RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 51 of 61
- SHRI LAXMI KUNJ1.9 yr overdueV S BUILDERS & DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000002755· filed Jun 2018 → now Dec 2024· 85% built
- The Kings Way - A1, A2 and A31.9 yr overdueThe Kings Way AOP · ghorpadi, PuneP52100003300· filed Jun 2019 → now Dec 2024· 96.8% built· 1 complaint
- AARNA HILLS1.9 yr overdueRADHE GOVIND REALTORS · BANER, PuneP52100046166· 81.8% built
- Geeta Heights1.9 yr overdueMAYUR GROUP (RD) · Rambaugh, ThaneP51700029333· 90.9% built
- KANTHARIA LAKESIDE1.9 yr overduePROACTIVE HOUSING LLP · Vasai, PalgharP99000020016· filed Dec 2022 → now Dec 2024· 81.8% built
- BLUE SAPPHIRE1.9 yr overdueMODERN DEVELOPERS · Haveli, PuneP52100045946· 81.8% built
- BHASKAR VASTUPURTI1.9 yr overduePRATIK BUILDCON · AURANGABAD, AurangabadP51500005068· filed Dec 2018 → now Dec 2024· 51.8% built
- BHOOMI CELESTIA - A WING1.9 yr overdueSASHWAT CONSTRUWELL PRIVATE LIMITED · Librity Garden, Opp. S.N.D.T. Girls Collage, Mumbai SuburbanP51800011623· filed Dec 2022 → now Dec 2024· 30.5% built
- VRINDAVAN PARK1.9 yr overdueSIDDHIVINAYAK BUILDCON · GUT NO 305 PLOT NO 10 VRINDAVAN NAGAR NEAR SENT PETTER SCHOOL ADGAON SHIVAR NASHIK, NashikP51600029679· 95.5% built
- JUPITER1.9 yr overdueCHARRUDATTA CHANDRASHEKHAR KKALE · KOTHARI LAY OUT, KACHHIMET, NagpurP50500048042· 90.9% built
- PRITESH CHAMBERS1.9 yr overduePRALHAD LADU ARONDEKAR · Kumbharli, SindhudurgP52900011467· filed Mar 2019 → now Dec 2024· 90.9% built
- ELEGANT-91.9 yr overduePRADEEP KASHINATH BHINGARE · Haveli, PuneP52100034293· 27.3% built
- B-ORBIT PALMS1.9 yr overdueB Orbit Group · KALA NAGAR LANE NO 5, NashikP51600029811· 72.7% built
- Teerth Avila1.9 yr overdueVIJAY TUKARAM RAUNDAL · Parkhe Vasti, PuneP52100034662· 62.7% built· 1 complaint
- Bileshwar Darshan CHSL1.9 yr overdueM/s. Desai Residency Private Limited · Vile Parle East, Mumbai SuburbanP51800047797· 90.9% built
- CYRSTAL PLAZA1.9 yr overdueMANGESH EKNATH THAKUR · Panvel, RaigarhP52000008712· filed Dec 2018 → now Dec 2024· 40% built· 12 complaints
- GVC SAPTAGIRI GREENS II1.9 yr overdueGVC DEVELOPERS · KAUTHA, NandedP51100029308· 81.8% built
- SALEEL161.9 yr overdueGANGOTREE GREENBUILD · Sahakarnagar, PuneP52100029108· 81.8% built
- YASHODA COMPLEX1.9 yr overdueCHAITANYA MAHADEV GHULE · AMBEGAON BK, PuneP52100048559· 81.4% built
- ALAG ASHTAPAD1.9 yr overdueCONTOUR DEVELOPERS LLP · Kurla, Mumbai SuburbanP51800031922· 90.9% built
- ARJUN HEIGHTS1.9 yr overdueSHRIRANG DNYANOBA DHODADE · Haveli, PuneP52100002334· filed Dec 2022 → now Dec 2024· 81.8% built· 1 complaint
- MAHALAXMI TOWER1.9 yr overdueMAHALAXMI CONSTRUCTIONS · MANTRI COLONY, SangliP53100049431· 81.8% built
- MASTER BUSINESS CENTRE1.9 yr overdueMASTER BUSINESS CENTRE · Ambarnath, ThaneP51700055525· 68.2% built
- Shiv ganga Apartment1.9 yr overdueSHREE SWAMI SAMARTH CONSTRUCTION · Ulhasnagar, ThaneP51700047981· 45.5% built
