RERA projects past their possession deadline
11,768 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 29 of 59
- DLH DREAM TOWER5.4 yr overdueDEV LAND & HOUSING PVT LTD · Andheri, Mumbai SuburbanP51800006778· filed Sept 2019 → now Mar 2021· 99.1% built
- Bishopsgate5.4 yr overdueBridgeview Real Estate Development LLP · Ward ABCD, Mumbai CityP51900001325· filed Sept 2019 → now Mar 2021· 71.3% built· 10 complaints
- KRISSH INFRA5.4 yr overdueKRISSH INFRA · CHEHEDI BK, NashikP51600013543· filed Sept 2019 → now Mar 2021· 90.9% built
- Apartment 205.4 yr overdueAbhishek Agrawal · Khanda Colony, RaigarhP52000013194· 90.9% built
- DASARATH PLAZA5.4 yr overduePRABHAT BUILDERS & DEVELOPERS · Kalyan, ThaneP51700013428· 65.5% built
- AARADHYA NINE5.4 yr overdueMICL REALTY LLP · Kurla, Mumbai SuburbanP51800000229· 90.9% built
- Rachana Park Wing H5.4 yr overdueShree Construction Builders and Developers · Near Sai City, AhmednagarP52200021790· 90.9% built
- ROHAN LEHER 2 WING A5.4 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · Pune (M Corp.), PuneP52100000610· 86.4% built
- SHREERAM RESIDENCY5.4 yr overdueNARENDRA ATMARAM PATIL · DANDEKAR NAGAR, JalgaonP49900025239· 90% built
- HARI LEELA RESIDENCY5.4 yr overdueHARI LILA ENTERPRISES · Ulawe, RaigarhP52000012706· 90.9% built
- AKSHATA ANAND RESIDENCY5.4 yr overdueANAND CONTRACTORS AND DEVELOPERS · INDAPUR, PuneP52100016189· 90.9% built
- Somershwar Apartment5.4 yr overdueHarihar Builders & Developers · Palghar, PalgharP99000011912· filed Oct 2018 → now Mar 2021· 53.6% built· 1 complaint
- CHRISHH FORTUNE5.4 yr overdueCHRISHH HOLDINGS · Talegaon Dabhade (M Cl), PuneP52100008612· 77.3% built
- Shubham Sarayu5.4 yr overdueShubham Realty · Kurla, Mumbai SuburbanP51800004927· filed Jun 2019 → now Mar 2021· 90.9% built
- SHIVTEJ PUSHPA5.4 yr overdueYOGESH RAMDAS SARJINE · Panvel, RaigarhP52000013064· 90.9% built
- DATTA VIHAR5.4 yr overdueMAITREE BUILDERS · Palaspe, RaigarhP52000013719· 90.9% built
- VERTICA5.4 yr overdueINFINITY CORP · Mulshi, PuneP52100000863· 52.3% built
- La Montana Phase III5.4 yr overdueTata Value Homes Limited · Mawal, PuneP52100000145· filed Sept 2019 → now Mar 2021· 90.9% built· 1 complaint
- FORTUNE SIRI5.4 yr overdueRadiance Erectors Pvt. Ltd · Nagpur (M Corp.), NagpurP50500011845· filed Sept 2018 → now Mar 2021· 90.7% built· 2 complaints
- Beverly Hills - Building F5.4 yr overdueSheth Developers · Hinjewadi, PuneP52100008510· filed Mar 2020 → now Mar 2021· 38.2% built· 1 complaint
- KANAKIA RAINFOREST5.4 yr overdueKANAKIA SPACES REALTY PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000224· 87.6% built· 14 complaints
- The Metrozone Athens A35.4 yr overdueSanklecha Construction Private Limited · INDIRA NAGAR, NashikP51600009518· filed Sept 2018 → now Mar 2021· 90.9% built· 1 complaint
- VENKATESH NANDANVAN C WING5.4 yr overdueSANJAY DNYANOBA JAGTAP · Sasvad (M Cl), PuneP52100011768· 41.8% built
