RERA projects past their possession deadline
11,768 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 38 of 59
- K B RESIDENCY3.6 yr overdueK B INFRA · HARSOOL, AurangabadP51500009150· filed Jul 2019 → now Dec 2022· 90.9% built· 1 complaint
- Construction of 674 EWS T/s 409 MIG T/s 104 HIG T/s under PMAY at Akoli Amravati / EWS and MIG3.6 yr overdueAmravati Housing And Area Development Board Amravati · Akoli, AmravatiP50300015120· 89.1% built
- SHANTI VAIBHAV APARTMENT3.6 yr overdueSAHYOG VASTU UDYOG · BEHIND PALM HOTEL, NashikP51600018728· 90.9% built
- SAPPHIRE HEIGHTS3.6 yr overdueJAMALUDDIN HIMAYATALI SHAIKH · Vasai, PalgharP99000011761· filed Jun 2021 → now Dec 2022· 70% built· 1 complaint
- CLASSIQUE3.6 yr overdueSHRUSHTI DEVELOPERS · NEAR NAVALI PHATAK, PalgharP99000014864· 90.9% built
- La Ventana Phase 23.6 yr overdueLAVENTANA LLP · Kondhwa, PuneP52100021496· 90.9% built
- VENKATESH GRAFFITI PHASE 63.6 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAVNAGAR MUNDHWA, PuneP52100021891· 90.9% built
- C VINAYAK INDUSTRIAL ESTATE3.6 yr overdueVINAYAK CONSTRUCTION · Palghar, PalgharP99000008974· filed Dec 2018 → now Dec 2022· 72.7% built
- Euro Ville Phase II3.6 yr overdueVastu Rachana JV · Kharade, ThaneP51700001090· 54.5% built
- VISTARA3.6 yr overdueBuildstrong Estate Realtors LLP · Chikhali, PuneP52100022491· 90.9% built
- AJIT RESIDENCY3.6 yr overdueAJIT DEVELOPERS · BEED BY PASS ROAD, AurangabadP51500023785· 90.9% built
- Rustomjee Seasons - Wing A3.6 yr overdueKEYSTONE REALTORS LIMITED · Andheri, Mumbai SuburbanP51800001433· 89.1% built· 4 complaints
- NIRVANA BEYOND B WING3.6 yr overdueDIAMOND NEXUS PROPERTIES · KATALE WASTI, PuneP52100019054· 90.5% built
- KONARK MEADOWS Phase-13.6 yr overdueAtlanta Landmark · Varap, ThaneP51700009313· 90.9% built· 1 complaint
- AVIGHNA3.6 yr overdueV.S.CONSTRUCTIONS · Panvel, RaigarhP52000013885· 90.9% built
- Four Seasons Private Residences Phase - 13.6 yr overdueProvenance Land Private Limited · Ward GSouth, Mumbai CityP51900002789· filed Dec 2020 → now Dec 2022· 81.8% built
- Primus Residences3.6 yr overdueGurukrupa Developers · Andheri, Mumbai SuburbanP51800003522· 83.9% built· 3 complaints
- Siddharth Residency Building no 2 wing d and e3.6 yr overdueRamesh Jadhavji Gajra · Kurla, Mumbai SuburbanP51800010378· 90.9% built
- ANIKA REGALIA3.6 yr overdueArun Pitamber Sheth · GULTEKADI, MUKUNDNAGAR, PUNE, PuneP52100019498· 93.6% built
- GALAXY CITY3.6 yr overdueJITU PROPERTIES & DEVELOPMENTS PVT LTD · Lonavala (M Cl), PuneP52100001605· filed May 2018 → now Dec 2022· 89.1% built
- EVEREST PLAZA3.6 yr overdueCHOICE DEVELOPERS · JADHAVWADI, PuneP52100002269· 90.9% built· 1 complaint
- SALANGPUR NIRMAN3.6 yr overdueSALANGPUR NIRMAN · MIRA ROAD EAST, ThaneP51700020659· 90.9% built
- KAILASA3.6 yr overdueDEVNANI DEVELOPERS · CHEMBUR WEST, Mumbai SuburbanP51800017580· filed Jun 2021 → now Dec 2022· 90.9% built· 2 complaints
