RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 38 of 61
- KALPITA HEIGHTS3.9 yr overdueSHRI R N GOLI DEVELOPERS · Solapur (M Corp.), SolapurP52600004884· filed Dec 2018 → now Dec 2022· 76.4% built
- ROHAN ABHILASHA BUILDING D3.9 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · WAGHOLI, PuneP52100000673· 90.9% built· 1 complaint
- AURIS SERENITY TOWER 13.9 yr overdueTRANSCON-SHETH CREATORS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800001080· 98.2% built· 4 complaints
- Pelican Phase B3.9 yr overdueLaukik Construction Company · Pirangut, PuneP52100000949· filed Dec 2019 → now Dec 2022· 42.9% built· 1 complaint
- Richmond Park3.9 yr overdueLA CASA SHELTERS LLP · Rahatani, PuneP52100001358· filed Jun 2021 → now Dec 2022· 96.7% built
- Mangal Vishwa - Phase 23.9 yr overdueG.T.DEVELOPERS · Kiwale, PuneP52100018839· 90.9% built
- EXCEL GALAXY3.9 yr overdueEXCEL CONSTRUCTIONS · ULWE, RaigarhP52000017632· 90.9% built
- EVEREST PLAZA3.9 yr overdueCHOICE DEVELOPERS · JADHAVWADI, PuneP52100002269· 90.9% built· 1 complaint
- AAWAS DEEP3.9 yr overdueSHREE KRISHNA BUILDCON · YASHRAJ NAGAR, ThaneP51700014893· 27.7% built
- KONARK SOLITAIRE - PHASE II3.9 yr overdueKONARK REALTIES J.V. · Ambivali, ThaneP51700023163· 90.9% built
- SAI RESIDENCY3.9 yr overdueREVANJI RAMU CHOUGULE · NEAR RAJPUT COMPLEX, KolhapurP53000025158· 90.9% built
- Kalpataru Hills - Building 2A3.9 yr overdueKalpataru Properties (Thane) Pvt. Ltd. · Thane, ThaneP51700000584· 98.5% built· 2 complaints
- SUNRISE GLORY PHASE II3.9 yr overdueSUNRISE LIFESPACES LLP · Thane, ThaneP51700003397· 90.9% built· 10 complaints
- SHREE AMBA BUSINESS PARK WING B PHASE II3.9 yr overdueSHREE AMBA BUSINESS PARK · RAHATGAON, AmravatiP50300019011· 72.7% built
- Vaikunth Dham CHS Ltd3.9 yr overdueShivshankar Singh & Others · Kurla, Mumbai SuburbanP51800006275· 86.7% built
- Aapla Ghar Chakan Phase II Amenity Bldg A3.9 yr overdueMaple Estates · Nanekarwadi (CT), PuneP52100008123· 18.2% built
- Mohan Areca3.9 yr overdueMOHAN LIFESPACES LLP · Ambarnath, ThaneP51700000829· filed Dec 2019 → now Dec 2022· 88.6% built· 14 complaints
- PALAVA URBANO G AND H3.9 yr overdueLodha Developers Limited · Kalyan, ThaneP51700000696· 81.8% built· 1 complaint
- Life Republic Sector R16 - 16th Avenue3.9 yr overdueKOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED · Jambe, PuneP52100009640· 90.9% built· 1 complaint
- FIA PARADISE3.9 yr overdueNIMISH LAXMICHAND PASAD · PALGHAR, PalgharP99000015897· 81.8% built
- NISARG3.9 yr overdueKULSWAMINI ASSOCIATES PROMOTOERS AND BUILDERS · chakan, PuneP52100002785· filed Dec 2018 → now Dec 2022· 90.9% built
- MARATHON NEXZONE ALTIS -23.9 yr overdueSANVO RESORTS PVT. LTD. · PALASPE PHATA, RaigarhP52000000677· filed Jun 2021 → now Dec 2022· 72.7% built· 1 complaint
- KINGSBURY PHASE I3.9 yr overdueJaikul Associates · CHARHOLI, PuneP52100001994· 96.8% built· 2 complaints
