed Dec 2025 → now Jun 2026· 75% built
- Lodha Kandivali Project - Tower 34 mo overdueLodha Developers Limited · Akurli Village, Mumbai SuburbanP51800031346· filed Oct 2025 → now Jun 2026· 81.8% built
- Komal Kounteya CHSL4 mo overdueRander Bandhu Corporation LLP · Borivali, Mumbai SuburbanP51800049376· 94.5% built
- PUSHKRAJ NAKSHATRA4 mo overduePUSHKRAJ BUILDCON · Satpur, NashikP51600052964· 81.8% built
- CITY PLAZA4 mo overdueBharat Builders and Developers · CHAKAN, PuneP52100023832· 90.9% built
- 24 EAST4 mo overdueMALHAR DEVELOPERS · Thane, ThaneP51700049178· 96.4% built
- GHARKUL HEIGHT4 mo overdueANGATH PROPERTIES LLP · Kurla, Mumbai SuburbanP51800017037· filed Dec 2022 → now Jun 2026· 26.4% built· 27 complaints
- Abundanttiafull - By Bholas4 mo overdueSandeep Dalchand Jain · Borivali, Mumbai SuburbanP51800052704· 67.7% built
- ADIAMVILLE4 mo overdueM/S J.N.BUILDERS · Ahead Balaji Temple, PuneP52100025763· 72.5% built
- SAMARTH HERITAGE4 mo overdueSHAMIK PRAVIN LADKAT · Haveli, PuneP52100048999· filed Dec 2025 → now Jun 2026· 57.7% built
- MADHUSAGAR4 mo overdueSIDDHASHILA VENTURES LLP · Pune City, PuneP52100047028· filed Dec 2025 → now Jun 2026· 90.9% built
- Ruparel Iris4 mo overdueRuparel Estates India Pvt Ltd · Mumbai City, Mumbai CityP51900005988· filed Dec 2019 → now Jun 2026· 83.6% built· 8 complaints
- Blueridge-The Groves4 mo overdueNOVA DEVELOPERS PVT LTD · Hinjawadi, PuneP52100027419· 90% built
- NEBULA4 mo overdueRUBBERWALA REALTY · Mumbai City, Mumbai CityP51900010038· 96.6% built· 5 complaints
- Manan Jijai4 mo overdueRanjana Prakash Jagnade · Panvel, RaigarhP52000053367· 81.8% built
- REGENCY SAPPHIRE4 mo overdueREGENCY NIRMAN LTD · DOMBIVALI, ThaneP51700053596· 59.1% built
- GATEWAY4 mo overdueRAICHANDANI CONSTRUCTIONS PRIVATE LIMITED · Pune City, PuneP52100048395· filed Dec 2025 → now Jun 2026· 83.3% built
- ARV Newtown Phase III4 mo overdueVedant Infracon · Haveli, PuneP52100027214· 90.3% built· 1 complaint
- GURMEHARS Silver and Devi Co-operative housing society4 mo overdueGURMEHARS Silver and Devi Co-operative housing society · Haveli, PuneP52100079573· 81.8% built
- Unique Youtopia Phase II4 mo overdueUnique Associates · Haveli, PuneP52100046003· 90.9% built
- TOP TOWERS - A4 mo overdueRAGA DEVELOPERS · Mulshi, PuneP52100034929· filed Dec 2025 → now Jun 2026· 81.8% built· 1 complaint
- SDPL Aashray Godhani4 mo overdueSANDEEP DWELLERS PVT. LTD. · Godhani, NagpurP50500030259· 93.3% built
- VRAJ LIFE SPACE4 mo overdueSHREE INFRA PROJECT · MAKHAMALABAD SHIVAR PETH ROAD, NEAR APMC MARKET, NashikP51600026362· 81.8% built
- SURBHI SAMRUDHI4 mo overduePrakriti Space LLP · Haveli, PuneP52100052668· 88.7% built
- VNSVL Shubh Nirvana - Phase II4 mo overdueViman Nagar Shubh Ventures LLP · Haveli, PuneP52100050937· 95.5% built
- 172W Inclusive Housing4 mo overdueVilas Javdekar Lifestyle Developers Pvt. Ltd. · Wakad, PuneP52100049412· 68.2% built
- ASTRUM ANNEX4 mo overdueASTRUM REALITY PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800048947· filed Dec 2024 → now Jun 2026· 70% built
- Swayam4 mo overdueGala Habitats LLP · Mahim WestP51900033034· filed Dec 2025 → now Jun 2026· 90.9% built
