RERA projects past their possession deadline
11,768 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 37 of 59
- MY NEST3.9 yr overdueRohit Tanaji Omase · NEAR MLA SURESH BHAU KHADE SCHOOL, SangliP53100028107· 90.9% built
- DIVINE MIST3.9 yr overdueV & T Properties · Kalewadi Rahatani, PuneP52100003638· filed Feb 2021 → now Sept 2022· 73.5% built
- SHREE CHINTAMANI APARTMENTS3.9 yr overdueNISHIKANT SHARAD CHAUDHARI · Pashan, PuneP52100007779· filed Sept 2018 → now Sept 2022· 53.9% built
- HIRA HEIGHTS3.9 yr overdueSALASAR DEVELOPERS · Akoli Bk., AkolaP50100012728· filed Jul 2019 → now Sept 2022· 99.7% built
- MOHAN APARTMENT PHASE I3.9 yr overdueARCHWAY PROPERTIES · SADASHIV PETH, PuneP52100019812· 90.9% built
- Aeropolis Phase III3.9 yr overdueKrishna developers · Lohgaon, PuneP52100019401· 90.9% built
- GANESHKUNJ APARTMENT3.9 yr overdueGURULAXMI BUILDERS · NEAR SAI BABA MANDIR, AurangabadP51500011695· filed Feb 2019 → now Sept 2022· 90.9% built
- Rustomjee Azziano Wing K3.9 yr overdueKapstone Constructions Private Limited · Thane, ThaneP51700013649· 89.8% built· 1 complaint
- MAYUR RESIDENCY3.9 yr overdueGAUTAM KACHARDAS SANCHETI · BHOKARDAN, JalnaP51500006370· filed Sept 2019 → now Sept 2022· 1.5% built
- NISHA BAFNA PLAZA3.9 yr overdueTAPADIA AND KASLIWAL VENTURES · NEAR MONDHA NAKA, AurangabadP51500010207· filed Dec 2018 → now Sept 2022· 66.5% built
- PLOT NO 01 SECTOR 11 DRONAGIRI3.9 yr overdueCITY AND INDUSTRIAL DEVELOPEMENT CORPORATION OF MAHARASHTRA LTD · DRONAGIRI, RaigarhP52000017480· filed Dec 2020 → now Sept 2022· 78.2% built
- PINNACLE GLORIA3.8 yr overdueKAPLESHWARA BUILDERS AND DEVELOPERS · Kolshet Road, ThaneP51700008627· 42.3% built· 1 complaint
- Exotica3.8 yr overdueShivsiddhi Developers · Sangli Miraj Kupwad (M Corp.), SangliP53100001885· filed Jun 2021 → now Oct 2022· 81.8% built
- RISHAB ENCLAVE3.8 yr overdueShruti Promoters · Hazaripahad, NagpurP50500018264· 90.9% built
- DARGOPATIL APARTMENT3.8 yr overdueAJINKYA CONSTRUCTIONS · GURUWAR PETH, SolapurP52600020948· 90.9% built
- KALPVRUKSH RESIDENCY3.8 yr overdueVISION REALITIES · GAJANAN HOUSING SOCIETY, SangliP53100020987· 90.9% built
- DATTARAJ HEIGHTS3.8 yr overduePUSHPA NANDKISHOR SAHARE · SAWANGI, AurangabadP51500013996· 90.9% built
- DISHA APARTMENT3.8 yr overdueNORTH POINT HOME · ULWE NAVI MUMBAI, RaigarhP52000021949· 27.3% built
- CROWN C13.8 yr overdueDMK INFRASTRUCTURE PVT LTD · MOSHI, PuneP52100020978· 46.4% built· 1 complaint
- blueberry3.8 yr overdueBLUEBERRY HOMES · WAGHOLI, PuneP52100009610· filed Mar 2019 → now Oct 2022· 72.8% built
- SAI MEGHDOOT3.8 yr overdueANIL SHANKAR AHER · HANUMANWADI, NashikP51600013390· 63.6% built
- SHRIRAM PARK3.8 yr overdueUNIQUE BUILDERS · Aurangabad (M Corp.), AurangabadP51500000615· 90.9% built
- 41 ELITE3.8 yr overdueM/S KRISALA ENTERPRISES · NEAR SHARAYU TOYOTA SHOWROOM, PuneP52100018193· 56.4% built