- Godrej Central5.4 yr overdueGodrej Landmark Redevelopers Private Limited · Kurla, Mumbai SuburbanP51800001107· 89.1% built· 15 complaints
- OM CYGNUS5.4 yr overdueOM BUILDERS AND SUPERSTRUCTURES · ULWE, RaigarhP52000010728· 82.1% built
- SUKHADWALA MANSION5.4 yr overdueSISODIA CANNING PVT LTD · Mumbai City, Mumbai CityP51900010180· 30.9% built
- RUNAL GATEWAY PHASE - II5.4 yr overdueRajendra Suresh Jain · Kiwale, PuneP52100019500· 90.9% built
- SAISHRIYA SAMRUDDHI5.4 yr overdueSAI SHRIYA BUILDERS · WAGHOLI, PuneP52100005815· 24.8% built
- Ramaa Keshav Residency5.4 yr overdueVijay Keshav Lele · Sangli Miraj Kupwad (M Corp.), SangliP53100010033· 55.5% built
- Nilaya5.4 yr overdueFour Seasons Holdings · Pune City, PuneP52100013216· 78.5% built
- LA IMPERIA5.4 yr overdueIMPERIAL BUILDCON ·P52100013605· 90.9% built
- NYATI ENCHANTE II5.4 yr overdueNYATI BUILDERS PRIVATE LIMITED · VADGAONSHERIP52100020656· 75.4% built
- TruSpace Prima Domus Phase 25.4 yr overdueAtharva Enterprises · Balewadi, PuneP52100016331· 45.9% built
- Kohinoor Castles5.4 yr overdueKohinoor Castles · Ambarnath, ThaneP51700001641· 90.9% built
- Unique Prospero5.4 yr overdueUnique Group Unit No. 4 · Haveli, PuneP52100013353· 86.8% built
- DWARKA HEIGHTS5.4 yr overdueDWARKA BUILDERS & DEVELOPERS · Chiplun (M Cl), RatnagiriP52800013685· 82.7% built
- SILVER OAK5.4 yr overdueSHREE SIDDHIVINAYAK CONSTRUCTION · PUNE, PuneP52100019281· 6.8% built
- SAROJ CHSL5.4 yr overdueAssociated Recons LLP · DAHANUKAR COLONY, PuneP52100014747· 81.8% built
- VISION INDRABHUMI5.4 yr overdueVISION INFRASTRUCTURE · DUDULGAON, PuneP52100018032· 90.9% built
- ROYAL RADIANCE5.4 yr overdueM/S.Five Star Shelters · RAHATANI, PuneP52100022253· 81.8% built
- GANESH GALAXY5.4 yr overdueV.N.D CONSTRUCTION · PUNE, PuneP52100004383· filed Sept 2019 → now Mar 2021· 42.7% built
- Varija Apartment5.4 yr overdueGanesha Developers · Kalyan, ThaneP51700004648· 9.1% built
- VENKATESH NANDANVAN D WING5.4 yr overdueSANJAY DNYANOBA JAGTAP · Sasvad (M Cl), PuneP52100009712· 44.5% built
- STUDIO HIGH 5 Phase 25.3 yr overdueRAMSHIROMANI LURKHUR YADAV · DHAMOTE, RaigarhP52000003207· filed May 2019 → now Mar 2021· 81.8% built
- PLOT NO 63 SECTOR 12 DRONAGIRI5.3 yr overdueCITY AND INDUSTRIAL DEVELOPEMENT CORPORATION OF MAHARASHTRA LTD · Uran, RaigarhP52000017365· filed Dec 2020 → now Mar 2021· 78.2% built
- ECSTASIA5.3 yr overdueA V BHAT BUILDERS PRIVATE LIMITED · Haveli, PuneP52100013096· filed Sept 2018 → now Mar 2021· 90.9% built
- TULSI TOWER5.3 yr overdueSHRI KALKI ENTERPRISES · Village Vadavali, ThaneP51700016781· filed Sept 2020 → now Mar 2021· 18.2% built
- KISHOR KUNJ5.3 yr overdueBHAGWATI BUILDERS AND DEVELOPERS · Vasai, PalgharP99000006836· filed Dec 2017 → now Mar 2021· 90.9% built
- SPLENDOUR GREENS SEETAI LAKE5.3 yr overdueJORI DAGADE ASSOCIAS · Bhugaon, PuneP52100005973· filed Aug 2019 → now Mar 2021· 99.1% built
