12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 25 of 61
- PRANSHU SQUARE6.1 yr overdueJANANI BUILDERS AND DEVELOPERS · MORE VASTI, PuneP52100011084· filed Jun 2019 → now Sept 2020· 81.8% built
- ARIHANT ARSHIYA PHASE II6.1 yr overdueARIHANT SUPERSTRUCTURES LIMITED · Khalapur, RaigarhP52000002342· filed Mar 2019 → now Sept 2020· 87.4% built
- 9 RADHA6.1 yr overdueISHAAN DEVELOPERS · Ward FNorth, Mumbai CityP51900005726· filed Mar 2019 → now Sept 2020· 60.5% built· 1 complaint
- PANVELKAR OPTIMA6.1 yr overdueVARAD VINAYAK DEVELOPERS · AAPTEWADI, ThaneP51700015392· 40.2% built
- Pansare Paradise Phase 16.1 yr overdueHari Om Builders & Developers · Shirur, PuneP52100015622· 90.9% built
- THE BLUE RIDGE6.1 yr overdueBLUEBERRY DEVELOPERS · CHOWRAI NAGAR, PuneP52100015515· 57.3% built
- Haware Pinnacle6.1 yr overdueSuresh Kashinath Haware · Bhiwandi, ThaneP51700000464· 78.2% built
- Atlantis6.1 yr overdueManoj Yeole Ramdas Yeole · Pune (M Corp.), PuneP52100002148· 49.5% built
- MANGESHI DAZZLE - III6.1 yr overdueKALYAN DEVELOPMENT CORPORATION · Kalyan, ThaneP51700005137· filed Mar 2019 → now Sept 2020· 84.2% built
- United Courtyard Phase I6.1 yr overdueUnited Builders · BEHIND INOX, NashikP51600001925· filed Mar 2019 → now Sept 2020· 90.9% built
- VARSHA Phase II6.1 yr overdueSADGURU Developers · Baner, PuneP52100019844· 89.1% built
- HARI OM NAGAR6.1 yr overdueRRB BUILDER · Devlai, AurangabadP51500011402· 69.4% built
- Dreams Lynnea A B wings6.1 yr overdueDreams Construction ( Pune) Pvt. Ltd. · WAGHOLI, PuneP52100000237· filed Mar 2019 → now Sept 2020· 68.8% built· 12 complaints
- The Mist -Phase I6.1 yr overdueGeeCee Ventures Limited · Karjat, RaigarhP52000007101· 87.2% built· 4 complaints
- Antheia B36.1 yr overdueMahindra Lifespace Developers limited · Haveli, PuneP52100016677· 90.9% built· 1 complaint
- MANGAL VIHAR WING B6.1 yr overdueMANGAL CONSTRUCTION · Solapur (M Corp.), SolapurP52600002066· 34.5% built
- Earth Residency6.1 yr overdueEarth Builder & Developers · Palghar, PalgharP99000007170· filed Mar 2019 → now Sept 2020· 90.9% built
- COZY LIFE6.1 yr overdueCOZY LIFE · PUNE, PuneP52100011208· 28.6% built· 2 complaints
- NIVRUTTI HEIGHTS6.1 yr overdueKALKI DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100011757· filed Mar 2019 → now Sept 2020· 90.9% built· 8 complaints
- TIRUPATI ENCLAVE6.1 yr overdueEKALAWYA WASEKAR & OTHERONE · Nagpur (M Corp.), NagpurP50500007836· 81.8% built
- SHREE CHINMAY GAURANG GRIHSANKUL6.1 yr overdueSHREE CHINMAY GAURANG INFRASTRUCTURE · PANVEL, RaigarhP52000004925· 90.9% built· 1 complaint
- BLUE FORTUNA6.1 yr overdueATUL PROJECTS INDIA PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800010900· 90.9% built· 1 complaint
- SHIVLEELA6.1 yr overdueEkdant Developers · Jejuri (M Cl), PuneP52100001802· 73.2% built
- VATSALYA VIHAR6.1 yr overdueATUL HANUMANT MORE · SHANIWAR PETH, SataraP52700015221· 27.3% built