- SUHRUD3.9 yr overdueGANGOTREE GREENBUILD · Erandwane, PuneP52100013402· 90.9% built
- Pratik Residency3.9 yr overdueM/s Pratik constructions · Panvel, RaigarhP52000007028· 97.5% built
- MAHAVIR PARADISE , PHASE - 13.9 yr overdueMAHAVIR ENTERPRISES · CHIKLOLI, ThaneP51700016012· 90.9% built
- ROYAL EXOTICA PHASE I3.9 yr overdueSVG Builders LLP · KONDHWA BUDRUK, PuneP52100018700· 89.1% built
- RADHA KRISHNA3.9 yr overdueRAMPRASAD SOHANLAL AGRAWAL · Thane, ThaneP51700016450· 90.9% built
- M M VALEY A23.9 yr overdueALFA ENTERPRISES · Thane, ThaneP51700010237· 87.5% built· 2 complaints
- Palladio Phase 23.9 yr overdueVilas Javdekar Eco Developers Pvt. Ltd. · behind D Y Patil college, PuneP52100017306· 91.5% built
- SHIVASAMRITI APARTMENT3.9 yr overdueSANJIV LAXMAN SALVI · Chiplun (M Cl), RatnagiriP52800011328· 22.7% built
- SAI DARSHAN3.9 yr overdueSAI SHRUTI DEVELOPERS · Haveli, PuneP52100004582· 81.8% built
- PRATHAM3.9 yr overdueVARDHMAN ENTERPRISES · Andheri, Mumbai SuburbanP51800009959· filed Dec 2017 → now Dec 2022· 90.9% built· 7 complaints
- Indiabulls Greens - 43.9 yr overdueLucina Land Development Limited · Panvel, RaigarhP52000002658· filed Jun 2021 → now Dec 2022· 99.5% built· 7 complaints
- KRUSHAN DHAM3.9 yr overdueKRUSHAN DHAM BUILDERS & DEVELOPERS · Ambarnath, ThaneP51700015294· 90.9% built
- KRISHNA HERITAGE3.9 yr overdueKRISHNA ENTERPRISES · KANDIVALI WEST, Mumbai SuburbanP51800017093· 90.9% built
- AMAR ELITE APARTMENT3.9 yr overdueAMAR BUILDTECH PRIVATE LIMITED · AUDUMBAR STOP, NashikP51600022938· 81.8% built
- Building no. 1 , Uptown Avenue3.9 yr overdueSimran Enterprises · Sai Nagar, RaigarhP52000016037· 90.9% built
- SAUSHILYA3.9 yr overdueSILVER LEAF REALTY · Mamdapur, RaigarhP52000004115· 90.9% built
- GANESHMURTI APARTMENT3.9 yr overdueNOOR MOHAMMED IDRIS JALGAONKAR · SECTOR R4 PUSHPAK, RaigarhP52000021824· 90.9% built
- CLOVER HILLS PLAZA3.9 yr overdueClover Buildcorp · NIBM road, PuneP52100002324· 50% built
- VENKATESH GRAFFITI PHASE 63.9 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAVNAGAR MUNDHWA, PuneP52100021891· 90.9% built
- JALARAM MANGALAM3.9 yr overdueSHRI JALARAM DUGDHA KENDRA · HINGNA, NagpurP50500009887· filed Dec 2021 → now Dec 2022· 81.8% built· 3 complaints
- Vakratund Heights3.9 yr overdueShivanjali Infrastructure · Palghar East, PalgharP99000020206· 90.5% built· 1 complaint
- SHANKHESHWAR LAKE VIEW3.9 yr overdueSHREE SHANKHESHWAR ENTERPRISES · KHABALPADA, ThaneP51700015923· 90.9% built
- AVIGHNA3.9 yr overdueV.S.CONSTRUCTIONS · Panvel, RaigarhP52000013885· 90.9% built
- CHANDRAMA HEIGHTS3.9 yr overdueBABANRAO DAGU JADHAV · KAMATWADA, NashikP51600023390· 81.8% built
- Hemant Arcade3.9 yr overdueM/s VISHAL CONSTRUCTION · Nr Amrapali Hotel, ThaneP51700021187· 0% built
- The Serenes Villa No 83.9 yr overdueMahindra Lifespace Developers limited · Nagaon, RaigarhP52000012883· 34.4% built