- LOTUS PARK1.9 yr overdueSAJANSING MOTILAL JARWAL · Tisgaon, AurangabadP51500034156· 90.9% built
- Mokate Heritage1.9 yr overdueMokate Constructions · Kothrud, PuneP52100035155· 90.9% built
- AMC AVENUE1.9 yr overdueKAMDHENU SPACES LLP · PUNE, PuneP52100033404· 81.8% built
- Ark One1.9 yr overdueIYI Milestone Realities LLP · Haveli, PuneP52100045548· 90.9% built
- NYATI DEFENCE ENCLAVE II1.9 yr overdueNYATI BUILDERS PRIVATE LIMITED · NEAR NYATI WINDCHIMES, PuneP52100048851· 76% built
- UNIQUE PRIDE1.9 yr overdueAKSHAD INFRASTRUCTURE AND DEVELOPERS · MOLACH ODHA, SataraP52700032387· 90.9% built
- URBAN NEST BLDG - 11.9 yr overdueCLLARO ENTERPRISES LLP · BEVERLY PARK MIRA ROAD EAST, ThaneP51700046736· 90.9% built
- ROONGTA FLORENZA APARTMENT1.9 yr overdueROONGTA HOMES LLP · NASHIK, NashikP51600033635· 89.1% built· 3 complaints
- VRINDAVAN PARK1.9 yr overdueJADHAV CIVIL PROJECT · Junnar, PuneP52100046916· 77.3% built
- SEQUOIA1.9 yr overdueAUM PRIMA LLP · Andheri, Mumbai SuburbanP51800032970· 56.8% built
- SUNDAR RESIDENCY F WING1.9 yr overdueNAVADITYA DEVELOPERS · GAURIPADA, ThaneP51700030083· 12.5% built
- ANUSAYA NEST1.9 yr overdueRed Brick Habitants · CHOVISAWADI GAOTHAN, PuneP52100047088· 90.9% built
- NEELKANTH DARSHAN1.9 yr overdueSKYTECH INFRA · KAMOTHE, RaigarhP52000034879· 84.5% built
- SWAPNSHILP PLAZA1.9 yr overdueSHAHEEN MANSOOR BIJALI · NEAR VEERSHAIV BANK, KolhapurP53000033062· 50.9% built
- RISHABRAJ GARDENIA1.9 yr overdueH RISHABRAJ REALTY · Andheri, Mumbai SuburbanP51800035106· 89.1% built
- Shree Ganesh Apartment1.9 yr overdueSHRI GANESH BUILDER AND DEVELOPERS · Ulhasnagar, ThaneP51700048692· 72.7% built
- SIDDHIVINAYAK RESIDENCY1.9 yr overdueSAIRAJ DEVELOPERS · BADLAPUR, ThaneP51700033059· 72.7% built
- VEDRITI1.9 yr overdueSURENDRA BAPUSAHEB PATHARE · Chandan NagarP52100030287· 78.2% built
- PANCHARATNA HEIGHTS1.9 yr overduePANCHARATNA BUILDERS · NEAR MAULI LAWNS, NashikP51600033520· 82.5% built
- Silver Springs1.9 yr overdueMahalaxmi Developers · Kolhapur (M Corp.), KolhapurP53000009173· filed Feb 2019 → now Dec 2024· 90.9% built· 6 complaints
- Tirupati Vishwa1.9 yr overdueSAI DEVELOPERS · Mahanagar 1, AurangabadP51500034327· 90.9% built
- CRESCENTPOINT-II1.9 yr overdueK K CONSTRUCTION · KALAWATI MANDIR AREA, PalgharP99000020521· filed Dec 2022 → now Dec 2024· 90.9% built
- CITI NEST1.9 yr overdueBasons Investments Private Limited · ANDHERI - EAST, Mumbai SuburbanP51800049340· 36.8% built
- STAR CHS LTD1.9 yr overdueHEALTH COLONIES & CONSTRUCTION PVT.LTD. · POWAI, Mumbai SuburbanP51800035098· 23.6% built
- Pragati Revanta1.9 yr overduePragati Enterprises · Ghatkopar, Mumbai SuburbanP51800032025· 90.9% built
- MANGALMURTI HERITAGE1.9 yr overdueSANJAM DEVELOPERS · DAHIVALI TARFE NEED, RaigarhP52000048848· 90.9% built
- NEELAYA PROJECT 31.9 yr overdueNAIKNAVARE BUILDCON PVTLTD · TALEGAON, PuneP52100030648· 66.4% built
- Eraville Phase I1.9 yr overdueNeha Constructions · Sadesataranali Hadapsar, PuneP52100016089· filed Jun 2021 → now Dec 2024· 70.7% built