- Memories6.1 yr overdueM/s NAMO DEVELOPERS · MOHAMMADWADI, PuneP52100001168· filed Mar 2019 → now Sept 2020· 51.8% built· 1 complaint
- Yogi Milan Phase 36.1 yr overdueShiv Builders · NR. BALAJI TEMPLE, Dadra & Nagar HaveliP49600000022· 90.9% built
- KRISHNABAN Phase 26.1 yr overdueBhuvi Landmarks LLP · Jalna, JalnaP51400011318· filed Mar 2019 → now Sept 2020· 78.2% built
- PATWARDHAN SANKUL6.1 yr overduePATWARDHAN BUILDERS · Sangli Miraj Kupwad (M Corp.), SangliP53100011580· filed Mar 2019 → now Sept 2020· 32.1% built
- HARI KUNJ III6.1 yr overdueKUKREJA CONSTRUCTION CO · Kurla, Mumbai SuburbanP51800007495· 59.1% built
- DWARIKA VALLEY PHASE I6.1 yr overdueDWARIKA REAL INFRA LLP · Matoshree Nagar, RaigarhP52000003025· filed Mar 2019 → now Sept 2020· 78.8% built· 5 complaints
- AASRA6.1 yr overdueIMPRESSA LAXMI · NAGPUR, NagpurP50500013844· 90.9% built· 1 complaint
- Life Republic Sector R2 - 2nd Avenue6.1 yr overdueKOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED · Marunji, PuneP52100002682· filed Mar 2019 → now Sept 2020· 78.2% built
- METRO JAZZ6.1 yr overdueBALAJI REALTY · Baner, PuneP52100004597· filed Mar 2019 → now Sept 2020· 76.4% built· 1 complaint
- SWASTIK DREAMS6.1 yr overdueDHANANJAY DAMODHAR DAREKAR · Pimpri Chinchawad (M Corp.), PuneP52100005665· 45.5% built
- SHREE ELIGANCE6.1 yr overdueABHILASHADEVELOPER · CHIKHALI, PuneP52100007582· filed Mar 2019 → now Sept 2020· 62.3% built
- KANAKIA MIAMI6.1 yr overdueKANAKIA SPACES REALTY PRIVATE LIMITED · Ward GNorth, Mumbai CityP51900000206· 98.9% built· 4 complaints
- RAMDOOT6.1 yr overdueHARESHKUMAR RASIKLAL SHAH · KARANAJADE PANVEL, RaigarhP52000016188· 8.2% built
- MEDHA CHSL6.1 yr overdueC H PATIL AND SONS LLP · Borivali, Mumbai SuburbanP51800006437· filed Mar 2019 → now Sept 2020· 90.9% built
- KUM KUM BHAGYA6.1 yr overdueKUM KUM ENTERPRISES · Bopele, RaigarhP52000009221· filed Mar 2019 → now Sept 2020· 81.8% built
- Chandra Villa6.1 yr overdueM/s. Accord Realtors · Mumbai City, Mumbai CityP51900002098· 66.8% built
- Dhruvika Enclave6.1 yr overdueManoyadnya Developers · Joveli Gaon, ThaneP51700015355· 81.8% built
- GIRNAR6.1 yr overdueABHAY CHANDRAMOHAN SAWANT · Daund (M Cl), PuneP52100007331· filed Mar 2019 → now Sept 2020· 81.8% built
- Aundh Riviera6.1 yr overdueSujay Shirish Bhansali · Haveli, PuneP52100002165· filed Mar 2019 → now Sept 2020· 90.9% built
- Lotus Niwas / Satya Niwas6.1 yr overdueK L Ventures and Enterprises · Borivali, Mumbai SuburbanP51800002047· filed Mar 2019 → now Sept 2020· 81.8% built
- DEEP DESTINY6.1 yr overdueSAMBHAV REALTY · KARANJADE, RaigarhP52000002407· 89.5% built
- SHRI INDUSTRIAL ESTATE6.1 yr overdueSHRI ENTERPRISES · Vasai, PalgharP99000008391· 65.5% built
- BUSINESS SQUARE6.1 yr overdueVASTUKRUPA CONSTRUCTION (INDIA) PVT LTD · Nashik, NashikP51600000211· filed Mar 2019 → now Sept 2020· 90.9% built
- CD Plot No 69 Lumiere6.1 yr overdueSD SVP Nagar Redevelopment Private Limited · Andheri, Mumbai SuburbanP51800005440· filed Sept 2019 → now Sept 2020· 99.7% built· 43 complaints