- Narhar Complex3.9 yr overdueYamuna Developers · Chowphala, SolapurP52600013908· 95.9% built
- SAROVAR3.9 yr overdueS D Buildcon · Uran, RaigarhP52000001908· 70.5% built
- GVC SHAGUN CITY PHASE 13.9 yr overdueSHAGUN ASSOCIATES · KAUTHA, NandedP51100015116· 78.2% built
- Mohnesh3.9 yr overdueMotwani International Services · Kalundre (CT), RaigarhP52000012024· filed Dec 2019 → now Dec 2022· 67.7% built
- Geras Imperium Oasis3.9 yr overdueGera Developments Private Limited · Pimpri Waghere Pune, PuneP52100015514· 81.8% built· 5 complaints
- GATHA AARAMBH3.9 yr overdueSAFFRON PROPERTIES · Haveli, PuneP52100003408· 90.9% built
- Barrington3.9 yr overdueROMA BUILDERS PRIVATE LIMITED · Thane, ThaneP51700000117· 90.9% built
- Puraniks Abitante Phase 1B3.9 yr overduePuranik Buildcon Private Limited · Bavadhan BK, PuneP52100000569· 90.9% built· 1 complaint
- Rustomjee Elements - Wing SC3.9 yr overdueRustomjee Realty Private Limited · Andheri, Mumbai SuburbanP51800005738· filed Jun 2021 → now Dec 2022· 69.5% built
- CLASSIQUE3.9 yr overdueSHRUSHTI DEVELOPERS · NEAR NAVALI PHATAK, PalgharP99000014864· 90.9% built
- Blue Pearl Industrial Estate3.9 yr overdueM/s Mount Realtors · Village Bapane, PalgharP99000022109· 27.3% built
- ABHIMAN SHRI3.9 yr overdueRATNADEEP PRAMOTERS AND BUILDERS · Charholi Khurd, PuneP52100014831· filed Dec 2021 → now Dec 2022· 99.1% built
- SAI CHARAN COMPLEX BUILDING NO 33.9 yr overdueOM SAI CHARAN BUILDERS · Thane, ThaneP51700001132· 90.9% built
- WINDSOR TOWER3.9 yr overdueS AND S ENTERPRISES · PUNE, PuneP52100020138· 90.9% built
- Shiv Plaza3.9 yr overdueGanesh Thakur · Parasnath Nagri, PalgharP99000019525· 75% built
- Nivara Nere Part-13.9 yr overdueBVG Five Elements Shelters · Nere, PuneP52100014012· 90.9% built
- SHREE SWAMI SAMARTH APARTMENT PH-II3.9 yr overdueSUMAN ASSOCIATES · Shirur, PuneP52100014970· 66.8% built
- Vishal Viviana3.9 yr overdueVISHAL REALTORS · Mundhawa, PuneP52100000765· 90.9% built
- LA ROYALE - A BUILDING3.9 yr overdueDEVI SHAKTI REALTY LLP · UNDRI, PuneP52100012441· 18.2% built· 1 complaint
- MONTESOUTH-13.9 yr overdueSWAYAM REALTORS & TRADERS LLP · NEXT TO BYCULLA FIRE BRIGADEP51900001936· 93.1% built
- AJIT RESIDENCY3.9 yr overdueAJIT DEVELOPERS · BEED BY PASS ROAD, AurangabadP51500023785· 90.9% built
- SAHIL OM PARK3.9 yr overdueVAISHNAVI PROMOTERS AND DEVELOPERS · Moshi, PuneP52100011417· filed Dec 2019 → now Dec 2022· 72.7% built
- Nisarg Vatika Phase II3.9 yr overdueNisarg Ventures · Borhadewadi, PuneP52100020731· 90.9% built
- ACE HOMES3.9 yr overdueAARTI ESTATES · KASARVADAVALI, ThaneP51700016575· 90.9% built
- 87 NINAD3.9 yr overdueMAAULI CREATIONS PVT LTD · Mumbai City, Mumbai CityP51900018948· 0.5% built
- Vrundavan Residency3.9 yr overdueTejal Builders and Developers · Aurangabad (M Corp.), AurangabadP51500006020· 71.8% built