- CELESTIA APARTMENT4 mo overdueSHRI VRINDAVAN BUILDERS & DEVELOPERS LLP · DWARKA, NashikP51600027562· 58.7% built
- BUILDING A1-SHREE KRUPA HEIGHTS4 mo overdueSHREE KRUPA BUILDERS AND DEVELOPERS · TISGAON, ThaneP51700025692· filed Jun 2022 → now Jun 2026· 90.9% built
- Sapphire4 mo overdueLayra Phoenix Realty LLP · Haveli, PuneP52100054005· filed Dec 2025 → now Jun 2026· 81.8% built
- VISHNU BLISS4 mo overdueLEGACY BUILDERS & INNOVATORS · ., ThaneP51700055630· filed Dec 2025 → now Jun 2026· 79.6% built· 1 complaint
- Nakshatra i-Land Phase 44 mo overdueEllora Homemakers Pvt. Ltd. · Haveli, PuneP52100046743· 23.6% built
- Kohinoor Eden B64 mo overdueKGI REALTY PRIVATE LIMITED · Kalyan East, ThaneP51700052179· 57.3% built
- AMARYLLIS TOWERS AND PLAZA4 mo overdueNAHAR BUILDERS LTD. · Kurla, Mumbai SuburbanP51800028801· 80.5% built
- EAGLE NEST4 mo overdueIlika Realtors · Vadgaon SheriP52100079759· 27.3% built
- Panache4 mo overdueCedrus Assets · Ghorpadi, PuneP52100010652· filed Dec 2024 → now Jun 2026· 76.1% built
- SKYWAY PARVATI4 mo overdueSKYWAY PARVATI · Haveli, PuneP52100056478· 72.7% built
- STELLA4 mo overdueKAPIL NANDKISHOR NATHANI · Hiwari, NagpurP50500047840· filed Oct 2025 → now Jun 2026· 90% built
- The Icon Phase 24 mo overdueLeading Frontier Private Limited · Dhokali, ThaneP51700028535· 88.1% built· 1 complaint
- CODENAME RARE BY RUNWAL4 mo overdueRunwal Developers Ltd · Andheri, Mumbai SuburbanP51800034594· 90.9% built
- SWAMI SAMARTH ENCLAVE4 mo overdueRK BUILDER AND DEVELOPER · ZINGABAI TAKLI, NagpurP50500049196· 78% built
- D SOLITAIRE4 mo overdueKRISHNAN AND KAMAL ASSOCIATES · Borivali, Mumbai SuburbanP51800031850· filed Mar 2023 → now Jun 2026· 64.7% built
- Panchratna Hills Phase 24 mo overduePanchratna Construction · Haveli, PuneP52100027976· filed Jun 2025 → now Jun 2026· 89.5% built
- GAURAV SAFFRON4 mo overdueRavi Developments · Thane, ThaneP51700003472· filed Dec 2022 → now Jun 2026· 69.9% built· 42 complaints
- ENSO SANZA4 mo overdueSai Aastha Developers · Borivali, Mumbai SuburbanP51800013955· filed Dec 2023 → now Jun 2026· 82.5% built· 41 complaints
- SHREE BALAJI HEIGHTS4 mo overdueSHREE BALAJI DEVELOPERS · Haveli, PuneP52100050055· filed Dec 2025 → now Jun 2026· 90.4% built
- VARADSIDDHI PLAZA4 mo overdueVARADSIDDHI ASSOCIATES · Haveli, PuneP52100052597· 81.8% built
- Aarambh - C4 mo overdueM/s. Annapurna Lifespaces LLP · Thane, ThaneP51700000940· 90.9% built· 1 complaint
- BLA BUSINESS PARK4 mo overdueBLA Developers LLP · C.T.S. No. 492/A, 492/A/1, 492/A/2, 492/A/3, 492/A/4, 492/B, Mumbai SuburbanP51800049334· filed Mar 2026 → now Jun 2026· 90.9% built
- Godrej Emerald Thane4 mo overdueGodrej Greenview Housing Private Limited · Thane, ThaneP51700000120· filed Dec 2024 → now Jun 2026· 99.6% built· 30 complaints
- Building A3 - VENICIA4 mo overdueLEENA CONSTRUCTIONS · Baner, PuneP52100046862· filed Dec 2025 → now Jun 2026· 97.3% built
- AKN ANNEXE4 mo overdueAKN ANNEXE · Andheri, Mumbai SuburbanP51800055901· filed Sept 2025 → now Jun 2026· 81.8% built
- THE EMPIRE4 mo overdueBHAVIK & SARAF VENTURES · Tilakwadi, NashikP51600025617· 77.3% built
- SERENE BAY4 mo overdueSHUBHA GRUHA · Ward GNorth, Mumbai CityP51900047047· 64.6% built· 1 complaint