- Prakriti -D- Navyangan6.1 yr overdueCALYX MERLIN VENTURES LLP · Mulshi, PuneP52100000312· filed Mar 2019 → now Sept 2020· 83.1% built
- KACHWALA PALACE6.1 yr overdueCREST VENTURES LIMITED · Andheri, Mumbai SuburbanP51800005902· 81.8% built
- TIRUPATI RESIDENCY BUILDING C6.1 yr overdueSAJANSING MOTILAL JARWAL · NEAR CIDCO WATER TANK, AurangabadP51500015607· 90.9% built
- Emerald Tower6.1 yr overdueS M Enterprises · Vasai, PalgharP99000004995· filed Mar 2018 → now Sept 2020· 90% built
- Bloomdale Building 096.1 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500006483· filed Mar 2019 → now Sept 2020· 90.9% built· 2 complaints
- ANAND6.1 yr overdueNAREN ENTERPRISES · Karanjade, RaigarhP52000006710· 70.9% built
- CASA LOTUS6.1 yr overdueR. C. CON ASSOCIATES JV · Wanadongri, NagpurP50500002363· filed Dec 2019 → now Sept 2020· 90.9% built
- KANCHAN CHSL6.1 yr overdueC H PATIL AND SONS LLP · Borivali, Mumbai SuburbanP51800011409· filed Mar 2019 → now Sept 2020· 90.9% built
- HATKESH HEIGHTS6.1 yr overdueS. M. INFRASTRUCTURES · Thane, ThaneP51700008077· 90.9% built· 13 complaints
- NYATI EVARA II6.1 yr overdueNYATI BUILDERS PRIVATE LIMITED · Undri, PuneP52100021346· 78.6% built
- PUSHPAJAL APT.6.1 yr overdueM/s Jagtap Pawar & Associates · SATARA, SataraP52700005094· filed Aug 2018 → now Sept 2020· 90.9% built
- KAPIL SANKALP6.1 yr overdueAVADHOOT CONSTRUCTIONS · Near Perugate Police Chauki, PuneP52100006505· filed Mar 2019 → now Sept 2020· 89.1% built
- SUVARNA6.1 yr overdueRavetkar Realties · Kothrud, PuneP52100013022· 37.3% built· 1 complaint
- MORYA RESIDENCY6.1 yr overdueSAIRATNA CONSTRUCTION · Badlapur (M Cl), ThaneP51700012171· 80% built
- PADMAVATI VILLA6.1 yr overduePADMAVATI DEVELOPERS · Ulawe, RaigarhP52000005830· 36.4% built
- UDAYA BHUVAN6.1 yr overdueSHREE KRISHNA HOMES PVT LTD · CHEMBUR, Mumbai SuburbanP51800011308· filed Mar 2019 → now Sept 2020· 40.5% built
- FLORISTA COUNTY6.1 yr overdueI BUILD SUPREME UNION JV · Hadapsar, PuneP52100001416· filed Mar 2018 → now Sept 2020· 90.9% built· 6 complaints
- SHUBHARAMBH6.1 yr overdueI BUILD SUPREME UNION JV · Haveli, PuneP52100001406· filed Mar 2018 → now Sept 2020· 90.9% built· 2 complaints
- Godrej Prana6.1 yr overdueDREAM WORLD LANDMARKS LLP · UNDRI, PuneP52100001372· 89.1% built· 5 complaints
- SOLITARE6.1 yr overdueSHIV PARVATI INFRA PVT LTD · plot no 77, RaigarhP52000014455· 90.9% built
- ZEE CHAHYA6.1 yr overdueZEE COM TRADE PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800007998· 53.4% built
- Orchid Crown6.1 yr overdueLandmarks Orchid Homes Infraventures · Somalwada, NagpurP50500015614· 82.7% built
- NIRMITEE NANDAN6.1 yr overdueNIRMITEE BUILDERS & DEVELOPERS · KUDAL BAZARPETH, SindhudurgP52900016322· 81.8% built
- EKAAKSHARA HEIGHTS6.1 yr overdueSHIV CONSTRUCTION AND DEVELOPERS · Chakan (CT), PuneP52100004891· filed Mar 2018 → now Sept 2020· 56.4% built