- Indiabulls Greens - 43.6 yr overdueLucina Land Development Limited · Panvel, RaigarhP52000002658· filed Jun 2021 → now Dec 2022· 99.5% built· 7 complaints
- Anant Sapphire3.6 yr overdueAnant Realty · Adai, RaigarhP52000017134· 90.9% built
- ITREND HOMES PHASE-I3.6 yr overdueHighpoint Landmark LLP · Man, PuneP52100001119· 90.9% built
- LEELA APARTMENT3.6 yr overdueSHUBHAM BUILDERS AND DEVELOPERS · BHAYANDER, ThaneP51700016282· 59.1% built
- KHALIFE GARDEN3.6 yr overdueM/S NSK ESTATES · Rajapur (M Cl), RatnagiriP52800013767· 90.9% built
- Dev Darshan3.6 yr overdueCITY ESTATE DEVELOPERS LIMITED · Kurla, Mumbai SuburbanP51800007029· 45.5% built· 1 complaint
- TULSI APARTMENT3.6 yr overdueSHEETAL BUILDERS AND DEVELOPERS · Vasai, PalgharP99000016287· 90.9% built
- SHUBHAM HEIGHTS3.6 yr overdueSHYAMSUNDER RADHYSHYAM AGRAWAL · Mira-Bhayandar (M Corp.), ThaneP51700004023· 39.5% built
- VRINDAVAN COMPLEX3.6 yr overdueKRISHNARAJ REALTORS · VILLAGE MAHIM,, PalgharP99000016299· 72.7% built
- NISARG3.6 yr overdueKULSWAMINI ASSOCIATES PROMOTOERS AND BUILDERS · chakan, PuneP52100002785· filed Dec 2018 → now Dec 2022· 90.9% built
- DHAVAL3.6 yr overdueSHREEJI AND INNOVATIVE DEVELOPERS · VILLAGE BELVALI ,BACK SIDE OF RIDDHI SIDDHI BUILDING, ThaneP51700028136· 81.8% built
- SANSKRUTI3.6 yr overdueM/S. V.R. BUILDERS · Sector 19, RaigarhP52000014578· 90.9% built
- MAHAVIR PARADISE , PHASE - 13.6 yr overdueMAHAVIR ENTERPRISES · CHIKLOLI, ThaneP51700016012· 90.9% built
- ANGELS PARAMOUNT3.6 yr overdueACECON VENTURES · OPP JAYANTI NAGRI II, NagpurP50500019515· 90.9% built
- SHANKHESHWAR LAKE VIEW3.6 yr overdueSHREE SHANKHESHWAR ENTERPRISES · KHABALPADA, ThaneP51700015923· 90.9% built
- EMINENCE PROJECT 13.6 yr overdueNAIKNAVARE DEVELOPERS PVT LTD · VIMAN NAGAR, PuneP52100001061· filed Dec 2019 → now Dec 2022· 94.5% built· 4 complaints
- SHIV-SAI PLAZA3.6 yr overduePRAFULLA SADASHIV GHAG · Devrukh (CT), RatnagiriP52800002788· filed Jul 2018 → now Dec 2022· 38.6% built
- SHREE AMBA BUSINESS PARK WING B PHASE II3.6 yr overdueSHREE AMBA BUSINESS PARK · RAHATGAON, AmravatiP50300019011· 72.7% built
- ROYAL GRANDE3.6 yr overdueFive Star Construction Company · Bhumkar Nagar, Wakad, PuneP52100015350· 77.3% built
- FIA REGENCY3.6 yr overdueNIMISH LAXMICHAND PASAD · Palghar, PalgharP99000013880· 49.5% built
- VITTHAL SAI ENCLAVE3.6 yr overdueMOHAN RAMRAO GAIKWAD · Khamla, NagpurP50500008164· filed Jul 2019 → now Dec 2022· 27.3% built
- THE SKYLARK PHASE 13.6 yr overdueMOHISHA REALTORS LLP · KIWALE, PuneP52100015274· 97.3% built· 7 complaints
- Lodha Kolshet Plot A - Tower J3.6 yr overdueLODHA DEVELOPERS LIMITED · Thane, ThaneP51700015243· 81.8% built
- addressOne - Phase 13.6 yr overduePeninsula Land Limited · Nr Maharashtra Cricket Association Stadium, Gahunje Pune, PuneP52100015756· 69.2% built· 4 complaints
- SATIMATA APARTMENT3.6 yr overdueKRUTADNYA BUILDER AND DEVELOPERS · TISGAON, AurangabadP51500020900· 39.5% built