- Mont Vert Yolo3.9 yr overdueMont Vert Elegance · Bhugaon, PuneP52100007210· 24.7% built
- Shrushti Aarambh, Wing - C of Phase - I3.9 yr overdueSHRUSHTI DEVELOPERS · Valivali, Badlapur (W), ThaneP51700015554· 80% built
- EKTA TRINITY3.9 yr overdueEKTA HOUSING PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800005021· 94.3% built
- GRACIA3.9 yr overdueSAGA CHRISHH ASSOCIATES · TALEGAON DABHADE, PuneP52100023014· 27.3% built
- The Serenes Villa No 223.9 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012523· 40.9% built
- addressOne - Phase 13.9 yr overduePeninsula Land Limited · Nr Maharashtra Cricket Association Stadium, Gahunje Pune, PuneP52100015756· 69.2% built· 4 complaints
- MALHAR HEIGHTS3.9 yr overdueSAI SAMARTH DEVELOPERS · NEAR SHARDUL PETROL PUMP, SolapurP52600020963· 90.9% built
- BALAJI EXOTICA-PHASE 13.9 yr overdueBALAJI WORLD · CHIKANGHAR, ThaneP51700015155· 90.9% built· 1 complaint
- SHREE MAHALAXMI HOMES3.9 yr overdueMAHALXMI FORTUNE · CHIKLOLI, ThaneP51700016810· 69.7% built
- PANCHAMI RESIDENCY3.9 yr overdueS K BUILDCON · PATHARDI, NashikP51600018928· 90.9% built
- Eagleton3.9 yr overdueROMA BUILDERS PRIVATE LIMITED · Thane, ThaneP51700000089· 90.9% built
- SHIVALIK SPARSH3.9 yr overdueMADHUBHAI BABUBHAI KOTHIYA · PATHARDI, NashikP51600016159· 90.9% built
- Fairway3.9 yr overdueROMA BUILDERS PRIVATE LIMITED · Thane, ThaneP51700000152· 90.9% built
- VIHANGS VERMONT3.9 yr overdueVIHANG ENTERPRISES · Thane, ThaneP51700001458· 84% built· 3 complaints
- M 193.9 yr overdueSUVIDHA LIFESPACES · Ward FNorth, Mumbai CityP51900007305· 62.7% built
- Sai Satyam Homes3.9 yr overdueSai Satyam Developers · Kalyan, ThaneP51700001809· filed Jun 2021 → now Dec 2022· 90.9% built
- Aangan Phase II3.9 yr overdueGalaxy Associates · Mawal, PuneP52100019915· 2.3% built
- PRIDE SIGNATURE3.9 yr overduePRIDELAND PROPERTY · Malwan (M Cl), SindhudurgP52900009932· 78.4% built
- MANSAROVAR RESIDENCY E WING3.9 yr overdueKIRAN REALTY · Thane, ThaneP51700006405· 90.9% built
- PARK EXPRESS PHASE III3.9 yr overduePARK EXPRESS JOINT VENTURE · BALEWADI, PuneP52100018658· 65.5% built
- NAVNEET SADAN CHS LTD3.9 yr overdueSHREE SWAMI SAMARTH BUILDERS & DEVELOPERS · Kurla, Mumbai SuburbanP51800011489· 80% built
- Manaswi Apartment3.9 yr overdueNitin Amrutkar & Associates · Indiranagar, NashikP51600013686· 90.9% built
- Apratim Park Uttam Nagari3.9 yr overdueGanesh Parvatrao Jaybhaye · Aurangabad (M Corp.), AurangabadP51500002890· 39.8% built· 1 complaint
- DYNAMIC CREST PHASE I - RIMO/EVEREST3.9 yr overdueSNEH MAKEWELL LLP · DOMBIVALI, ThaneP51800001460· filed Jun 2021 → now Dec 2022· 72.7% built
- Patson Orchid3.9 yr overduePatson Builders · Kolhapur (M Corp.), KolhapurP53000003032· 90.9% built
- OLYMPIA PHASE 13.9 yr overdueOXFORD INFRA GROUP · Wakad, PuneP52100009480· filed Dec 2018 → now Dec 2022· 52.3% built· 15 complaints