- SPACE ELENA6.1 yr overdueSPACE VENTURES · Bavdhan, PuneP52100008019· 45.5% built
- Sukhwani Palms6.1 yr overdueSUKHWANI PROMOTERS & BUILDERS · Wagholi, PuneP52100000672· filed Mar 2019 → now Sept 2020· 90.5% built
- KAKADE AVISHKAR6.1 yr overdueBMK PROPERTIES · BHISE COLONY, VARALE, PuneP52100016186· 81.8% built
- Shivani Heritage6.1 yr overdueGajanan Shyamrao Khabale · Thane, ThaneP51700008458· filed Mar 2019 → now Sept 2020· 57% built
- DESTINATION OSTIA BLDG A6.1 yr overdueD R GAVHANE LANDMARKS LLP · Bhosari, PuneP52100007927· 80.9% built
- 4 Ville6.1 yr overdueTRIMITEE CONSTRUCTIONS · Lonavala (M Cl), PuneP52100014434· 81.8% built
- SHREYAS APARTMENT6.1 yr overdueRUPAL VINOD TRAPASIA · SECTOR 06, RaigarhP52000016460· 90.9% built
- INDRAPRASTH WING C6.1 yr overdueSONAM SPARK INFRA LIMITED · Thane, ThaneP51700002491· 57% built
- Vidyadhan Wing D6.1 yr overdueKale Promoters and Developers · Haveli, PuneP52100001543· 72.7% built
- SHANTI ENCLAVE6.1 yr overdueSADGURU BUILDERS AND DEVELOPERS · Vasai, PalgharP99000009944· filed Mar 2019 → now Sept 2020· 45.1% built
- ROYAL CATALEYA6.1 yr overdueROYAL GROUP OF DEVELOPERS · Haveli, PuneP52100005226· filed Mar 2019 → now Sept 2020· 89.1% built
- Vasudevsmruti6.1 yr overdueLAGOO APTE · Pune City, PuneP52100014160· 81.8% built
- ZEE SARGAM6.1 yr overdueZEE PRAGATEE DEVELOPERS LLP · Andheri, Mumbai SuburbanP51800003624· 48.5% built
- DARSHAN SWAPNALOK PHASE 16.1 yr overdueINTELLIGENT LANDMARKS LLP · Palghar, PalgharP99000013108· 81.8% built
- RAJ TEJ COMMERCIAL COMPLEX6.1 yr overdueSANGRAM ANANTRAO THOPTE · Bhor, PuneP52100010209· filed Mar 2019 → now Sept 2020· 90.9% built
- Raj Aangan6.1 yr overdueMorayaRajAssociates · Haveli, PuneP52100000781· 81.8% built
- SANDHYA BUILDING6.1 yr overdueS D BHALERAO CONSTRUCTIONS PVT LTD - SANDHYA · Thane, ThaneP51700005398· filed Mar 2019 → now Sept 2020· 90.9% built· 2 complaints
- MATRUCHHAYA6.1 yr overdueSUJYOTI FININVEST PVT LTD · Kurla, Mumbai SuburbanP51800005037· filed Mar 2019 → now Sept 2020· 90.9% built
- TILAK INDRAYANI CHS LTD6.1 yr overdueRELIANCE CORPORATION · Kurla, Mumbai SuburbanP51800002913· 90.9% built· 1 complaint
- YASHRAJ GARDEN PHASE 16.1 yr overdueYASHRAJ INFRASTRUCTURE · AURANGABAD, AurangabadP51500015997· 41.8% built
- GRANDEUR6.1 yr overdueM/S. ROYAL BUILDERS & DEVELOPERS · PEN, RaigarhP52000001212· 47.7% built
- SARITA VAIBHAV B5 AND B66.1 yr overdueBELVALKAR HOUSING COMPANY · PARAVTI, PuneP52100000336· filed Mar 2019 → now Sept 2020· 90.9% built
- FLORIDA RIVER WALK PHASE I6.1 yr overdueONE EARTH · MUNDHWA, PuneP52100015819· 73.2% built· 2 complaints
- KAMAL VILLA II6.1 yr overdueRAJ HOUSING CORPORATION · Gokulnagar, PuneP52100001209· filed Mar 2019 → now Sept 2020· 87.3% built
- omkar garden phase III6.1 yr overdueM/S. OMKAR DEVELOPERS · Sidhanathwadi (Rural), SataraP52700008193· 90.9% built
- EMPRESS C WING6.1 yr overdueVENTURE BUILDERS · Titwala, ThaneP51700007775· 84.5% built
