Delayed projects in Pune
3,402 MahaRERA-registered projects in Pune are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 3 of 18
- SONIGARA LANDMARK8.1 yr overdueSONIGARA PROMOTERS · Wakad, PuneP52100001618· 61.8% built
- DHARMARAJ PLAZA8.1 yr overdueM/S. SHREENIVAS ENTERPRISES · Junnar, PuneP52100012872· 45.2% built
- MULIK LUXURIA B WING8.1 yr overdueTUKARAM SOPANRAO MULIK · Pune (M Corp.), PuneP52100011511· 90.9% built
- AKASH RAJ PHASE ONE8.1 yr overdueNIRMAN PROPERTIES · Pimpri Chinchawad (M Corp.), PuneP52100002839· filed Dec 2017 → now Aug 2018· 79.1% built
- Shraddha Orchid8.1 yr overdueD.A.BORADE AND SONS · Pimpri Chinchawad (M Corp.), PuneP52100007519· 90.9% built
- AKSHAR8.1 yr overdueAKSHAR ASSOCIATES · Talegaon Dabhade (M Cl), PuneP52100008202· 90.9% built
- KATE CENTRAL8.1 yr overdueM/S Kate Construction · Haveli, PuneP52100013078· filed Dec 2017 → now Aug 2018· 81.8% built
- ROSHAN ONE WING B8.1 yr overdueRAHUL BHAGWANDAS SANKLA · Varale, PuneP52100004526· 81.8% built
- Anjana Phase II8.1 yr overdueSURESH TOTARAM SUKHWANI · Rahatani, PuneP52100016735· 61.8% built
- GOLDEN HEIGHTS8.1 yr overdueM/S BHAGAT LANDMARKS · Junnar, PuneP52100007012· 70.9% built
- The Leaf8.1 yr overdueShree Pushkar Developers · YAWALEWADI, PuneP52100001414· 87.3% built
- Aura City D1,D28.1 yr overdueBhagvati infra · Shirur, PuneP52100003069· 76.4% built
- AUREATE - PHASE 28.1 yr overdueRAVIRAJ VENTURES · Pimpale Saudagar, PuneP52100009424· filed Mar 2018 → now Aug 2018· 46.6% built
- PRISTINE PACIFIC PART-28.1 yr overdueMelange Developers · AMBEGAON Bk, PuneP52100000275· 90.9% built
- ADITYA VIVAAZ8.1 yr overdueADITYA PROMOTERS · Pimpri Chinchawad (M Corp.), PuneP52100001419· 81.8% built
- Uttam Townscapes8.1 yr overdueFORTUNE DEVELOPERS AND INFRASTRUCTURES · Haveli, PuneP52100002613· 89.3% built
- SAI SNEH PHASE-II8.1 yr overdueGS DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100002952· 63.6% built
- Shri Sai Park8.1 yr overdueSairam Builders And Developers · WAKAD, PuneP52100013343· 43.6% built· 1 complaint
- NIRMITI VIHAR8.1 yr overdueNIRMITI ASSOCIATES · Rui, PuneP52100005795· 77.1% built
- Anjana8.1 yr overdueSURESH TOTARAM SUKHWANI · Haveli, PuneP52100000328· 66.4% built
- PARTH ENCLAVE E BUILDING8.1 yr overduePARTH DEVELOPERS · Haveli, PuneP52100000678· 81.8% built· 1 complaint
- Kute Fortune - B Building8.1 yr overdueSHIVKAILAS DEVELOPMENT CORPORATION · Pimpri Chinchawad (M Corp.), PuneP52100005618· 81.8% built
- Dinashree8.1 yr overdueAmeya Arun Joshi · Parvati, PuneP52100004054· 90.9% built
- FUSION CITY8.1 yr overdueKUMBARE ENTERPRISES · Haveli, PuneP52100007763· 90.9% built