- SPAN EXOTICA3.8 yr overdueSPAN STRUCTURES · Ulawe, RaigarhP52000008675· 90.9% built· 1 complaint
- KAMALA KASTURI3.8 yr overdueMEHUL SURESH GARG · Haveli, PuneP52100011567· filed Dec 2018 → now Oct 2022· 50.9% built
- SHUBHARAMBHA PLAZA3.8 yr overdueR K INFRACONSTRUCT · Kudal (CT), SindhudurgP52900005183· filed Dec 2019 → now Oct 2022· 54.5% built
- Stella Residency3.8 yr overdueVaibhavLaxmi Builders and Developers · Vikhroli East, Mumbai SuburbanP51800006691· filed Apr 2021 → now Oct 2022· 43.8% built· 1 complaint
- SUMANSHILP RESIDENCY3.8 yr overdueSATYAJIT GOVIND LELE · DATTA COLONY EAST, SangliP53100018626· 90.9% built
- ACE AASTHA BUILDING A3.8 yr overdueSAKSHI DEVELOPERS · OPP. TANISHQ ORCHID SOCIETY, PuneP52100016214· 99.8% built
- Vision Ace MHADA3.8 yr overdueVISION ACE · OPP INDIRA SCHOOL NEAR AKSHRA SCHOOL TATHAWADE, PuneP52100026135· 59.1% built
- Indradhanu3.8 yr overdueNirman Infrastructures and Realtors · Karlekarwadi, RatnagiriP52800002653· filed Apr 2021 → now Oct 2022· 81.8% built
- Lifestyle City Kalyan - Applause A3.8 yr overdueNirmal Lifestyle (Kalyan) Private Limited · Kalyan, ThaneP51700003274· filed Sept 2018 → now Oct 2022· 79.1% built· 30 complaints
- PRITHVI PRIDE PHASE-I3.8 yr overduePRITHVI LAND DEVELOPERS · MIRA ROAD EAST, ThaneP51800008848· filed Sept 2021 → now Oct 2022· 51.4% built· 2 complaints
- Suma Sam CHSL3.8 yr overdueSuma Sam Co-op. Hsg. Soc. Ltd. · Borivali, Mumbai SuburbanP51800018744· 90.9% built
- KVK ARUM3.8 yr overdueM/S. KVK BUILDERS & DEVELOPERS · VADAGHAR, RaigarhP52000015928· 90.9% built
- Palava Clara J-M3.8 yr overdueLodha Developers Limited · Kalyan, ThaneP51700000420· 81.8% built· 2 complaints
- UPPER THANE - TIARA A to B3.8 yr overdueLODHA DEVELOPERS LIMITED · Bhiwandi, ThaneP51700014814· 81.8% built· 1 complaint
- Hrim Ssky City Phase II3.8 yr overdueAshok Baheti · BEED BY PASS, AurangabadP51500003253· 76.8% built
- Skyways Esfera 23.8 yr overdueMoze Associates · Lohegaon, PuneP52100018101· 81.8% built
- VINAYAK SANKUL PHASE I3.8 yr overdueM/S VINAYAK ASSOCIATES · Dahivali Tarfe Need, RaigarhP52000016291· 90.9% built
- Alliance Ravi Kiran3.8 yr overdueALLIANCE CITY DEVELOPERS REALTORS PVT LTD · Kurla, Mumbai SuburbanP51800018068· 90.9% built
- Jayakunj Apartment CHSL3.8 yr overdueJayakunj Apartment CHSL · Borivali, Mumbai SuburbanP51800018749· 90.9% built
- Primus Business Park3.8 yr overdueHEMANT KASHIKAR · Thane, ThaneP51700018492· 90.9% built
- SATYAM LOTUS3.8 yr overdueOMSATYAM BUILDCONS PRIVATE LIMITED · GODHANI, NagpurP50500018515· 43.9% built
- MANOHAR SHREEJI NIRVANA PHASE 43.8 yr overdueDEEPLAXMI DEVELOPERS · KATRAP, ThaneP51700015978· 89.1% built
- Emvis Tower C3.8 yr overdueM/S Emerald Developers · Mahadik Wadi Behind Pen Court, RaigarhP52000025984· 90.9% built
- GRAND CASA3.8 yr overdueKONARK ASSOCIATES · PCMC(DANGE CHOWK) CHINCHWAD, PuneP52100009837· filed Apr 2021 → now Oct 2022· 38.2% built