- PARTH RENAISSANCE1.9 yr overdueBIRARI INFRATECH · Nashik, NashikP51600029998· 72.7% built
- Shree Ram Krupa CHSL1.9 yr overdueJ.B Realty · MCCH Society, RaigarhP52000034989· 90.9% built
- Lotus Residency1.9 yr overdueLotus Logistics and Developers pvt ltd · Mumbai, Mumbai SuburbanP51800006322· filed Jun 2021 → now Dec 2024· 80.9% built· 2 complaints
- VATSALYA PURAM BUILDING A1.9 yr overdueNANDAN DEVELOPERS · KUMBARE TOWNSHIP, PuneP52100033502· 99.8% built
- Success Windsor Tower1.9 yr overdueSUCCESS INFRA · Haveli, PuneP52100029582· 90.9% built
- RENDEZVOUS PREMISES CO-OP SOCIETY LTD1.9 yr overdueJGB BUILDERS LLP (CA to Owner) · Mumbai, Mumbai SuburbanP51800033783· 95.5% built
- Shree Rajrajeshwari Chhaya Chs Ltd.1.9 yr overdueSUNIL DINKAR SHINDE · Bhandup East, Mumbai SuburbanP51800032685· 90.9% built
- Shrivishwa1.9 yr overdueGowardhan Builders & Developers · Behind Ebrahim & Sons Nachane Raod, Near MSEBE Office Maruti Mandir Ratnagiri, RatnagiriP52800032376· 90.9% built
- ADVENT NEEL1.9 yr overdueREGENT ASSOCIATES · Andheri, Mumbai SuburbanP51800032332· 78.9% built
- SHREE SAI TOWERS1.9 yr overdueBRS BUILDERS AND DEVELOPERS · NERAL EAST, RaigarhP52000049335· 90.9% built
- BUILDARCH DAISY1.9 yr overdueBUILDARCH LAND DEVLOPERS PVT. LTD. · DADAR SHIVAJI PARK, Mumbai CityP51900030673· 81.8% built
- SUKRUTI NILAYA1.9 yr overdueSUKRUTI CONSTRUCTIONS · GANGAPUR ROAD, NashikP51600048811· 11.8% built
- Laxmi Kunj1.9 yr overdueGeeCee Ventures Limited · Andheri, Mumbai SuburbanP51800046721· 88.2% built
- NYATI ELAN CENTRAL II1.9 yr overduePSQUARE BUILDERS LLP · WAGHOLI, PuneP52100031800· 78.2% built
- ND VILLA1.9 yr overdueND DEVELOPERS · PAKHALE MALA, SataraP52700032140· 72.7% built
- Apoorva Rise1.9 yr overdueApoorva Housing · Chembur, Mumbai SuburbanP51800031714· 97.7% built
- DP STAR TRIVENI1.9 yr overdueDP BUILDHOMES LLP · BHANDUP WEST, Mumbai SuburbanP51800004550· filed Dec 2021 → now Dec 2024· 85.5% built
- SAI PRAKASH HEIGHTS1.9 yr overdueJAIN BUILDCON · GURUDATTA COLONY NEAR SHREE KRUSHNA COLONY, JalgaonP49900050466· 81.8% built
- Kohinoor Heights1.9 yr overdueVISHWA DEVELOPERS · Chikhali, PuneP52100033158· 90.9% built
- RUNWAL PEARL1.9 yr overdueRunwal Construction Private Limited · Thane, ThaneP51700001383· filed May 2019 → now Dec 2024· 95.5% built· 6 complaints
- Sukruti Serenity1.9 yr overdueArihant Developers · Near Mehrun Lake, Mehrun Shivar, JalgaonP49900032651· 60% built
- PRIYANKA PARADISE1.9 yr overduePRIYANKA REGENCY LLP · Thane, ThaneP51700051357· 90.9% built
- RISHABRAJ VILLA STELLA1.9 yr overdueH RISHABRAJ REALTY · Borivali, Mumbai SuburbanP51800034790· 72.7% built
- INDRAYANI PURAM1.9 yr overdueSHIVKRUPA DEVELOPERS · CHOVISAWADI, PuneP52100034310· 64.1% built
- SHREE LAXMI PRIDE1.9 yr overdueSHREE LAXMI VENTURE PVT LTD · PIPLA BESA, NagpurP50500030899· 92.4% built
- SHIV RESIDENCY1.9 yr overdueM AND K BUILDERS · VAKHARBHAG, SangliP53100032201· filed Dec 2023 → now Dec 2024· 90.9% built
