Delayed projects in Thane
1,593 MahaRERA-registered projects in Thane are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 3 of 8
- Madan Vilas7.4 yr overdueIshaan Enterprise · Thane, ThaneP51700001871· filed Mar 2018 → now Mar 2019· 90.9% built· 1 complaint
- SHREE GANESH VYAPARI SANKUL7.4 yr overdueRAJDEEP BUILDERS AND DEVELOPERS · Badlapur (M Cl), ThaneP51700007269· 74.5% built
- SHIV PARVATI RESIDENCY7.4 yr overdueSHRIKRISHNA DEVELOPERS · Ambarnath, ThaneP51700005502· 43.6% built
- Rustomjee Azziano Wing J7.4 yr overdueKapstone Constructions Private Limited · Thane, ThaneP51700000950· 87% built· 1 complaint
- HIGHLAND HAVEN BUILDING 2B DEW-A PHASE 27.4 yr overdueSIDDHI KRISH DEVELOPERS · Thane, ThaneP51700005689· 83.9% built· 1 complaint
- MOHAN HEIGHTS -PHASE 17.4 yr overdueBHAVANI ENTERPRISES · Kalyan, ThaneP51700004730· filed Mar 2018 → now Mar 2019· 90.9% built· 1 complaint
- Ganesh Pratima7.4 yr overdueHome Makers · Titwala, ThaneP51700007373· 60.3% built
- Mohan Suburbia IIB7.4 yr overdueMOHAN LIFESPACES LLP · Ambernath, ThaneP51700010658· filed Mar 2018 → now Mar 2019· 89.1% built· 1 complaint
- KRISHNA DARSHAN7.4 yr overdueS.K. DEVELOPERS · Kalyan, ThaneP51700007961· 43.6% built
- MARATHE FORTUNE7.4 yr overdueSAIJI DEVELOPERS · Titwala, ThaneP51700008862· 4.2% built
- PUSHKAR APARTMENT7.4 yr overdueSAYALEE SANJESH PATKAR · Badlapur (M Cl), ThaneP51700010103· 41.8% built
- ARYAN ONE WING E AND F7.4 yr overdueKonark Lifespaces · Shirgaon, ThaneP51700009247· filed Apr 2018 → now Mar 2019· 90.9% built
- JAI MATADEE7.4 yr overdueAARADHANA DEVELOPERS · Thane, ThaneP51700000884· filed Mar 2018 → now Mar 2019· 50% built
- HIGHLAND HAVEN BUILDING 4D CORAL-A PHASE 47.4 yr overdueSIDDHI KRISH DEVELOPERS · Thane, ThaneP51700006815· 83.9% built
- Purva Apartment7.4 yr overdueDEEPAK MOTIRAM DALAL · AMBERNATH, ThaneP51700014812· 18.2% built
- MANGESHI FLORA7.4 yr overdueOM REALTY · Kalyan, ThaneP51700005811· 62.7% built
- RATHADIA CO-OPERATIVE HOUSING SOCIETY LTD7.4 yr overdueJ SQUARE INFRA · KULGAON, ThaneP51700015329· 90.9% built
- Jeevan Lifestyles7.4 yr overdueJEEVAN ENTERPRISES · Badlapur (M Cl), ThaneP51700004929· 72.7% built
- SHANKHESHWAR PLATINUM-PHASE 17.4 yr overdueSHANKHESHWAR KREATERS · Kalyan, ThaneP51700000445· 90.9% built
- SAMRUDDHI EVERGREEN-PHASE-4B7.4 yr overduePoddar Housing and Development Limited · Badlapur (M Cl), ThaneP51700009016· 70.6% built
- PATELS RESIDENCY7.4 yr overduePARAM BUILDERS AND DEVELOPERS · Ambarnath, ThaneP51700000865· filed Mar 2018 → now Mar 2019· 56.4% built
- Swagat Heights7.4 yr overdueSwagat Property Developers · Thane, ThaneP51700008280· 68.9% built
- Maithili7.4 yr overdueSHARDA VASTU NIRMITEE PVT. LTD. · Thane, ThaneP51700002777· 78.4% built
- COSMOS HABITATE7.4 yr overdueCONCORDE ASSOCIATES · Majiwada, ThaneP51700006637· 44.9% built