- SHREYA APARTMENT8.1 yr overdueDUNU MEGHAWAT · MOHAN NAGAR, PuneP52100014832· 19.5% built
- BELIEVE HOMES8.1 yr overdueRAHUL SHIVLAL PATEL · Talegaon Dabhade (M Cl), PuneP52100010536· 47.3% built
- KULSWAMINI KASTURI8.1 yr overdueSHANKAR BABAN GAWADE · medankarwadi, PuneP52100012222· 81.8% built· 2 complaints
- ADORN BUSINESS CENTRE8.1 yr overdueHASIB AHMED SHAIKH · Pune City, PuneP52100002403· 81.8% built
- Prachi Apartment8.1 yr overdueOm Siddhi Associates · Lingali, PuneP52100010681· 90.9% built
- ALCOVE8.1 yr overdueZENDE PROPERTIES · Pune (M Corp.), PuneP52100000822· 89.7% built
- SARISHA8.0 yr overdueSAI SAMARTTHA PROPERTIES · Punawale, PuneP52100010390· 50% built
- BHAKTI GENESIS D WING8.0 yr overdueMAHAVIR CONSTRUCTIONS AND DEVELOPERS · SHEDGE WASTI, PuneP52100002159· 81.8% built
- ADITYA VIHAR8.0 yr overdueADITYA ASSOCIATES · Talegaon Dabhade (R), PuneP52100002988· 82.7% built
- SHREE NAVNATH APARTMENT8.0 yr overdueRAGHU BAPUJI KUDE · Wadagaon (CT), PuneP52100008550· 90.9% built
- Saijeevan8.0 yr overdueTRICON CONSTRUCTION COMPANY · Katraj, PuneP52100014544· 50% built
- ANAND VIHAR8.0 yr overdueSHREE GANESH CONSTRUCTION · Talegaon Dabhade (M Cl), PuneP52100006140· 57.3% built
- SBH Wakad C-3 1st and 2nd Floor8.0 yr overdueClassic Promoters and Builders Private Limited · Wakad, PuneP52100007034· filed Mar 2018 → now Sept 2018· 81.8% built
- VASTUSHILP 28.0 yr overdueBETTER CREATION · CHARHOLI, PuneP52100005612· 90.9% built
- AKASHGANGA8.0 yr overdueAKASH PROMOTER AND DEVELOPERS COMPANY PROPRIETOR KISHOR GENBHAU DANGAT · Ale, PuneP52100011456· 78.2% built
- LODHA BELMONDO Pebble Beach E, Estancia A8.0 yr overdueLodha Developers Limited · Gahunje, PuneP52100000350· 90.9% built· 2 complaints
- 7 Gulmohar8.0 yr overdueCrystalstar Landscapes LLP · Pune City, PuneP52100008432· 90.9% built
- VIVA SAROVAR PHASE 18.0 yr overdueM/S. VIVA SWASTIK ASSOCIATES · Pune (M Corp.), PuneP52100007659· 99.8% built
- SAI SHIVAM8.0 yr overdueMANGAL MURTI DEVELOPERS PROP NARESH THAKURDAS WADHWANI · RAHATANI, PuneP52100002125· 77.3% built
- Panchtirth8.0 yr overdueShree Siddhagiri Developers · Hagawane Nagar, PuneP52100003520· 90.9% built
- JAGDAMB HEIGHTS8.0 yr overdueARIHANT RAHI PROMOTERS · Pune (M Corp.), PuneP52100011801· 28.6% built
- Ivy Estate Umang Premier8.0 yr overdueKOLTE-PATIL DEVELOPERS LIMITED · WAGHOLI, PuneP52100000655· 90.9% built
- PAVAN PARK8.0 yr overdueSATISH APPAJI SAWANT · MOHAMMADWADI, PuneP52100012803· 51.5% built
- SOHAM PURANDAR HEIGHTS8.0 yr overdueSOHAM PROPERTIES · Hadapsar, PuneP52100002553· 37.3% built
- SHRADDHA HEIGHTS8.0 yr overdueRAJENDRA BALASAHEB JAMBHULKAR · Talegaon Dabhade (M Cl), PuneP52100011988· 59.1% built