- Santoshi Apartment6.1 yr overdueKavita Jayendra Ahirkar · Layout of Vidharbha Housing Construciton Workers Association, NagpurP50500015746· 81.8% built
- RAISONI ROYALLE6.1 yr overdueRAISONI BUILDARS · Haveli, PuneP52100004785· filed Mar 2019 → now Sept 2020· 72.7% built
- Suyog Center Phase II6.1 yr overdueSuyog Development Corporation Limited · Gultekadi, PuneP52100012337· filed Mar 2019 → now Sept 2020· 81.8% built
- SWAPNASAMRAT6.1 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Erandwane, PuneP52100000035· filed Mar 2019 → now Sept 2020· 99.1% built
- SANKALP RESIDENCY6.1 yr overdueKALPATARU DEVELOPERS · Gijavane, KolhapurP53000010218· 24.1% built
- Apollo Retail6.1 yr overdueLODHA DEVELOPERS LIMITED · Thane, ThaneP51700016927· 81.8% built
- Gokul Niwas6.1 yr overdueShree Krishna Developers · New Panvel, RaigarhP52000013742· 90.9% built
- DEEP DEVANSH-36.1 yr overdueSAMBHAV ARENA LLP · PANVEL, RaigarhP52000015670· 81.8% built
- NYATI ENCHANTE I6.1 yr overdueNYATI BUILDERS PRIVATE LIMITED · VADGAONSHERIP52100015299· 79% built
- GREEN PALMS6.1 yr overdueGREEN LEAF REALTY · NERAL, RaigarhP52000004448· filed Mar 2019 → now Sept 2020· 90.9% built
- Omega Business Park6.1 yr overdueArha Buildpro LLP · Thane, ThaneP51700015589· 81.8% built
- ASTER6.1 yr overdueLEVERAGE INFRASTRUCTURES PRIVATE LIMITED · Bokhara, NagpurP50500001906· 86.4% built
- ARIHANT ARSHIYA PHASE III6.1 yr overdueARIHANT SUPERSTRUCTURES LIMITED · Khalapur, RaigarhP52000003422· 81.1% built· 2 complaints
- VENKATESH CLASSIC6.1 yr overdueOMSHRINIWAS DEVELOPERS · Hadapsar, PuneP52100001014· filed Mar 2019 → now Sept 2020· 84.2% built
- MAHI ANAND RESIDENCY6.1 yr overdueBHAGWAN MACHINDRA MAHADIK · BABRAS MALA, PuneP52100016298· 72.7% built
- Shiv Shrushti Apartment6.1 yr overdueHarsh Constrution · NANDIMALNAKA, RaigarhP52000011617· filed Mar 2019 → now Sept 2020· 90.9% built
- Dreams Rakshak G H wings6.1 yr overdueDreams Landmark · Wagholi, PuneP52100000401· filed Mar 2018 → now Sept 2020· 83.2% built· 1 complaint
- SHREE SADGURU RESIDENCY6.1 yr overdueSAIDATTA BUILDCON SPECIALITIES PRIVATE LIMITED · SHELU, RaigarhP52000016133· 5.3% built
- RSM NIYATI6.1 yr overdueRSM HOMES LLP · Uran, RaigarhP52000002549· 90.9% built
- PREET TOWER6.1 yr overduePREET CONSTRUCTION · SHENDRA, AurangabadP51500002176· 90.9% built
- ROHA GREEN6.1 yr overdueABS GROUP · Roha Ashtami (M Cl), RaigarhP52000002271· 90.9% built
- Shree Durga Apartment6.1 yr overdueMittal Developers · Nagpur (M Corp.), NagpurP50500001801· 72.7% built· 1 complaint
- ZEE USHA6.1 yr overdueZEE COM TRADE PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800005143· 85% built
- VAASTU Prathamesh6.1 yr overdueVAASTU Builders & Developers · Panvel, RaigarhP52000006919· 90.9% built
- VANALIKA6.1 yr overdueM/S. AVIOR MAJESTIQUE PROPERTIES · Mulshi, PuneP52100001569· filed Mar 2019 → now Sept 2020· 90.1% built
