Delayed projects in Mumbai Suburban
1,533 MahaRERA-registered projects in Mumbai Suburban are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 8 of 8
- SAFAL TRADEMARK3 mo overdueJAI MATA DI HOME CONSTRUCTION PVT LTD · Kurla, Mumbai SuburbanP51800003754· filed Dec 2023 → now May 2026· 81.4% built· 34 complaints
- MIDAS-BHAKTI MEADOWS3 mo overdueIRENE EDWYN DMELLO · Kurla, Mumbai SuburbanP51800013457· filed Jun 2019 → now May 2026· 76.4% built· 19 complaints
- MANRAJ VIEW3 mo overdueEkta Developers · Kurla, Mumbai SuburbanP51800011821· filed Jun 2021 → now May 2026· 40.9% built
- Mangal Varsha3 mo overdueMangal Varsha · Andheri, Mumbai SuburbanP51800054491· 58.2% built· 1 complaint
- VATIKA SUDARSAN2 mo overdueVATIKA SUDARSAN · Andheri, Mumbai SuburbanP51800056335· 81.8% built
- CHARKOP JEEVAN MANGAL C.H.S. LTD2 mo overdueSANDHYA KSHITIJ BUILDERS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800034943· filed Oct 2024 → now Jun 2026· 90.9% built
- SHREE GOVIND KRUPA2 mo overdueMAMTORA FOUNDATION · Borivali, Mumbai SuburbanP51800046222· filed Dec 2024 → now Jun 2026· 81.8% built
- AKASH CHSL2 mo overdueAKASH CHSL · Borivali, Mumbai SuburbanP51800077950· 48.2% built
- VERDANT2 mo overdueVERDANT · Andheri, Mumbai SuburbanP51800054425· filed Jun 2025 → now Jun 2026· 51.8% built
- SHRADHA RESIDENCY2 mo overdueKONARK SHRADHA REALTORS · Andheri, Mumbai SuburbanP51800027190· filed Jun 2023 → now Jun 2026· 57.7% built
- SUN SUMIT JEEVAN MANGAL2 mo overdueSUN SUMIT VENTURE · Borivali, Mumbai SuburbanP51800046062· filed Jun 2025 → now Jun 2026· 81.8% built
- Komal Kounteya CHSL2 mo overdueRander Bandhu Corporation LLP · Borivali, Mumbai SuburbanP51800049376· 94.5% built
- BLOSSOM RESIDENCY2 mo overdueHF REALTY · Andheri, Mumbai SuburbanP51800028538· filed Jun 2024 → now Jun 2026· 90.8% built
- SHUBHAM ATHENA2 mo overdueSHUBHAM ATHENA · Kurla, Mumbai SuburbanP51800054167· 38.5% built
- GAURI EXCELLENCY2 mo overdueM/S GAURI LAND DEVELOPERS LLP · Borivali, Mumbai SuburbanP51800004832· filed Dec 2020 → now Jun 2026· 82.8% built· 10 complaints
- PRIME AURA2 mo overduePRIME GROUP · Borivali, Mumbai SuburbanP51800046359· filed Dec 2025 → now Jun 2026· 90.9% built
- PRABHU PLAZA2 mo overdueM/S UNITED HOUSING CORPORATION · Borivali, Mumbai SuburbanP51800028151· 90.9% built· 1 complaint
- GHARKUL HEIGHT2 mo overdueANGATH PROPERTIES LLP · Kurla, Mumbai SuburbanP51800017037· filed Dec 2022 → now Jun 2026· 26.4% built· 24 complaints
- Shankar Bhavan Premises Co-operative Society Limited2 mo overdueMishal Construction Private Limited · Kurla, Mumbai SuburbanP51900009596· filed Dec 2019 → now Jun 2026· 46.1% built
- Arvind Niwas2 mo overdueArvind Niwas · Borivali, Mumbai SuburbanP51800052356· filed Jun 2025 → now Jun 2026· 75% built
- MARATHON MILLENNIUM 22 mo overdueTERRAPOLIS ASSETS PVT LTD · Kurla, Mumbai SuburbanP51800021203· 29.4% built