- CHINTAMANI HEIGHTS TYPE E WING Q R S7.4 yr overdueJASHNANI CONSTRUCTION PRIVATE LIMITED · Cherpoli, ThaneP51700004624· 81.8% built
- ORCHID7.4 yr overdueMEHTA REALTORS · Thane, ThaneP51700001234· 72.7% built
- ORIANA BUSINESS PARK7.4 yr overdueDREAM BUSINESS VENTURE · Thane, ThaneP51700001659· 35.9% built
- Munisuvrat Arc - Building 1 Plot 1 and Munisuvrat Royal - Building 2 on Plot 27.4 yr overdueShree Munisuvrat Realty · Bhiwandi, ThaneP51700004825· 57.3% built
- GAJANAN NANA HEIGHTS7.4 yr overdueVASTU GANESH BUILDERS AND DEVELOPERS · Kalyan, ThaneP51700010902· 46.4% built
- AVIGHNA KARAN WING A7.4 yr overdueAVIGHNA KARAN · Kalyan, ThaneP51700010306· 90.9% built
- Mohan Ritteka7.4 yr overdueSHREE KRISHNA ENTERPRISES · Ulhasnagar, ThaneP51700004103· filed Mar 2018 → now Mar 2019· 90.9% built
- Saket Iris7.3 yr overdueANIL SHILPAYATAN PRIVATE LIMITED · Kalyan, ThaneP51700001875· 90.9% built
- PARSHVADHARA7.3 yr overduePARSHVANATH DEVELOPERS · Badlapur (M Cl), ThaneP51700010323· 70.2% built· 1 complaint
- KRISHNA ENCLAVE7.3 yr overdueOM SAI DEVELOPERS · jarimari mata mandir, ThaneP51700007291· 40.5% built
- SKY HILL7.3 yr overdueSEVEN HILL BUILDCON · Ambarnath, ThaneP51700002510· 81.8% built· 2 complaints
- PANVELKAR DAFFODIL7.3 yr overdueAMEYA DEVELOPERS · AMBERNATH, ThaneP51700019159· 90.9% built
- DHARMAVIHAR7.3 yr overdueMKY Infrastructure · Bhiwandi, ThaneP51700010249· filed Jul 2018 → now Apr 2019· 90.9% built· 1 complaint
- GLOBE ESTATE PHASE 27.3 yr overdueGLOBE ENTERPRISES · MIDC PHASE 1,, ThaneP51700015240· 81.8% built
- Parshuram Residency7.2 yr overdueShree Radha Developers · Ambarnath(M Cl), ThaneP51700013256· 39.6% built
- PANVELKAR SANKALP WING B7.2 yr overdueGEETAI ENTERPRISES · Ambarnath, ThaneP51700011019· 90.9% built
- PLATINUM HERITAGE7.2 yr overdueDARSHAN SAGAR DEVELOPERS · patlipada, ThaneP51700005172· filed May 2018 → now May 2019· 78.2% built· 12 complaints
- Rustomjee Azziano Wing H7.2 yr overdueKapstone Constructions Private Limited · Thane, ThaneP51700001453· 89.1% built
- GIRIVIHAR7.2 yr overdueABHINANDAN ENTERPRISE · Thane, ThaneP51700009018· 48.2% built
- SAMRUDDHI7.2 yr overdueKishor Ramchandra Kulkarni · DOMBIVLI, ThaneP51700013478· 74.5% built
- RACHANA HEIGHTS7.2 yr overdueRESHMA VIKAS BAMBULKAR · Badlapur (M Cl), ThaneP51700014144· 74.1% built
- COSMOS ORCHID7.1 yr overdueMONARCH DEVELOPERS · Thane (M Corp.), ThaneP51700011044· 87.3% built
- Vrindavan Park7.1 yr overdueMohammed Salim Yusuf · Kalyan, ThaneP51700003010· 88.5% built
- POONAM ESTATE CL 2 BLG NO 7 8 97.1 yr overdueRavi Developments · Thane, ThaneP51700008166· 68.2% built
- BHAIRAAV SIGNATURE7.1 yr overdueSHARPMIND INFRASTRUCTURE PRIVATE LIMITED · Thane, ThaneP51700003768· filed Jun 2018 → now Jun 2019· 98.2% built
- DEEP ENCLAVE7.1 yr overdueDATTAGURU ENTERPRISES · BADLAPUR, ThaneP51700014690· 20.5% built
- ANNAPURNA JEWELS7.1 yr overdueANNAPURNA CREATORS · Thane, ThaneP51700000893· 88.2% built