- OWAIS TOWER6.1 yr overdueKUTUBUDDIN JAMAL SHAIKH · VAISHYAWADA, SindhudurgP52900014691· 98.6% built
- SAI AURA6.1 yr overdueSHREE SAI CREATIONS · Kiwale, PuneP52100003031· 78.8% built
- VARDHAMAN HEIGHT6.1 yr overdueCHRISHH OMKARA CONSTRUCTIONS · Varale, PuneP52100005792· 90.9% built
- SUYOJIT ONE WORLD PHASE-I, RESIDENTIAL SECTOR6.1 yr overdueSUN INFRASTRUCTURES PVT. LTD · Near Birla Hospital, Nashik Road, Nashik, NashikP51600002632· filed Mar 2019 → now Sept 2020· 90.5% built
- EV CITY CENTRE6.1 yr overdueEV HOMES CONSTRUCTIONS PVT. LTD. · Panvel, RaigarhP52000009119· 97.7% built
- Preksha6.1 yr overdueSugee Six Developers LLP · Ward FNorth, Mumbai CityP51900000978· 90.9% built
- Nirmiti Royal6.1 yr overdueNirmiti Homes · Baramati (M Cl), PuneP52100006518· filed Mar 2019 → now Sept 2020· 82.5% built
- Godrej Infinity6.1 yr overdueOXFORD REALTY LLP · MUNDWA, PuneP52100003129· 89.1% built· 31 complaints
- NIRMAL HEIGHTS6.1 yr overdueBANSAL BUILDCON · DIGHIP52100006328· filed Mar 2019 → now Sept 2020· 90.9% built
- K L REGALIA6.1 yr overdueK L HOUSING LLP · Andheri, Mumbai SuburbanP51800011323· filed Mar 2018 → now Sept 2020· 67.5% built
- MONT KIARA6.1 yr overdueTANISHQ BUILDERS · Mumbai City, Mumbai CityP51900002127· filed Mar 2019 → now Sept 2020· 41.8% built· 1 complaint
- HEUU INDUSTRIAL SPACES6.1 yr overdueSONIGARA JEWELLERS PRIVATE LIMITED · AKURDI MIDC, PuneP52100007159· 41.8% built
- IT-PARK6.1 yr overdueVIDARBHA INFOTECH PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500007181· 48.3% built
- EARTH HEIGHTS I6.1 yr overdueEARTH INFRA · 13/14,NEW AMAR NAGAR, NagpurP50500016144· 90.9% built· 1 complaint
- SOLITAIRE6.1 yr overdueRADIANT BUILDERS · Ulawe, RaigarhP52000001816· 90.9% built
- SHREE MAHALAKSHMI PARK BUILDING NO.26.1 yr overdueJAYVARDHAN INFRAPROJECTS PVT. LTD. · Dhamote, Neral, RaigarhP52000000460· 81.8% built
- SANKALP HEIGHT6.1 yr overdueSANKALP INFRATECH · Amravati (M Corp.), AmravatiP50300003775· filed Mar 2019 → now Sept 2020· 81.8% built
- MAULI SHANKAR KRUPA6.1 yr overdueBadri Construction · Baramati (M Cl), PuneP52100013080· 34.5% built
- GULAB VILLA6.1 yr overdueSAGAR PROPERTIES · BANSILAL NAGAR, AurangabadP51500024411· 97.7% built
- MADHUBAN F1 F26.1 yr overdueAbhilasha Venture · Titwala, ThaneP51700002614· filed Mar 2019 → now Sept 2020· 90.9% built
- Sky Heights6.1 yr overdueSadguru Developers · Vasai, PalgharP99000003527· filed Mar 2018 → now Sept 2020· 90.9% built
- CHANDRADARSHAN6.1 yr overdueCHANDRADARSHAN DEVELOPERS · Pen (M Cl), RaigarhP52000002075· 87.7% built
- Shivraj Complex6.1 yr overduePANDHARINATH MADHUKAR JOSHI · Government Colony, Near Sphurti Chowk, SangliP53100017706· 34.1% built
- GALAXY MANSION VII6.1 yr overdueGALAXY ASSOCIATES · Beltarodi, NagpurP50500014357· 90.9% built
- Saarrthi Shivalik6.1 yr overdueSiddharth Real Ventures Limited Liability Partnership · Kothrud, PuneP52100014200· 90.9% built