- PLENUM PARK PART 28.0 yr overdueP & M DEVELOPERS · Keshavnagar-Mundwa, PuneP52100008219· filed Dec 2017 → now Sept 2018· 72.7% built
- Defence Colony Pune Phase28.0 yr overdueDefence Colony Pune · WAGHOLI, PuneP52100007420· filed Dec 2017 → now Sept 2018· 96.4% built
- SUVIDHA DNYANGANGA PHASE-II8.0 yr overdueSUVIDHA PROJECTS · Wadgaon Budruk, PuneP52100003146· 81.8% built
- MANTRI ETERNITY B8.0 yr overdueOMEGA PREMISES PVT LTD · Haveli, PuneP52100011690· filed Dec 2017 → now Sept 2018· 99.9% built· 3 complaints
- Visions Indradhanu Phase 28.0 yr overdueVISION DEVELOPERS · Haveli, PuneP52100001900· 88.6% built· 1 complaint
- AZALEA8.0 yr overdueACME SAWANT VENTURES · BHILAREWADI, PuneP52100004621· 36.3% built
- VISION KALPAVRIKSHA PHASE 28.0 yr overdueVISION ENTERPRISES · Pimpri Chinchawad (M Corp.), PuneP52100007200· 90.9% built
- GRANDBAY A5 A6 B38.0 yr overduePRAKASH HARAKCHAND PARAKH · PUNE, PuneP52100002050· filed Mar 2018 → now Sept 2018· 90.9% built· 2 complaints
- ACHAL PROMOTERS AAKASH8.0 yr overdueACHAL PROMOTERS AAKASH · Pune (M Corp.), PuneP52100004363· filed Mar 2018 → now Sept 2018· 72.7% built
- LALCHAND NAGAR8.0 yr overdueNAVKAR DEVELOPER · Daund, PuneP52100011134· 65% built
- YASHASHREE RESIDENCY8.0 yr overdueM/S OM DEVELOPERS · Junnar, PuneP52100010456· filed Dec 2017 → now Sept 2018· 68.2% built
- AVANI NILAY8.0 yr overdueABG CITY · Shirur, PuneP52100007735· 90.9% built
- RAJASHREE8.0 yr overduePANDIT JAVDEKAR ASSOCIATES · NEAR KASTURKUNJ, PuneP52100000457· 81.8% built
- 24K Sereno Buildings C and D8.0 yr overdueNOW Realty Promoters and Builders Private Limited · Baner, PuneP52100005080· 90.9% built· 1 complaint
- AURA VILLE8.0 yr overdueSai Developers · Pune City, PuneP52100007565· 38.9% built
- ROHAN LEHER 2 WING B C DE8.0 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · Pune City, PuneP52100000796· 90.9% built
- Riddhi Residency8.0 yr overdueATMIYA ENTERPRISES · Talegaon Dabhade (M Cl), PuneP52100003883· 82.7% built
- Aishwarya Villa8.0 yr overdueAishwarya Developers · Haveli, PuneP52100011035· 90.5% built
- NIRMAN RESIDENCY8.0 yr overdueNIRMAN GROUP · Ambegaon, PuneP52100009602· 57.9% built
- Vishal Greens8.0 yr overdueGreystone Landmark · Hadapsar, PuneP52100004064· 90.9% built
- Goodwill Nirmiti A Building8.0 yr overdueUnique Choice Ventures · LOHGAON, PuneP52100002683· 90.9% built
- DEVYANI8.0 yr overdueM/S KHARDE PATIL · Kothrud, PuneP52100013394· 76% built
- BHAIRAVI8.0 yr overdueM/S KHARDE PATIL · Kothrud, PuneP52100013401· 82.3% built
- KALYANI8.0 yr overdueM/S KHARDE PATIL · Kothrud, PuneP52100013317· 82.2% built
- VIVA HALLMARK PHASE 18.0 yr overdueM/S. VIVA SWARAJ · PUNE, PuneP52100006330· 98% built· 1 complaint
