Delayed projects in Mumbai Suburban
1,523 MahaRERA-registered projects in Mumbai Suburban are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 7 of 8
- The Greens - Radhakunj1.7 yr overdueEthics Infra Development Pvt Ltd · Kandivali East, Mumbai SuburbanP51800029355· filed May 2024 → now Feb 2025· 90% built
- REDEVELOPMENT OF PLOT NO. 2121.6 yr overduePRANAV CONSTRUCTIONS LIMITED · MUMBAI, Mumbai SuburbanP51800034087· 90.9% built
- SHUBH REGENCY1.6 yr overdueSHUBH ENTERPRISE · MULUND, Mumbai SuburbanP51800003145· filed Jun 2022 → now Feb 2025· 90.9% built· 2 complaints
- Kasturi Milan1.6 yr overdueH RISHABRAJ REALTY · Borivali West, Mumbai SuburbanP51800051982· 90.9% built
- DEEPA CHS LTD1.6 yr overdueREGENT SPACES · VILE PARLE EAST, Mumbai SuburbanP51800026864· 96.4% built
- DHANRAJ1.6 yr overdueANEISHA LIVINGS LLP · BORIVALI (W), Mumbai SuburbanP51800034955· 90.9% built
- SUPREME HAPPY HOME1.6 yr overdueShelby Realty LLP · Kandivali West, Mumbai SuburbanP51800034043· 90.9% built
- GHATKOPAR AVENUE AARADHYA ONE EARTH B PHASE III1.5 yr overdueMAN REALTORS AND HOLDINGS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800027659· 63.6% built
- GHATKOPAR AVENUE AARADHYA ONE EARTH PHASE I1.5 yr overdueMAN REALTORS AND HOLDINGS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800024676· 87.6% built
- OM MADHUSADAN CHS LTD1.5 yr overdueREGENT BUILDERS · CHITRKAR KETKAR MARG VILE PARLE EAST MUMBAI, Mumbai SuburbanP51800034194· 93.6% built
- KAMLA PRASANNA JEEVAN BUILDING 21.5 yr overdueKAMLA HOMES AND LIFESTYLES PVT LTD · BORIVALI WEST, Mumbai SuburbanP51800029752· 90.9% built
- ROMELL SERENE1.5 yr overdueROMELL REAL ESTATE PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800034025· 81.8% built
- MODIREALTY KALPVRIKSH1.5 yr overdueMODIREALTY DEVELOPERS PVT LTD · ANDHERI WEST, Mumbai SuburbanP51800034375· 90.9% built
- Utkarsh1.5 yr overdueAmbrosial Developers Private Limited · Santacruz East, Mumbai SuburbanP51800030434· 83% built
- REDEVELOPMENT OF SPARSH CHSL1.5 yr overduePRANAV CONSTRUCTIONS LIMITED · Borivali, Mumbai SuburbanP51800031623· 90.9% built
- HANSINI ELEGANCE1.5 yr overdueKARSAN BACHU SATRA · Borivali, Mumbai SuburbanP51800010085· filed Dec 2019 → now Mar 2025· 64.6% built
- DEM Cygnus1.5 yr overdueDEM ESTATES LLP · Kandivali - west, Mumbai SuburbanP51800034396· 90% built
- AMAZON PARK BUILDING NO 2 - WING C1.5 yr overdueR.J. CONSTRUCTIONS · BORIVALI WEST, Mumbai SuburbanP51800002956· filed Jun 2021 → now Mar 2025· 53.6% built· 14 complaints
- Saideep Apartment1.5 yr overdueDARSHAN INFRA · Andheri, Mumbai SuburbanP51800045356· 90.9% built
- GANGASADAN1.5 yr overdueNAVPADH REALTY LLP · GORAS WADI, Mumbai SuburbanP51800048440· 90.9% built
- Om Laxmi Sadan CHS Ltd1.5 yr overdueMAVERICK REALTORS · Mulund West, Mumbai SuburbanP51800029133· 59.5% built· 1 complaint