- SECTOR 22, TALOJA5.3 yr overdueCITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED · SECTOR 22, RaigarhP52000017425· filed Dec 2020 → now Mar 2021· 78.2% built· 1 complaint
- Dreamz Landmark5.3 yr overdueM/S DREAMZ INFRASTRUCTURE · Amravati (M Corp.), AmravatiP50300005178· 31.4% built
- SHIVNIL5.3 yr overdueSHIVKAILAS DEVELOPMENT CORPORATION · NEAR MOSHI TOLL PLAZA, PuneP52100023537· filed Dec 2020 → now Mar 2021· 81.8% built
- CHARMS HEIGHTS PHASE-II A1-A25.3 yr overdueCharms Developers · Titwala, ThaneP51700002670· filed Mar 2019 → now Mar 2021· 90.9% built
- SHAGUN5.3 yr overdueSIDDHESH DEVELOPERS · Near Nal Stop , Karve Road , Erandwane, PuneP52100026627· 90.9% built
- Dineshkunj CHS Ltd5.3 yr overdueSwastik Realty Pvt Ltd · Borivali, Mumbai SuburbanP51800004364· filed Jun 2018 → now Mar 2021· 90.9% built· 1 complaint
- BELMAC RIVERSIDE-I5.3 yr overdueSUPREME HOLDINGS & HOSPITALITY (INDIA) LIMITED · Akurli Village, RaigarhP52000014630· filed Mar 2020 → now Mar 2021· 81.8% built
- Golden Arcs5.3 yr overdueAmol Kalani · Nath Seeds, AurangabadP51500004343· filed Oct 2018 → now Mar 2021· 90.9% built
- SHEETAL OM JAY ARADHANA5.3 yr overdueD.G.LAND DEVELOPERS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800000446· filed Dec 2018 → now Mar 2021· 44.1% built· 4 complaints
- KRUPACHHATRA COMPLEX5.3 yr overdueMEHTA BUILDERS · Jalochi, PuneP52100013921· 90.9% built
- ECO SHOPPY5.3 yr overdueNAMRATA DEVELOPERS PVT. LTD · s, PuneP52100015225· 80% built
- Arun Viva5.3 yr overduecelesta developers · Pune, PuneP52100013048· 90.9% built
- Aadinath Nagar Phase - I5.3 yr overdueArihant Vastu Nirman Pvt. Ltd · Nachane (CT), RatnagiriP52800000156· 90.9% built
- RAJ VASTU5.3 yr overdueRAJ BUILDCON · NEW MIDC, SataraP52700016374· 81.8% built
- PANCHAVATI NEST5.3 yr overduePANCHAVATI DEVELOPERS · chikhali, PuneP52100005358· 81.8% built
- Sanvi Marvel5.3 yr overdueMeghraj Spaces Private Limited · Khed, PuneP52100007075· filed Oct 2019 → now Apr 2021· 27.1% built· 3 complaints
- SINHGAD PLANET B WING5.3 yr overdueANANT NARAYAN GANDALE · NARHE, PuneP52100003473· filed Oct 2019 → now Apr 2021· 27.3% built
- VARDHAMAN PEARL-ABOLI5.3 yr overdueVardhman Pearl · Raghav nagar, PuneP52100000751· filed Oct 2019 → now Apr 2021· 90.9% built
- KATE VRUNDAVAN5.3 yr overdueVRUNDAVAN DEVELOPERS · Haveli, PuneP52100000189· 48% built
- PRITHVI REGENCY5.3 yr overduePRITHVI PROPERTY DEVELOPERS · PALGHAR, PalgharP99000015122· 90.9% built
- SAI LOTUS5.2 yr overdueMAKHIJA CONSTRUCTION · Ulhasnagar, ThaneP51700014625· 35.5% built
- PARIJAT5.2 yr overdueM/s Shri Sadguru Developers · NARSALA, NagpurP50500018590· 63.6% built
- Palm5.2 yr overduePranjee Properties Pvt. Ltd · Katrap, ThaneP51700004695· 9.1% built· 1 complaint
- Neelkanth Woods Olivia5.2 yr overdueT Bhimjyani Realty Pvt.Ltd. · Thane, ThaneP51700004591· 93.5% built· 78 complaints
- VARSHA MEADOWS5.2 yr overdueJAYESH BUILDCON · Kalyan, ThaneP51700005257· 80.6% built· 5 complaints