- DEVIS PLATINUM6.1 yr overdueDEVI INFRASPACE PRIVATE LIMITED · SAI NAGAR SATURNA, AmravatiP50300015308· 0% built· 1 complaint
- Vrundavan6.1 yr overdueYogesh Kishorbhai Dattani HUF · Besides Meet Abhas, NashikP51600021653· 90.9% built
- Nehru Nagar Ekta Co Op Hsg Soc Ltd6.1 yr overdueRachana Homes · Kurla, Mumbai SuburbanP51800011743· filed Sept 2018 → now Sept 2020· 60.3% built
- SKYLINE JEWEL6.1 yr overdueUNIQUE SUPER INFRA PRIVATE LIMITED · Taloje Panchnad, RaigarhP52000015945· 90.9% built
- Redevelopment of Juhu Shantivan CHSL6.1 yr overdueShree Mahavir Properties · Mumbai, Mumbai SuburbanP51800001772· filed Mar 2019 → now Sept 2020· 90.9% built
- STAR RIGHT - 46.1 yr overdueSTAR RIGHT ESTATES INDIA PRIVATE LIMITED · SECTOR - 01, RaigarhP52000013338· 90.9% built
- LOTUS LAXMI 36.1 yr overdueSURYA PROPERTIES · RAVET, PuneP52100015530· 85.5% built
- DEV RESIDENCY6.1 yr overdueCHUPON BUILDCON · PATHARDI, NashikP51600016087· 81.8% built
- SHILP SAMRUDDHI6.1 yr overdueHEMANT DATTATRAYA GAIKWAD · Shivram Nagar, NashikP51600010415· 81.8% built
- AVENUE 6416.1 yr overdueDIMPLE CREATIONS · BORIVALI, Mumbai SuburbanP51800014768· 90.9% built
- SARVODAY SNEH6.1 yr overdueEKTA LAND DEVELOPERS · THAKURLI EAST, ThaneP51700015356· 90.9% built
- ANMOL HILLSIDE6.1 yr overdueAnmol Builders & developers · Nachane (CT), RatnagiriP52800008337· 90.9% built
- AARKAY GOLD6.1 yr overdueAAR KAY ENTERPRISES · Vasai, PalgharP99000005943· 65.5% built
- EXPRESS ENCLAVE6.1 yr overdueMD GLOBUS REALTY PVT LTD · Andheri, Mumbai SuburbanP51800009088· 90.9% built
- DEEP GARDEN6.1 yr overdueATHARVA DEVELOPER · Vasai, PalgharP99000010593· filed May 2018 → now Sept 2020· 81.8% built
- GURU KRUPA6.1 yr overdueKushal Dattaram Mahadik · Kalambaste, RatnagiriP52800016986· 66.8% built
- KIRIK ORIOLE PHASE 1A6.1 yr overdueKIRIK ENTERPRISES · Shankar Kalat Nagar, PuneP52100015859· 72.7% built
- Akash Towers C-D6.1 yr overdueLunkad Builders LLP · Pimple Nilakh, PuneP52100000402· 81.8% built
- EXOTICA-II6.1 yr overdueDEEPAK SHANKARRAO PATIL · AGASHIVNAGAR, SataraP52700014899· 50.9% built
- Ajmera Zeon6.1 yr overdueAjmera Realty & Infra India Ltd. · Kurla, Mumbai SuburbanP51800000779· 91.6% built· 1 complaint
- PRITHVI SRISHTI6.1 yr overduePrithvi Anand Housing and Land Developers · Palghar, PalgharP99000014102· 90% built
- SAGARIKA6.1 yr overdueESS GEE TRADEFIN PVT LTD · Uran, RaigarhP52000001052· 90.9% built
- Atlantis6.1 yr overdueManoj Yeole Ramdas Yeole · Pune (M Corp.), PuneP52100014390· 1.4% built· 1 complaint
- Azure - A,C,D,E and F6.1 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Tathwade, PuneP52100000241· 98.2% built
- PERFECT 10 Phase II6.1 yr overdueShagun Manav Spaces LLP · Pune (M Corp.), PuneP52100001101· 90.9% built
- Swaraj Capital - Phase I6.1 yr overdueSim Realty · Borhadewadi,Moshi, PuneP52100003900· filed Mar 2019 → now Sept 2020· 71.8% built
- VARADVINAYAK6.1 yr overduePANDHARI CONSTRUCTION · Haveli, PuneP52100010384· 23.6% built
