RERA projects past their possession deadline
11,767 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 25 of 59
- RAJ TEJ COMMERCIAL COMPLEX5.8 yr overdueSANGRAM ANANTRAO THOPTE · Bhor, PuneP52100010209· filed Mar 2019 → now Sept 2020· 90.9% built
- MANGESHI DAZZLE - III5.8 yr overdueKALYAN DEVELOPMENT CORPORATION · Kalyan, ThaneP51700005137· filed Mar 2019 → now Sept 2020· 84.2% built
- KAMAL VILLA II5.8 yr overdueRAJ HOUSING CORPORATION · Gokulnagar, PuneP52100001209· filed Mar 2019 → now Sept 2020· 87.3% built
- SKYLINE JEWEL5.8 yr overdueUNIQUE SUPER INFRA PRIVATE LIMITED · Taloje Panchnad, RaigarhP52000015945· 90.9% built
- EXOTICA-II5.8 yr overdueDEEPAK SHANKARRAO PATIL · AGASHIVNAGAR, SataraP52700014899· 50.9% built
- United Courtyard Phase I5.8 yr overdueUnited Builders · BEHIND INOX, NashikP51600001925· filed Mar 2019 → now Sept 2020· 90.9% built
- EV CITY CENTRE5.8 yr overdueEV HOMES CONSTRUCTIONS PVT. LTD. · Panvel, RaigarhP52000009119· 97.7% built
- K L REGALIA5.8 yr overdueK L HOUSING LLP · Andheri, Mumbai SuburbanP51800011323· filed Mar 2018 → now Sept 2020· 67.5% built
- PLATINUM GHARONDA5.8 yr overdueJAY GURUDEV CONSTRUCTIONS · Bhuwaneshwar (CT), RaigarhP52000004277· 41.8% built
- Antheia B35.8 yr overdueMahindra Lifespace Developers limited · Haveli, PuneP52100016677· 90.9% built· 1 complaint
- SHEETAL BUSINESS CENTRE5.8 yr overdueSWASTIK REALTORS · Mumbai City, Mumbai CityP51900002746· filed Mar 2019 → now Sept 2020· 29.5% built
- ARIHANT ARSHIYA PHASE III5.8 yr overdueARIHANT SUPERSTRUCTURES LIMITED · Khalapur, RaigarhP52000003422· 81.1% built· 2 complaints
- FEEL BLISS PHASE-I5.8 yr overdueMaple Ravima Realtors · Bavdhan, PuneP52100003782· filed Mar 2019 → now Sept 2020· 90.9% built
- KACHWALA PALACE5.8 yr overdueCREST VENTURES LIMITED · Andheri, Mumbai SuburbanP51800005902· 81.8% built
- MANGAL VIHAR WING B5.8 yr overdueMANGAL CONSTRUCTION · Solapur (M Corp.), SolapurP52600002066· 34.5% built
- NYATI EVARA II5.8 yr overdueNYATI BUILDERS PRIVATE LIMITED · Undri, PuneP52100021346· 78.6% built
- PRITHVI SRISHTI5.8 yr overduePrithvi Anand Housing and Land Developers · Palghar, PalgharP99000014102· 90% built
- SUBHADRA RESIDENCY5.8 yr overdueHARISH SUDHAKAR SHENDE · WARDHA, WardhaP50400015669· 90.9% built
- GAGAN UNNATII PHASE 25.8 yr overdueGagan Unnati Ventures · Kondhwa, PuneP52100001818· filed Mar 2019 → now Sept 2020· 96.9% built
- ROHA GREEN5.8 yr overdueABS GROUP · Roha Ashtami (M Cl), RaigarhP52000002271· 90.9% built
- SPACE ELENA5.8 yr overdueSPACE VENTURES · Bavdhan, PuneP52100008019· 45.5% built
- IT-PARK5.8 yr overdueVIDARBHA INFOTECH PRIVATE LIMITED · Nagpur (M Corp.), NagpurP50500007181· 48.3% built
- Raj Aangan5.8 yr overdueMorayaRajAssociates · Haveli, PuneP52100000781· 81.8% built
- Azure - A,C,D,E and F5.8 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Tathwade, PuneP52100000241· 98.2% built