- INDRAPRASTHA PHASE 2 Includes Building no. 5,95.2 yr overdueM/s Indraprastha Associates · Gondhalpada, RaigarhP52000018038· 79.1% built
- NILKANTH APPARTMENT5.2 yr overdueANGIRA INFRA DEVELOPER PVT LTD · Nashik, NashikP51600005210· filed Jul 2020 → now Jun 2021· 89.1% built
- BLISS NIRMAN INDUSTRIAL ESTATE5.1 yr overdueBLISS DEVELOPERS · Goraipada, PalgharP99000029700· 81.8% built
- MAHAVIR SADAN A5.1 yr overdueRajesh Construction · Palghar, PalgharP99000021076· 90.9% built
- SAI ANAND RESIDENCY5.1 yr overdueSAI ANAND REALTY · ANAND DHAM, AhmednagarP52200019491· 40.9% built
- Silver Treasure Wing B5.1 yr overdueMark Bulidcon · Vadgaon Phata, PuneP52100013384· 61.8% built
- SIDDHIVINAYAK5.1 yr overdueTriumph Ventures · Borivali, Mumbai SuburbanP51800011066· 90.9% built· 4 complaints
- Courtyard One phase 25.1 yr overdueSIGMA ONE DHOOT VENTURES Previously Sigmaone Remonesa Ventures · WAKAD, PuneP52100004083· 87.3% built
- 32 Pinewood Drive -Phase 15.1 yr overdueS S Properties · Hingewadi Phase 3, PuneP52100001171· 79.1% built
- CRD Gardenia Apartments 6 - Phase II5.1 yr overdueDr Chandrashekhar Raghunath Dound · Velgaon, PalgharP99000019665· 81.8% built
- JP REGENCY PHASE 15.1 yr overdueJP DEVELOPERS · AMBERNATH OLD VILLAGE, ThaneP51700013777· 87.9% built
- SANVEG RESIDENCY - PHASE I5.1 yr overdueOM VASTU HOMES · BADLAPUR GAON, ThaneP51700014705· 99.5% built
- QN GREENS PHASE 25.1 yr overdueQUALITAS NAMAN HOME MAKERS LLP · TALOJA PHASE 2, RaigarhP52000015726· 86.4% built
- ARWADE ALTIA5.1 yr overduemrk infracon · NORTH SHIVAJINAGAR, SangliP53100017830· 98.2% built
- Rite Oscar5.1 yr overdueRITE PROPERTIES · Borivali, Mumbai SuburbanP51800020831· 90.9% built
- DIVYA PLAZA5.1 yr overdueADITYA ENTERPRISES · Karjat, RaigarhP52000014481· 90.9% built
- Automatic Co-Operative Housing Society Ltd5.1 yr overdueJOSHI ENTERPRISES · Thane, ThaneP51700014895· 91.4% built
- Sun Exotica Phase 25.1 yr overdueJindal Mittal Graha Nirman Pvt. Ltd. · S. No. 10/2/4, PuneP52100018347· 93.3% built
- SAI SHARNAM- TYBE B5.1 yr overdueANJANA SAHEBRAO CHAVAN · WADEGHAR, ThaneP51700015504· 40.9% built
- SECTOR-27 TALOJA5.1 yr overdueCITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASTRA LIMITED · SECTOR 27, RaigarhP52000017438· filed Mar 2021 → now Jun 2021· 64.5% built
- Nilkhanth residency5.1 yr overdueM/s Pavan and GJ construction co · Zadgaon CT, RatnagiriP52800014011· 90.9% built
- SAI PRASAD5.1 yr overdueADITYARAJ BUILDERS · Kurla, Mumbai SuburbanP51800004104· 55% built
- HORIZON CLASSIQUE-25.1 yr overdueSACHIN ENTERPRISES · OWALA, ThaneP51700015081· 90.9% built
- Building D Voyage5.1 yr overdueKasturi Shelters · Borhadewadi, PuneP52100006188· 99.8% built
- METRO IMPERIAL5.1 yr overdueMETRO BALAJI DEVELOPERS · BADLAPUR, ThaneP51700015305· 90.9% built
- Plot 1 Sector 10 GHANSOLI5.1 yr overdueCIDCO of Maharashtra Ltd. · Thane, ThaneP51700017366· 81.8% built