- 126 FLORENCIO6.1 yr overdueARHAM ENGINEERS · Kurla, Mumbai SuburbanP51800005828· filed Mar 2019 → now Sept 2020· 72.1% built· 8 complaints
- VASANT VILLA6.1 yr overdueR&P DEVELOPERS · FDCM, ChandrapurP50900015809· 29.1% built
- Sindhusmruti6.1 yr overdueYogiraj Powertech Pvt Ltd · Thane, ThaneP51700006699· filed Nov 2018 → now Sept 2020· 47.7% built· 1 complaint
- AMRUT LEGACY6.1 yr overdueNITIN AMRUTLAL SHAH · Andheri, Mumbai SuburbanP51800009017· 54.1% built
- DEEP DEVANSH - 26.1 yr overdueSAMBHAV BUILDCON · PUSHPAK NODE, RaigarhP52000016024· 90.9% built
- CHINTAMANI HABITAT DAFFODILS TYPE G - E6.1 yr overdueJASHNANI CONSTRUCTION PRIVATE LIMITED · Shahapur (CT), ThaneP51700001853· 63% built
- SHEETAL BUSINESS CENTRE6.1 yr overdueSWASTIK REALTORS · Mumbai City, Mumbai CityP51900002746· filed Mar 2019 → now Sept 2020· 29.5% built
- EDEN HEIGHTS6.1 yr overduePARTRACT ESTATE & INVESTMENT PVT. LTD. · Gangapur Gaon, NashikP51600010798· filed Mar 2019 → now Sept 2020· 90.9% built
- SHUBHANGI6.1 yr overdueOMKAR BUILDERS · Kurla, Mumbai SuburbanP51800004391· 90.9% built
- Hiraco Eminence Phase 16.1 yr overdueKASHIMIRA CERAMIC PRODUCTS LLP · Thane, ThaneP51800008105· 88.6% built· 99 complaints
- GAGAN UNNATII PHASE 26.1 yr overdueGagan Unnati Ventures · Kondhwa, PuneP52100001818· filed Mar 2019 → now Sept 2020· 96.9% built
- SHRIRAM REALITY6.1 yr overdueSHRIRAM REALITY · Chakan (CT), PuneP52100006883· 81.8% built
- Krishna Arcade6.1 yr overdueKrishna Arcade Developers · Bansilal Nagar, JalnaP51400016639· 63.6% built
- SUBHADRA RESIDENCY6.1 yr overdueHARISH SUDHAKAR SHENDE · WARDHA, WardhaP50400015669· 90.9% built
- PLATINUM GHARONDA6.1 yr overdueJAY GURUDEV CONSTRUCTIONS · Bhuwaneshwar (CT), RaigarhP52000004277· 41.8% built
- VENKATESH JOYNEST PHASE - 56.1 yr overdueSHREE VENKATESH GROUP · Haveli, PuneP52100018125· 76.5% built
- Bloomdale Building 086.1 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500008536· filed Mar 2019 → now Sept 2020· 90.9% built· 4 complaints
- FEEL BLISS PHASE-I6.1 yr overdueMaple Ravima Realtors · Bavdhan, PuneP52100003782· filed Mar 2019 → now Sept 2020· 90.9% built
- AMIKRUPA6.1 yr overdueAAROHI DEVELOPMENT CORPORATION · Chikanghar, ThaneP51700008884· 90.9% built
- JAAI PHASE II6.1 yr overdueVERSATILEREALTORSPRIVATELIMITED · Vasai, PalgharP99000016273· 90.9% built
- MADHURANGAN APARTMENT6.1 yr overdueSHRI YOGESH PRABHAKAR DHOLE · MALAD TALUKA BARAMATI, PuneP52100016018· 37.5% built
- Shivneri CHS Ltd6.1 yr overdueShree Chamunda Properties · Andheri, Mumbai SuburbanP51800012532· filed Mar 2019 → now Sept 2020· 56.7% built
- GOURI SHANKAR6.1 yr overdueKULKARNI JANKAR BUILDERS · NEAR SANGLI MIRAJ ROAD, SangliP53100015957· 33.6% built
- AKAR ONE6.1 yr overdueAKAR CONSTRUCTION · OPPOSITE TV TOWER, RatnagiriP52800001746· 90.9% built
- AKAR VISHWA PHASE 16.1 yr overdueAKAR INFRASTRUCTURE · BEHIND CHIRAYU HOSPITAL, RatnagiriP52800011556· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.