- METRO HIGHLAND PHASE I7.1 yr overdueMETRO DEVELOPERS · Ambarnath, ThaneP51700005374· filed Jun 2018 → now Jun 2019· 90.5% built
- Uma Vatika7.1 yr overdueUma Creative · Ambarnath, ThaneP51700003281· 66.8% built
- Riverview Classic Building No.2,Phase II7.1 yr overdueRUTU BUILDERS · Kalyan, ThaneP51700001351· 98.6% built· 1 complaint
- PATEL ESTATES7.1 yr overdueVINOD GORDHANBHAI PATEL · GANDHI CHOWK, ThaneP51700010036· 72.7% built
- NEELKANTH JYOT7.1 yr overduePRAPTI ENTERPRISES · Sape, ThaneP51700010769· 90.9% built
- VASANT SPRINGWOODS PHASE 27.1 yr overdueM/S SHREE CONSTRUCTIONS · Badlapur (M Cl), ThaneP51700008622· 90.9% built
- KRISHNA PARADISE7.1 yr overdueGOPAL KRISHNA DEVELOPERS · Kalyan-Dombivali (M Corp.), ThaneP51700012318· 90.9% built
- SIDDHICITY7.1 yr overdueSiddhitech Homes Private Limited · Ambarnath, ThaneP51700001597· filed Jun 2018 → now Jun 2019· 85.2% built· 24 complaints
- UMIYA DARSHAN7.1 yr overdueSHREE UMIYA GROUP · Badlapur (M Cl), ThaneP51700008860· filed Jun 2018 → now Jun 2019· 70.5% built· 2 complaints
- SRI HERITAGE7.1 yr overdueFOURWAY REALTY · Ambarnath, ThaneP51700004111· 77.3% built· 1 complaint
- UNIQUE GREEN7.1 yr overdueMADHU HARSHAD DOSHI · Thane (M Corp.), ThaneP51700009563· filed Jun 2018 → now Jun 2019· 90.9% built· 11 complaints
- COSMOS ENCLAVE7.1 yr overdueASHIRWAD DEVELOPERS · Thane, ThaneP51700001476· 33.9% built· 1 complaint
- MOTIRAM DARSHAN NX7.1 yr overdueMOTIRAM DARSHAN NX · Ambarnath, ThaneP51700006708· 38.6% built
- MAYFAIR AASAAN7.1 yr overdueMAYFAIR HOUSING PRIVATE LIMITED · VALSHET, ThaneP51700013741· 83.7% built
- Mohan Willows I7.1 yr overdueMOHAN LIFESPACES LLP · Ambarnath, ThaneP51700002731· filed Jun 2018 → now Jun 2019· 90.9% built· 1 complaint
- LODHA SPLENDORA PLATINO E TO G , VIVANT A TO D7.1 yr overdueLODHA DEVELOPERS LIMITED · Thane, ThaneP51700000199· 78.2% built· 14 complaints
- OPAL SQUARE7.1 yr overdueShuban Buildpro LLP · Thane, ThaneP51700005705· 63.6% built
- KONARK SOLITAIRE - PHASE 17.1 yr overdueKONARK REALTIES J.V. · NEXT TO KDMC "A" WARD, ThaneP51700009356· 90.9% built
- Sahajeevan Residency Bldg 2, C-Wing7.1 yr overduePappu Developers & Group · Kalyan, ThaneP51700010437· 81.8% built
- Girnar Tirth7.1 yr overdueParshwa Associates · Kalyan, ThaneP51700007746· 45.5% built· 2 complaints
- SHIVSHAKTI COMPLEX7.1 yr overdueSHIV SHAKTI CORPORATION · Ambarnath, ThaneP51700006887· 51.9% built
- VASUDEV SKY HIGH7.1 yr overdueSHREE PRATHAMESH DEVELOPER · Thane, ThaneP51700003503· 59% built
- VALLABH C H S LTD PROPOSED7.1 yr overdueSpendor Shelters Private Limited · Kalyan, ThaneP51700001106· 31.8% built
- VASANT ELITE7.1 yr overdueM/S VASANT BUILDERS AND DEVELOPERS · Kalyan, ThaneP51700003400· filed Jun 2018 → now Jun 2019· 90.9% built
- MAITRI HILLS7.1 yr overdueESHWAR ENTERPRISES · Badlapur (M Cl), ThaneP51700011254· 54.5% built