- Vistaara Residences5.1 yr overdueVistaara Lifespaces LLP · Gultekdi Pune, PuneP52100015297· 81.8% built
- SHARV PARADISE5.1 yr overdueAshok Pawar & Sons · Padavewadi, RatnagiriP52800012763· 72.7% built· 1 complaint
- MARBLE HEIGHTS5.1 yr overdueSHREE SAI ENTERPRISES · Borivali, Mumbai SuburbanP51800007464· 39.1% built
- MATOSHRI HEIGHTS5.1 yr overdueSUJAL DEVELOPERS · Kalyan, ThaneP51700010731· 90.9% built
- SAI VYANKATESH5.1 yr overdueANJANA SAHEBRAO CHAVAN · NEAR CHATRI BUNGLOW, BEHIND ALISHAN RESIDENCY, ThaneP51700016410· 88.9% built
- SIDDHESHWAR ARAMBHA5.1 yr overdueSIDDHESHWAR DEVELOPERS AND BUILDERS · MOSHI GAOTHAN, PuneP52100016365· 27.3% built
- MADHOORS TALEKAR CHAMBER5.1 yr overdueMadhoor Buildwell Pvt. Ltd. · Ashok Stambh, NashikP51600017279· 53% built
- PRABHU LOK5.1 yr overduePRABHU LOK ENTERPRISES · Khalapur, RaigarhP52000003248· 90.9% built
- NIRVANA BEYOND A WING5.1 yr overdueDiamond Nexus Properties · KATALE VASTI, PuneP52100015425· 90.5% built
- ELEMENTS5.1 yr overdueUMA REALTY · Thane, ThaneP51700015118· 90.9% built
- THE WORLD TOWERS - WORLD ONE - TIER III AND TRINITY5.1 yr overdueMACROTECH DEVELOPERS LIMITED · Ward GSouth, Mumbai CityP51900008962· 63.6% built· 10 complaints
- Chhoriya Prestige, Tuljapur5.1 yr overdueDhariwal And Chhoriya Buildcon Pvt Ltd · Tuljapur, OsmanabadP52500016155· 34.1% built
- Samadhan5.1 yr overdueShivam Parivar Developers Pvt Ltd · Andheri, Mumbai SuburbanP51800016620· 90.9% built· 8 complaints
- FUSION TOWERS PHASE I5.1 yr overdueRAMA SYNERGY SPACES · Hinjawadi - Phase III, PuneP52100018013· 95.5% built· 3 complaints
- Rajyog Royal5.1 yr overdueRajyog Builders and Developers · Haveli, PuneP52100013691· 80.5% built
- GANESH EMERALD B WING5.1 yr overdueEKDANTA NEST LLP · CHIKHALI, PuneP52100019225· 72.3% built
- RAPID RESIDENCY5.1 yr overduePARK VIEW DEVELOPERS · NERAL, RaigarhP52000010355· 99% built· 3 complaints
- PARVATI SADAN5.1 yr overdueMEENA BUILDER UNIT OF V N RAIKAR HUF · PLOT NO 49A PARVATI SADAN FRONT OF DHANLAXMI BANK CHEMBUR MUMBAI, Mumbai SuburbanP51800016081· 87.3% built
- MAHALAXMI RECEDENCY5.1 yr overdueSATYABHAMAVITTHAL CONSTRUCTION AND LAND DEVELOPERS PRIVATE LIMITED BARSHI · NEAR RAILWAY STATION, SolapurP52600024725· 55.3% built
- Krishnakunj Vihar Phase-15.0 yr overduePooja Shridhar Kangralkar · Karanje Tarf Satara, SataraP52700019447· 86.4% built
- GEM PARADISE5.0 yr overdueVAYUPUTTRA BUILDERS & INFRASTRUCTURES PVT. LTD. · Vira Desai Road Andheri west, Mumbai SuburbanP51800014003· 90.9% built· 7 complaints
- WAMAN HEIGHTS5.0 yr overdueLAXMI DEVELOPERS · Kalyan, ThaneP51700015114· 90.5% built
- PEACE APARTMENT5.0 yr overdueSaleem Shamsher Patel · Padegaon, AurangabadP51500015185· 74.1% built
- RAJ KIRTI INDUSTRIAL ESTATE4.9 yr overdueRAJ DEVELOPERS · VASAI, PalgharP99000029685· 81.8% built
- VRUNDAVAN PARK4.9 yr overdueShree Saishraddha Developers & Builders · Shirur, PuneP52100018019· 18.2% built