- Jinkushal Residency8.0 yr overdueM/s Prakash Spaces · Haveli, PuneP52100008396· 75% built
- Vikram Goldmine8.0 yr overdueVikram Venkatrao Gaikwad · Pune City, PuneP52100004105· 81.8% built
- SAI VIDHI8.0 yr overdueVARDHAMAN ASSOCIATES · Pune City, PuneP52100012531· 56.4% built
- Essenseia28.0 yr overdueAruna Ashok Bhat · kondhwa BK, PuneP52100006735· filed Apr 2018 → now Oct 2018· 90.9% built
- premia B-1 Phase II8.0 yr overdueC.D. Developers · NARHE, PuneP52100008990· 43.6% built
- SAI KRISNA8.0 yr overdueBAJAJ&JAIN ASSOCIATES · kondhwa BK, PuneP52100000996· 90.9% built
- JEET PARADISE8.0 yr overdueJEET INFRASTRUCTURE · Daund, PuneP52100003996· 63.6% built
- Aura City D3,D48.0 yr overdueBhagvati infra · Shirur, PuneP52100004141· 75.5% built
- SIMPLICITY - E4 AND E58.0 yr overdueJ K P DEVELOPERS UNIT NO 2 · Haveli, PuneP52100000504· 90.9% built
- NAVKAR DARSHAN8.0 yr overdueABHAY POPATLAL DHOKA · Pimpri Chinchawad (M Corp.), PuneP52100008176· 53.6% built
- Dorabjees Royale Heritage Mall8.0 yr overdueJehangir Nariman Dorabjee · MOHAMMEDWADI, PuneP52100008824· filed Dec 2017 → now Oct 2018· 81.8% built
- SWOJAS CHINTAMANI8.0 yr overdueSWOJAS PROPERTIES · ERANDWANA, PuneP52100015937· 36.4% built
- TULIP8.0 yr overdueD.P.DEVELOPERS · Pune (M Corp.), PuneP52100012336· 89.5% built
- GALAXY APARTMENT8.0 yr overdueSharayu Associates · CHARHOLI, PuneP52100010982· 52.3% built
- Aura City D5,D68.0 yr overdueBhagvati infra · Shirur, PuneP52100003585· 76.4% built
- CELEBRIA8.0 yr overdueVISHNU VENTURES · Pune (M Corp.), PuneP52100005241· filed Jan 2018 → now Oct 2018· 60% built
- PATIL PLAZA8.0 yr overdueSHIRKE AND PATIL ASSOCIATES · Haveli, PuneP52100004218· 81.4% built
- Greens - Beech - GH8.0 yr overdueAMJ Land Developers · Chinchwad, PuneP52100002813· 72.7% built
- FORTUNE HOUSE8.0 yr overdueFORTUNE DEVELOPERS · Pune (M Corp.), PuneP52100005111· 71.8% built
- SUN SET AVENUE8.0 yr overdueRENAISSANCE DEVELOPERS · Baner, PuneP52100011228· filed May 2018 → now Oct 2018· 76.8% built
- KARAN HEIGHTS8.0 yr overduePALLADIUM REALITY · Pune (M Corp.), PuneP52100004687· 90.9% built
- Malkans8.0 yr overdueGokhale Builders LLP · Pune (M Corp.), PuneP52100006798· 80.5% built
- NISARG SRUSHTI7.9 yr overdueNISARG DEVELOPERS · MANJARI Bk, PuneP52100001446· 88.2% built
- KESHAV RUKMINI SANKUL7.9 yr overdueBHUMKAR PROMOTERS AND BUILDERS · NARHE, PuneP52100012696· 62.3% built
- Rivers Edge7.9 yr overdueKOKANE BUILDERS · Pimpri Chinchawad (M Corp.), PuneP52100010937· 90.9% built
- Arihant Heights7.9 yr overdueJAS DEVELOPERS · Haveli, PuneP52100005332· 72.7% built
- DEV RESIDENCY PHASE 17.9 yr overdueSHRADDHA CONSTRUCTION · URULI DEVACHI, PuneP52100015506· 84.5% built· 3 complaints