- SHREE KAMAL RESIDENCY1.9 yr overdueSHREE DEVELOPERS · KAMATHWADA, NashikP51600048846· 90.9% built
- The Palm1.9 yr overdueISHWARLAL MULJI PATEL · Agartakli, NashikP51600031552· 22.7% built
- SIDDHI VINAYAK APPARTMENT-21.9 yr overdueSIDDHI VINAYAK ENTERPRISES · DADRA, Dadra & Nagar HaveliP49600000158· 90.9% built
- NAVKAR RESIDENCY1.9 yr overdueVINOD RAMANLAL DHADIWAL · SUSHILA PARK, PuneP52100048714· 64.5% built
- DEVIPRABHA VAKRATUND1.9 yr overdueDEVIPRABHA REAL ESTATE · RAMNAGAR, NagpurP50500049031· 55.9% built
- SHEEL APARTMENTS BY MAYFAIR1.9 yr overdueMAYFAIR HOUSING PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800031040· 82.7% built
- Shree Jalaram Heights1.9 yr overdueNitinkumar Chhaganlal Ganatra · Ward No. 12, BuldanaP50000032877· 81.8% built
- Kalpataru Jade Residences D1.9 yr overdueAstrum Developments Private Limited · Baner, PuneP52100029693· 80.5% built· 1 complaint
- Shakambari Business Center1.9 yr overdueS P Builders & Developers · Tapadiya Nagar, AkolaP50100052994· 81.8% built
- SHREE GAJANAN HEIGHTS1.9 yr overdueSACHIN DEVELOPERS - - · DHULE, DhuleP49800034502· 81.8% built
- Shri Siddhivinayak Pride1.9 yr overdueShree Siddhivinayak Builders and Developers · Kolhapur (M Corp.), KolhapurP53000010585· filed Jun 2021 → now Dec 2024· 98.1% built
- Krishna Kunj Phase IV1.9 yr overdueKrishna developr · Bypass Road, JalnaP51400050223· 63.6% built
- A R IMPERIA1.9 yr overdueA R REALTY · WAKAD, PuneP52100032942· 78.6% built· 3 complaints
- ARRPAN VIHAR1.9 yr overdueANANDA DEVELOPERS · HIRAWADI, NashikP51600031424· 90.9% built
- ABHANG HEIGHTS B BUILDING1.9 yr overdueR K Lunkad Housing Company · Chovisawadi Pimpri Chinchwad (M.corp), PuneP52100031783· 90.9% built
- VRUKSHVELI1.9 yr overdueFORTUNE DEVELOPERS · SHANTI SHEELA SOCIETY, ERANDWANE, PLOT NUMBER 76/29, PuneP52100030782· 81.8% built
- SHRI RENUKA ASSOCIATES VANSHRI MAMURDI PROJECT1.9 yr overdueSHRI RENUKA ASSOCIATES · NEAR MAVAL GATE HOTEL, PuneP52100013840· filed Oct 2020 → now Dec 2024· 18.2% built
- OM ARNESH APARTMENT1.9 yr overdueINFINITI INFRAVENTURES · ZINGABAI TAKLI NAGPUR, NagpurP50500032036· 81.8% built
- MADHUKUNJ1.9 yr overdueNAKSHATRA CREATIONS · JEVHERI COLONY, PuneP52100048351· 49.1% built
- SAIKRUPA1.9 yr overdueSaidutta Developers · MOUJE-SATURNA, AmravatiP50300032125· 69.1% built
- KAUSHALYA HEIGHTS1.9 yr overdueMAULI DEVELOPERS · MAKHMALABAD, NashikP51600047905· 81.8% built
- FIA CONSTRUCTION COMPANY A/C FIA ENIGMA1.9 yr overdueNIMISH LAXMICHAND PASAD · Palghar, PalgharP99000029742· 90.9% built
- Dipti Royal Arc1.9 yr overdueDipti Associates · Shivaji Park, Mumbai CityP51900034863· 84.1% built
- HS ALAG1.9 yr overdueHS ALAG REALTY LLP · Kurla, Mumbai SuburbanP51800031693· 90.9% built
- ANAND AVENUE1.9 yr overdueDEEPAK PANDURANG MATALE · AMBAD, NashikP51600033614· 59.1% built
- FLORA1.9 yr overdueROYAL ENTERPRISE · Nr Ayyappa Temple, Dadra & Nagar HaveliP49600000107· 90.9% built