- NYATI ENCHANTE I5.8 yr overdueNYATI BUILDERS PRIVATE LIMITED · VADGAONSHERIP52100015299· 79% built
- AASRA5.8 yr overdueIMPRESSA LAXMI · NAGPUR, NagpurP50500013844· 90.9% built· 1 complaint
- VASANT VILLA5.8 yr overdueR&P DEVELOPERS · FDCM, ChandrapurP50900015809· 29.1% built
- Preksha5.8 yr overdueSugee Six Developers LLP · Ward FNorth, Mumbai CityP51900000978· 90.9% built
- SHREE MAHALAKSHMI PARK BUILDING NO.25.8 yr overdueJAYVARDHAN INFRAPROJECTS PVT. LTD. · Dhamote, Neral, RaigarhP52000000460· 81.8% built
- KANCHAN CHSL5.8 yr overdueC H PATIL AND SONS LLP · Borivali, Mumbai SuburbanP51800011409· filed Mar 2019 → now Sept 2020· 90.9% built
- NIRMITEE NANDAN5.8 yr overdueNIRMITEE BUILDERS & DEVELOPERS · KUDAL BAZARPETH, SindhudurgP52900016322· 81.8% built
- SWAPNASAMRAT5.8 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Erandwane, PuneP52100000035· filed Mar 2019 → now Sept 2020· 99.1% built
- UDAYA BHUVAN5.8 yr overdueSHREE KRISHNA HOMES PVT LTD · CHEMBUR, Mumbai SuburbanP51800011308· filed Mar 2019 → now Sept 2020· 40.5% built
- KANAKIA MIAMI5.8 yr overdueKANAKIA SPACES REALTY PRIVATE LIMITED · Ward GNorth, Mumbai CityP51900000206· 98.9% built· 4 complaints
- Atlantis5.8 yr overdueManoj Yeole Ramdas Yeole · Pune (M Corp.), PuneP52100002148· 49.5% built
- Omega Business Park5.8 yr overdueArha Buildpro LLP · Thane, ThaneP51700015589· 81.8% built
- Haware Pinnacle5.8 yr overdueSuresh Kashinath Haware · Bhiwandi, ThaneP51700000464· 78.2% built
- SARVODAY SNEH5.8 yr overdueEKTA LAND DEVELOPERS · THAKURLI EAST, ThaneP51700015356· 90.9% built
- NIRMAL HEIGHTS5.8 yr overdueBANSAL BUILDCON · DIGHIP52100006328· filed Mar 2019 → now Sept 2020· 90.9% built
- Bloomdale Building 095.8 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500006483· filed Mar 2019 → now Sept 2020· 90.9% built· 2 complaints
- CHANDRADARSHAN5.8 yr overdueCHANDRADARSHAN DEVELOPERS · Pen (M Cl), RaigarhP52000002075· 87.7% built
- BUSINESS SQUARE5.8 yr overdueVASTUKRUPA CONSTRUCTION (INDIA) PVT LTD · Nashik, NashikP51600000211· filed Mar 2019 → now Sept 2020· 90.9% built
- SUYOJIT ONE WORLD PHASE-I, RESIDENTIAL SECTOR5.8 yr overdueSUN INFRASTRUCTURES PVT. LTD · Near Birla Hospital, Nashik Road, Nashik, NashikP51600002632· filed Mar 2019 → now Sept 2020· 90.5% built
- Shivani Heritage5.8 yr overdueGajanan Shyamrao Khabale · Thane, ThaneP51700008458· filed Mar 2019 → now Sept 2020· 57% built
- Krishna Arcade5.8 yr overdueKrishna Arcade Developers · Bansilal Nagar, JalnaP51400016639· 63.6% built
- TILAK INDRAYANI CHS LTD5.8 yr overdueRELIANCE CORPORATION · Kurla, Mumbai SuburbanP51800002913· 90.9% built· 1 complaint
- ANAND5.8 yr overdueNAREN ENTERPRISES · Karanjade, RaigarhP52000006710· 70.9% built
- GULAB VILLA5.8 yr overdueSAGAR PROPERTIES · BANSILAL NAGAR, AurangabadP51500024411· 97.7% built
- DEEP DEVANSH-35.8 yr overdueSAMBHAV ARENA LLP · PANVEL, RaigarhP52000015670· 81.8% built
- LOTUS LAXMI 35.8 yr overdueSURYA PROPERTIES · RAVET, PuneP52100015530· 85.5% built