- KAPILVASTU7.9 yr overdueANIL ANANDRAO PATIL · Haveli, PuneP52100012615· 94.5% built· 1 complaint
- RAVIKIRAN PHASE I7.9 yr overdueDREAMHOUSE CONSTRUCTIONS PRIVATE LIMITED · Wadmukhwadi, PuneP52100000492· 90.9% built
- AKSHAY BUSINESS SQUARE7.9 yr overdueMANGILAL GANESHMAL BAFNA · Pune (M Corp.), PuneP52100010084· 80.9% built
- PARAG7.9 yr overdueVARDAAN ASSOCIATES · Pune City, PuneP52100005661· filed Jun 2018 → now Nov 2018· 81.8% built
- PRIMEROSE7.9 yr overdueGURUKRUPA DEVELOPERS · AMBEGAON, PuneP52100008282· 90.9% built· 1 complaint
- Vighnaharta Sankul7.9 yr overdueVighnaharta Construction · Haveli, PuneP52100013166· 72.7% built
- MARIGOLD7.9 yr overdueSWAPNIL PRAKASHRAO KSHIRSAGAR · Haveli, PuneP52100005576· 90.9% built
- KUMAR VISTA7.9 yr overdueBINOD KUMAR RAI · LOHGAON, PuneP52100005133· 12.7% built
- 25 GLORY7.9 yr overdueVIJAYRAJ ASSOCIATES · Haveli, PuneP52100008877· 80% built
- Vighnaharta Residency7.9 yr overdueVikas Bhimdev Kale · Baramati (M Cl), PuneP52100008577· 62% built
- SWASTIK MANGAL7.9 yr overdueSWASTIK CONSTRUCTION · Mahalunge, PuneP52100009924· 48.2% built
- VRUNDAVAN PARK7.8 yr overdueVEDANT DEVELOPERS · Baramati (M Cl), PuneP52100006477· 82.7% built
- Vedant Heights7.8 yr overdueMoraya Developers · Pimpri Chinchawad (M Corp.), PuneP52100011636· 51.8% built· 3 complaints
- Vardhaman Residency7.8 yr overdueSwastik Builders · Talegaon Dabhade (M Cl), PuneP52100004534· 43.6% built
- Futura7.8 yr overdueEon Hadapsar Infrastructure Pvt Ltd · Hadapsar, PuneP52100001536· 74.5% built
- DODKE SHOBHAN7.8 yr overdueDODKE REALTORS · Haveli, PuneP52100008770· 53% built
- DESTINY7.8 yr overdueBALAJI REALTORS · Pimpale Saudagar, PuneP52100012186· 99.5% built
- Muktangan Niwas7.8 yr overdueRavindra Arun Kate · Pimpale Saudagar, PuneP52100011365· 90.9% built
- Amar Developers and Construction7.8 yr overdueRahul Balasaheb Gavali · Haveli, PuneP52100012296· 44.5% built
- Vistaar Shubharambh7.8 yr overdueMarathwada Developers · Balewadi, PuneP52100002463· 81.8% built
- Nirmiti Vasundhara Park7.8 yr overdueVasundhara Nirmiti Homes · Baramati (M Cl), PuneP52100006128· 88.2% built
- KAKADE PARK7.8 yr overdueSuryakant Kakade · Chinchwad, PuneP52100007904· 90.9% built
- INSPIRA PHASE I7.8 yr overdueANAND REALTIES · Kondhwa Budruk, PuneP52100006715· 56.6% built
- River edge7.8 yr overdueS K ASSOCIATES · Shirur, PuneP52100005662· 49.1% built
- Sai Avishkar7.8 yr overdueSUYOG ANJANI AVISHKAR ASSOCIATES · Haveli, PuneP52100004067· 80.9% built
- SHREERAM TRADECON7.8 yr overdueSHREERAMTRADECON · Chakan, PuneP52100003029· 65% built