- REDEVELOPMENT OF RAMESH MANDIR CHSL1.5 yr overduePRANAV CONSTRUCTIONS LIMITED · MUMBAI, Mumbai SuburbanP51800032468· 76.9% built
- GIRIVAN LA QUINTA1.5 yr overdueAbhishek Mahesh Garodia · Kurla, Mumbai SuburbanP51800026169· 97.7% built
- Drushti Sapphire1.5 yr overdueDrushti Realtors Pvt Ltd · Ghatkopar East, Mumbai SuburbanP51800032434· 54.5% built· 7 complaints
- Supreme Imperial1.5 yr overdueSupreme Real Estate Developer · Borivali, Mumbai SuburbanP51800032164· 94.5% built
- MADHUBAN HEGHTS1.4 yr overdueHIRAL REAL ESTATE DEVELOPERS LLP · KANDIVALI WEST, Mumbai SuburbanP51800046035· 90.9% built
- Darpan Niketan Cooperative Society1.4 yr overdueBricks and Blocks Construction LLP · Kurla, Mumbai SuburbanP51800048133· 90.9% built
- GARDEN VIEW1.4 yr overdueSMLIFE SHREEJI DEVELOPERS LLP · BORIVALI WEST, Mumbai SuburbanP51800046071· 90.9% built
- Supreme Elysia1.4 yr overdueSupreme Mega Constructions LLP · Andheri, Mumbai SuburbanP51800034860· 95.5% built
- REDEVELOPMENT OF NAV VIKAS CHSL1.4 yr overdueSwara Constructions · VILE PARLE EAST, Mumbai SuburbanP51800046341· 57.3% built
- Redevelopment of Parle Satam CHS Ltd1.4 yr overdueR R CONSTRUCTIONS · vile parle east, Mumbai SuburbanP51800046583· 71.4% built
- THE LISA1.4 yr overdueSHETHWALA INFRA · Andheri, Mumbai SuburbanP51800046662· 90.9% built
- VISION HEIGHTS WING C1.4 yr overdueFiona Realty Private Limited · Andheri, Mumbai SuburbanP51800007259· filed Dec 2023 → now Jun 2025· 78.6% built
- Horizon Giridarshan1.4 yr overdueHORIZON PROMOTERS INDIA LTD · Mulund West, Mumbai SuburbanP51800049813· 90.9% built
- 66 Palazzio1.3 yr overdueParsh Realty · Borivali, Mumbai SuburbanP51800026378· 76.5% built
- Mahavir Galaxy1.3 yr overdueNayan Builders · Kurla, Mumbai SuburbanP51800001952· filed Jun 2021 → now Jun 2025· 99.9% built· 1 complaint
- HARSIDDHI SADAN CHS LTD1.3 yr overdueRK CONSTRUCTION · Borivali East, Mumbai SuburbanP51800052312· 79.9% built
- KURLA SAHAYOG CHS LTD., BLDG. NO.681.3 yr overduePARSN CONSTRUCTION AND DEVELOPERS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800009819· filed Jun 2018 → now Jun 2025· 90.9% built· 7 complaints
- PRABHAT KUNJ1.3 yr overdueLAKSHMICONSTRUCTION · Mumbai, Mumbai SuburbanP51800047024· 89.1% built
- Rajkamal1.3 yr overdueKhushi Associates · Borivali- West, Mumbai SuburbanP51800028704· 90.9% built
- BORIVALI YASHODHAN CHSL1.3 yr overdueTGN REALTOR LLP · BORIVALI WEST, Mumbai SuburbanP51800048607· filed Jun 2024 → now Jun 2025· 90.9% built
- Redevelopment of Sri Guruvayurappan Balmukund Co-operative Housing Society Ltd.1.3 yr overdueSMERA HOMES LLP · Chembur, Mumbai SuburbanP51800045578· filed Sept 2024 → now Jun 2025· 81.8% built