- PRASANNA I SQUARE4.9 yr overduePRASANNA DEVELOPERS · Chakan (CT), PuneP52100011288· filed Dec 2017 → now Sept 2021· 90.9% built
- GREEN GLORY B WING4.8 yr overdueShree Mahalaxmi Group · Mawal, PuneP52100002374· filed Mar 2019 → now Sept 2021· 73.5% built
- BALKRUSHNA ARCADE4.8 yr overdueSHIVAJI PARSHURAM KATHORE · OPP TALATHI OFFICE, BADLAPUR WEST, ThaneP51700020212· 31.8% built
- SHREE RAM KRISHNA4.8 yr overdueVARDHAMAN DEVELOPERS · KARANJADE PANVEL, RaigarhP52000017661· 82.7% built
- VASANT VILLA4.8 yr overdueVASANT CONSTRUCTION · ADARSH NAGAR, PalgharP99000015257· filed Sept 2020 → now Sept 2021· 0% built· 1 complaint
- Sukhwani Coloronic Phase II4.8 yr overdueS. S. D. Construction · Ravet, PuneP52100019968· 88% built
- URBAN GLORY WING A4.8 yr overduePARADISE INFRASTRUCTURE · PARSODI, NagpurP50500013215· 78.6% built· 10 complaints
- MELANGE RESIDENCES - PHASE III4.8 yr overdueRAMA SYNERGY SPACES · Hinjawadi Phase III, PuneP52100017090· 94.5% built
- Balaji Infra Projects4.8 yr overdueBalaji Infra Projects · Kagal, KolhapurP53000015463· filed Feb 2021 → now Oct 2021· 72.7% built
- SAIDHAM4.8 yr overdueRajmata Construction · Baramati (M Cl), PuneP52100003158· 90.9% built
- Shree Samarth Krupa4.8 yr overdueShri Labsons Builders and Developers Pvt Ltd · Vinayak nagar , Moshi, PuneP52100010272· filed Dec 2018 → now Oct 2021· 76.4% built
- ATMIYA LUXURIA4.8 yr overdueAKSHAR BUILDERS AND DEVELOPER · Sonavale, ThaneP51700009857· 90.9% built
- BALAJI PARK4.8 yr overdueDHANWANTARI BUILDER AND DEVELOPERS · Kumbhari, BuldanaP50000014183· 90.9% built
- SADANAND RESIDENCY4.8 yr overdueJYOTI CONSTRUCTIONS · FORT, SangliP53100014209· 81.8% built
- IRIS RESIDENCY4.8 yr overdueRathi Infracon · Solapur (M Corp.), SolapurP52600011078· 90.9% built
- MAJESTIC VILLA4.8 yr overdueSSCONSTRUCTIONS · Sangli Miraj Kupwad (M Corp.), SangliP53100006584· filed Apr 2019 → now Oct 2021· 90.9% built
- ANUSHRI KLASSIC4.8 yr overdueBalaji Developers · Kalas, PuneP52100015672· 81.8% built
- PARIJATAK, MADHUBAN PHASE 54.8 yr overdueSAHYADRI PROPERTIES · Haveli, PuneP52100010997· filed Sept 2019 → now Oct 2021· 50% built
- EKTARA4.8 yr overdueArtharaj Realtors · Haveli, PuneP52100006129· filed Oct 2019 → now Oct 2021· 90.9% built
- PUSHKARAJ HEIGHTS4.8 yr overdueATUL ANIL NERPAGAR · NASHIK SHIWAR, NASHIK, NashikP51600016236· 90.9% built
- PARSHWA GOLD COUNTY WING A4.8 yr overduePARSHWA PROPERTIES · charohli, PuneP52100000180· 90.9% built
- Zinnia Row Houses4.8 yr overdueMagarpatta Township Development & Construction Co. Ltd. · Haveli, PuneP52100018373· 87.1% built
- SHIVAM GREENCOURT4.8 yr overdueSHIVAM DEVELOPERS PVT. LTD. · Mahalunge, PuneP52100010035· 90.9% built
- VIVANTE4.8 yr overdueMahindra Lifespace Developers limited · Andheri, Mumbai SuburbanP51800000242· filed Oct 2019 → now Oct 2021· 84.8% built· 1 complaint
- BAMUBAI SADAN4.8 yr overdueSAMARTH DEVELOPERS · Kalyan, ThaneP51700003704· filed Oct 2019 → now Oct 2021· 58.6% built