- KUM KUM BHAGYA5.8 yr overdueKUM KUM ENTERPRISES · Bopele, RaigarhP52000009221· filed Mar 2019 → now Sept 2020· 81.8% built
- GREEN PALMS5.8 yr overdueGREEN LEAF REALTY · NERAL, RaigarhP52000004448· filed Mar 2019 → now Sept 2020· 90.9% built
- Shivneri CHS Ltd5.8 yr overdueShree Chamunda Properties · Andheri, Mumbai SuburbanP51800012532· filed Mar 2019 → now Sept 2020· 56.7% built
- RAISONI ROYALLE5.8 yr overdueRAISONI BUILDARS · Haveli, PuneP52100004785· filed Mar 2019 → now Sept 2020· 72.7% built
- GIRNAR5.8 yr overdueABHAY CHANDRAMOHAN SAWANT · Daund (M Cl), PuneP52100007331· filed Mar 2019 → now Sept 2020· 81.8% built
- ANMOL HILLSIDE5.8 yr overdueAnmol Builders & developers · Nachane (CT), RatnagiriP52800008337· 90.9% built
- VARDHAMAN HEIGHT5.8 yr overdueCHRISHH OMKARA CONSTRUCTIONS · Varale, PuneP52100005792· 90.9% built
- SHILP SAMRUDDHI5.8 yr overdueHEMANT DATTATRAYA GAIKWAD · Shivram Nagar, NashikP51600010415· 81.8% built
- DEEP GARDEN5.8 yr overdueATHARVA DEVELOPER · Vasai, PalgharP99000010593· filed May 2018 → now Sept 2020· 81.8% built
- Shree Durga Apartment5.8 yr overdueMittal Developers · Nagpur (M Corp.), NagpurP50500001801· 72.7% built· 1 complaint
- EDEN HEIGHTS5.8 yr overduePARTRACT ESTATE & INVESTMENT PVT. LTD. · Gangapur Gaon, NashikP51600010798· filed Mar 2019 → now Sept 2020· 90.9% built
- SWASTIK DREAMS5.8 yr overdueDHANANJAY DAMODHAR DAREKAR · Pimpri Chinchawad (M Corp.), PuneP52100005665· 45.5% built
- TIRUPATI ENCLAVE5.8 yr overdueEKALAWYA WASEKAR & OTHERONE · Nagpur (M Corp.), NagpurP50500007836· 81.8% built
- DEV RESIDENCY5.8 yr overdueCHUPON BUILDCON · PATHARDI, NashikP51600016087· 81.8% built
- MEDHA CHSL5.8 yr overdueC H PATIL AND SONS LLP · Borivali, Mumbai SuburbanP51800006437· filed Mar 2019 → now Sept 2020· 90.9% built
- nehru nagar ekta co op hsg soc ltd5.8 yr overdueRachana Homes · Kurla, Mumbai SuburbanP51800011743· filed Sept 2018 → now Sept 2020· 60.3% built
- Orchid Crown5.8 yr overdueLandmarks Orchid Homes Infraventures · Somalwada, NagpurP50500015614· 82.7% built
- SHRI INDUSTRIAL ESTATE5.8 yr overdueSHRI ENTERPRISES · Vasai, PalgharP99000008391· 65.5% built
- CASA LOTUS5.8 yr overdueR. C. CON ASSOCIATES JV · Wanadongri, NagpurP50500002363· filed Dec 2019 → now Sept 2020· 90.9% built
- EKAAKSHARA HEIGHTS5.8 yr overdueSHIV CONSTRUCTION AND DEVELOPERS · Chakan (CT), PuneP52100004891· filed Mar 2018 → now Sept 2020· 56.4% built
- Emerald Tower5.8 yr overdueS M Enterprises · Vasai, PalgharP99000004995· filed Mar 2018 → now Sept 2020· 90% built
- FLORISTA COUNTY5.8 yr overdueI BUILD SUPREME UNION JV · Hadapsar, PuneP52100001416· filed Mar 2018 → now Sept 2020· 90.9% built· 6 complaints
- PERFECT 10 Phase II5.8 yr overdueShagun Manav Spaces LLP · Pune (M Corp.), PuneP52100001101· 90.9% built
- Hiraco Eminence Phase 15.8 yr overdueKASHIMIRA CERAMIC PRODUCTS LLP · Thane, ThaneP51800008105· 88.6% built· 99 complaints