- CAPITAL CORNER7.8 yr overdueKACHA DEVELOPERS · BEHIND VISHAL LAWNS, PuneP52100004801· 75.5% built
- TRADEMARK LIFE7.8 yr overdueNEW FRONT PRABHAVEE VENTURES · Mulshi, PuneP52100008152· filed Mar 2018 → now Dec 2018· 90% built
- IMPERIO7.8 yr overdueBLUESTONE PROPERTIES · Pimpri Chinchawad (M Corp.), PuneP52100002929· filed Jun 2018 → now Dec 2018· 52.7% built
- 25 KARAT7.8 yr overdueMEGHASWANA CONSTRUCTIONS · Talegaon Dabhade (M Cl), PuneP52100006816· 43.3% built· 1 complaint
- SHIROMANI HEIGHTS7.8 yr overdueSudarshan Construction · Haveli, PuneP52100007178· 67.3% built· 1 complaint
- Welhome Galaxy Phase 17.8 yr overdueWelhome Properties · WAGHOLI, PuneP52100013204· 72.7% built
- Disha Heights7.8 yr overdueDinesh Prabhakar Baravkar · Daund, PuneP52100009125· 84.1% built
- SHREE GANESH HILLVIEW7.8 yr overdueMUKESH JAGDISH GOYAL · CHARHOLI, PuneP52100005537· 40.9% built
- DWARKA7.8 yr overdueCUBIX DEVELOPERS · Pune (M Corp.), PuneP52100007405· 79.1% built
- Chandra Mukkut7.8 yr overdueCHANDRA REALITY · WAGHOLI, PuneP52100011295· 81.8% built
- Jijaushrrusti7.8 yr overdueJijaushrusti · Rui, PuneP52100012782· 81.8% built
- GOLDEN BELLS PHASE II7.8 yr overduePIONEER CONSTRUCTIONS · Haveli, PuneP52100003229· 90.9% built
- Kiran Shubhamkaroti B7.8 yr overdueM/S KIRAN CREATORS & DEVELOPERS THROUGH PROPRIETOR MR. KASHINATH GANESH NEHETE · Sus, PuneP52100010215· 53.2% built
- Gopalkrupa7.8 yr overdueLAGOO APTE · Haveli, PuneP52100003479· 81.8% built
- SAIRAJ COMPLEX7.8 yr overdueSHOBHA ATUL BALGUDE · Baramati (M Cl), PuneP52100003625· 33.3% built
- VIGHNHARTA RESIDENCY7.8 yr overdueSANJAY BUILDCON · PUNE, PuneP52100012592· 90.9% built
- DAMODAR HERITAGE7.8 yr overdueROHIT RAJIV SHETH · Pune (M Corp.), PuneP52100003968· 81.8% built
- PANACHE7.8 yr overdueTRIMURTI SAI NATH INFRAS LLP · Katraj, PuneP52100005287· 54.6% built
- DELTA RACHANA7.8 yr overdueDELTA RACHANA · Pimpri Chinchawad (M Corp.), PuneP52100013828· 32.7% built· 1 complaint
- GANRAYA PLAZA7.8 yr overdueVASANT VISHNU BANKHELE WITH ATUL BALIRAM THORAT ASSOCIATION OF PERSONS · Ambegaon, PuneP52100009301· 64.5% built
- RICH WOODS7.8 yr overdueJAGRUTI PROMOTORS · Bhosari, PuneP52100004375· 81.8% built
- MSR REGENCY7.8 yr overdueBhandari Infrastructure & Construction Development Pvt. Ltd. · Pune (M Corp.), PuneP52100004593· filed Jul 2018 → now Dec 2018· 90.9% built
- SAI YASH JEWEL - Phase I7.8 yr overdueM/s. Sai Erectors · Thergaon, PuneP52100004138· 85.1% built· 2 complaints
- Vrundavan Homes Wing A7.8 yr overduePrapti Spaces · Alandi Rural, PuneP52100005873· 81.4% built
- DS VRINDAVAN PHASE II7.8 yr overdueDSP DEVELOPERS · DHANORI, PuneP52100016171· 76.4% built