- PALAVA URBANO D AND E3.8 yr overdueLodha Developers Limited · Kalyan, ThaneP51700000577· 78.9% built· 1 complaint
- Lifestyle City Kalyan - Advantage A3.8 yr overdueNirmal Lifestyle (Kalyan) Private Limited · Kalyan, ThaneP51700005436· filed Sept 2018 → now Oct 2022· 78.6% built· 36 complaints
- The Metrozone Aspen C33.8 yr overdueSanklecha Construction Private Limited · Nashik (M Corp.), NashikP51600007130· filed Jun 2018 → now Oct 2022· 90.9% built
- Skyways Esfera B Wing3.8 yr overdueMoze Associates · Lohegaon, PuneP52100025786· 81.8% built
- The Metrozone Hampston B23.8 yr overdueSanklecha Construction Private Limited · INDIRA NAGAR, NashikP51600008309· filed Jun 2018 → now Oct 2022· 90.9% built
- The Metrozone Athens A23.8 yr overdueSanklecha Construction Private Limited · INDIRA NAGAR, NashikP51600005464· filed Sept 2018 → now Oct 2022· 90.9% built· 10 complaints
- WAWLE HEIGHTS3.8 yr overdueDIVYAYASHA BUILDERS PROMOTERS AND DEVELOPERS · BHANGARWADI, PuneP52100016547· 90.9% built
- Avaneesh3.8 yr overdueSunita Pradeep Patwardhan · Wanleswadi , Vijaynagar, SangliP53100018354· 82.7% built
- Sukhwani Celaeno3.8 yr overdueSuresh Totaram Sukhwani · Pimple Saudagar, PuneP52100000325· 32.7% built
- SONAI DADA HEIGHTS3.8 yr overdueK M DEVELOPERS · PUNE, PuneP52100023642· 52.9% built
- PATESHWAR COMPLEX3.7 yr overdueRAJ CONSTRUCTION · SAWANTWADI, SindhudurgP52900001049· 81.8% built
- vishwakarma vasant plaza3.7 yr overduevishwakarma developers · Kolhapur (M Corp.), KolhapurP53000004076· 81.5% built
- Pacific3.7 yr overduePrashant Madhusudan Naik · Alibag, RaigarhP52000007367· 81.8% built
- SONIGARA KIMAYA3.7 yr overdueSONIGARA SAWANT ENTERPRISES · Ambegaon, PuneP52100012331· filed Jul 2022 → now Nov 2022· 53% built
- Yash Emerald3.7 yr overdueYash Ventures · Kolhapur (M Corp.), KolhapurP53000007198· filed Nov 2019 → now Nov 2022· 90.9% built· 1 complaint
- SWAMI PRAASAD3.7 yr overdueMODEL DEVELOPERS AND BUILDERS · MANGALWAR PETH, SataraP52700021482· 81.8% built
- Nanda HiLife3.7 yr overdueNanda Properties · Shankar Nagar, AmravatiP50300018483· 72.8% built
- AKSHAY HEIGHTS3.7 yr overdueR R LUNKAD BUILDERS AND PROMOTERS · Wakad, PuneP52100002094· 81.8% built
- KESHAV KUNJ3.7 yr overdueUDAY NIVARATTIRAO PATIL · VRINDAWAN COLONY, LaturP52400014816· 10% built
- Sarvesh Dream City3.7 yr overdueSAI SHRADHA DEVELOPERS · Juveli, ThaneP51700015729· 28.7% built· 1 complaint
- Pratik Sahaniwas3.7 yr overdueM/s Ekdant Housing · Lokmanya Society, ThaneP51700020405· 73.5% built
- Lodha Majiwada - Tower 13.7 yr overdueMACROTECH DEVELOPERS LIMITED · Thane, ThaneP51700013263· 81.8% built
- Nova3.7 yr overdueMagarpatta City Dev, Co. Pvt. Ltd. · Mundhawa, PuneP52100021358· 86.4% built
- 2Elite3.7 yr overdueNarayani Buildcon · Chikhli, PuneP52100020832· 90.9% built
- EKDANT GALAXY3.7 yr overdueVSK CONSTRUCTION · Datir Nagar, NashikP51600025336· 90.9% built
- Krishna Pride3.7 yr overdueKrishna Realtors · Hingna, NagpurP50500008022· 63.6% built