- 126 FLORENCIO5.8 yr overdueARHAM ENGINEERS · Kurla, Mumbai SuburbanP51800005828· filed Mar 2019 → now Sept 2020· 72.1% built· 7 complaints
- GURU KRUPA5.8 yr overdueKushal Dattaram Mahadik · Kalambaste, RatnagiriP52800016986· 66.8% built
- DWARIKA VALLEY PHASE I5.8 yr overdueDWARIKA REAL INFRA LLP · Matoshree Nagar, RaigarhP52000003025· filed Mar 2019 → now Sept 2020· 78.8% built· 5 complaints
- OWAIS TOWER5.8 yr overdueKUTUBUDDIN JAMAL SHAIKH · VAISHYAWADA, SindhudurgP52900014691· 98.6% built
- SANDHYA BUILDING5.8 yr overdueS D BHALERAO CONSTRUCTIONS PVT LTD - SANDHYA · Thane, ThaneP51700005398· filed Mar 2019 → now Sept 2020· 90.9% built· 2 complaints
- Dreams Lynnea A B wings5.8 yr overdueDreams Construction ( Pune) Pvt. Ltd. · WAGHOLI, PuneP52100000237· filed Mar 2019 → now Sept 2020· 68.8% built· 12 complaints
- CD Plot No 69 Lumiere5.8 yr overdueSD SVP Nagar Redevelopment Private Limited · Andheri, Mumbai SuburbanP51800005440· filed Sept 2019 → now Sept 2020· 99.7% built· 43 complaints
- Sukhwani Palms5.8 yr overdueSUKHWANI PROMOTERS & BUILDERS · Wagholi, PuneP52100000672· filed Mar 2019 → now Sept 2020· 90.5% built
- Godrej Infinity5.8 yr overdueOXFORD REALTY LLP · MUNDWA, PuneP52100003129· 89.1% built· 31 complaints
- Gokul Niwas5.8 yr overdueShree Krishna Developers · New Panvel, RaigarhP52000013742· 90.9% built
- Yogi Milan Phase 35.8 yr overdueShiv Builders · NR. BALAJI TEMPLE, Dadra & Nagar HaveliP49600000022· 90.9% built
- SHREE ELIGANCE5.8 yr overdueABHILASHADEVELOPER · CHIKHALI, PuneP52100007582· filed Mar 2019 → now Sept 2020· 62.3% built
- AMRUT LEGACY5.8 yr overdueNITIN AMRUTLAL SHAH · Andheri, Mumbai SuburbanP51800009017· 54.1% built
- SAI AURA5.8 yr overdueSHREE SAI CREATIONS · Kiwale, PuneP52100003031· 78.8% built
- VATSALYA VIHAR5.8 yr overdueATUL HANUMANT MORE · SHANIWAR PETH, SataraP52700015221· 27.3% built
- GRANDEUR5.8 yr overdueM/S. ROYAL BUILDERS & DEVELOPERS · PEN, RaigarhP52000001212· 47.7% built
- MADHUBAN F1 F25.8 yr overdueAbhilasha Venture · Titwala, ThaneP51700002614· filed Mar 2019 → now Sept 2020· 90.9% built
- ROYAL CATALEYA5.8 yr overdueROYAL GROUP OF DEVELOPERS · Haveli, PuneP52100005226· filed Mar 2019 → now Sept 2020· 89.1% built
- omkar garden phase III5.8 yr overdueM/S. OMKAR DEVELOPERS · Sidhanathwadi (Rural), SataraP52700008193· 90.9% built
- Memories5.8 yr overdueM/s NAMO DEVELOPERS · MOHAMMADWADI, PuneP52100001168· filed Mar 2019 → now Sept 2020· 51.8% built· 1 complaint
- Akash Towers C-D5.8 yr overdueLunkad Builders LLP · Pimple Nilakh, PuneP52100000402· 81.8% built
- SHUBHANGI5.8 yr overdueOMKAR BUILDERS · Kurla, Mumbai SuburbanP51800004391· 90.9% built
- VANALIKA5.8 yr overdueM/S. AVIOR MAJESTIQUE PROPERTIES · Mulshi, PuneP52100001569· filed Mar 2019 → now Sept 2020· 90.1% built
- Dhruvika Enclave5.8 yr overdueManoyadnya Developers · Joveli Gaon, ThaneP51700015355· 81.8% built