- Geras Imperium Oasis3.6 yr overdueGera Developments Private Limited · Pimpri Waghere Pune, PuneP52100015514· 81.8% built· 5 complaints
- GATHA AARAMBH3.6 yr overdueSAFFRON PROPERTIES · Haveli, PuneP52100003408· 90.9% built
- Kalash3.6 yr overdueKemi Creation earlier known as Taru Venture · Vasai, PalgharP99000003386· filed Dec 2018 → now Dec 2022· 90.9% built
- GANESHMURTI APARTMENT3.6 yr overdueNOOR MOHAMMED IDRIS JALGAONKAR · SECTOR R4 PUSHPAK, RaigarhP52000021824· 90.9% built
- Mahindra Happinest Palghar Phase V3.6 yr overdueMAHINDRA HAPPINEST DEVELOPERS LIMITED(Formerly known as Mahindra Happinest Developers Pvt. LTD) · nandore, PalgharP99000015852· 81.8% built· 2 complaints
- CASSITA HILLS3.6 yr overdueRISING STAR REALTY ·P52100012759· filed Jun 2021 → now Dec 2022· 81.8% built
- VASANT OASIS DAFFODIL BLDG 73.6 yr overdueNEEPA REAL ESTATES PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000798· 84.1% built· 6 complaints
- ACE HOMES3.6 yr overdueAARTI ESTATES · KASARVADAVALI, ThaneP51700016575· 90.9% built
- DEVIKE CONSTRUCTION3.6 yr overdueSURESH GANPAT MORE · PANCHIL NAGAR, RaigarhP52000015551· 75.5% built
- SAHIL OM PARK3.6 yr overdueVAISHNAVI PROMOTERS AND DEVELOPERS · Moshi, PuneP52100011417· filed Dec 2019 → now Dec 2022· 72.7% built
- VASANT OASIS PETUNIA BLDG 83.6 yr overdueNEEPA REAL ESTATES PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000691· 82.3% built· 2 complaints
- Kashish Park Ghatkopar3.6 yr overdueLadam Homes Pvt Ltd. · Kurla, Mumbai SuburbanP51800002692· filed Jun 2021 → now Dec 2022· 90.8% built· 11 complaints
- MIDAS RESIDENCY -23.6 yr overdueMIDAS TOUCH INFRA · PRABHAT COLONY MAHAD CITY, RaigarhP52000015215· 81.8% built
- SHREE MADHUVANDHAM3.6 yr overdueSUNDER CORPORATION · Borivali, Mumbai SuburbanP51800008266· 42.9% built
- MARATHON NEXZONE ALTIS -23.6 yr overdueSANVO RESORTS PVT. LTD. · PALASPE PHATA, RaigarhP52000000677· filed Jun 2021 → now Dec 2022· 72.7% built· 1 complaint
- CLOVER HILLS PLAZA3.6 yr overdueClover Buildcorp · NIBM road, PuneP52100002324· 50% built
- Cloverdale3.6 yr overdueROMA BUILDERS PRIVATE LIMITED · Thane, ThaneP51700000153· 90.9% built
- CASA ASUD - PHASE I3.6 yr overdueSKYLINE DEVELOPERS · Asud, RatnagiriP52800006057· filed Dec 2018 → now Dec 2022· 69.1% built
- SHUBHAMANGAL3.6 yr overdueSHUBHAMANGAL DEVELOPERS · BAHINABAI NAGAR, JalgaonP49900020433· 40.5% built
- KAVERI RESIDENCY3.6 yr overdueRAMESH RAMCHANDRA MASAL · Sangalikar Mala, SangliP53100022669· 81.8% built
- Haware Meadows Phase 13.6 yr overdueHAAAS Corporation Private Limited · Mamdapur, RaigarhP52000015126· 90.9% built
- Gokul3.6 yr overdueRadha Madhav Developers · Vrindavan, NagpurP50500000854· 88.6% built· 1 complaint
- AAWAS DEEP3.6 yr overdueSHREE KRISHNA BUILDCON · YASHRAJ NAGAR, ThaneP51700014893· 27.7% built
- Jupiter Prime3.6 yr overdueArjun Ashok Tarachandani · Pushpak New, RaigarhP52000018263· 53.6% built
- NISARG TULIPS3.6 yr overdueADITYA SHAGUN DEVELOPERS · BAVDHAN, PuneP52100014405· 70% built