- MEGHA EDGE- RED ROSE2 mo overdueMEGHA LAKSHMI ENTERPRISE · Borivali, Mumbai SuburbanP51800046888· filed Sept 2025 → now Jun 2026· 90.5% built
- Sudarshan CHS Ltd2 mo overdueSUDARSHAN CO-OPERATIVE HOUSING SOCIETY LIMITED · Ghatkopar - East, Mumbai SuburbanP51800032217· 90.9% built
- VARDHAN HEIGHTS2 mo overdueVARDHAN HOUSING · Kurla, Mumbai SuburbanP51800014198· filed Dec 2022 → now Jun 2026· 58% built· 10 complaints
- SHRI SIDDHIVINAYAK BY DEM2 mo overdueDEM Realty LLP · Borivali, Mumbai SuburbanP51800049306· filed Feb 2026 → now Jun 2026· 90.9% built
- BHUVNESHWAR VINTAGE2 mo overdueS P INFRA · Kurla, Mumbai SuburbanP51800022717· filed Mar 2023 → now Jun 2026· 72.7% built
- DEVRAJ RESIDENCY2 mo overdueSHAMS ENTREPRISES · Malad - West, Mumbai SuburbanP51800051682· filed Jun 2024 → now Jun 2026· 89.1% built
- CRYSTAL PRIDE2 mo overdueCRYSTAL CONSTRUCTION COMPANY · Borivali, Mumbai SuburbanP51800009735· filed Dec 2019 → now Jun 2026· 78.6% built
- TOWER 282 mo overdueShiv Shakti Builders And Developers · Borivali, Mumbai SuburbanP51800009511· filed Jun 2022 → now Jun 2026· 62.1% built· 80 complaints
- 19 DEGREE NORTH2 mo overdueARUNIS EDIFICE PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800050846· 66.8% built
- AKN ANNEXE2 mo overdueAKN ANNEXE · Andheri, Mumbai SuburbanP51800055901· filed Sept 2025 → now Jun 2026· 81.8% built
- AMARYLLIS TOWERS AND PLAZA2 mo overdueNAHAR BUILDERS LTD. · Kurla, Mumbai SuburbanP51800028801· 80.5% built
- MAHINDRA ALCOVE WING D AND E2 mo overdueMahindra Lifespace Developers limited · Kurla, Mumbai SuburbanP51800028352· 29.1% built
- PLATINUM VISTA2 mo overduePLATINUMCORP SKYTOWERS LLP · Andheri, Mumbai SuburbanP51800049496· 60.8% built
- CODENAME RARE BY RUNWAL2 mo overdueRunwal Developers Ltd · Andheri, Mumbai SuburbanP51800034594· 90.9% built
- O AND S BUSINESS SUITES2 mo overdueSUCHITA ORANGE HDM PROJECT · Kurla, Mumbai SuburbanP51800006703· filed Dec 2025 → now Jun 2026· 81.8% built
- AAKRUTI AASHVI APARTMENT2 mo overdueAakruti Aashvi Developers · Kurla, Mumbai SuburbanP51800003018· filed Jun 2022 → now Jun 2026· 81.4% built
- Trimbac2 mo overdueTrimbac · Kurla, Mumbai SuburbanP51800055483· 81.8% built
- Haware Intelligentia Sigma South JVLR Wing C2 mo overdueSuresh Kashinath Haware · Kurla, Mumbai SuburbanP51800028288· 90.9% built
- Pruthvi Pushpanjali2 mo overdueFlying Earth LLP · Andheri, Mumbai SuburbanP51800046070· 82.4% built
- DELTA HOUSE2 mo overdueRIGHT CHANNEL CONSTRUCTION PVT LTD · Borivali, Mumbai SuburbanP51800003828· filed Dec 2022 → now Jun 2026· 90.9% built· 5 complaints
- Shubhada Co-operative Housing Society Ltd.2 mo overdueBHOOMIVIJAY PROPERTIES PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800001693· filed Jun 2021 → now Jun 2026· 90.9% built· 1 complaint
- Valentina CHS2 mo overdueShree S S Developers Private Limited · Kurla, Mumbai SuburbanP51800025836· 81.8% built
- 63 ELEGANCE2 mo overdueSIDDHARTH DEVELOPERS · Mumbai, Mumbai SuburbanP51800009011· filed Dec 2022 → now Jun 2026· 60.9% built