- MARVEL ARCO B BUILDING7.8 yr overdueMARVEL SIGMA HOMES PRIVATE LIMITED · Hadapsar, PuneP52100008708· 75.9% built· 4 complaints
- PEARL RESIDENCY7.8 yr overdueSHREE SAMARTH DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100004979· 61.5% built
- Swapnalok Nagari Building no. 34,35,36,377.8 yr overdueSWAPNALOK DEVELOPERS · Bhor, PuneP52100001827· 90.9% built
- QUEENSLAND7.8 yr overdueMOTI UDHARAM PANJABI · Moshi-Boradewadi, PuneP52100001606· 86.5% built
- SONTERRA RESIDENCES7.8 yr overdueJAISONS PROPERTIES LLP · Mulshi, PuneP52100004313· filed Dec 2017 → now Dec 2018· 55% built
- KOOL HOMES SIGNATURE7.8 yr overdueMADISON HOLDINGS · Nyati County, PuneP52100005690· 87.9% built
- THE BLUE PLAQUES7.8 yr overdueBLUEBERRY DEVELOPERS · Somatane, PuneP52100000688· 90.9% built
- SHUBHANGAN PHASE I7.8 yr overdueVenkateshwara Gangotree Associates · Pirangut, PuneP52100004294· 86.4% built
- Pratham7.8 yr overduePrimary Housing Corporation LLP · Shirur, PuneP52100008426· filed Dec 2017 → now Dec 2018· 89.1% built
- ELEMENTA7.8 yr overdueAKSHAR LAND DEVELOPERS PRIVATE LIMITED · Tathwade, PuneP52100002903· 89.1% built
- Sai Pearl Phase 17.8 yr overdueSSD PROMOTERS AND BUILDERS · Pimpale Saudagar, PuneP52100001207· 89.2% built
- AISHWARYA RESIDENCY7.8 yr overdueVYAS BUILDCON PVT. LTD. · Baner, PuneP52100002455· filed Mar 2018 → now Dec 2018· 72.4% built
- ROHAN ABHILASHA BUILDING E7.8 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · WAGHOLI, PuneP52100000832· 90.7% built· 3 complaints
- Ozarde Residency7.8 yr overdueOnkar Developers · Baramati (M Cl), PuneP52100007697· 80% built
- Yashada Residency7.8 yr overdueAgresar Construction · Daund, PuneP52100002610· 37.2% built
- SAI HIRA CLASSIQUE7.8 yr overdueSAI ASHTAVINAYAK INFRA · Pimpri Chinchawad (M Corp.), PuneP52100011756· 50.5% built
- Karan Suncoast7.8 yr overdueKaran Developers · Bavadhan BK, PuneP52100000474· 87.7% built
- Shubharambh7.8 yr overdueFive Elements Erectors and landmarks LLP · Pimpri Chinchawad (M Corp.), PuneP52100003800· 90.9% built
- Jadhav Complex7.8 yr overdueDisha Constructions · Wadagaon (CT), PuneP52100010809· 69.1% built
- Anika Mangalam7.8 yr overdueArun Sheth Properties · Pune City, PuneP52100002636· 90.9% built
- GOLDEN PALMS- PHASE 1 B WING7.8 yr overdueGEETA VIDHYAI CONSTRUCTIONS · Mulshi, PuneP52100012378· 49.6% built
- ORIENT PALACE7.8 yr overdueBOKHARA BUILDTECH · Haveli, PuneP52100013287· 90.9% built
- NIRMANA ENCLAVE7.8 yr overdueNIRMANA DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100001680· 90.9% built
- Times Square7.8 yr overdueSheth Developers · Hinjavadi (CT), PuneP52100009391· filed Dec 2017 → now Dec 2018· 69.1% built