- Lodha Majiwada - Tower 43.7 yr overdueMACROTECH DEVELOPERS LIMITED · Thane, ThaneP51700013789· 81.8% built· 4 complaints
- DISHA RESIDENCY3.7 yr overdueDEEPAK LALASAHEB PAWAR · Saidapur Village, SataraP52700016530· 90.9% built
- Lodha Mira Road Project 13.7 yr overdueLODHA DEVELOPERS LIMITED · ., ThaneP51700012991· 81.8% built· 8 complaints
- ARPAN RESIDENCY3.7 yr overdueAKASH DEVELOPERS · Vasai, PalgharP99000005384· filed May 2019 → now Nov 2022· 90.9% built
- Redevelopment of Sanjog CHS Ltd3.7 yr overdueHeritage Lifestyles LLP · Borivali, Mumbai SuburbanP51800000984· filed Dec 2018 → now Nov 2022· 53.6% built
- AKash 213.7 yr overdueAkash Construction · Behind Athare Patil School, AhmednagarP52200026602· 81.8% built
- Navkar City Phase III Part 13.7 yr overdueNavkar Estate and Homes Pvt Ltd · Vasai-Virar City (M Corp), PalgharP99000011641· filed Jun 2021 → now Nov 2022· 89.5% built
- infiniti homes3.7 yr overdueinfinity builders & developers · kesarker peth, SataraP52700008113· filed Nov 2021 → now Nov 2022· 68.6% built
- Dattatraya Annex3.7 yr overdueIndu Enterprise · Kurla, Mumbai SuburbanP51800006110· filed Dec 2018 → now Nov 2022· 81.4% built
- AASHRAY AANAND PHASE-II3.7 yr overdueDREAM CORPRATION · GAIKWADPADA, ThaneP51700026268· 86.4% built
- KK VASTU -B3.7 yr overdueSANDEEP VIJAYRAO KALE · RAJPUT COLONY, SangliP53100025585· 80% built
- VRUNDAVN-PARK3.7 yr overdueRAMESH RAMCHANDRA MASAL · Vrundavan Colony, SangliP53100027290· 81.8% built
- HARI PRASAD BUILDING3.7 yr overdueNIRMITEE DEVELOPERS · SHRIKRISHNA NAGAR, BORIVALI (EAST), Mumbai SuburbanP51800027395· 9.1% built
- GRACE SQUARE TYPE D53.7 yr overdueSHREE SUMATINATH ENTERPRISES LLP · Thane, ThaneP51700008389· 90.9% built
- NAMAN MADHUMALTI HEIGHTS3.7 yr overdueANAND GROUP BUILDERS AND DEVELOPERS · MANIK NAGAR, NashikP51600019581· 90.9% built
- SAI NAKSHATRA APARTMENT3.7 yr overdueDilip Veljibhai Patel · Sadguru Nagar, NashikP51600023278· 90.9% built
- Samarth Chandresh Apt3.7 yr overduesamarth associates · vishrambag, SangliP53100018646· 21.8% built
- Bramha Vantage C3.7 yr overdueBramhacorp Limited · Bavadhan, PuneP52100002254· 85.5% built· 1 complaint
- Kasturi3.7 yr overdueNAKSHATRA BUILDCON · kadolkar colony, PuneP52100023848· 90.9% built
- DATTA MAULI CO-OPERATIVE HOUSING SOCIETY3.7 yr overdueDATTA MAULI CO-OPERATIVE HOUSING SOCIETY LIMITED · Nashik Road, NashikP51600004846· filed Oct 2018 → now Dec 2022· 81.8% built
- SAI VANDAN3.7 yr overdueShree om sai developers · Near Akashawani, SangliP53100019896· 81.8% built
- NIRMANS MANGALUM3.7 yr overdueNIRMAN ESTATE DEVELOPERS PVT LTD · BEHIND GURUJI RUGNALAYA, OFF GANGAPUR ROAD, NashikP51600018587· 78.2% built
- CASA RIO PHASE II3.7 yr overdueYASHODEEP ENGINEERS & BUILDERS · CHIKHALI, PuneP52100024679· 90.9% built
- Madhav Ganga3.7 yr overdueDolphin Developers · Khalapur, RaigarhP52000003944· 90.9% built