- ALAG ENDEAVOUR2 mo overdueALAG ENDEAVOUR · Kurla, Mumbai SuburbanP51800028404· 0% built· 7 complaints
- VISHAKHA HEIGHTS AND VISHAKHA REGENCY2 mo overdueM/s Keytech · Kurla, Mumbai SuburbanP51800046013· filed Dec 2025 → now Jun 2026· 62.7% built
- JP Eminence2 mo overdueJ. P. INFRA (MUMBAI) PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800026524· 90.9% built· 1 complaint
- GARUDA SHATRUNJAY2 mo overdueMESSERS SHREE UMIYA BUILDERS & DEVELOPERS · Borivali, Mumbai SuburbanP51800011329· filed Dec 2024 → now Jun 2026· 53.2% built· 22 complaints
- Saptashringi2 mo overdueSiroya Developers Pvt Ltd · Kurla, Mumbai SuburbanP51800012064· filed Dec 2019 → now Jun 2026· 43.5% built
- Ghodawat Skystar LLP2 mo overdueGhodawat Skystar LLP · Borivali, Mumbai SuburbanP51800032000· filed Dec 2025 → now Jun 2026· 71.4% built
- KSHITIJ EMINENCE2 mo overdueKSHITIJ DEVELOPERS · Kurla, Mumbai SuburbanP51800028688· 99.5% built
- Nasar Enclave Sale Building A and B Wing2 mo overdueM/s. Nasar Associates · Andheri, Mumbai SuburbanP51800028733· 77.9% built
- GAURI EXCELLENCY NX2 mo overdueM/S GAURI LAND DEVELOPERS LLP · Borivali, Mumbai SuburbanP51800029939· filed Dec 2023 → now Jun 2026· 80.2% built
- ALAG ANANTA2 mo overdueAlag Square LLP · Kurla, Mumbai SuburbanP51800045309· filed Sept 2024 → now Jun 2026· 90.9% built
- MINT2 mo overdueMINT · Andheri, Mumbai SuburbanP51800053816· 90.9% built
- TULSI CHAMBER PHASE II2 mo overdueSURANA CONSTRUCTION (CHEMBUR ) · Kurla, Mumbai SuburbanP51800027210· filed Jun 2024 → now Jun 2026· 85.9% built
- GAURAV LEGEND2 mo overdueMonarch and Querish Builders · Andheri, Mumbai SuburbanP51800010967· filed Dec 2023 → now Jun 2026· 52.2% built· 47 complaints
- ASHTAVINAYAK APARTMENTS2 mo overdueSHIV SHRUTI DEVELOPERS LLP · Andheri, Mumbai SuburbanP51800049920· filed Dec 2025 → now Jun 2026· 77.7% built
- W2.O BY SANDU DEVELOPERS2 mo overdueSandu Developers · Kurla, Mumbai SuburbanP51800027979· 55.9% built
- SHREE SANTOSH APPARTMENT2 mo overdueBHARAT NAVINCHANDRA GALA · Borivali, Mumbai SuburbanP51800007795· filed Dec 2018 → now Jun 2026· 75.9% built· 4 complaints
- AARADHYA EVOQ2 mo overdueMAN INFRA CONTRACTS LLP · Andheri, Mumbai SuburbanP51800034587· 90.9% built
- Kush Pride2 mo overdueKush Housing LLP · Borivali, Mumbai SuburbanP51800033962· filed Dec 2025 → now Jun 2026· 77.4% built
- Shubham Atlanta2 mo overdueAVVAD HOUSING LLP · Kurla, Mumbai SuburbanP51800051726· 90% built
- Abundanttiafull - By Bholas2 mo overdueSandeep Dalchand Jain · Borivali, Mumbai SuburbanP51800052704· 67.7% built
- GOVIND SOLITAIRE2 mo overdueSHANKH DEVELOPERS LIMITED LIABILITY PARTNERSHIP · Kurla, Mumbai SuburbanP51800030555· filed Jul 2024 → now Jun 2026· 77.7% built
- ZODIAC ANJANESHWAR2 mo overdueZODIAC ANJANESHWAR · Andheri, Mumbai SuburbanP51800054548· filed Jun 2025 → now Jun 2026· 59.6% built