- Maple Row House4.8 yr overdueAkash Construction · Sai Nagar, AhmednagarP52200022209· 60.5% built
- PRERNA ELITE4.8 yr overdueVARDAN BUILDCON · Nagpur (M Corp.), NagpurP50500015398· 90.9% built
- DIVYAL HEIGHTS4.8 yr overdueDISHANT BUILDERS AND LAND DEVELOPERS · Vasai, PalgharP99000005192· filed Jul 2018 → now Oct 2021· 90.9% built
- ROYAL MYSTIC4.8 yr overdueFive Star Construction Company · RAHATANI,, PuneP52100016160· 81.8% built
- BALAJI VISHWA4.8 yr overdueBALAJI DEVELOPERS · NARHE, PuneP52100013310· 90.9% built
- Rajyog annexe4.8 yr overdueJhala and kodre associates · Wadgaon Khurd, PuneP52100000570· filed Oct 2019 → now Oct 2021· 90.9% built
- Datar Heights4.8 yr overdueSaleem Abdul Shaikh · Badlapur (M Cl), ThaneP51700010631· filed Oct 2019 → now Oct 2021· 41.4% built
- Perfect 10 Phase III4.8 yr overdueShagun Manav Spaces LLP · Balewadi, PuneP52100001096· 90.9% built
- FIA CONSTRUCTION COMPANY FIA IMPERIA4.8 yr overdueNIMISH LAXMICHAND PASAD · Palghar, PalgharP99000003189· 62.7% built
- SAYLEE ENCLAVE4.8 yr overdueFUNSIGN HOUSING PVT. LTD · Borivali, Mumbai SuburbanP51800001965· 90.9% built
- VASANT KUNJ CHS LTD4.8 yr overdueCALVIN SHRESTH PROPERTIES LLP · Andheri, Mumbai SuburbanP51800002566· 80.5% built
- Skyways Esfera 14.8 yr overdueMoze Associates · Lohegaon, PuneP52100018128· 90.9% built
- TIRUPATI CITY PHASE IV4.8 yr overdueTIRUPATI SUPERSTRUCTURES PVT LTD · WASHIM, WashimP50200001506· 30.3% built
- Vaidya Cottage CHS Ltd4.8 yr overdueShamik Enterprises Pvt Ltd. · Vile Parle (east), Mumbai SuburbanP51800001902· filed Jun 2020 → now Oct 2021· 90.9% built· 2 complaints
- The Legend4.8 yr overdueShree Sankalp Associates · Hinjawadi, PuneP52100007333· filed Dec 2020 → now Oct 2021· 18.2% built· 1 complaint
- PGD Pinnacle4.8 yr overduePGD Land LLP · Keshavnagar, PuneP52100002015· 90.9% built
- MANTRA CITY 360 PHASE034.8 yr overdueMANTRA ISLAND HOMES TALEGAON LLP · TALEGAON, PuneP52100002880· filed Oct 2019 → now Oct 2021· 88.2% built
- K52 Building A4.8 yr overdueM/S Shri Sairaj Associates · Pune City, PuneP52100019093· 90.9% built
- SINGAPORE LIFE CITY4.8 yr overdueDHL INFRABULLS · Gotal Panjari, NagpurP50500002626· filed Oct 2019 → now Oct 2021· 0% built· 1 complaint
- Dreams Avani C wing4.8 yr overdueDreams Corporation Pvt Ltd · Manjari, PuneP52100000157· filed Jun 2019 → now Oct 2021· 65.9% built· 8 complaints
- BHAGYASHREE4.8 yr overdueRANJEKAR REALTY · KOTHRUD, PuneP52100015709· 36.4% built
- SHEETAL ARCADE4.8 yr overdueSHIVRAM CONSTRUCTION · NEAR BUS DEPO, ThaneP51700022304· filed Oct 2020 → now Oct 2021· 50% built
- GATHA HEIGHTS4.8 yr overdueOMGATHA BUILDERS AND DEVELOPERS PVT LTD · CHOVISAWADI, PuneP52100026233· filed Jan 2021 → now Oct 2021· 72.7% built
- Hi Face4.8 yr overdueMBM Developers · Pimpale Saudagar, PuneP52100004321· filed Oct 2018 → now Oct 2021· 55.7% built· 7 complaints