- Anjani Tirth1.9 yr overdueGeeta Space Realtors · Borivali (West), Mumbai SuburbanP51800033828· 90.9% built
- MAXX GLORY1.9 yr overdueMAXX BUILDER AND DEVELOPERS · MANISH NAGAR AREA, NagpurP50500022443· filed Sept 2024 → now Dec 2024· 86.7% built
- ALAG ARTIS1.9 yr overdueALAG LIFESPACE LLP · GHATKOPAR EAST, Mumbai SuburbanP51800032385· 84.5% built
- SHUBHAM AVALON CO-OPERATIVE HOUSING SOCIETY LIMITED1.9 yr overdueAVVAD HOUSING LLP · GHATKOPAR EAST, Mumbai SuburbanP51800045851· 90.9% built
- MAITRY HEIGHTS1.9 yr overdueRAJ MAITRY & ESKON DEVELOPERS · Vasai, PalgharP99000005628· filed Jul 2019 → now Dec 2024· 56.7% built
- YASH HEIGHTS1.9 yr overdueDEELIPRAO DAULATRAO DEORE · KAMATHWADE, NashikP51600046131· 9.1% built
- a Familia1.9 yr overdueNidisha Buildcon LLP · Telco Colony Dattanagar, PuneP52100030581· 79.7% built
- Badlani Business Center1.9 yr overdueBadlani Builders & Developers Pvt Ltd · Lakhala, WashimP50200054445· 81.8% built
- Khol Khandoba Tower1.9 yr overduePride Group · Khol Khandoba, KolhapurP53000029324· 0.9% built
- BALAJI SERENITY1.9 yr overdueBalaji Buildcon · BANER, PuneP52100031813· 32.9% built· 1 complaint
- AMI PARK1.9 yr overdueNEXON INFRA · RAMKRISHNA PARAMHANS SOCIETY, SangliP53100045377· 63.5% built
- GRUHYOG1.9 yr overduePRAVINSINH JAYSINGRAO GHATGE · Kolhapur (M Corp.), KolhapurP53000001246· filed Jan 2021 → now Dec 2024· 90.9% built· 1 complaint
- CENTRO1.9 yr overdueLUSHLIFE REAL ESTATE LLP · Autade Handewadi, PuneP52100014734· filed Sept 2022 → now Dec 2024· 50% built
- Panvelkar Estate - Stanford - Phase II - R1 - B1.9 yr overduePanvelkar Infrastructures Private Limited · Mankivali, ThaneP51700031879· 90.9% built
- GANDHARV GALAXIA1.9 yr overdueGANDHARV REALTY · HADAPSAR, PuneP52100009123· filed Dec 2019 → now Dec 2024· 90.9% built
- PARK ROYALE1.9 yr overdueMAHAVEER BUILDCON · COLLECTOR BUNGLOW AREA, JalgaonP49900032274· 27.3% built
- ANNAVISTA1.9 yr overdueTRISONS BUILDERS · BANDRA WEST, Mumbai SuburbanP51800034372· 74.1% built
- OMKARA PARK WING B1.9 yr overdueOMKARA BUILDCON · Dhruv Nagar, NashikP51600045585· 81.8% built
- FIA CONSTRUCTION COMPANY A/C FIA ENCLAVE1.9 yr overdueNIMISH LAXMICHAND PASAD · Palghar, PalgharP99000029790· 90.9% built
- First City, Commercial Shopping-11.9 yr overdueNagpur Integrated Township Private Limited · MIHAN Non-SEZ area, NagpurP50500034615· 81.8% built· 1 complaint
- SHREE ADINATH PALACE1.9 yr overduePREM TOPANDAS JHAMNANI · TULSINAGAR, NagpurP50500032973· 90.9% built
- VARDHMAN PEARL1.9 yr overdueDIWALI DEVELOPERS · MALAD WEST, Mumbai SuburbanP51800032809· 36.4% built
- Park Infinia - L1, K3 and I41.9 yr overdueKumar Properties and Real Estate Pvt. Ltd. · Hadapsar, PuneP52100045667· 86.2% built
- TIRUPATI APPARTMENT1.9 yr overdueSATYEN CHANDRASHEKHAR DADHE · JAITALA, NagpurP50500030132· 73.7% built
- SMITA APARTMENT1.9 yr overdueFORTUNE DEVELOPERS · CTS NO 40/2 ERANDWANE, FINAL PLOT NO 56 SUB PLOT NO 2, ERANDWANE, PUNE-411004, PuneP52100033240· 70% built