- Sanskruti Splendour3.9 yr overdueSanskruti Nirman Pvt. Ltd. · BORIVALI, Mumbai SuburbanP51800009760· 58.2% built· 1 complaint
- VRINDAVAN COMPLEX3.9 yr overdueKRISHNARAJ REALTORS · VILLAGE MAHIM,, PalgharP99000016299· 72.7% built
- SIGNATURE BUSINESS PARK3.9 yr overdueSwastik Developers · Chembur, Mumbai SuburbanP51800007575· 79.1% built· 1 complaint
- Eternia Space3.9 yr overduePLANET SPACE · Karjat, RaigarhP52000008057· 81.8% built· 1 complaint
- TULIP ELEMENT3.9 yr overdueTushar Mohanrao Khatavkar · E ward, KolhapurP53000026601· 30.5% built
- Mahindra Happinest Palghar Phase - IV3.9 yr overdueMAHINDRA HAPPINEST DEVELOPERS LIMITED(Formerly known as Mahindra Happinest Developers Pvt. LTD) · Nandore, PalgharP99000017770· 81.8% built· 1 complaint
- SHUBHAM HEIGHTS3.9 yr overdueSHYAMSUNDER RADHYSHYAM AGRAWAL · Mira-Bhayandar (M Corp.), ThaneP51700004023· 39.5% built
- LOTUS PARK3.9 yr overdueREAL ENTERPRISE · SHAHPUR, ThaneP51700020522· 74.5% built
- TEJ VIHAR3.9 yr overdueTEJ BUILDCON THROUGH PROPRIETOR SHIVTEJ PRAMOD JAGTAP · SAGUNAMATANAGAR, SataraP52700025315· 72.7% built
- Nirman Vimla Kanti3.9 yr overdueNirman Construction · Roha Ashtami (M Cl), RaigarhP52000003155· 90% built
- SHUBHAMANGAL3.9 yr overdueSHUBHAMANGAL DEVELOPERS · BAHINABAI NAGAR, JalgaonP49900020433· 40.5% built
- Anant Sapphire3.9 yr overdueAnant Realty · Adai, RaigarhP52000017134· 90.9% built
- THAKUR ASPIRE3.9 yr overdueTHAKUR REALTY PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800003848· 21.8% built
- Casa Emerald3.9 yr overdueHEMALI INVESTMENTS & FINANCE PVT.LTD. · Ward E, Mumbai CityP51900003998· 98.6% built
- ITREND HOMES PHASE II WING B3.9 yr overdueHighpoint Landmark LLP · HINJEWADI, PuneP52100017586· 90.9% built
- Kalash3.9 yr overdueKemi Creation earlier known as Taru Venture · Vasai, PalgharP99000003386· filed Dec 2018 → now Dec 2022· 90.9% built
- SWAPNABAN3.9 yr overdueBHAISHREE VENTURES · NEAR GRAMPANCHAYAT OFFICE, AurangabadP51500016418· 76.8% built
- Anandgriha Phase III3.9 yr overdueKACHHI PROPERTIES · Satara, SataraP52700007506· filed Dec 2019 → now Dec 2022· 40% built
- LODHA SEAVIEW3.9 yr overdueMACROTECH DEVELOPERS LIMITED · Ward ABCD, Mumbai CityP51900010326· 90.9% built· 9 complaints
- GREEN NEST3.9 yr overdueRohit Tanaji Omase · BASUGADE MALA, SangliP53100024043· 81.8% built
- Raheja Imperia - I3.9 yr overdueRaheja Universal (Pvt.) Ltd. · Ward GSouth, Mumbai CityP51900009379· 99.5% built· 7 complaints
- LATA APARTMENT3.9 yr overdueBabasaheb Pandurang Patil · Vengurla, SindhudurgP52900007169· 68.2% built
- VIJAY SILICA3.9 yr overdueV Y NIKHAR & ASSOCIATES · Bhandara (M Cl), BhandaraP50600007749· 90.9% built
- SADANAND SHILP3.9 yr overdueDEVYANI HARISHCHANDRA ULWEKAR · Kalundre, RaigarhP52000013481· 82.3% built
- SAI YASH COMPLEX3.9 yr overdueMahatma Infrasturcture (India) LLP · Shirgaon, PalgharP99000013008· 9.4% built