- VIJAY VIHAR3.6 yr overdueCOL. RPS RAWAT · WAGHOLI, PuneP52100009408· filed Dec 2019 → now Dec 2022· 43.3% built· 13 complaints
- DWARKANATH COMPLEX3.6 yr overdueGHARKUL CONSTRUCTION · Sawantwadi (M Cl), SindhudurgP52900005596· filed Dec 2021 → now Dec 2022· 90.9% built
- GRISHMA3.6 yr overdueSHRI MAULI BUILDCON · SHAHUNAGAR, SolapurP52600014664· 63.8% built
- RAVIRAJ CORAL3.6 yr overdueRAVINDRA SHANKAR SAWANT · Kankavali, SindhudurgP52900008639· 63.9% built
- SWAMI HEIGHTS3.6 yr overdueMAULI BUILDERS AND DEVELOPERS · NEAR SWAMI SAMARTH KENDRA ROAD, NashikP51600022664· 90.9% built
- VIDYA SAGAR VILLA3.6 yr overdueRAVINDRA SHANKAR SAWANT · Palghar, PalgharP99000008038· 64.1% built· 2 complaints
- Gokuldham Residency3.6 yr overdueAbhishek Ghanshyamji Bagdi · Behind Balaji Mangal Karyalaya, Pimpalgaon byepass, Mouza Pimpalgaon, Yavatmal, YavatmalP51000017532· 81.8% built
- RAVIRAJ TARANG3.6 yr overdueRAVINDRA SHANKAR SAWANT · Borivali, Mumbai SuburbanP51800010482· 60.6% built· 1 complaint
- Sanaya Elysium3.6 yr overdueM/s Sanaya Realties Pvt Ltd · Kurla, Mumbai SuburbanP51800001739· 85.7% built· 1 complaint
- SHRI DURGANAND HEIGHTS3.6 yr overdueBabulal Punjaji Magar · Aurangabad (M Corp.), AurangabadP51500014424· 90.9% built
- Nirmiti 7 Hills3.6 yr overdueNirmiti Properties · Baramati (M Cl), PuneP52100008020· 40.9% built
- Om Prabha3.6 yr overdueOm Build Corp · Ramanand Nagar, JalgaonP49900022788· 90.9% built
- KANK MOTI3.6 yr overdueRushikesh Anil Pisal · OPP INAMDAR GARAJ, SataraP52700023004· 36.4% built
- CD HEIGHT3.6 yr overdueKALPANA BUILDCON · Vasai, PalgharP99000005581· 60.2% built
- PRUTHVI TOWERS3.6 yr overduePRUTHVI DEVELOPERS · VITA, SangliP53100023295· 40% built
- RS EXOTICA3.6 yr overdueRS BUILDERS & DEVELOPERS · Panvel, RaigarhP52000006872· filed Dec 2021 → now Dec 2022· 61.8% built
- sparkle avenue3.6 yr overdueSPARKLE BUILDER ·P52100009624· 66.7% built
- PRAYAG MEADOWS PHASE - l3.6 yr overduePRAYAG BUILDERS AND DEVELOPERS · VICHUMBE, RaigarhP52000017065· 90.9% built
- Neelkanth Co.Op.Soc.3.6 yr overdueswapnil mohan kalyankar · Khalapur, RaigarhP52000009820· 84.8% built
- PURPLEHEIGHTS3.6 yr overdueKIRAN JAYANTIBHAI PATEL · PANCHAVATI, NashikP51600017085· 72.7% built
- KSP RESIDENCY A WING3.6 yr overdueKrushnat Shahu Powar · Nachane (CT), RatnagiriP52800014879· 86.4% built
- TRISHUL GOLDEN VILLE3.6 yr overdueA PLUS LIFE SPACE · BADLAPUR WEST, ThaneP51700015246· 90.9% built
- Jyotsna Ramchandra Apartment3.6 yr overduePinki Mahavir Jain · Kuwarbav, RatnagiriP52800018782· 80% built
- SHANKARVINAYAK APARTMENT3.6 yr overdueA AND D CONSTRUCTION · BALEWADI, PuneP52100016973· filed Dec 2020 → now Dec 2022· 81.8% built
- KOYNA3.6 yr overdueshree shakti developers · Thane, ThaneP51700009082· filed Jun 2021 → now Dec 2022· 27.3% built
- PRAGA SERENE3.6 yr overduePRATIK CONSTR · Katraj, PuneP52100011257· filed Jun 2021 → now Dec 2022· 90.9% built