- SHRESHTHA SWAPNA CO-OP HOUSING SOCIETY LTD1.9 yr overdueOM SHREE SAI BUILDERS AND DEVELOPERS · Taluka Ambarnath, ThaneP51700031812· 46.8% built
- AUDUMBAR APARTMENTS CHS LTD1.9 yr overdueMASAKIN DEVELOPERS · MALAD WEST MUMBAI, Mumbai SuburbanP51800034993· 90.9% built
- TruSpace Prima Angulus1.9 yr overdueAtharva Enterprises · Balewadi, PuneP52100029972· 98.2% built
- Elina1.9 yr overdueTulip Venture · Pimple Nilakh, PuneP52100048472· 72.7% built
- GAIA CARNIVAL - ROW HOUSES1.9 yr overdueZambad Disha Pride Infrastructure LLP · Gut no. 308, South Republic, Near Sudhakar Nagar, Satara parisar, Aurangabad, AurangabadP51500030703· 90.9% built
- Prakash B Zone1.9 yr overduePrakash Ventures · Moshi , Sec-4 (Pradhikaran), PuneP52100047362· 81.8% built
- NIDHI REALTY PHASE I1.9 yr overdueLALIT NAGINDAS DOSHI · Vasai, PalgharP99000002258· filed Dec 2018 → now Dec 2024· 80.2% built
- ELIXIR GIRIK1.9 yr overdueELIXIR BUILDERS · CHANDSHI, NashikP51600033898· 90.9% built
- SHANTI HEIGHTS1.9 yr overdueSUNNY DEVELOPERS · MULUND WEST, Mumbai SuburbanP51800032643· 97.7% built
- KUMAR PRISM1.9 yr overdueKUMAR PROPERTIES AND PROMOTERS PRIVATE LIMITED · MUNDHAWA, PuneP52100034109· 36.4% built
- OM SAI HOME-D1.9 yr overdueM/S. INFINI DEVELOPERS · KAMATGHAR, ThaneP51700032786· 90.9% built
- PRANAV HEIGHTS1.9 yr overdueSHRI SADGURU ASSOCIATES · GOLE COLONY, NashikP51600033716· 79.5% built
- Sharda Heights1.9 yr overdueSWANAND REALTIES · near paithan gate, AurangabadP51500046206· 90.9% built
- Shreeram Vaishali1.9 yr overdueADITYA REALTORS · Dombivali East, ThaneP51700032988· 60% built
- SUYASH CO.OP. HOUSING SOCIETY LTD1.8 yr overdueSNA Build-Tech · Thane, ThaneP51700030476· 87.3% built
- Vitthal Shanti1.8 yr overdueVitthal Shant Enterprises · Somvar Peth, PuneP52100050241· filed Dec 2024 → now Jan 2025· 81.8% built
- SUPREME MADHUKAR1.8 yr overdueSUPREME ENTERPRISE · BORIVALI, Mumbai SuburbanP51800032692· 86.8% built
- APEX DEVELOPERS1.8 yr overdueAPEX DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000007741· filed Jun 2022 → now Jan 2025· 70.9% built
- DIYA WOODS1.8 yr overdueKRISHA ENTERPRISES · TITWALA, ThaneP51700021634· filed Dec 2022 → now Jan 2025· 89.1% built
- LAXMISHRIHARI COMPLEX1.8 yr overdueAbhishek Nandkumar Phadke · Shukrawar Peth, SataraP52700051893· 33.6% built· 1 complaint
- Shree Ganesh Northstar1.8 yr overdueSHREE GANESH BUILDERS LIMITED · Dixit Nagar, NagpurP50500024282· 86% built
- VED VIHAR PHASE II - BUILDING NO. 41.8 yr overdueROHAN PATE GROUP OF CONSTRUCTIONS LLP · Kothrud, PuneP52100012713· filed Dec 2021 → now Jan 2025· 95.6% built· 2 complaints
- SIDDHESHWAR HEIGHTS A WING FROM 2nd TO 14th FLOOR1.8 yr overdueSHREE JAI MALHAR ENTERPRISES · Kalyan, ThaneP51700031142· filed Dec 2024 → now Jan 2025· 37.5% built
- Agastya sea view apartments1.8 yr overdueM/s Phatak Developers · Harne, RatnagiriP52800033048· filed Dec 2024 → now Jan 2025· 61.4% built