- DEVIS PLATINUM5.8 yr overdueDEVI INFRASPACE PRIVATE LIMITED · SAI NAGAR SATURNA, AmravatiP50300015308· 0% built· 1 complaint
- SHREYAS APARTMENT5.8 yr overdueRUPAL VINOD TRAPASIA · SECTOR 06, RaigarhP52000016460· 90.9% built
- Saarrthi Shivalik5.8 yr overdueSiddharth Real Ventures Limited Liability Partnership · Kothrud, PuneP52100014200· 90.9% built
- ZEE SARGAM5.8 yr overdueZEE PRAGATEE DEVELOPERS LLP · Andheri, Mumbai SuburbanP51800003624· 48.5% built
- Lotus Niwas / Satya Niwas5.8 yr overdueK L Ventures and Enterprises · Borivali, Mumbai SuburbanP51800002047· filed Mar 2019 → now Sept 2020· 81.8% built
- HARI OM NAGAR5.8 yr overdueRRB BUILDER · Devlai, AurangabadP51500011402· 69.4% built
- Dreams Rakshak G H wings5.8 yr overdueDreams Landmark · Wagholi, PuneP52100000401· filed Mar 2018 → now Sept 2020· 83.2% built· 1 complaint
- EMPRESS C WING5.8 yr overdueVENTURE BUILDERS · Titwala, ThaneP51700007775· 84.5% built
- RSM NIYATI5.8 yr overdueRSM HOMES LLP · Uran, RaigarhP52000002549· 90.9% built
- SOLITARE5.8 yr overdueSHIV PARVATI INFRA PVT LTD · plot no 77, RaigarhP52000014455· 90.9% built
- INDRAPRASTH WING C5.8 yr overdueSONAM SPARK INFRA LIMITED · Thane, ThaneP51700002491· 57% built
- GALAXY MANSION VII5.8 yr overdueGALAXY ASSOCIATES · Beltarodi, NagpurP50500014357· 90.9% built
- VENKATESH CLASSIC5.8 yr overdueOMSHRINIWAS DEVELOPERS · Hadapsar, PuneP52100001014· filed Mar 2019 → now Sept 2020· 84.2% built
- KAKADE AVISHKAR5.8 yr overdueBMK PROPERTIES · BHISE COLONY, VARALE, PuneP52100016186· 81.8% built
- Santoshi Apartment5.8 yr overdueKavita Jayendra Ahirkar · Layout of Vidharbha Housing Construciton Workers Association, NagpurP50500015746· 81.8% built
- HATKESH HEIGHTS5.8 yr overdueS. M. INFRASTRUCTURES · Thane, ThaneP51700008077· 90.9% built· 12 complaints
- SHREE CHINMAY GAURANG GRIHSANKUL5.8 yr overdueSHREE CHINMAY GAURANG INFRASTRUCTURE · PANVEL, RaigarhP52000004925· 90.9% built· 1 complaint
- 9 RADHA5.8 yr overdueISHAAN DEVELOPERS · Ward FNorth, Mumbai CityP51900005726· filed Mar 2019 → now Sept 2020· 60.5% built· 1 complaint
- Nirmiti Royal5.8 yr overdueNirmiti Homes · Baramati (M Cl), PuneP52100006518· filed Mar 2019 → now Sept 2020· 82.5% built
- HARI KUNJ III5.8 yr overdueKUKREJA CONSTRUCTION CO · Kurla, Mumbai SuburbanP51800007495· 59.1% built
- SAGARIKA5.8 yr overdueESS GEE TRADEFIN PVT LTD · Uran, RaigarhP52000001052· 90.9% built
- KIRIK ORIOLE PHASE 1A5.8 yr overdueKIRIK ENTERPRISES · Shankar Kalat Nagar, PuneP52100015859· 72.7% built
- VENKATESH JOYNEST PHASE - 55.8 yr overdueSHREE VENKATESH GROUP · Haveli, PuneP52100018125· 76.5% built
- PREET TOWER5.8 yr overduePREET CONSTRUCTION · SHENDRA, AurangabadP51500002176· 90.9% built
- ZEE USHA5.8 yr overdueZEE COM TRADE PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800005143· 85% built
- Sindhusmruti5.8 yr overdueYogiraj Powertech Pvt Ltd · Thane, ThaneP51700006699· filed Nov 2018 → now Sept 2020· 47.7% built· 1 complaint