- NAMDEV PLAZA7.1 yr overdueMETRO INFRA · Ambarnath, ThaneP51700003887· 58.2% built
- PALAVA EVIVA K to T, URBANO A, B, C and F, URBANO I to T7.1 yr overdueLodha Developers Limited · Kalyan, ThaneP51700000419· 78.2% built· 4 complaints
- SHIVNERI7.1 yr overdueAAVISHKAR ASSOCIATES · Kalyan, ThaneP51700008705· filed Dec 2018 → now Jul 2019· 90.9% built
- MARUTI DARSHAN7.1 yr overdueKOMAL DREAM BUILDERS PRIVATE LIMITED · Thane, ThaneP51700002727· 73.4% built
- SHREE SAVALI WING B7.1 yr overdueUMESH RAOSAHEB PAWAR PATIL HUF · Thane, ThaneP51700005638· 90.9% built
- MAHALAXMI PARADISE7.1 yr overdueSHREE MAHALAXMI BUILDERS AND DEVELOPERS · Ambarnath, ThaneP51700003224· 52.7% built
- MAHADEV PARADISE7.1 yr overdueNANDKUMAR MAHADEV PATIL · BHAYANDAR, ThaneP51700010608· 61.5% built
- ORCHID7.1 yr overdueROYALE URBANSPACE LLP · SHAHAPUR, ThaneP51700011790· 90.9% built· 2 complaints
- HERAMB PARK PHASE II7.1 yr overdueSAI SAMRUDDHI CONSTRUCTION CO · Badlapur (M Cl), ThaneP51700004551· 44.8% built
- mayurs nature glory phase-37.1 yr overduemukund balu keni · Thane, ThaneP51700008450· 81.9% built
- THARWANIS MEGHNA MONTANA PHASE - I7.1 yr overdueTHARWANI CONSTRUCTIONS PVT LTD · Ambarnath, ThaneP51700004242· filed Jun 2018 → now Jul 2019· 89.1% built· 40 complaints
- Lifestyle City Kalyan - Victory B7.1 yr overdueNirmal Lifestyle (Kalyan) Private Limited · Kalyan, ThaneP51700003544· filed Jul 2018 → now Jul 2019· 64.6% built· 7 complaints
- ARYAN ONE WING G AND H7.1 yr overdueKonark Lifespaces · Ambarnath, ThaneP51700002130· filed Jul 2018 → now Jul 2019· 89.5% built
- Lifestyle City Kalyan - Victory A7.1 yr overdueNirmal Lifestyle (Kalyan) Private Limited · Kalyan, ThaneP51700003212· filed Jul 2018 → now Jul 2019· 64.6% built· 13 complaints
- DHOLES EMPIRE7.1 yr overdueELITE DEVELOPERS · Thane, ThaneP51700011206· 90.9% built
- IDEAL PARK7.0 yr overdueIDEAL BUILDER & DEVELOPERS · Mira-Bhayandar (M Corp.), ThaneP51700009100· 90.9% built
- AVANTIKA RESIDENCY7.0 yr overdueSANCHITA CONSTRUCTION · Badlapur (M Cl), ThaneP51700010159· filed Aug 2018 → now Aug 2019· 90.9% built
- MAN OPUS7.0 yr overdueMAN GLOBAL LTD. · Thane, ThaneP51700008395· filed Dec 2018 → now Aug 2019· 65.6% built· 112 complaints
- SEASONS ELITE7.0 yr overdueSAI MAHAVIR DEVELOPERS · Thane, ThaneP51700012166· 81.8% built
- SRUSHTI RESIDENCY D TYPE WING 17.0 yr overdueM/S. KULSWAMINI BUILDERS · DOMBIVLI, ThaneP51700012479· 41.4% built
- PEARL7.0 yr overdueSagar Enterprise · Thane, ThaneP51700002276· 90.9% built
- KULSWAMINI PRASSANNA7.0 yr overdueKULSWAMINI DEVELOPERS · DOMBIVLI, ThaneP51700012480· 90.9% built
- SRUSHTI RESIDENCY D-TYPE WING-27.0 yr overdueKulswamini Builders · Kalyan, ThaneP51700005884· 60.5% built
- VASTU SIDDHI6.9 yr overdueSIDDHIVINAYAK GROUP · Ambarnath (R), ThaneP51700011663· 90% built
- RAGHUNANDAN-NX6.9 yr overdueVASTU DEVELOPERS · NAVAPADA GANESH NAGAR, ThaneP51700014552· 90.9% built