- YASHADA SPLENDID PARK1.8 yr overdueYASHADA DEVELOPERS · Dudulgaon, PuneP52100021070· 95.2% built
- ROHAN HEIGHTS1.8 yr overdueSANJAY RAMCHANDRA JADHAV · KOYANAVASAHAT, SataraP52700031672· filed Dec 2023 → now Jan 2025· 90.9% built
- Shikara Orchid1.8 yr overdueShikara Constructions Pvt. Ltd. · Akurli Village, RaigarhP52000018510· filed Jan 2024 → now Jan 2025· 90.9% built
- BORIVALI NEELKANTH NAGAR CHS LTD1.8 yr overdueMAHAVIR INFRASTRUCTURE · Borivali, Mumbai SuburbanP51800006154· filed Dec 2020 → now Jan 2025· 90.9% built
- ROONGTA ASHOK VIHAR APARTMENT1.8 yr overdueSHREE CHAWO SATI BUILDERS PRIVATE LIMITED · NASHIK, NashikP51600046725· 81.8% built
- Bank of Maharashtra Employees Manisha Co-Operative Housing Society Limited1.8 yr overdueJ B Constructions · Tilak nagar, ThaneP51700050442· 90.9% built
- Joyville Hadapsar Annexe Phase 21.8 yr overdueJoyville Shapoorji Housing Private Limited · Shewalewadi, PuneP52100026479· 90.9% built· 1 complaint
- BHOLEBABA HEIGHTS1.8 yr overdueSHARAD DINKAR DESHMUKH · MAKHMALABAD SHIWAR, NASHIK, NashikP51600035162· 84.1% built
- LAXMI HEIGHTS1.8 yr overdueNASALAPURE KULKARNI BUILDERS AND DEVELOPERS · Laxmi Nagar Kupwad, SangliP53100034987· 63.6% built
- JOYVILLE HADAPSAR ANNEXE PHASE 11.8 yr overdueJoyville Shapoorji Housing Private Limited · Shewalewadi, PuneP52100026451· 90.9% built· 3 complaints
- RACHANA EKAA1.8 yr overdueRachana construction Co. (Nagpur) Pvt. Ltd. · MOUZA CHINCHBHUVAN, NagpurP50500034119· filed Mar 2024 → now Jan 2025· 90.5% built
- SAI HEIGHTS APARTMENT1.8 yr overdueSHRI SAI CONSTRUCTION · SHANI CHOWK SHRAMIK NAGAR, NashikP51600033867· 90.9% built
- GHATKOPAR PARK VIEW CHS LIMITED1.8 yr overdueEV AND SARAF REALTY · KURLA, Mumbai SuburbanP51800014255· filed Dec 2019 → now Jan 2025· 86.4% built
- LUMINARE HEIGHTS1.8 yr overdueDarsheel Group · Lipane Wasti, PuneP52100030987· filed Jul 2024 → now Jan 2025· 90.9% built
- Rose Castle1.8 yr overdueRose Crystal Developers · Borhadewadi, PuneP52100030687· filed Jul 2024 → now Jan 2025· 20% built
- NYSA BUSINESS CENTER1.8 yr overdueR D BUILDWELL · MAKHAMALABAD, NashikP51600029342· 90.9% built
- Joyville Hadapsar Annexe Phase 31.8 yr overdueJoyville Shapoorji Housing Private Limited · Shewalewadi, PuneP52100026480· 90.9% built· 3 complaints
- Umang Pride - Building C1.8 yr overdueCorolla Gulmohar · Wagholi, PuneP52100054285· filed Dec 2024 → now Feb 2025· 90.9% built
- Kumar Pratham - A B C and Shops1.7 yr overdueKumar Agro Products Pvt Ltd · Moshi - Borhadewadi, PuneP52100022486· 97.7% built
- Sahavas Apartments1.7 yr overdueYojak Developers · Osmanpura, AurangabadP51500019967· filed Jul 2021 → now Feb 2025· 90.7% built
- The Greens - Radhakunj1.7 yr overdueEthics Infra Development Pvt Ltd · Kandivali East, Mumbai SuburbanP51800029355· filed May 2024 → now Feb 2025· 90% built
- RAHUL CO.OP. HOUSING SOCIETY LTD1.7 yr overdueSNA Build-Tech · PANCHPAKHADI, ThaneP51700030595· 80% built