- VIJAY SUNSTONE3.9 yr overdueV Y NIKHAR & ASSOCIATES · Bhandara (M Cl), BhandaraP50600008375· 90.9% built
- FIA EMERALD3.9 yr overdueNIMISH LAXMICHAND PASAD · Palghar, PalgharP99000013971· 81.8% built
- SHREE RAM KRUPA APARTMENT3.9 yr overdueVISHAL DILIP DOSHI · NEAR UBHA MARUTI, RaigarhP52000017712· 90.9% built
- Keshar Kunj3.9 yr overdueKeshar Realities · Panvel, RaigarhP52000008372· 55.1% built
- Goodwill Unique Zest County Phase 13.9 yr overdueZENITH BUILDCON · Lohegaon, PuneP52100016454· 90.9% built
- The Serenes Villa No 473.9 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000017563· 40.9% built
- SURATWALA MARK PLAZZO - WING B - PHASE 13.9 yr overdueSURATWWALA BUSINESS GROUP LIMITED · HINJAWADI, PuneP52100017784· 79.5% built· 1 complaint
- Mahindra Happinest Palghar Phase V3.9 yr overdueMAHINDRA HAPPINEST DEVELOPERS LIMITED(Formerly known as Mahindra Happinest Developers Pvt. LTD) · nandore, PalgharP99000015852· 81.8% built· 2 complaints
- SALANGPUR NIRMAN3.9 yr overdueSALANGPUR NIRMAN · MIRA ROAD EAST, ThaneP51700020659· 90.9% built
- M P Keshav3.9 yr overdueM P Construction · Pushpak New, RaigarhP52000019549· 90.9% built
- KAMALJA3.9 yr overdueM/S. SAIVIJAY BUILDERS AND DEVELOPERS JADHAV KADU · ULWE, RaigarhP52000017514· 81.8% built
- Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG3.9 yr overdueAmravati Housing And Area Development Board Amravati · Akoli, AmravatiP50300015120· 89.1% built
- WESTERN PARK3.9 yr overdueSHAKTI DEVELOPERS · Vasai, PalgharP99000005755· filed Jun 2021 → now Dec 2022· 84.1% built
- Mahaavir Majesty - Phase II3.9 yr overdueMahaavir Impex · Near Taloja Phase II, RaigarhP52000016434· 90.9% built
- SYLVAN HEIGHTS H BUILDING3.9 yr overdueNAIKNAVAREDEVELOPERSPVTLTD · AUNDH, PuneP52100021048· 66.4% built
- FONTANA A ,B, I and J3.9 yr overduePalava Dwellers Private Limited · Kalyan, ThaneP51700000506· 81.8% built· 2 complaints
- KHALIFE GARDEN3.9 yr overdueM/S NSK ESTATES · Rajapur (M Cl), RatnagiriP52800013767· 90.9% built
- Haware Meadows Phase 13.9 yr overdueHAAAS Corporation Private Limited · Mamdapur, RaigarhP52000015126· 90.9% built
- FLORENTIA3.9 yr overdueSIDDHIVINAYAK HOMES PVT. LTD. · MIRA BHAYANDAR, ThaneP51900009486· 90.9% built· 1 complaint
- Rise Alta3.9 yr overdueM/s. Anand Developers · Tathawade, PuneP52100010096· filed Dec 2019 → now Dec 2022· 45.5% built
- HILLSIDE SPACE3.9 yr overdueSPACE HOUSING · Karjat, RaigarhP52000006003· 79.5% built
- Avadha Annexe3.9 yr overdueVrundavan Developers · Samarth Nagar, Pathardi, NashikP51600015198· 90.9% built
- MORAYA PARK PHASE III3.9 yr overdueHARSIDDHI BUILDERS · HARSUL, AurangabadP51500017172· 32.7% built
- EMPIRE ESTATE3.9 yr overdueCHHATRAPATI SAMRAJYA · IN FRONT OF SAHYADRI HOSPITAL NARAYAN COLONY KAKADE PLOT, OsmanabadP52500015208· 59.1% built
- WINDCHIME HOMES PHASE 23.9 yr overdueSUJAY VENTURES · -, PuneP52100004047· filed Jun 2021 → now Dec 2022· 57.5% built