- RABIYA RESIDENCY6.9 yr overdueA R CONSTRUCTION · Bhiwandi (M Corp.), ThaneP51700013542· 47.3% built
- Vijay Vatika -56.9 yr overdueVIJAY SURAKSHA REALTY LLP · Village Kavesar, Ghodbunder Road, ThaneP51700005805· filed Sept 2018 → now Sept 2019· 90.9% built
- ADITI VILLA6.9 yr overdueATLANTIC CONSTRUCTION · Badlapur (M Cl), ThaneP51700008416· 43.2% built
- TEEJADEEP HEIGHTS6.9 yr overdueTEEJADEEP DEVELOPERS · Thane, ThaneP51700010345· filed Sept 2018 → now Sept 2019· 91.8% built· 1 complaint
- Sai Savitri Villa6.9 yr overdueSavitri Group · Thane, ThaneP51700010636· 90.9% built· 2 complaints
- SHREE SAI POOJA APARTMENT6.9 yr overdueOM SAI REALTY · BADLAPUR, ThaneP51700020600· 85.5% built
- VISHWAJEET PARADISE6.9 yr overdueKOHINOOR INFRA DEVELOPMENT · Ambarnath, ThaneP51700008406· filed Sept 2018 → now Sept 2019· 81.8% built· 1 complaint
- KAVITA PEARL6.8 yr overdueKAVITA INFRA · Kalyan-Dombivali (M Corp.), ThaneP51700007502· 90.9% built
- PATELS ELYSIUM - 16.8 yr overdueAPACE REALTY · Ambarnath(M Cl), ThaneP51700009543· 87.3% built
- GRAND ARENA6.7 yr overdueS H CONSTRUCTIONS · Thane, ThaneP51700012136· filed Nov 2018 → now Nov 2019· 66.3% built· 1 complaint
- PENTAGON HEIGHTS6.7 yr overdueDAMJI HARI CONSTRUCTIONS · Bhiwandi, ThaneP51700010871· filed Nov 2018 → now Nov 2019· 90.9% built· 7 complaints
- LODHA AMARA - TOWER 1 - 5, 7 - 196.7 yr overdueLODHA DEVELOPERS LIMITED · Thane, ThaneP51700001065· 78.2% built· 26 complaints
- Pranjee Garden City Phase -II6.7 yr overduePranjee Properties Pvt. Ltd · Katrap, ThaneP51700005963· filed Nov 2018 → now Nov 2019· 81.5% built· 5 complaints
- SHREE ASHTAVINAYAK VASTU PRAKALPA6.7 yr overdueBALKRISHNA KASHINATH BHOIR · Badlapur (M Cl), ThaneP51700007934· 73.9% built
- vedant imperial ABC phase 16.7 yr overdueMOHAN HARDASMAL THARWANI · Badlapur (M Cl), ThaneP51700006197· 78.5% built
- N G CANARY6.7 yr overdueRNA Builders (NG) · Thane, ThaneP51700000320· 39.1% built
- NG GRAND PLAZA PHASE I6.7 yr overdueOM NAMAH SHIVAY DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700000068· 54.8% built
- SADGURU RESIDENCY6.7 yr overdueRAM LAXMAN DEVELOPERS · DAIGHAR VILLAGE, ThaneP51700019675· 90.9% built
- UMIYA NAKSHATRA6.7 yr overdueM/s. Jigar Enterprise · Badlapur (M Cl), ThaneP51700008369· 90.9% built
- WOODLAND6.7 yr overdueSHAURYA INFRA BUILDERS AND DEVELOPERS · Ambarnath, ThaneP51700005808· filed Dec 2018 → now Dec 2019· 90.9% built
- VASANT VIHAR6.7 yr overdueJAIDEEP CONSTRUCTION · AMBERNATH EAST, ThaneP51700019139· 81.8% built
- GAJANAN SMRUTI6.7 yr overdueJAIDEEP CONSTRUCTION · AMBERNATH EAST, ThaneP51700019112· 81.8% built
- Panvelkar Nisarg Phase-I6.6 yr overduePanvelkar Realty Private Limited · Ambarnath, ThaneP51700004393· filed Dec 2018 → now Dec 2019· 90.9% built
- SHREE KRISHNA PLAZA6.6 yr overdueSHREE HANUMAN ENTERPRISES · Thakurli, Cholegaon, ThaneP51700014660· 90.9% built· 2 complaints