- TULIP ELEMENT3.6 yr overdueTushar Mohanrao Khatavkar · E ward, KolhapurP53000026601· 30.5% built
- AVIOR -AATMAN PHASE -II3.6 yr overdueAVIORENTERPRISES LLP · Pune City, PuneP52100019422· 81.8% built
- SHRIRAM CORNER3.6 yr overdueDG DEVELOPERS · DHAYARI, PuneP52100013792· 27.3% built
- MAHAVIR KUNJ D WING A TYPE C13.6 yr overdueRajesh Realtors · Palghar, PalgharP99000024188· 90.9% built
- YashONE Pirangut Phase II3.6 yr overdueVilas Javdekar Eco Homes · Mulshi, PuneP52100023378· 12.7% built
- SAMARTH RESIDENCY3.6 yr overdueAJAY SITARAM SURVE · Borivali, Mumbai SuburbanP51800013678· 90.9% built· 2 complaints
- M P Keshav3.6 yr overdueM P Construction · Pushpak New, RaigarhP52000019549· 90.9% built
- Kismat Residency3.6 yr overdueKISMAT DEVLOPERS · Mira-Bhayandar (M Corp.), ThaneP51700009235· filed Dec 2021 → now Dec 2022· 62.7% built
- Nirman Riverside3.6 yr overdueGururaj Narsinha Joshi · Haveli, PuneP52100016887· 90.9% built
- NARMADA MOHAN3.6 yr overdueK.M.DEVELOPERS · Vasai, PalgharP99000012568· filed Jul 2018 → now Dec 2022· 90.8% built· 5 complaints
- SHIVSHAKTI GREENS3.6 yr overdueSHIVSHAKTI REALITY · JOVELI GAON, ThaneP51700013872· 90.9% built
- Lodha Amara - Tower 36 373.6 yr overdueLODHA DEVELOPERS LIMITED · ., ThaneP51700013961· 81.8% built· 3 complaints
- SAPTASHRUNGI SAHARA3.6 yr overduePRAGATI DEVELOPERS · GAMANE STADIUM, NashikP51600021736· 48.2% built
- EKAVIRA APARTMENT3.6 yr overdueMATOSHRI BUILDCON · ADGAON, NashikP51600016085· 90.9% built
- SATYAM SHEELA3.6 yr overdueSHREE SATYAM GROUP · Ambarnath, ThaneP51700000943· 60.6% built· 1 complaint
- Shiv Plaza3.6 yr overdueGanesh Thakur · Parasnath Nagri, PalgharP99000019525· 75% built
- Bhoomi Acres L wing3.6 yr overdueV R Constructors Private Limited · Thane, ThaneP51700020184· 98.5% built· 3 complaints
- M 193.6 yr overdueSUVIDHA LIFESPACES · Ward FNorth, Mumbai CityP51900007305· 62.7% built
- Kalpataru Hills - Building 2A3.6 yr overdueKalpataru Properties (Thane) Pvt. Ltd. · Thane, ThaneP51700000584· 98.5% built· 2 complaints
- Leelaangan3.6 yr overduePravin Kashinath Haware · Ambarnath, ThaneP51700002749· 77.5% built· 1 complaint
- GVC SHAGUN CITY PHASE II3.6 yr overdueSHAGUN ASSOCIATES · KAUTHA, NandedP51100017950· 78.2% built
- The Serenes Villa No 213.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012819· 40.9% built
- The Serenes Villa No 103.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000013927· 40.9% built
- SUKHADA CO-OP HOUSING SOCIETY3.6 yr overdueKAUSTUBH JEEVAN KULKARNI · VIDYANAGAR EAST, RaigarhP52000021391· 90.9% built
- Mahim Garden3.6 yr overdueShree Oshiyaji Builders & Developers LLP · Mahim, PalgharP99000013118· 45.5% built
- NEW VANDANA CO-OP HSG. SOC. LTD.3.6 yr overdueBhoomi Associates · Borivali, Mumbai SuburbanP51800016757· 64.5% built
- The Serenes Villa No 203.6 yr overdueMahindra Lifespace Developers limited · NAGAON, RaigarhP52000012522· 40.9% built