- The Mist -Phase I5.8 yr overdueGeeCee Ventures Limited · Karjat, RaigarhP52000007101· 87.2% built· 4 complaints
- SARITA VAIBHAV B5 AND B65.8 yr overdueBELVALKAR HOUSING COMPANY · PARAVTI, PuneP52100000336· filed Mar 2019 → now Sept 2020· 90.9% built
- EXPRESS ENCLAVE5.8 yr overdueMD GLOBUS REALTY PVT LTD · Andheri, Mumbai SuburbanP51800009088· 90.9% built
- DEEP DESTINY5.8 yr overdueSAMBHAV REALTY · KARANJADE, RaigarhP52000002407· 89.5% built
- Swaraj Capital - Phase I5.8 yr overdueSim Realty · Borhadewadi,Moshi, PuneP52100003900· filed Mar 2019 → now Sept 2020· 71.8% built
- ASTER5.8 yr overdueLEVERAGE INFRASTRUCTURES PRIVATE LIMITED · Bokhara, NagpurP50500001906· 86.4% built
- KAPIL SANKALP5.8 yr overdueAVADHOOT CONSTRUCTIONS · Near Perugate Police Chauki, PuneP52100006505· filed Mar 2019 → now Sept 2020· 89.1% built
- RAMDOOT5.8 yr overdueHARESHKUMAR RASIKLAL SHAH · KARANAJADE PANVEL, RaigarhP52000016188· 8.2% built
- Atlantis5.8 yr overdueManoj Yeole Ramdas Yeole · Pune (M Corp.), PuneP52100014390· 1.4% built· 1 complaint
- YASHRAJ GARDEN PHASE 15.8 yr overdueYASHRAJ INFRASTRUCTURE · AURANGABAD, AurangabadP51500015997· 41.8% built
- Redevelopment of Juhu Shantivan CHSL5.8 yr overdueShree Mahavir Properties · Mumbai, Mumbai SuburbanP51800001772· filed Mar 2019 → now Sept 2020· 90.9% built
- HEUU INDUSTRIAL SPACES5.8 yr overdueSONIGARA JEWELLERS PRIVATE LIMITED · AKURDI MIDC, PuneP52100007159· 41.8% built
- SANKALP HEIGHT5.8 yr overdueSANKALP INFRATECH · Amravati (M Corp.), AmravatiP50300003775· filed Mar 2019 → now Sept 2020· 81.8% built
- BLUE FORTUNA5.8 yr overdueATUL PROJECTS INDIA PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800010900· 90.9% built· 1 complaint
- AMIKRUPA5.8 yr overdueAAROHI DEVELOPMENT CORPORATION · Chikanghar, ThaneP51700008884· 90.9% built
- MATRUCHHAYA5.8 yr overdueSUJYOTI FININVEST PVT LTD · Kurla, Mumbai SuburbanP51800005037· filed Mar 2019 → now Sept 2020· 90.9% built
- Life Republic Sector R2 - 2nd Avenue5.8 yr overdueKOLTE-PATIL INTEGRATED TOWNSHIPS LIMITED · Marunji, PuneP52100002682· filed Mar 2019 → now Sept 2020· 78.2% built
- Bloomdale Building 085.8 yr overdueMahindra Bebanco Developers Limited · Khapri, NagpurP50500008536· filed Mar 2019 → now Sept 2020· 90.9% built· 4 complaints
- MONT KIARA5.8 yr overdueTANISHQ BUILDERS · Mumbai City, Mumbai CityP51900002127· filed Mar 2019 → now Sept 2020· 41.8% built· 1 complaint
- SANKALP RESIDENCY5.8 yr overdueKALPATARU DEVELOPERS · Gijavane, KolhapurP53000010218· 24.1% built
- SUVARNA5.8 yr overdueRavetkar Realties · Kothrud, PuneP52100013022· 37.3% built· 1 complaint
- AVENUE 6415.8 yr overdueDIMPLE CREATIONS · BORIVALI, Mumbai SuburbanP51800014768· 90.9% built
- SHREE SADGURU RESIDENCY5.8 yr overdueSAIDATTA BUILDCON SPECIALITIES PRIVATE LIMITED · SHELU, RaigarhP52000016133· 5.3% built
- MADHURANGAN APARTMENT5.8 yr overdueSHRI YOGESH PRABHAKAR DHOLE · MALAD TALUKA BARAMATI, PuneP52100016018· 37.5% built