- PANT NAGAR SARASWATI CHSL2 mo overdueKYRAA INFRA PROJECTS · GHATKOPAR, Mumbai SuburbanP51800027377· 90.9% built· 1 complaint
- Lodha Kandivali Project - Tower 32 mo overdueLodha Developers Limited · Akurli Village, Mumbai SuburbanP51800031346· filed Oct 2025 → now Jun 2026· 81.8% built
- SHUBHAM AURUM2 mo overdueSHUBHAM AURUM · Kurla, Mumbai SuburbanP51800054393· 38.5% built
- New Saket Co-operative Housing Society Ltd.2 mo overdueSM Magnate Construction · Andheri, Mumbai SuburbanP51800049992· 90.9% built
- KUBER VILLA2 mo overdueKUBER VILLA · Andheri, Mumbai SuburbanP51800054808· 81.8% built
- MASS IONICS2 mo overdueMASS BUILDSQUARE STRUCTURE PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800027417· 66% built
- ASTRUM ANNEX2 mo overdueASTRUM REALITY PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800048947· filed Dec 2024 → now Jun 2026· 70% built
- THE SANCTUARY - TOWER 42 mo overdueRunwal Construction Private Limited · Kurla, Mumbai SuburbanP51800025926· 99.8% built· 1 complaint
- Sparkle Umadarshan2 mo overdueSPARKLE EARTH DEVELOPER · Borivali, Mumbai SuburbanP51800051376· filed Dec 2025 → now Jun 2026· 62.3% built
- APEX GREEN WOOD2 mo overdueAPEX INFRATEC · Borivali, Mumbai SuburbanP51800047381· 72.7% built
- Solaris 14th Floor2 mo overdueHubtown Limited · Andheri, Mumbai SuburbanP51800028276· 41.5% built
- TULSI CHAMBERS2 mo overdueSURANA CONSTRUCTION (CHEMBUR ) · Kurla, Mumbai SuburbanP51800012437· filed Jun 2021 → now Jun 2026· 90% built· 15 complaints
- DPS NAKSHATRA HEIGHTS2 mo overdueDPS NAKSHATRA HEIGHTS · Borivali, Mumbai SuburbanP51800052649· 90.9% built
- ENSO SANZA2 mo overdueSai Aastha Developers · Borivali, Mumbai SuburbanP51800013955· filed Dec 2023 → now Jun 2026· 82.5% built· 32 complaints
- Alfa Padma Vasant2 mo overdueZakiruddin Gaffar Sayyed · Kurla, Mumbai SuburbanP51800051797· 38.6% built
- ORCHID HEIGHTS2 mo overdueNIMESH KIRTIKUMAR SHAH · Borivali, Mumbai SuburbanP51800029631· filed Jun 2024 → now Jun 2026· 90.9% built
- GHATKOPAR AVENUE AARADHYA ONE EARTH I PHASE V2 mo overdueMAN REALTORS AND HOLDINGS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800027922· 63.6% built
- D SOLITAIRE2 mo overdueKRISHNAN AND KAMAL ASSOCIATES · Borivali, Mumbai SuburbanP51800031850· filed Mar 2023 → now Jun 2026· 64.7% built
- MARIGOLD AANGAN2 mo overdueMARIGOLD CONSTRUCTIONS · Kurla, Mumbai SuburbanP51800029006· filed Mar 2024 → now Jun 2026· 81.8% built· 1 complaint
- GOMANT KUTIR CHSL2 mo overdueJBR HOUSECON LLP · Borivali, Mumbai SuburbanP51800052397· filed Dec 2025 → now Jun 2026· 81.8% built
- Pashmina Casa2 mo overduePashmina Buildcon Private Limited · Andheri, Mumbai SuburbanP51800047054· 81.7% built· 4 complaints
- COMMERZ 542 mo overdueSHREE VINAYAK REALITY PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800020069· filed Dec 2022 → now Jun 2026· 52.1% built
- MAHINDRA ALCOVE WING A AND C2 mo overdueMahindra Lifespace Developers limited · Kurla, Mumbai SuburbanP51800033573· 13.2% built