- Hayaat Moon4.8 yr overdueNewstar Builders · Vasai, PalgharP99000003825· filed Oct 2019 → now Oct 2021· 22.7% built
- SAI SHIVAM4.8 yr overdueS.R. DEVELOPERS · Navlakh Umbre, PuneP52100012266· filed Apr 2019 → now Oct 2021· 81.8% built
- SAI PARADISE PROJECT B4.8 yr overdueAvenuegold Landmarks LLP · Itkheda, AurangabadP51500018753· 90.9% built
- Rudra Heights4.8 yr overdueMinakshi Datta Sonawane · Nashik (M Corp.), NashikP51600014310· 81.8% built
- MEGHDOOT ENCLVE E WING4.8 yr overdueRAGHAV ASSOCIATES · HUDKESHWAR, NagpurP50500014263· 4.5% built
- Gulmohar Apartment4.8 yr overdueM/S SHREERAM BUILDERS · OPP SHINDE HIGH SCHOOL, PuneP52100017155· 81.8% built
- Meridia4.8 yr overdueAccord Builders · Kurla, Mumbai SuburbanP51800009440· 90.9% built· 27 complaints
- KANAKIA LEVELS4.8 yr overdueKANAKIA SPACES REALTY PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800000223· filed Oct 2019 → now Oct 2021· 99% built· 8 complaints
- LAXMI NARAYAN APPARTMENT4.8 yr overdueANAND BANSILAL PANDIT · SATARA NEERA ROAD, SataraP52700024886· 60.5% built
- VIJAY SAI PRIDE4.8 yr overdueVIJAY DEVELOPERS · Satara, SataraP52700009574· filed Dec 2019 → now Oct 2021· 39.8% built
- SUMERU VEDANTA4.8 yr overdueMARIGOLD REALITY · BENODA, AmravatiP50300016756· filed Feb 2021 → now Oct 2021· 90.9% built
- Audumber4.8 yr overdueOmChidanand · Haveli, PuneP52100014216· 17.6% built
- DAFFODIL HEIGHTS4.8 yr overdueNIHIT PRAVIN MALUSHTE · Nachane (CT), RatnagiriP52800014301· 90.9% built
- Kumar Sanctum - A1 and B14.8 yr overdueKumar Govind J V · Ivory Estate, PuneP52100004814· filed Nov 2019 → now Nov 2021· 82.6% built
- SAI KRISHNA AVENUE4.7 yr overdueHITESH MANSUKHBHAI VIRPARA · Nashik, NashikP51600003101· 49.5% built
- KVK KESHAR BAUG I4.7 yr overdueM/S. KVK HOMES · Navi Mumbai Panvel Rigardh (CT), RaigarhP52000002105· 90.9% built
- VINAYAK154.7 yr overdueBADHEKAR DEVELOPERS · Rambaug Colony, PuneP52100007478· 81.8% built
- CRYSTAL HARMONY4.7 yr overdueCRYSTAL BUILDERS & DEVELOPERS · Andheri, Mumbai SuburbanP51800008387· 36.4% built
- DYANESHWAR BHAWAN4.7 yr overdueSUJEET SHARAD SHEDGE · Satara, SataraP52700013011· 90.9% built
- MALHAR LIFESPACES4.7 yr overdueMALHAR LIFESPACES · PALGHAR CITY, PalgharP99000014945· 90.9% built
- VIDYA VILAS4.7 yr overdueRajyog Builders through its Proprietor Vinayak Alias Prakash Shankar Manohar · Mulshi, PuneP52100013901· 90.9% built
- VIVANTA LIFE VERONIKA4.7 yr overdueVIVANTA REALTY · Pimpale Saudagar, PuneP52100002206· 90.9% built
- Neelkanth Woods Bungalow L 574.7 yr overdueT Bhimjyani Realty Pvt.Ltd. · Thane, ThaneP51700003404· 95.5% built
- MURGA GIRAN4.7 yr overdueLAKADAWALA DEVELOPERS PVT. LTD. · Mumbai City, Mumbai CityP51900007404· 90.1% built
- AXIS VERTIGA4.7 yr overdueAXIS LIFESPACES LLP · PUNE, PuneP52100003159· filed Nov 2019 → now Nov 2021· 90.9% built
- Om Shiv Vatika A Wings4.7 yr overdueOm Shiv Developers · Badlapur (M Cl), ThaneP51700014398· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.