- PADMAVATI VILLA5.8 yr overduePADMAVATI DEVELOPERS · Ulawe, RaigarhP52000005830· 36.4% built
- SHIVLEELA5.8 yr overdueEkdant Developers · Jejuri (M Cl), PuneP52100001802· 73.2% built
- Aundh Riviera5.8 yr overdueSujay Shirish Bhansali · Haveli, PuneP52100002165· filed Mar 2019 → now Sept 2020· 90.9% built
- DEEP DEVANSH - 25.8 yr overdueSAMBHAV BUILDCON · PUSHPAK NODE, RaigarhP52000016024· 90.9% built
- STAR RIGHT - 45.8 yr overdueSTAR RIGHT ESTATES INDIA PRIVATE LIMITED · SECTOR - 01, RaigarhP52000013338· 90.9% built
- Vasudevsmruti5.8 yr overdueLAGOO APTE · Pune City, PuneP52100014160· 81.8% built
- MAULI SHANKAR KRUPA5.8 yr overdueBadri Construction · Baramati (M Cl), PuneP52100013080· 34.5% built
- DARSHAN SWAPNALOK PHASE 15.8 yr overdueINTELLIGENT LANDMARKS LLP · Palghar, PalgharP99000013108· 81.8% built
- Pansare Paradise Phase 15.8 yr overdueHari Om Builders & Developers · Shirur, PuneP52100015622· 90.9% built
- SHUBHARAMBH5.8 yr overdueI BUILD SUPREME UNION JV · Haveli, PuneP52100001406· filed Mar 2018 → now Sept 2020· 90.9% built· 2 complaints
- KRISHNABAN Phase 25.8 yr overdueBhuvi Landmarks LLP · Jalna, JalnaP51400011318· filed Mar 2019 → now Sept 2020· 78.2% built
- ZEE CHAHYA5.8 yr overdueZEE COM TRADE PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800007998· 53.4% built
- THE BLUE RIDGE5.8 yr overdueBLUEBERRY DEVELOPERS · CHOWRAI NAGAR, PuneP52100015515· 57.3% built
- PANVELKAR OPTIMA5.8 yr overdueVARAD VINAYAK DEVELOPERS · AAPTEWADI, ThaneP51700015392· 40.2% built
- SHANTI ENCLAVE5.8 yr overdueSADGURU BUILDERS AND DEVELOPERS · Vasai, PalgharP99000009944· filed Mar 2019 → now Sept 2020· 45.1% built
- VARSHA Phase II5.8 yr overdueSADGURU Developers · Baner, PuneP52100019844· 89.1% built
- METRO JAZZ5.8 yr overdueBALAJI REALTY · Baner, PuneP52100004597· filed Mar 2019 → now Sept 2020· 76.4% built· 1 complaint
- FLORIDA RIVER WALK PHASE I5.8 yr overdueONE EARTH · MUNDHWA, PuneP52100015819· 73.2% built· 2 complaints
- Shiv Shrushti Apartment5.8 yr overdueHarsh Constrution · NANDIMALNAKA, RaigarhP52000011617· filed Mar 2019 → now Sept 2020· 90.9% built
- PUSHPAJAL APT.5.8 yr overdueM/s Jagtap Pawar & Associates · SATARA, SataraP52700005094· filed Aug 2018 → now Sept 2020· 90.9% built
- DESTINATION OSTIA BLDG A5.8 yr overdueD R GAVHANE LANDMARKS LLP · Bhosari, PuneP52100007927· 80.9% built
- MAHI ANAND RESIDENCY5.8 yr overdueBHAGWAN MACHINDRA MAHADIK · BABRAS MALA, PuneP52100016298· 72.7% built
- Ajmera Zeon5.8 yr overdueAjmera Realty & Infra India Ltd. · Kurla, Mumbai SuburbanP51800000779· 91.6% built· 1 complaint
- Suyog Center Phase II5.8 yr overdueSuyog Development Corporation Limited · Gultekadi, PuneP52100012337· filed Mar 2019 → now Sept 2020· 81.8% built
- Chandra Villa5.8 yr overdueM/s. Accord Realtors · Mumbai City, Mumbai CityP51900002098· 66.8% built
- MORYA RESIDENCY5.8 yr overdueSAIRATNA CONSTRUCTION · Badlapur (M Cl), ThaneP51700012171· 80% built