- AMAIRA RESIDENCY2 mo overdueAMAIRA RESIDENCY · Andheri, Mumbai SuburbanP51800046422· 29.1% built
- RAKHI TOWER PHASE 3 12TH TO 15TH FLOOR PART2 mo overdueRAKHI TOWER PHASE 3 12TH TO 15TH FLOOR PART · Borivali, Mumbai SuburbanP51800027354· 36.4% built
- Vivaana Heights2 mo overdueN K BUILDERS & DEVELOPERS · Andheri, Mumbai SuburbanP51800025788· 44.3% built· 1 complaint
- Ruparel Livia2 mo overdueShree Siddhivinayak Classic Construction Private Limited · Kurla, Mumbai SuburbanP51800026450· filed Jun 2024 → now Jun 2026· 67.7% built· 9 complaints
- MAVERICK MOOLDEEP2 mo overdueJAI SUN MAVERICK REALTORS · Kurla, Mumbai SuburbanP51800003963· filed Dec 2022 → now Jun 2026· 89.9% built· 2 complaints
- Neelyog Aashiyana II2 mo overdueNeelyog Construction Pvt Ltd · KANDIVALI WEST, Mumbai SuburbanP51800034106· 90.9% built
- SHREYA2 mo overdueBHARAT NAVINCHANDRA GALA · Borivali, Mumbai SuburbanP51800002243· filed Dec 2018 → now Jun 2026· 36.2% built· 1 complaint
- The Residency2 mo overdueLak & Hanware Realty LLP · Andheri, Mumbai SuburbanP51800004331· filed Jun 2021 → now Jun 2026· 93.2% built· 4 complaints
- UNICORN2 mo overdueSaroj Landmark Realty LLP · Andheri, Mumbai SuburbanP51800028365· 99.1% built· 4 complaints
- RAJDEEP CHS LTD2 mo overdueCHINNAPAN SWAMY ANTHONY · Borivali, Mumbai SuburbanP51800049463· filed Dec 2025 → now Jun 2026· 90.7% built
- Gayatri Heights2 mo overdueGayatri Properties · Andheri, Mumbai SuburbanP51800049323· 90.2% built
- PRIYA CO-OPERATIVE HOUSING SOCIETY LTD.2 mo overdueARJUNSINGH BHOORSINGH RATHORE · Andheri, Mumbai SuburbanP51800021193· filed Jun 2023 → now Jun 2026· 34.1% built· 2 complaints
- Hubtown Seasons - Ardennes2 mo overdueJoynest Premises Private Ltd · Kurla, Mumbai SuburbanP51800032784· 77.3% built
- ROOPNIKETAN CO.OPERATIVE HOUSING SOCIETY LTD.2 mo overdueSHREE SHINGAR CONSTRUCTIONS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800051469· filed Dec 2025 → now Jun 2026· 70.9% built
- FINE HEIGHTS2 mo overdueFINE HEIGHTS · Borivali, Mumbai SuburbanP51800055299· filed Dec 2025 → now Jun 2026· 81.8% built
- BRINDAVAN CHSL2 mo overdueBRINDAVAN CHSL · Borivali, Mumbai SuburbanP51800076772· 50.5% built· 1 complaint
- Florence Heights A and B Wing2 mo overdueM/s Vinayak Developers · Borivali, Mumbai SuburbanP51800049192· filed Dec 2024 → now Jun 2026· 76.3% built
- Vayuputra Trident2 mo overdueVayuputra Trident · Andheri, Mumbai SuburbanP51800053280· 44.7% built
- ODC 11 mo overdueNVN Buildcon LLP · Goregaon West, Mumbai SuburbanP51800046544· filed Dec 2024 → now Jul 2026· 81.8% built
- Rudra Paradise1 mo overdueR-Stone Design and Build Private Limited · Andheri, Mumbai SuburbanP51800008159· filed Jan 2021 → now Jul 2026· 76.2% built
- PRERANA CHSL1 mo overduePRERANA CHSL · Andheri, Mumbai SuburbanP51800053537· 90.9% built
- GANESH RESIDENCY1 mo overdueSHREE VENKATESHWARA DEVELOPERS · Kurla, Mumbai SuburbanP51800021114· filed Jul 2023 → now Jul 2026· 58.7% built