- VASTULAXMI3.6 yr overdueLAGOO BUILDERS · MALI COLONY KUPWAD, SangliP53100016209· 82.7% built
- ANUPAMA-AMRAPALI HEIGHTS3.6 yr overdueJARRY PROFITS · NARI, NagpurP50500016379· 90.9% built
- ROYAL RESIDENCY3.6 yr overdueSHUBHANKAR DEVELOPERS · MANGIRE MALA, SolapurP52600014907· 90.9% built
- MORAYA PARK PHASE III3.6 yr overdueHARSIDDHI BUILDERS · HARSUL, AurangabadP51500017172· 32.7% built
- INTERNATIONAL BUSINESS BAY3.6 yr overdueSAKET DILIP SHAH · Pune City, PuneP52100021989· 90.9% built
- RAJ ENCLAVE3.6 yr overdueRASHID RAJESAHEB HATTIWALE · CSNO 49A+49B, AT- VAKHAR BHAG SANGLI, SangliP53100023991· 81.8% built
- GREEN NEST3.6 yr overdueRohit Tanaji Omase · BASUGADE MALA, SangliP53100024043· 81.8% built
- SANSKAR PLAZA3.6 yr overdueLAXMAN EKNATH GOMASE · PATHARDI PHATA, NASHIK-10, NashikP51600021281· 90.9% built
- DEEP CLASSIC TOWER3.6 yr overdueSAI SANGAM DEVELOPERS · Vasai, PalgharP99000012178· filed Jun 2021 → now Dec 2022· 89.7% built· 6 complaints
- SONALI EDIFICE3.6 yr overdueASHOKKUMAR PANDURANG KADAM · NEAR SAI SHRADHHA HP PETROL PUMP, AYODHYA NAGARI NASHIK, NashikP51600021415· 90.9% built
- ARB HEIGHTS3.6 yr overdueRAMCHANDRA BUILDERS AND DEVELOPERS · OPP MARKET YARD, SangliP53100025132· 81.8% built
- Anand Park3.6 yr overdueVISTA PROPERTIES · Nagardevale, AhmednagarP52200011296· 37.9% built
- AVIOR AATMAN3.6 yr overdueAVIORENTERPRISES LLP · Pune City, PuneP52100019192· 81.8% built
- GREEN HEIGHTS3.6 yr overdueSAI LEELA REALTORS · Vasai, PalgharP99000008455· filed Jun 2021 → now Dec 2022· 90.9% built
- VEER SPLENDOR3.6 yr overdueVeer Global Infraconstruction Limited · Vasai, PalgharP99000011282· filed Jun 2021 → now Dec 2022· 70% built
- HILLSIDE RESIDENCY3.6 yr overdueRAJSHREE LANDMARK LLP · OFF DUDULGAON, PuneP52100018135· 53.6% built
- GHATKOPAR SHILPAKALA CHS LIMITED3.6 yr overdueM/S SUN-VUB · GARODIA NAGAR, Mumbai SuburbanP51800018507· 10.7% built
- VASANT OASIS DANICA BLDG NO 153.6 yr overdueNEEPA REAL ESTATES PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800015556· 76.4% built
- ROHAN ABHILASHA BUILDING D3.6 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · WAGHOLI, PuneP52100000673· 90.9% built· 1 complaint
- SAI RESIDENCY3.6 yr overdueSAI RIDDHI CONSTRUCTION · Vasai, PalgharP99000008335· filed Jun 2019 → now Dec 2022· 48.6% built
- Kalpataru Avana3.6 yr overdueKalpataru Limited · Ward FSouth, Mumbai CityP51900000793· 89.3% built· 21 complaints
- SHREE GANESH3.6 yr overdueSHREE ENTERPRISES · SECTOR 5A, RaigarhP52000020556· 81.8% built
- Aapla ghar Shirwal Phase I3.6 yr overdueMaple Aurus Realty · SHIRWAL, SataraP52700007048· 53.4% built· 1 complaint
- The Serenes Villa No 163.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012788· 40.9% built
- VIJAY SUNSTONE3.6 yr overdueV Y NIKHAR & ASSOCIATES · Bhandara (M Cl), BhandaraP50600008375· 90.9% built
- SAI YASH COMPLEX3.6 yr overdueMahatma Infrasturcture (India) LLP · Shirgaon, PalgharP99000013008· 9.4% built