- NIVRUTTI HEIGHTS5.8 yr overdueKALKI DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100011757· filed Mar 2019 → now Sept 2020· 90.9% built· 8 complaints
- Vidyadhan Wing D5.8 yr overdueKale Promoters and Developers · Haveli, PuneP52100001543· 72.7% built
- Godrej Prana5.8 yr overdueDREAM WORLD LANDMARKS LLP · UNDRI, PuneP52100001372· 89.1% built· 5 complaints
- Apollo Retail5.8 yr overdueLODHA DEVELOPERS LIMITED · Thane, ThaneP51700016927· 81.8% built
- AARKAY GOLD5.8 yr overdueAAR KAY ENTERPRISES · Vasai, PalgharP99000005943· 65.5% built
- Prakriti -D- Navyangan5.8 yr overdueCALYX MERLIN VENTURES LLP · Mulshi, PuneP52100000312· filed Mar 2019 → now Sept 2020· 83.1% built
- EARTH HEIGHTS I5.8 yr overdueEARTH INFRA · 13/14,NEW AMAR NAGAR, NagpurP50500016144· 90.9% built· 1 complaint
- PATWARDHAN SANKUL5.8 yr overduePATWARDHAN BUILDERS · Sangli Miraj Kupwad (M Corp.), SangliP53100011580· filed Mar 2019 → now Sept 2020· 32.1% built
- COZY LIFE5.8 yr overdueCOZY LIFE · PUNE, PuneP52100011208· 28.6% built· 2 complaints
- SHRIRAM REALITY5.8 yr overdueSHRIRAM REALITY · Chakan (CT), PuneP52100006883· 81.8% built
- Shivraj Complex5.8 yr overduePANDHARINATH MADHUKAR JOSHI · Government Colony, Near Sphurti Chowk, SangliP53100017706· 34.1% built
- JAAI PHASE II5.8 yr overdueVERSATILEREALTORSPRIVATELIMITED · Vasai, PalgharP99000016273· 90.9% built
- SOLITAIRE5.8 yr overdueRADIANT BUILDERS · Ulawe, RaigarhP52000001816· 90.9% built
- VARADVINAYAK5.8 yr overduePANDHARI CONSTRUCTION · Haveli, PuneP52100010384· 23.6% built
- TIRUPATI RESIDENCY BUILDING C5.8 yr overdueSAJANSING MOTILAL JARWAL · NEAR CIDCO WATER TANK, AurangabadP51500015607· 90.9% built
- 4 Ville5.8 yr overdueTRIMITEE CONSTRUCTIONS · Lonavala (M Cl), PuneP52100014434· 81.8% built
- Earth Residency5.8 yr overdueEarth Builder & Developers · Palghar, PalgharP99000007170· filed Mar 2019 → now Sept 2020· 90.9% built
- CHINTAMANI HABITAT DAFFODILS TYPE G - E5.8 yr overdueJASHNANI CONSTRUCTION PRIVATE LIMITED · Shahapur (CT), ThaneP51700001853· 63% built
- GOURI SHANKAR5.8 yr overdueKULKARNI JANKAR BUILDERS · NEAR SANGLI MIRAJ ROAD, SangliP53100015957· 33.6% built
- AKAR ONE5.8 yr overdueAKAR CONSTRUCTION · OPPOSITE TV TOWER, RatnagiriP52800001746· 90.9% built
- AKAR VISHWA PHASE 15.8 yr overdueAKAR INFRASTRUCTURE · BEHIND CHIRAYU HOSPITAL, RatnagiriP52800011556· 90.9% built
- Shyam Heaven5.8 yr overdueMAA BUILDWELL · Nashik (M Corp.), NashikP51600014299· 81.8% built
- VAASTU DREAMS5.8 yr overdueSai Essen Vaastu Developers LLP · CHIKHALI, PuneP52100007364· 64.8% built
- SHRI RAM PLAZA5.8 yr overdueOMKAR CONSTRUCTION · Gadhinglaj, KolhapurP53000002629· 90.9% built
- BAPPA RESIDENCY5.8 yr overdueSTONE SHELTERS LLP · Hinjavadi (CT), PuneP52100003451· filed Apr 2019 → now Oct 2020· 72.7% built
- SHIVAJI ENCLAVE - 25.8 yr overdueSUBHASH DEVIDAS BHARSAKALE · AMRAVATI, AmravatiP50300008036· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.