- CASA ASUD - PHASE I3.9 yr overdueSKYLINE DEVELOPERS · Asud, RatnagiriP52800006057· filed Dec 2018 → now Dec 2022· 69.1% built
- ARIHANT RESIDENCY3.9 yr overdueARIHANT BUILDERS AND DEVELOPERS · YADOGOPAL PETH, SataraP52700022113· 6.4% built
- NISARG TULIPS3.9 yr overdueADITYA SHAGUN DEVELOPERS · BAVDHAN, PuneP52100014405· 70% built
- AVIOR AATMAN3.9 yr overdueAVIORENTERPRISES LLP · Pune City, PuneP52100019192· 81.8% built
- Itrend Homes Phase III3.9 yr overdueHighpoint Landmark LLP · Hinjewadi, PuneP52100022236· 62.7% built
- SHREE VIRAJ RESIDENCY WING C PHASE -II3.9 yr overdueSHREE VIRAJ ENTERPRISES · SHIRGAON, BADLAPUR (EAST), ThaneP51700018669· 90.9% built
- BLUE EMPIRE3.9 yr overdueBLUEBERRY DEVELOPERS · NEAR FOREST VIEW SOC., PuneP52100020878· 90.9% built
- Avant Heritage II-Basement plus stilt plus 3 Podium plus 20 Upper Habitable Floors3.9 yr overdueAishwarya Avant Builders LLP · Andheri, Mumbai SuburbanP51800015537· filed Jun 2021 → now Dec 2022· 80% built· 5 complaints
- Dwarka3.9 yr overdueMorajkar Estates LLP · Karanjade, RaigarhP52000020710· 78.2% built
- Bhoomi Acres L wing3.9 yr overdueV R Constructors Private Limited · Thane, ThaneP51700020184· 98.5% built· 3 complaints
- NOVA RESIDENCY3.9 yr overdueAMIT JUGALKISHOR RATHI · BEHIND RAJASHREE SHAU COLLEGE, PuneP52100018498· 95.5% built
- Avighna IX - Building No. 43.9 yr overdueNish Developers Private Limited · CURRY ROADP51900003525· 94.4% built
- Regalia Phase 13.9 yr overdueTirupati Tingre Builtcon · Anand ParkP52100019785· 90.9% built
- Nirman Ajinkyatara Wing C3.9 yr overdueNIRMAN DEVELOPERS · Ambegaon Budruk, PuneP52100013288· 32.7% built
- DEEP CLASSIC TOWER3.9 yr overdueSAI SANGAM DEVELOPERS · Vasai, PalgharP99000012178· filed Jun 2021 → now Dec 2022· 89.7% built· 6 complaints
- OSHO DAYARAM3.9 yr overduePARVATI CONSTRUCTION CO. · Thane, ThaneP51700003187· 90.9% built
- Shri Baba Ramdev Textile and Housing Market- Wing A-13.9 yr overdueN. Jaju Malpani Infra Pvt. Ltd. · Ichalkaranji (M Cl), KolhapurP53000009180· 23.1% built· 1 complaint
- SHREE GAURANG3.9 yr overdueGAURANG ASSOCIATES · NAUPADA, ThaneP51700015176· 0% built· 7 complaints
- C VINAYAK INDUSTRIAL ESTATE3.9 yr overdueVINAYAK CONSTRUCTION · Palghar, PalgharP99000008974· filed Dec 2018 → now Dec 2022· 72.7% built
- Marvel Piazza phase -013.9 yr overdueMARVEL ZETA DEVELOPERS PVT LTD · LOHGAON, PuneP52100003653· filed Jun 2021 → now Dec 2022· 61.1% built· 27 complaints
- Supare Nagar Township3.9 yr overdueS. K. Constructions · Yerkheda (CT), NagpurP50500006297· 78.2% built
- NILAM3.9 yr overdueNILAM RAMAKANT SANKHE · BOISAR, PalgharP99000020822· 27.3% built
- Four Seasons Private Residences Phase - 13.9 yr overdueProvenance Land Private Limited · Ward GSouth, Mumbai CityP51900002789· filed Dec 2020 → now Dec 2022· 81.8% built
- Urban Park3.9 yr overdueUrban Developers · Haveli, PuneP52100014555· 90.9% built