- Dynamic Grandeur3.6 yr overdueDYNAMIC REALTY ENTERPRISES · UNDRI, PuneP52100001831· 12.3% built
- TRAFALGAR TOWER3.6 yr overdueM/S. Akshay Radha Kishan Construction · Kurla, Mumbai SuburbanP51800006369· filed Dec 2019 → now Dec 2022· 58.3% built
- Rustomjee Elements - Wing SC3.6 yr overdueRustomjee Realty Private Limited · Andheri, Mumbai SuburbanP51800005738· filed Jun 2021 → now Dec 2022· 69.5% built
- SHREEJI NISARG PHASE I3.6 yr overdueSHREEJI DEVELOPERS · ERANJAD, 30 MTR BARVI DAM ROAD, ThaneP51700015127· 90.9% built
- Sai Park3.6 yr overdueRachana Constructions · Haveli, PuneP52100011387· filed Jun 2019 → now Dec 2022· 70% built
- SURATWALA MARK PLAZZO - WING B - PHASE 13.6 yr overdueSURATWWALA BUSINESS GROUP LIMITED · HINJAWADI, PuneP52100017784· 79.5% built· 1 complaint
- Clifton3.6 yr overdueROMA BUILDERS PRIVATE LIMITED · Thane, ThaneP51700000129· 90.9% built· 1 complaint
- SMGK ASSOCIATE RESIDENCY Wing B Phase 2 17th to 20th Floors3.6 yr overdueVastu Shilpa Complex Designers Pvt Ltd · Andheri, Mumbai SuburbanP51800004663· filed Dec 2019 → now Dec 2022· 51.5% built
- THAKUR ASPIRE3.6 yr overdueTHAKUR REALTY PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800003848· 21.8% built
- REDWOOD LANDMARK3.6 yr overdueREDWOOD DEVELOPERS · NEAR CARMEL SCHOOL, RaigarhP52000012810· filed Dec 2021 → now Dec 2022· 90.9% built
- AURIS SERENITY TOWER 13.6 yr overdueTRANSCON-SHETH CREATORS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800001080· 98.2% built· 4 complaints
- SHREE SWAMI SAMARTH APARTMENT PH-II3.6 yr overdueSUMAN ASSOCIATES · Shirur, PuneP52100014970· 66.8% built
- CHANDRAMOULI PINNACLE3.6 yr overdueCHANDRAMOULI PINNACLE · Satara Parisar, AurangabadP51500016229· 90.9% built
- GRAND EDIFICE3.6 yr overdueUJJWALA SATISH HAWARE · Borivali, Mumbai SuburbanP51700006407· filed Jun 2021 → now Dec 2022· 87.3% built
- PRATHAM3.6 yr overdueVARDHMAN ENTERPRISES · Andheri, Mumbai SuburbanP51800009959· filed Dec 2017 → now Dec 2022· 90.9% built· 7 complaints
- GALAXY MANSION- IX3.6 yr overdueGALAXY ASSOCIATES · Beltarodi Grampanchayat, NagpurP50500021986· 90.9% built
- WESTERN PARK3.6 yr overdueSHAKTI DEVELOPERS · Vasai, PalgharP99000005755· filed Jun 2021 → now Dec 2022· 84.1% built
- Nirman Ajinkyatara Wing C3.6 yr overdueNIRMAN DEVELOPERS · Ambegaon Budruk, PuneP52100013288· 32.7% built
- Mangal Vishwa - Phase 23.6 yr overdueG.T.DEVELOPERS · Kiwale, PuneP52100018839· 90.9% built
- NISHIGANDHA PARK PHASE 13.6 yr overdueM/S ARCHWAY ESTATES · Kothrud, PuneP52100005610· filed Dec 2018 → now Dec 2022· 61.4% built· 1 complaint
- RBI employees Ashish chsl3.6 yr overdueTRIVENI DEVELOPERS · KASTUR PARK, Mumbai SuburbanP51800007607· filed Dec 2018 → now Dec 2022· 90.9% built· 9 complaints
- Datar Radiant Plaza3.6 yr overdueM/S SD Associates · Datar Wada, KolhapurP53000015990· 90.9% built
- UMA GALAXY3.6 yr overdueUMIYA ENTERPRISES · TITWALA, ThaneP51700002937· filed Jun 2021 → now Dec 2022· 94.1% built