- Ganesh Heights6.6 yr overdueShiv Builders and Developers · Badlapur (M Cl), ThaneP51700006830· 90.9% built
- KUBER GANRAJ6.6 yr overdueKUBER ABHIRAJ INFRA · GANESH NAGAR, ThaneP51700008998· 81.7% built· 57 complaints
- NEPTUNE SWARAJYA SECTOR 2 - B106.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700005300· filed Dec 2018 → now Dec 2019· 56.3% built
- KUMKUM CORNER6.6 yr overdueRAJU JAIN · Thane, ThaneP51700003288· 99.1% built
- SWAMI HIGHLANDS6.6 yr overdueSHREE SWAMI SAMARTH ASSOCIATES · Badlapur (M Cl), ThaneP51700002816· 90.9% built
- MANORAMA CHS6.6 yr overdueRUPA PROPERTIES & SECURITIES PVT. LTD. · Thane, ThaneP51700005251· 90.9% built
- Mohan Areca II6.6 yr overdueMOHAN LIFESPACES LLP · Shirgaon, ThaneP51700017925· 90.9% built
- Amanda Shopping6.6 yr overdueHIRANANDANI PROPERTIES PRIVATE LIMITED · Thane, ThaneP51700000704· 90.9% built
- Shantiniketan Wing B46.6 yr overdueAnmol Associates · Kalyan, ThaneP51700011429· 75% built
- VARDHMAN GARDEN PHASE 16.6 yr overdueDIWALI CONSTRUCTION COMPANY · Thane, ThaneP51700010128· filed Dec 2018 → now Dec 2019· 90.9% built
- URBANVILLE6.6 yr overdueSAI KRUPA BUILDERS · Kalyan, ThaneP51700005910· 31% built
- KASTURI EXOTICA6.6 yr overdueACORN REALITIES · Ambarnath (R), ThaneP51700008788· 57% built
- Geetanjali6.6 yr overdueHonest Homes · Chikanghar, ThaneP51700009495· 90.9% built
- KUBER AAGAN6.6 yr overdueCRATIVE HOME MAKERS · Kalyan, ThaneP51700010264· 63.6% built· 3 complaints
- NEPTUNE SWARAJYA SECTOR 2 - B86.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700009785· filed Dec 2018 → now Dec 2019· 54.5% built· 3 complaints
- LAABH NEELKANTH6.6 yr overdueLAABH BUILDTECH · Thane, ThaneP51700010195· 83.9% built
- Mohan Nano estates II6.6 yr overdueMOHAN LIFESPACES LLP · AMBERNATH, ThaneP51700013253· 90.9% built
- ARCH GARDENS I AND II6.6 yr overdueSAI PREM DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700002994· filed Dec 2018 → now Dec 2019· 87.9% built
- NEPTUNE SWARAJYA SECTOR 2 - B96.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700005264· filed Dec 2018 → now Dec 2019· 53.4% built
- TULSI AAHAN6.6 yr overdueRAJ GROUP · Ambarnath, ThaneP51700000064· 73.9% built
- NEPTUNE SWARAJYA SECTOR 2 - B 146.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700003706· filed Dec 2018 → now Dec 2019· 65.8% built· 1 complaint
- NEPTUNE SWARAJYA SECTOR 2 - B126.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700008852· filed Dec 2018 → now Dec 2019· 60.2% built
- AMRUT VISHWA PHASE 26.6 yr overdueSAI SHRADHA DEVELOPERS · Ambarnath, ThaneP51700000808· 51.4% built
- RENTAL BUILDING A-1 R26.6 yr overdueSONAM SPARK INFRA LIMITED · Thane, ThaneP51700004747· filed Sept 2020 → now Dec 2019· 56.6% built
- AND SUNFLOWER6.6 yr overdueANANTNATH DEVELOPERS · Thane, ThaneP51700002966· 90.9% built· 1 complaint