- Primo 1121.7 yr overdueLuxora Infrastructure Private Limited · Mauza, NagpurP50500010660· filed Dec 2019 → now Feb 2025· 90.9% built
- VIGHNARAJ1.7 yr overduePATIL MAHAJAN · MOJE SATARE BHUSAWAL, JalgaonP49900051886· 16.4% built
- Mittal Park1.7 yr overdueAllwin Buildcon · Nandur Naka, NashikP51600022317· 85.1% built
- PARAS HEIGHTS1.7 yr overdueSUSHILP BUILDERS · PHALTAN, SataraP52700028909· filed Mar 2023 → now Feb 2025· 28.2% built
- SYMPHONY APARTMENTS1.7 yr overdueAakar Constructions · VITTHAL NAGAR, HADAPSAR, PuneP52100034426· 64.5% built
- GIRIRAJ RESIDENCY1.7 yr overdueGREENSTONE INFRASTRUCTURE · ZINGABAI TAKLI NAGPUR, NagpurP50500033121· 90.9% built
- Nabhraj Trimurti1.7 yr overdueNABHRAJ BUILDERS AND DEVELOPERS PVT LTD · Shreyanagar, Osmanpura, AurangabadP51500047311· 90.9% built
- REDEVELOPMENT OF PLOT NO. 2121.7 yr overduePRANAV CONSTRUCTIONS LIMITED · MUMBAI, Mumbai SuburbanP51800034087· 90.9% built
- SHIVSRUSHTI ANNEX1.7 yr overdueVISHAL LAXMAN GADEKAR · MAKHMALABAD, NashikP51600034167· 90.9% built
- SHUBH REGENCY1.7 yr overdueSHUBH ENTERPRISE · MULUND, Mumbai SuburbanP51800003145· filed Jun 2022 → now Feb 2025· 90.9% built· 2 complaints
- Megapolis Mystic - F1.7 yr overduePegasus Properties Pvt. Ltd. · Rajiv Gandhi Infotech Park Phase 3, PuneP52100029121· filed Jan 2025 → now Feb 2025· 90.9% built
- ELITE RIAAN1.7 yr overdueM/s. RIAAN ANKIT REALTECH · SHRAMIK NAGAR SATPUR, NashikP51600034237· 90.9% built
- AURALIA RESIDENCY1.7 yr overdueANUSHREE AND JHAMTANI REALTY · PUNAWALE, PuneP52100027347· 81.8% built
- Kasturi Milan1.7 yr overdueH RISHABRAJ REALTY · Borivali West, Mumbai SuburbanP51800051982· 90.9% built
- Prabhu Business Center1.7 yr overduePacific Builders · Wadala Shiwar, NashikP51600030755· 81.8% built
- SAMRAT SARTHAK1.7 yr overdueBORA REALTY LLP · 411046, PuneP52100023095· 90.9% built· 1 complaint
- DEEPA CHS LTD1.7 yr overdueREGENT SPACES · VILE PARLE EAST, Mumbai SuburbanP51800026864· 96.4% built
- Tejas Heritage1.7 yr overdueTejas Enterprises · Near Ramsheth Thakur Sports Complex, RaigarhP52000025147· 95.5% built
- DHANRAJ1.7 yr overdueANEISHA LIVINGS LLP · BORIVALI (W), Mumbai SuburbanP51800034955· 90.9% built
- SUPREME HAPPY HOME1.7 yr overdueShelby Realty LLP · Kandivali West, Mumbai SuburbanP51800034043· 90.9% built
- STAR HEIGHT1.7 yr overdueERIC INFRASTRUCTURE · Vasai-Virar City (M Corp), PalgharP99000008026· filed Jun 2019 → now Mar 2025· 90.9% built
- SANGHVI PARSSSVA CITY1.7 yr overdueSANGHVI PREMISES PRIVATE LIMITED · Atgaon, ThaneP51700009886· filed Dec 2020 → now Mar 2025· 81.8% built
- Madhu Milind Co-Op Housing Society Ltd1.7 yr overdueAditya Associates · Naupada, ThaneP51700034830· 87.7% built
- SHIV UTSAV1.7 yr overdueMARUTI ENTERPISES · Pashane, RaigarhP52000007812· filed Mar 2024 → now Mar 2025· 86.9% built
- KRISHNA KAMAL1.7 yr overdueJSM REALTORS PRIVATE LIMITED · SECTOR 8, NEW PANVEL, RaigarhP52000047687· 86.4% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.