- ABHIMAN SHRI3.6 yr overdueRATNADEEP PRAMOTERS AND BUILDERS · Charholi Khurd, PuneP52100014831· filed Dec 2021 → now Dec 2022· 99.1% built
- Keshar Kunj3.6 yr overdueKeshar Realities · Panvel, RaigarhP52000008372· 55.1% built
- Avadha Annexe3.6 yr overdueVrundavan Developers · Samarth Nagar, Pathardi, NashikP51600015198· 90.9% built
- COMFORT ZONE PLUS3.6 yr overdueADITYA SHAGUN DEVELOPERS · BALEWADI, PuneP52100014407· 90.9% built
- VISHNUBHUVAN CHS LTD3.6 yr overdueShree S S Developers Private Limited · Kurla, Mumbai SuburbanP51800009053· 78.5% built
- SEA GREEN APARTMENT3.6 yr overdueAAKASH BUILDERS & DEVELOPERS · Mira-Bhayandar (M Corp.), ThaneP51700011846· filed Dec 2019 → now Dec 2022· 90.5% built· 5 complaints
- Avant Heritage II-Basement plus stilt plus 3 Podium plus 20 Upper Habitable Floors3.6 yr overdueAishwarya Avant Builders LLP · Andheri, Mumbai SuburbanP51800015537· filed Jun 2021 → now Dec 2022· 80% built· 5 complaints
- Lords Estate3.6 yr overdueMountview Properties LLP · Pune City, PuneP52100012004· 62.6% built
- PARIMAL3.6 yr overdueRANADE REALTORS LLP · ERANDAVANE, PuneP52100023048· 90.9% built
- AAKAR INDIGO3.6 yr overdueAAKAR REALTIES · CHOVISAWADI, PuneP52100018758· 90.9% built
- MEMORIES 90 - COMMERCIAL3.6 yr overdueM/s NAMO DEVELOPERS · Mohammadwadi Pune, PuneP52100013482· 94.2% built
- TRIMURTI PARK3.6 yr overdueTRIMURTI CONSTRUCTION · Kalyan, ThaneP51700011458· 90.9% built
- BHIMASHANKAR HEIGHTS3.6 yr overdueMallhar Realtors Pvt Ltd · Borivali, Mumbai SuburbanP51800000274· 50.5% built· 2 complaints
- FLORENTIA3.6 yr overdueSIDDHIVINAYAK HOMES PVT. LTD. · MIRA BHAYANDAR, ThaneP51900009486· 90.9% built· 1 complaint
- RAHUL EXCELLENCE3.6 yr overdueSAROJ SHRAWANKUMAR BAGARIA · AMBARNATH, ThaneP51700012698· filed Dec 2018 → now Dec 2022· 60.9% built· 3 complaints
- SHIVASAMRITI APARTMENT3.6 yr overdueSANJIV LAXMAN SALVI · Chiplun (M Cl), RatnagiriP52800011328· 22.7% built
- Aapla Ghar Chakan Phase II3.6 yr overdueMaple Estates · Nanekarwadi (CT), PuneP52100004796· 87.9% built
- SHREE GANESH GANGA3.6 yr overdueGANGA REALTORS · Nagpur (M Corp.), NagpurP50500011125· filed Jun 2021 → now Dec 2022· 90.9% built
- CHESTERFIELD WING A AND WING B3.6 yr overdueKALYANEE FORTUNE PROPERTIES ·P52100003511· filed Jun 2021 → now Dec 2022· 63.6% built· 1 complaint
- SHIVALIK SPARSH3.6 yr overdueMADHUBHAI BABUBHAI KOTHIYA · PATHARDI, NashikP51600016159· 90.9% built
- Trinity Heights3.6 yr overdueShreeji Realtors · Virar, PalgharP99000010210· 59.1% built
- SWASTIK EMERALD3.6 yr overdueSwastik Realtors · Kurla, Mumbai SuburbanP51800014935· 90.9% built
- The Ruby - Ground and 1st Part, 21st to 39th Floor3.6 yr overdueMindset Estates Private Limited · Ward GNorth, Mumbai CityP51900009854· filed Jun 2021 → now Dec 2022· 89.5% built· 1 complaint
- CHANDRAMA HEIGHTS3.6 yr overdueBABANRAO DAGU JADHAV · KAMATWADA, NashikP51600023390· 81.8% built
- SHASHWAT PARK3.6 yr overdueATLANTA ASSOCIATES · Kurla, Mumbai SuburbanP51800003044· 71.5% built· 2 complaints