- SAI DHAM RESIDENCY6.6 yr overdueBUILDCON ENGINEERS · Bhiwandi, ThaneP51700009855· 81.8% built
- PUNYODAYA BHAVAN6.6 yr overdueHARAKCHAND NENMAL JAIN · Kalyan, ThaneP51700005373· 81.8% built
- OLIVE-16.6 yr overdueJVM ENTERPRISE · Thane, ThaneP51700001276· 35.9% built
- Panvelkar Estate - Rockford6.6 yr overdueVijay Ramchandra Panvelkar · Ambarnath, ThaneP51700000431· 72.7% built
- VIMAL RAJ WING A-1, MEDITYARAVIRAJ COMPLEX6.6 yr overdueRITESH RAMESH JAIN · Thane, ThaneP51700007634· 84.5% built
- RAIL VIEW6.6 yr overdueUMESH NARESH JAIN · Thane, ThaneP51700002009· 90.9% built
- NEPTUNE SWARAJYA SECTOR 2 - B15 AND B176.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700006446· filed Dec 2018 → now Dec 2019· 70.5% built· 2 complaints
- ASHWA PLATINUM6.6 yr overdueASHWAMEDH BUILDERS AND DEVELOPERS · Thane, ThaneP51700001143· 59.3% built· 1 complaint
- SUNANDA CIRCLE B WING PHASE 16.6 yr overdueRUDIS DEVELOPERS · Thane, ThaneP51700009812· 90.9% built· 1 complaint
- NEPTUNE SWARAJYA SECTOR 2 - B 196.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700009912· filed Dec 2018 → now Dec 2019· 57.1% built
- ARIHANT PLAZA6.6 yr overdueARIHANT DEVELOPERS · Thane, ThaneP51700006068· 72.3% built
- BALAJI ARCADE WING B6.6 yr overdueSHIKHAR DEVELOPERS · Kalyan, ThaneP51700010369· 78.2% built
- DEV RATNA6.6 yr overdueSDC DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700007785· 90.9% built
- BHARGAV6.6 yr overdueR N ENTERPRISES · Thane, ThaneP51700009004· 90.9% built
- Balaji Arcade Wing A6.6 yr overdueSHIKHAR DEVELOPERS · Kalyan, ThaneP51700012219· 90.9% built
- Joy Square6.6 yr overdueANANT SQUARE · Thane, ThaneP51700003827· 90.9% built
- Shree Sai Pooja6.6 yr overdueM/s Mahalaxmi Construction Co. · Ambarnath, ThaneP51700002237· 90.9% built
- GARDEN COURT TYPE B26.6 yr overdueDEEAARDEE ENTERPRISES · VASANT LEELA, ThaneP51700014836· 90.9% built
- GRAPE CITY PHASE I6.6 yr overdueMs AMBER ESTATE · ANANDVALLI BEHIND SHRI GURUJI HOSPITAL, ThaneP51700001499· filed Dec 2018 → now Dec 2019· 90.9% built
- Panvelkar Estate - Stanford - Phase 16.6 yr overduePanvelkar Infrastructures Private Limited · Ambarnath, ThaneP51700000366· filed Dec 2018 → now Dec 2019· 83% built
- Kamdhenu Commerz6.6 yr overdueKAMDHENU BUILDERS AND DEVELOPERS · Thane, ThaneP51700000559· 93.6% built
- SHREE SIDDHIVINAYAK HEIGHTS6.6 yr overdueAJIT KRISHNAN RATNAM · Titwala, ThaneP51700003326· filed Dec 2018 → now Dec 2019· 90.9% built
- Chintamani Heights6.6 yr overdueYASH ENTERPRISES · Kulgaon, ThaneP51700014730· 90.9% built
- Mohan Willows II6.6 yr overdueMOHAN LIFESPACES LLP · Ambarnath, ThaneP51700003971· filed Dec 2018 → now Dec 2019· 90.9% built
- TULIP N6.6 yr overdueROYALE URBANSPACE · SHAHAPUR, ThaneP51700011791· 53.2% built
- DEEP AANGAN6.6 yr overduePAREKH INFRAPROJECTS · Ambarnath, ThaneP51700001986· 33.4% built