- THARWANI ARIANA PHASE IV4 mo overdueANIL HARDASMAL THARWANI · CHIKLOLI, ThaneP51700047534· 36.6% built
- SPARKLE SPLENDOR4 mo overdueSPARKLE BUILDER · SR NO.79P52100030178· 72.7% built
- DOLPHIN MATRIX4 mo overdueM/S. MAHALAXMI PROMOTERS · HINJAWADI, PuneP52100054157· filed Dec 2024 → now Jun 2026· 90.9% built
- Komal4 mo overdueSRKD LANDMARK LLP · Haveli, PuneP52100047236· filed Jan 2025 → now Jun 2026· 72.7% built
- DODKE PALAZZO4 mo overdueDODKE LANDMARKS · Haveli, PuneP52100031044· filed Dec 2024 → now Jun 2026· 90.2% built
- THE SCENIC RESIDENCY PHASE I4 mo overdueVasai, PalgharP99000005001· filed Mar 2020 → now Jun 2026· 46.8% built· 4 complaints
- THE AMBIENCE GARDEN4 mo overdueMUKUND ARSS DEVELOPERS · Uran, RaigarhP52000012153· filed Jun 2018 → now Jun 2026· 90.7% built· 7 complaints
- ALAG ENDEAVOUR4 mo overdueALAG ENDEAVOUR · Kurla, Mumbai SuburbanP51800028404· 0% built· 7 complaints
- KRISHNA RESIDENCY4 mo overduePRATAP BABAJI SHINDE · TALOJA, RaigarhP52000034269· filed Dec 2025 → now Jun 2026· 98% built
- Florence Heights A and B Wing4 mo overdueM/s Vinayak Developers · Borivali, Mumbai SuburbanP51800049192· filed Dec 2024 → now Jun 2026· 76.3% built
- SIGNATURE PARK E F I AND J BUILDINGS4 mo overdueSHREE SONIGARA REALCON · Mulshi, PuneP52100027402· 88.5% built· 46 complaints
- Golden Core4 mo overdueGhule Patil Developers · Pune City, PuneP52100052849· 72.7% built
- AARADHYA EVOQ4 mo overdueMAN INFRA CONTRACTS LLP · Andheri, Mumbai SuburbanP51800034587· 90.9% built
- BARCODE4 mo overdueESSEN VENTURES · Haveli, PuneP52100026749· filed Jun 2023 → now Jun 2026· 81.8% built
- MARATHON NEXZONE CEDAR - 14 mo overdueSANVO RESORTS PVT. LTD. · PALASPE PHATA, RaigarhP52000023250· 99.7% built· 3 complaints
- SAGAR HEIGHTS4 mo overdueAADINATH DEVELOPERS · KHADAKPADA, ThaneP51700051990· filed Dec 2025 → now Jun 2026· 90.5% built
- Hubtown Seasons - Ardennes4 mo overdueJoynest Premises Private Ltd · Kurla, Mumbai SuburbanP51800032784· 77.3% built
- SKYLER PHASE II4 mo overdueSKYLER PHASE II · Haveli, PuneP52100027949· 44.5% built· 1 complaint
- LAXMIKRUPA4 mo overdueGANGOTREE HOMES · Haveli, PuneP52100045252· filed Dec 2025 → now Jun 2026· 88.9% built· 1 complaint
- Sai Ramdas4 mo overdueRahul Ramdas Tupe · Haveli, PuneP52100028366· filed Jun 2024 → now Jun 2026· 45.5% built
- Lodha Adrina4 mo overdueLODHA DEVELOPERS LIMITED · Ward GSouth, Mumbai CityP51900014937· filed Jul 2024 → now Jun 2026· 88.6% built· 1 complaint
- CRYSTAL PRIDE4 mo overdueCRYSTAL CONSTRUCTION COMPANY · Borivali, Mumbai SuburbanP51800009735· filed Dec 2019 → now Jun 2026· 78.6% built
- PARKSYDE NEST PHASE - 34 mo overdueJAIKUMAR CONSTRUCTIONS LTD · [ANCHAVATI ANNEX, NashikP51600025687· 97.4% built
- Ivy Dreamland Phase 14 mo overdueLeal Developers · Vasai, PalgharP99000051683· 89.1% built· 1 complaint
- Asya4 mo overdueMOIRA SPACES OPC PRIVATE LIMITED · Pune City, PuneP52100066499· filed Dec 2025 → now Jun 2026· 64.2% built
- Shankar Bhavan Premises Co-operative Society Limited4 mo overdueMishal Construction Private Limited · Kurla, Mumbai SuburbanP51900009596· filed Dec 2019 → now Jun 2026· 46.1% built
- SONIGARA SUNVIEW4 mo overdueSONIGARA SUNVIEW · Haveli, PuneP52100079565· 72.7% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.