- Serenity- Bldg 11 mo overdueJVPD Properties Private Limited · Kurla, Mumbai SuburbanP51800011181· 7.3% built· 392 complaints
- SHEPHERD HORIZON1 mo overdueGOODBUILD INDIA PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800046622· filed Jul 2025 → now Jul 2026· 77.8% built
- DEM PHOENIX1 mo overdueDEM BUILDWELL · Borivali, Mumbai SuburbanP51800048376· filed Oct 2025 → now Jul 2026· 82.1% built
- SAYBA ARCADIA1 mo overdueSTAR EMPIRE · Kurla West, Mumbai SuburbanP51800055257· filed Mar 2026 → now Jul 2026· 81.8% built
- Krishna Milan Heights1 mo overdueMilan Interbuilt Private Limited · Andheri, Mumbai SuburbanP51800032172· filed Dec 2024 → now Jul 2026· 62.4% built
- Hubtown Seasons - B Wing1 mo overdueJoynest Premises PrivateLimited · Kurla, Mumbai SuburbanP51800008552· filed Jul 2025 → now Jul 2026· 69.5% built
- Lodha Kandivali Project - Tower 51 mo overdueLodha Developers Limited · Borivali, Mumbai SuburbanP51800032605· filed Sept 2025 → now Jul 2026· 81.8% built
- SAHAKAR VISTA1 mo overdueSAHAKAR VISTA · Borivali, Mumbai SuburbanP51800053793· 67.3% built
- RISHABRAJ ARADHANA1 mo overdueRISHABRAJ ARADHANA · Borivali, Mumbai SuburbanP51800053420· 61.4% built
- RUSHABH APARTMENT1 mo overdueR R BUILDERS · Borivali, Mumbai SuburbanP51800030994· filed Aug 2024 → now Jul 2026· 49.5% built· 1 complaint
- BALDEVSINGH THAKUR SRA COOP HSG SOC LTD1 mo overdueKRISHNA NARSINGRAO PIMPLE · Kurla, Mumbai SuburbanP51800008254· filed Aug 2023 → now Jul 2026· 90.9% built
- Vidyalankar CHSL1 mo overdueDESAI RESIDENCY PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800052458· filed Jul 2025 → now Jul 2026· 79.1% built
- PRIMROSE1 mo overdueKaustubh Construction Private Limited · Borivali, Mumbai SuburbanP51800046761· 90.7% built
- The Wave1 mo overdueWebtech Realty LLP · Andheri, Mumbai SuburbanP51800050188· 71.3% built
- Hubtown Premiere Residences - Commercial1 mo overdueHubtown Limited · Andheri, Mumbai SuburbanP51800003575· 72.7% built· 2 complaints
- SEJAL KAJAL APARTMENT CHS LTD1 mo overdueNeminath Realtors · Borivali, Mumbai SuburbanP51800046493· 37.6% built· 1 complaint
- Hubtown Premiere Residences - Bel Air1 mo overdueHubtown Limited · Andheri, Mumbai SuburbanP51800005688· 58.4% built
- ROSE BLOSSOM CHSL1 mo overdueVINI DEVELOPERS · Andheri, Mumbai SuburbanP51800053800· 79.5% built
- Commercial Wing - NL Plaza and Residential Wing - NL Krishna1 mo overdueBEAUTIFUL PROPERTIES PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800048076· filed Aug 2025 → now Aug 2026· 79.5% built
- Jai Kamal1 mo overdueJai Kamal · Kurla, Mumbai SuburbanP51800052049· 64% built
- RASHMI MANORATH0 mo overdueRASHMI MANORATH · Borivali, Mumbai SuburbanP51800078598· 55.1% built
- THE KOLLAGE0 mo overdueZIRE RUSHI CONSTRUCTION · Andheri (East), Mumbai SuburbanP51800012084· filed Dec 2022 → now Aug 2026· 99.9% built· 4 complaints
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.