- MARVEL SERA A,B,C BUILDING3.9 yr overdueMARVEL SIGMA HOMES PRIVATE LIMITED · Hadapsar, PuneP52100001878· 0% built· 9 complaints
- ANGELS PARAMOUNT3.9 yr overdueACECON VENTURES · OPP JAYANTI NAGRI II, NagpurP50500019515· 90.9% built
- PRISTINE PURVRANG PART 13.9 yr overduePADMAVATI HOMES · Perane, PuneP52100001262· 80.3% built
- COMFORT ZONE3.9 yr overdueADITYA SHAGUN DEVELOPERS · BALEWADI, PuneP52100014406· 78.2% built· 1 complaint
- N G TIVOLI Phase I3.9 yr overdueRNA Builders (NG) · Mira Road, ThaneP51700015568· 37.5% built
- Willowcrest3.9 yr overdueROMA BUILDERS PRIVATE LIMITED · Thane, ThaneP51700000146· 90.9% built
- Lodha Amara - Tower 36 373.9 yr overdueLODHA DEVELOPERS LIMITED · ., ThaneP51700013961· 81.8% built· 4 complaints
- Samraat Gokuldham Project 023.9 yr overdueM/S Shweta Infrastructure & Housing (I) Pvt. Ltd. · Hirawadi, NashikP51600020375· 90.9% built
- NISHIGANDHA PARK PHASE 13.9 yr overdueM/S ARCHWAY ESTATES · Kothrud, PuneP52100005610· filed Dec 2018 → now Dec 2022· 61.4% built· 1 complaint
- BALAJI SHRUSHTI3.9 yr overdueVARSHA BUILDCON · Thane, ThaneP51700014837· 80.9% built
- RADHAKRISHNA CHS LTD3.9 yr overdueWESTIN SANKALP DEVELOPERS · Kandivli West, Mumbai SuburbanP51800018207· 90.9% built
- SWASTIK EMERALD3.9 yr overdueSwastik Realtors · Kurla, Mumbai SuburbanP51800014935· 90.9% built
- SHREE KRISHNA RESIDENCY3.9 yr overdueKARWA CONSTRUCTIONS AND DEVELOPERS · Golwadi, AurangabadP51500013874· 90% built
- The Serenes Villa No 43.9 yr overdueMahindra Lifespace Developers limited · Nagaon, RaigarhP52000012795· 38.2% built
- HARMONY COMPLEX - C - WING3.9 yr overdueGOOD LUCKDEVELOPERS · Thane, ThaneP51700004497· 39.8% built
- SHIVKRUPA HEIGHTS3.9 yr overdueSHIVKRUPA BUILDERS AND LAND DEVELOPERS · DATTA NAGAR, CHUNCHALE, NASHIK, NashikP51600023921· 90.9% built
- Legacy bliss3.9 yr overdueWhite Properties · Wakad, PuneP52100015391· 90.9% built
- Durga Palace3.9 yr overdueHardik Developers · Anandvalli, NashikP51600015780· 90.9% built
- AAKAR IMPERIA3.9 yr overdueAAKAR BUILDWELL · Dwaraka, NashikP51600015799· 90.9% built
- GAUTAMI MAI FLEUR3.9 yr overdueNitin Baburao Jirge · Tarabai Park, KolhapurP53000016326· 38.6% built
- Dias Residency Park3.9 yr overdueM/s Dias Properties & Projects · Sativali, PalgharP99000007801· filed Jun 2021 → now Dec 2022· 31.5% built
- Kashish Park Ghatkopar3.9 yr overdueLadam Homes Pvt Ltd. · Kurla, Mumbai SuburbanP51800002692· filed Jun 2021 → now Dec 2022· 90.8% built· 11 complaints
- KALPATARU RESIDENCY3.9 yr overdueDEVYANI R DODIA · Dadra & Nagar Haveli, Dadra & Nagar HaveliP49600000026· 50% built
- HILLSIDE RESIDENCY3.9 yr overdueRAJSHREE LANDMARK LLP · OFF DUDULGAON, PuneP52100018135· 53.6% built
- SHREEJI NISARG PHASE I3.9 yr overdueSHREEJI DEVELOPERS · ERANJAD, 30 MTR BARVI DAM ROAD, ThaneP51700015127· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.