- MAYFAIR GNYANADEEP1.3 yr overdueMAYFAIR HOUSING PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800034829· 89.5% built
- WHITE BERRY RESIDENCY1.3 yr overdueM/S. WHITE BERRY REALSPACES L.L.P. · Borivali, Mumbai SuburbanP51800027240· 90.9% built
- ANMOLPRITI1.3 yr overdueMuktistar Buildcon Private Limited · Borivali, Mumbai SuburbanP51800006598· filed Dec 2018 → now Jun 2025· 89.7% built· 6 complaints
- KUSH SYMPHONY1.3 yr overdueKush Buildcon LLP · Mulund West, Mumbai SuburbanP51800030410· filed Dec 2023 → now Jun 2025· 90.9% built
- REGENT HILL A B C D AND E WING1.3 yr overdueHGP Community Pvt. Ltd. · Kurla, Mumbai SuburbanP51800018620· 90.9% built· 2 complaints
- Rajshree Aashiyana1.3 yr overdueGanesh Chhaya Construction LLP · Ghatkopar East, Mumbai SuburbanP51800046829· 81.8% built
- SIESTA1.3 yr overduePRESTIGE MULUND REALTY PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800005285· filed Dec 2023 → now Jun 2025· 77.7% built· 13 complaints
- SHREE LAXMI VANDAN1.3 yr overduePRAGATI LAND DEVELOPERS · KANDIVALI WEST, Mumbai SuburbanP51800027654· filed Jun 2023 → now Jun 2025· 90.9% built
- Jyotsna Heritage Redevelopment of The Dahisar R.K. Nayak Niwasi CHS LTD1.3 yr overdueM/S SHREE SAINAMAH HOMES LLP · DAHISAR EAST, Mumbai SuburbanP51800047220· 88.2% built
- ANANYA1.3 yr overdueTRYKSHA PROJECTS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800026054· 90.9% built
- REDEVELOPMENT OF RUSHABH MAHAL CHSL1.3 yr overduePRANAV CONSTRUCTIONS LIMITED · MALAD EAST, Mumbai SuburbanP51800034099· 90.9% built
- GHATKOPAR AVENUE AARADHYA ONE EARTH H PHASE VII1.3 yr overdueMAN REALTORS AND HOLDING PRIVATE LIMITED · GHATKOPAR EAST, Mumbai SuburbanP51800046812· 63.6% built
- GHATKOPAR AVENUE AARADHYA ONE EARTH G PHASE VI1.3 yr overdueMAN REALTORS AND HOLDINGS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800029288· 63.6% built
- Lifescapes Prithvii1.3 yr overdueGirnar Builders & Developers · Mumbai, Mumbai SuburbanP51800001333· filed Jan 2021 → now Jun 2025· 91.1% built
- PROXIMUS1.3 yr overdueGeeCee Ventures Limited · CHEMBUR, Mumbai SuburbanP51800027318· 89.1% built
- HEMKUNJ1.3 yr overdueMAHENDRA RAVJIBHAI MAKWANA · Ghatkopar East, Mumbai SuburbanP51800047837· 63.6% built
- 19 North1.3 yr overdueKANDIVALI, Mumbai SuburbanP51800026243· 71.5% built
- The Arcade1.3 yr overdueCCI PROJECTS PRIVATE LIMITED · Magathane Telephone Exchange, Mumbai SuburbanP51800018662· filed Dec 2021 → now Jun 2025· 78.2% built
- TRITON1.3 yr overdueJade Constructions Private Limited · SANTACRUZ WEST, Mumbai SuburbanP51800031222· 90.5% built
- THE PARK RESIDENCES PHASE-I1.2 yr overdueDEVLAND INFRACON PVT. LTD. · OSHIWARA, Mumbai SuburbanP51800015211· 42.7% built
- BALI DIVINE1.2 yr overdueBALI ESTATES LLP · GOREGAON WEST MUMBAI, Mumbai SuburbanP51800047014· 81.8% built