- MARATHON NEXZONE AVIOR -23.6 yr overdueSANVO RESORTS PVT. LTD. · PALASPE PHATA, RaigarhP52000000713· filed Jun 2021 → now Dec 2022· 72.7% built· 6 complaints
- Celesta3.6 yr overdueHome Corp & Associates · MOHAMADWADI, PuneP52100004798· filed Jun 2021 → now Dec 2022· 98.2% built
- GREENWORLD DEVELOPERS PVT. LTD3.6 yr overdueGREENWORLD DEVLOPERS PVT. LTD. · Chikanghar, ThaneP51700009109· filed Jun 2021 → now Dec 2022· 99.1% built
- Lok Nagari Developer Ph - III3.6 yr overdueLok Nagari Developer · Ambarnath, ThaneP51700006820· filed Jun 2021 → now Dec 2022· 90.9% built· 4 complaints
- CASA GRANDE B WING3.6 yr overdueDOLPHIN BUILDCON · RAVET, PuneP52100005682· filed Jun 2021 → now Dec 2022· 85.5% built
- Shree Varad Residency3.6 yr overdueMr. Gurbasappa Mallappa Shetty & Smt. Ambavaa Mallappa Shetty · Shelagi, SolapurP52600013916· filed Dec 2021 → now Dec 2022· 72.7% built
- SHIVSAI HIGHTS3.6 yr overdueSHIVSAI ENTERPRISES · KATEMANEVALI, ThaneP51700010671· filed Jun 2021 → now Dec 2022· 27.6% built
- MUDRA3.6 yr overdueClassic Promoters and Builders Private Limited · BIBWEWADI, PuneP52100003715· filed Jun 2021 → now Dec 2022· 90.9% built· 1 complaint
- FIA PARADISE3.6 yr overdueNIMISH LAXMICHAND PASAD · PALGHAR, PalgharP99000015897· 81.8% built
- NAKSHATRA ENCLAVE3.6 yr overduePANCHARATNA ASSOCIATES · Vengurla (M Cl), SindhudurgP52900009370· 45.5% built
- Pyramid City 63.6 yr overduePyramid Ashok Megastructures Pvt.Ltd · Pipla, NagpurP50500004036· 80.6% built
- GLOBE PARADISE3.6 yr overdueGLOBE REALTORS · Kalyan, ThaneP51700004670· 63.6% built
- Blue Pearl Industrial Estate3.6 yr overdueM/s Mount Realtors · Village Bapane, PalgharP99000022109· 27.3% built
- VIMAL ICON3.6 yr overduePRAMOD NARAYAN PATKAR · Nashik, NashikP51600006454· 29.1% built
- Samraat Gokuldham Project 023.6 yr overdueM/S Shweta Infrastructure & Housing (I) Pvt. Ltd. · Hirawadi, NashikP51600020375· 90.9% built
- SAI DARSHAN3.6 yr overdueSAI SHRUTI DEVELOPERS · Haveli, PuneP52100004582· 81.8% built
- SWAMI DARSHAN3.6 yr overdueGIRISH Rupshi GADA · Junction of M. G. Road and Hunbow Lane, Mumbai SuburbanP51800014536· 64.1% built
- PRAMUKH NARAYAN3.6 yr overduePRAMUKH DEVELOPERS · TALOJA NEW, RaigarhP52000019977· 90.9% built
- Dwarka3.6 yr overdueMorajkar Estates LLP · Karanjade, RaigarhP52000020710· 78.2% built
- RAMESHWAR PARK - DAFFODIL A3.6 yr overdueRAMESHAWAR BUILDERS & DEVELOPERS · Thane, ThaneP51700014029· 78.6% built
- Aangan Phase II3.6 yr overdueGalaxy Associates · Mawal, PuneP52100019915· 2.3% built
- M M VALEY A23.6 yr overdueALFA ENTERPRISES · Thane, ThaneP51700010237· 87.5% built· 2 complaints
- SHAPOORJI PALLONJI THE DESIGNATE3.6 yr overdueBEHOLD SPACE DEVELOPERS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800001443· filed Jun 2021 → now Dec 2022· 80% built· 4 complaints
- AMAR ELITE APARTMENT3.6 yr overdueAMAR BUILDTECH PRIVATE LIMITED · AUDUMBAR STOP, NashikP51600022938· 81.8% built
- ROHAN MADHUBAN II WINGS D E3.6 yr overdueRohan Promoters & Developers · Pune City, PuneP52100002307· 90.9% built· 1 complaint