- NEPTUNE SWARAJYA SECTOR 2 - B166.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700011196· filed Dec 2018 → now Dec 2019· 59.2% built
- NEPTUNE SWARAJYA SECTOR 2 - B186.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700008868· filed Dec 2018 → now Dec 2019· 57.1% built
- VISHWAJEET MANOR6.6 yr overdueABHIJEET REALTY · Ambarnath, ThaneP51700001321· 45.5% built
- SUNCITY ORION6.6 yr overdueNESTOR SAI DEVELOPERS PVT LTD · Bhiwandi, ThaneP51700008247· filed Dec 2018 → now Dec 2019· 90.9% built
- SATYAM OLEANDER6.6 yr overdueSAHYOG GROUP · Ambarnath(M Cl), ThaneP51700010440· 74.2% built· 2 complaints
- SAI FORTUNE6.6 yr overdueSURESH GURALDAS THADANI · Ulhasnagar, ThaneP51700015389· 37.7% built
- VARDHMAN VATIKA6.6 yr overdueDIWALI DEVELOPERS · Thane, ThaneP51700018906· 90.9% built
- SAI APARTMENTS6.6 yr overdueGAJANAN KOTKAR & NANDINI KOTKAR · Thane, ThaneP51700004665· filed Dec 2018 → now Dec 2019· 9.1% built
- NANA PATIL PRIDE6.6 yr overduePATIL BUILDERS AND DEVELOPERS · Ambarnath, ThaneP51700008376· filed Dec 2018 → now Dec 2019· 80.2% built
- NEPTUNE SWARAJYA SECTOR 2 - B116.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700010381· filed Dec 2018 → now Dec 2019· 56.6% built· 1 complaint
- NILGAGAN CO-OPERATIVE HOUSING SOCIETY LIMITED6.6 yr overdueFSK BUILDERS & DEVELOPERS PRIVATE LIMITED · Thane, ThaneP51700002833· 90.9% built
- BLUE DIAMOND RESIDENCY6.6 yr overdueKIMAYA CONSTRUCTION · Ambarnath, ThaneP51700002359· 90.9% built
- NILOY6.6 yr overdueSHREE SAI BUILDERS & DEVELOPERS · Ambarnath, ThaneP51700000166· 81.8% built
- Shantiniketan Wing B36.6 yr overdueAnmol Associates · Kalyan, ThaneP51700010374· 75% built
- SAGAR SRUSHTI B WING6.6 yr overdueUMA SAGAR HOMES · Kalyan, ThaneP51700010980· filed Dec 2018 → now Dec 2019· 90.7% built
- Raj Height6.6 yr overdueBhavani Enterprises · SHIRGOAN, ThaneP51700006732· 90.9% built
- LODHA FRESHIA WING D, E6.6 yr overdueLodha Developers Limited · Kalyan, ThaneP51700006149· 90.9% built
- SAI KRUPA RESIDENCY6.6 yr overdueSAIRAJ DEVELOPERS · BADLAPUR, ThaneP51700015567· 90.9% built
- VIRAT AANGAN BUILDING NO 16.6 yr overdueSIDDHIVINAYAK DEVELOPERS · GANESH NAGAR, ThaneP51700007977· 72.7% built
- ANA Avant Garde Phase 16.6 yr overdueSTEELFAB ENGINEERING CORPORATION · Thane, ThaneP51700001388· filed Dec 2018 → now Dec 2019· 97.4% built· 25 complaints
- NEPTUNE SWARAJYA SECTOR 2 - 1B6.6 yr overdueNEPTUNE DEVELOPERS LTD · Kalyan-Dombivali (M Corp.), ThaneP51700003705· filed Dec 2018 → now Dec 2019· 55.6% built
- GOLDSTAR DECENT HOMES6.6 yr overdueGOLDSTAR SANKALP CONSTRUCTION · Thane, ThaneP51700000053· filed Dec 2018 → now Dec 2019· 82.9% built
- SAPPHIRE6.6 yr overdueJANGID BUILDERS PRIVATE LIMITED · Mira Road East, ThaneP51700020060· 28.4% built
- charms hill6.6 yr overdueM/S PRIME DEVELOPERS · Vangani (CT), ThaneP51700007816· filed Dec 2018 → now Dec 2019· 89.1% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.