- Samyak Residency7.8 yr overdueSahebrao Dagdu Kharat · Near Chitale Bandhu Shop, PuneP52100015334· 81.8% built
- Marvel Fuego7.8 yr overdueMARVEL REALTORS AND DEVELOPERS LTD · Hadapsar, PuneP52100006192· 86.4% built· 6 complaints
- Snehalbaug Co-operative Housing Society Limited7.8 yr overdueKelkar Pinnac Housing LLP · Parvati, PuneP52100004563· 50.9% built
- Shatavari Apartments7.8 yr overdueWAGHOLIKAR ASSOCIATES · Jalochi, PuneP52100001138· 69.1% built
- Sun Sapphire7.8 yr overdueJindal Mittal Graha Nirman Pvt. Ltd. · -, PuneP52100001938· 85.2% built
- BALAJI EMPIRE7.8 yr overdueAAKAR DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100001661· filed Mar 2018 → now Dec 2018· 72.7% built
- BELLEZZA7.8 yr overdueSIDDHISHREE BUILDCON · Pimpri Chinchawad (M Corp.), PuneP52100002229· 81.8% built
- MARVEL ARCO E BUILDING7.8 yr overdueMARVEL SIGMA HOMES PRIVATE LIMITED · Hadapsar, PuneP52100007022· 96.8% built· 3 complaints
- 7 Avenues7.8 yr overdueSai Innovision Associates · Baner, PuneP52100004977· 56.2% built
- Skyways Sereno7.8 yr overduePranam Associates · LOHGAON, PuneP52100002552· 85.8% built
- SHASHWAT RESIDENCY7.8 yr overdueDAULAT PANDURANG BHONDVE · Pimpri Chinchawad (M Corp.), PuneP52100006985· 90.9% built
- VISHWESHWAR NAGAR PHASE - 17.8 yr overdueM/S. VISION GROUP · ALANDI, PuneP52100006647· 81.8% built
- RATNAPADMA7.8 yr overdueANGAL & CO · Sheela Vihar Colony, PuneP52100000527· 81.8% built
- PAVILLION RESIDENCY7.8 yr overdueAPEX DEVELOPERS · Mahalunge, PuneP52100006615· 63.6% built
- TERRAZA7.8 yr overdueSanskruti City Space · Baner, PuneP52100006921· filed Dec 2017 → now Dec 2018· 90.9% built· 1 complaint
- ROHAN KRITIKA WINGS A C7.8 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · Pune (M Corp.), PuneP52100000486· 76.4% built
- Venkatesh Paradise A Wing7.8 yr overdueSANJAY DNYANOBA JAGTAP · Pisoli, PuneP52100001162· 89.1% built· 3 complaints
- TATHASTU7.8 yr overdueBALASAI ASSOCIATES · Mawal, PuneP52100001658· 81.8% built
- DNV ARCELIA PH 37.8 yr overdueDNV REALTY · Pimpri Chinchawad (M Corp.), PuneP52100013972· 79.6% built
- RIVER BREEZE7.8 yr overduePUSHPA DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100013499· filed Dec 2017 → now Dec 2018· 80.9% built
- PLATINUM7.8 yr overdueRohit Infra · KALA KADAK, PuneP52100016424· 90.9% built
- Sun Exotica Phase 17.8 yr overdueJindal Mittal Graha Nirman Pvt. Ltd. · -, PuneP52100001696· 85.5% built
- Green County Phase II Wing-C7.8 yr overdueAnand Developers · Fursungi, PuneP52100011772· 82.7% built
- ATHASHRI BANER COMMERCIAL7.8 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Baner, PuneP52100002667· filed Dec 2017 → now Dec 2018· 81.8% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.