- FONTANA A ,B, I and J3.6 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000506· 81.8% built· 2 complaints
- Nirman Vimla Kanti3.6 yr overdueNirman Construction · Roha Ashtami (M Cl), RaigarhP52000003155· 90% built
- SHANTI HARMONY3.6 yr overdueSHANTI DEVELOPERS · VAKADI, RaigarhP52000015820· 86.4% built
- KRUSHAN DHAM3.6 yr overdueKRUSHAN DHAM BUILDERS & DEVELOPERS · Ambarnath, ThaneP51700015294· 90.9% built
- Pratik Residency3.6 yr overdueM/s Pratik constructions · Panvel, RaigarhP52000007028· 97.5% built
- Vakratund Heights3.6 yr overdueShivanjali Infrastructure · Palghar East, PalgharP99000020206· 90.5% built
- AGARWAL EXOTICA3.6 yr overdueAGARWAL REALTORS · Vasai, PalgharP99000002405· 90.9% built
- YOU57 TOWER A3.6 yr overdueSANAS DEVELOPERS PRIVATE LIMITED · HINJEWADI, PuneP52100021770· 84.4% built· 1 complaint
- Kalpataru Serenity - Bldg. 53.6 yr overdueKalpataru Gardens Pvt. Ltd. · Pune, PuneP52100001267· 88.6% built· 3 complaints
- SHANTI GARDENS, SECTOR 5, BLDG. NO.83.6 yr overdueRAMNAGAR DEVELOPMENT CORPORATION · SHANTI GARDENS, ThaneP51700010577· 90.5% built
- PATELS ELYSIUM - 53.6 yr overdueAPACE REALTY · Ambarnath(M Cl), ThaneP51700010318· 33.2% built
- LOKNAGARI3.6 yr overdueRAMSINA CONSTRUCTIONS THROUGH PROPRIETOR VIKESH ABHAYKUMAR OSWAL · NAGALA PARK, KolhapurP53000019345· 63.6% built
- Mahaavir Majesty - Phase II3.6 yr overdueMahaavir Impex · Near Taloja Phase II, RaigarhP52000016434· 90.9% built
- INDRAYANI HILLS3.6 yr overdueVARAD LANDMARK · AALANDIP52100016050· 90.9% built
- GALAXY APARTMENTS3.6 yr overdueDIVINE DOLPHIN ENTERPRISES · Ulwe (New), RaigarhP52000018320· 90.9% built· 1 complaint
- WINDSOR TOWER3.6 yr overdueS AND S ENTERPRISES · PUNE, PuneP52100020138· 90.9% built
- SEA REGENCY3.6 yr overdueSUREKHA TUKARAM DUDHE · Navi Mumbai, RaigarhP52000010351· filed Dec 2021 → now Dec 2022· 98.2% built· 3 complaints
- Mohnesh3.6 yr overdueMotwani International Services · Kalundre (CT), RaigarhP52000012024· filed Dec 2019 → now Dec 2022· 67.7% built
- Sumit Garden Grove3.6 yr overdueSumit Garden Grove Construction LLP · Chikoowadi, Mumbai SuburbanP51800009864· filed Dec 2021 → now Dec 2022· 45.5% built
- SHREE VIRAJ RESIDENCY WING C PHASE -II3.6 yr overdueSHREE VIRAJ ENTERPRISES · SHIRGAON, BADLAPUR (EAST), ThaneP51700018669· 90.9% built
- SHREE SAI RAJ PARK BUILDING NO 3 C WING3.6 yr overduesarvodayrajconstructioncompany · Kalyan, ThaneP51700007216· filed Dec 2019 → now Dec 2022· 81.8% built
- Nisarg Vatika Phase II3.6 yr overdueNisarg Ventures · Borhadewadi, PuneP52100020731· 90.9% built
- SWAPNA RATNA3.6 yr overdueJADHAV ASSOCIATES · DEFENCE COLONY, PuneP52100019026· 90.9% built
- The Serenes Villa No 173.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012537· 40.9% built
- The Serenes Villa No 73.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012867· 40.9% built