- CARNIVAL RESIDENCY 13.6 yr overdueEMMANUEL DEVELOPERS · Vasai, PalgharP99000014179· 90.9% built
- Q Residences R23.6 yr overdueAurum RealEstate Developers Limited · Thane, ThaneP51700007844· 90.4% built
- Nirman Aura Wing B3.6 yr overdueGALAXY HILL PARADISE LLP · Ambegaon Budruk, PuneP52100014502· 90.9% built
- WHITE STONE B BLDG3.6 yr overdueKASHINATH SOPAN DABHADE · WAGHOLI, PuneP52100006439· filed Jun 2021 → now Dec 2022· 34.1% built
- SHRUSHTI PRARAMBH3.6 yr overdueSHRUSHTI DEVELOPERS · BADLAPUR, ThaneP51700016101· 90.9% built
- PRIDE SIGNATURE3.6 yr overduePRIDELAND PROPERTY · Malwan (M Cl), SindhudurgP52900009932· 78.4% built
- Juikar Heights3.6 yr overdueJuikar Heights Builders & Developers · Khed (M Cl), RatnagiriP52800013799· 90.9% built
- FIA REGENCY A3.6 yr overdueNIMISH LAXMICHAND PASAD · PALGHAR, PalgharP99000017479· 70.9% built
- R.K. MAJESTIC3.6 yr overdueR K CONSTRUCTION · -, RaigarhP52000020806· 9.1% built
- PARVATI HEIGHTS3.6 yr overdueHASTI BUILDCON · Thane, ThaneP51700015874· 86.4% built
- Anant Sakshi3.6 yr overdueAnant Builders · Sakshi Nagar, RaigarhP52000019773· 57.3% built
- SIDDHESHWAR RESIDENCY3.6 yr overdueSIDDHIVINAYAK ASSOCIATES · NEAR SIDDHESHWAR TEMPLE, RaigarhP52000016759· 82.2% built
- Life Republic Sector R16 - 16th Avenue3.6 yr overdueKOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED · Jambe, PuneP52100009640· 90.9% built· 1 complaint
- SYLVAN HEIGHTS H BUILDING3.6 yr overdueNAIKNAVAREDEVELOPERSPVTLTD · AUNDH, PuneP52100021048· 66.4% built
- SHIVKRUPA HEIGHTS3.6 yr overdueSHIVKRUPA BUILDERS AND LAND DEVELOPERS · DATTA NAGAR, CHUNCHALE, NASHIK, NashikP51600023921· 90.9% built
- SONU AAI COMPLEX3.6 yr overdueARVIND GOPAL PATIL AOP · Thane, ThaneP51700012035· 84.7% built
- Palladio Phase 23.6 yr overdueVilas Javdekar Eco Developers Pvt. Ltd. · behind D Y Patil college, PuneP52100017306· 91.5% built
- EXCEL GALAXY3.6 yr overdueEXCEL CONSTRUCTIONS · ULWE, RaigarhP52000017632· 90.9% built
- Vaikunth Cluster 13.6 yr overduePEPL Developers Pvt Ltd · Thane, ThaneP51700003535· 86.4% built· 9 complaints
- SUYOG SADAN3.6 yr overdueSUYOG BUILDERS · PANCHSHIL NAGAR, PuneP52100032390· 90.9% built
- Anandgriha Phase III3.6 yr overdueKACHHI PROPERTIES · Satara, SataraP52700007506· filed Dec 2019 → now Dec 2022· 40% built
- The Serenes Villa No 83.6 yr overdueMahindra Lifespace Developers limited · Nagaon, RaigarhP52000012883· 34.4% built
- KALASH3.6 yr overdueKemi Infrastructures earlier known as Taru Realtors · Vasai, PalgharP99000008304· filed Dec 2018 → now Dec 2022· 90.9% built
- Transcon Triumph Tower 13.6 yr overdueTranscon Developers Pvt. Ltd. · Andheri, Mumbai SuburbanP51800005361· 70.8% built· 6 complaints
- SWAPNABAN3.6 yr overdueBHAISHREE VENTURES · NEAR GRAMPANCHAYAT OFFICE, AurangabadP51500016418· 76.8% built
- Vishal Sagar3.6 yr overdueJ R Properties LLP · Kurla, Mumbai SuburbanP51800018676· 81.6% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.