- SHARDA TOWER - I3.6 yr overdueM/S. CHETANA REALTORS · VIRAR EAST, PalgharP99000014523· 65.9% built
- KONARK SOLITAIRE - PHASE II3.6 yr overdueKONARK REALTIES J.V. · Ambivali, ThaneP51700023163· 90.9% built
- AAKAR IMPERIA3.6 yr overdueAAKAR BUILDWELL · Dwaraka, NashikP51600015799· 90.9% built
- SUNDARAM PALACE APARTMENT3.6 yr overdueHASMUKHBHAI JERAMBHAI SUHAGIYA · MAKHMALABAD SHIVAR, NashikP51600015731· 89.4% built
- Shrushti Aarambh, Wing - C of Phase - I3.6 yr overdueSHRUSHTI DEVELOPERS · Valivali, Badlapur (W), ThaneP51700015554· 80% built
- BLUE EMPIRE3.6 yr overdueBLUEBERRY DEVELOPERS · NEAR FOREST VIEW SOC., PuneP52100020878· 90.9% built
- PALAVA URBANO G AND H3.6 yr overdueLodha Developers Limited · Kalyan, ThaneP51700000696· 81.8% built· 1 complaint
- Durga Palace3.6 yr overdueHardik Developers · Anandvalli, NashikP51600015780· 90.9% built
- Itrend Homes Phase III3.6 yr overdueHighpoint Landmark LLP · Hinjewadi, PuneP52100022236· 62.7% built
- CELLO DECENT HOMES PHASE 33.6 yr overdueDECENT HOMES · NEAR STATION PALGHAR, PalgharP99000016928· 71.5% built
- Rise Alta3.6 yr overdueM/s. Anand Developers · Tathawade, PuneP52100010096· filed Dec 2019 → now Dec 2022· 45.5% built
- Silver Park Residency Orchid3.6 yr overdueSuyash Enterprises · Bhiwandi, ThaneP51700007849· 90.9% built
- SARGAM RESIDENCY3.6 yr overdueShantee Housing · NAIGAON, PalgharP99000016959· 87.9% built
- VAJRESHWARI APARTMENT3.6 yr overdueSHREE ADESHWAR BUILDCOM · UMROLI EAST, PalgharP99000017638· 86.4% built
- JALARAM MANGALAM3.6 yr overdueSHRI JALARAM DUGDHA KENDRA · HINGNA, NagpurP50500009887· filed Dec 2021 → now Dec 2022· 81.8% built· 2 complaints
- HAPPYCITY TALEGAON3.6 yr overdueNAMRATA DEVELOPERS · Jijamata Chowk, PuneP52100017513· 90.9% built
- The Onyx3.6 yr overdueVastukalp Promoters And Builders · WAKAD, PuneP52100001650· filed Feb 2019 → now Dec 2022· 81.8% built· 5 complaints
- Shankeshwar Prestige3.6 yr overdueNitin Chhaganlal Jain · Moshi, PuneP52100017693· 90.9% built
- KINGSBURY PHASE I3.6 yr overdueJaikul Associates · CHARHOLI, PuneP52100001994· 96.8% built· 2 complaints
- Tinsel Town Phase II3.6 yr overdueNew World Realty LLP · Maan, PuneP52100017178· 99.5% built
- Legacy bliss3.6 yr overdueWhite Properties · Wakad, PuneP52100015391· 90.9% built
- Amrutdhara A building3.6 yr overdueLunkad Gruh Nirman Company · Sai Mandir Wadmukhwadi, PuneP52100021533· 90.9% built
- SADANAND SHILP3.6 yr overdueDEVYANI HARISHCHANDRA ULWEKAR · Kalundre, RaigarhP52000013481· 82.3% built
- HILLSIDE SPACE3.6 yr overdueSPACE HOUSING · Karjat, RaigarhP52000006003· 79.5% built
- Hampton3.6 yr overdueROMA BUILDERS PRIVATE LIMITED · Thane, ThaneP51700000091· 90.9% built
- NANDADEVI GALAXY3.6 yr overdueAAIJI GROUP · KARANJADE, RaigarhP52000009334· 86.4% built
- Parks Developers LLP - Tanishq Gold - Phase 13.6 yr overdueParks Developers LLP · Dahanu, PalgharP99000015423· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.