- Hubtown Seasons Czarnowo1.2 yr overdueJoynest Premises Private Limited · Kurla, Mumbai SuburbanP51800003012· 70% built
- VERVE1.2 yr overdueKOLTE-PATIL DEVELOPERS LIMITED · Bangur Nagar, Village Pahadi, Goregaon (West), Mumbai SuburbanP51800028783· 57.5% built
- AARAMBH WING A-B1.2 yr overdueSATELLITE DEVELOPERS PVT LTD · Appa Pada, Gandhi Nagar, Malad East, Mumbai SuburbanP51800028424· filed Sept 2024 → now Jul 2025· 48.6% built· 15 complaints
- RASHMI VASUDEO1.2 yr overdueModi's Navnirman Limited · BORIVALI WEST, Mumbai SuburbanP51800051769· 95.5% built
- BORIVALI PADAM CHSL1.2 yr overdueAMISHA CONSTRUCTIONS PRIVATE LIMITED · BORIVALI WEST, Mumbai SuburbanP51800032736· filed Jun 2025 → now Aug 2025· 81.8% built
- Kailas Ashish1.2 yr overdueDNK Developers KA LLP · Ghatkopar East, Mumbai SuburbanP51800045948· 90.9% built
- Gala Hub1.2 yr overdueGala Comp · Vile Parle West, Mumbai SuburbanP51800050876· filed Jun 2024 → now Aug 2025· 78.2% built
- RAGHAV MARVEL1.1 yr overdueRAGHAV RAJ BUILDERS & DEVELOPERS LLP · Nehrunagar, Mumbai SuburbanP51800045396· filed Aug 2024 → now Aug 2025· 88.6% built· 4 complaints
- ARIHANT VIEW1.1 yr overdueARIHANT LABDHI BUILDERS PRIVATE LIMITED · SANTACRUZ EAST MUMBAI, Mumbai SuburbanP51800055681· 43.2% built
- Avyukta Breeze1.1 yr overdueShivoham Associates · I C Colony, Mumbai SuburbanP51800034240· 72.7% built
- KUSH ELEGANTE1.1 yr overdueKUSH REALCON LLP · KANDIVALI WEST, Mumbai SuburbanP51800027575· filed Jun 2024 → now Sept 2025· 81.8% built· 1 complaint
- New Abhiram CHS LTD1.1 yr overduePeerless Constructions Pvt. Ltd. · Kastur Park, Mumbai SuburbanP51800045965· filed Jun 2025 → now Sept 2025· 73.2% built
- GHATKOPAR AVENUE AARADHYA ONE EARTH E PHASE II1.0 yr overdueMAN REALTORS AND HOLDINGS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800027588· 63.6% built
- REDEVELOPMENT OF GOLD COIN CHSL1.0 yr overduePRANAV CONSTRUCTIONS LIMITED · MUMBAI, Mumbai SuburbanP51800034931· 90.9% built· 1 complaint
- GHATKOPAR AVENUE AARADHYA ONE EARTH F PHASE IV1.0 yr overdueMAN REALTORS AND HOLDINGS PVT LTD · Kurla, Mumbai SuburbanP51800027826· 63.6% built
- REDEVELOPMENT OF NEW SHALIMAR APARTMENTS CHSL1.0 yr overduePRANAV CONSTRUCTIONS LIMITED · Borivali, Mumbai SuburbanP51800034915· 90.9% built
- APURVA VAISHALI CHSL1.0 yr overdueDIRAVYA DEVELOPERS LLP · BORIVALI EAST, Mumbai SuburbanP51800050330· 90.9% built
- Monte Verita North Annexe1.0 yr overdueM/s B G Shirke Redevelopment and Gas Pvt. Ltd. (Formerly M/s B G Shirke Oil and Gas India Pvt. Ltd.) · Gulmohar City, Magathane, Mumbai SuburbanP51800028561· 48.4% built· 2 complaints
- Kalpataru Bliss Apartments1.0 yr overdueKlassik Vinyl Products LLP · Andheri, Mumbai SuburbanP51800020262· 81.5% built· 3 complaints
- Pruthvi Park View1.0 yr overduePruthvi Enterprise · Vile Parle East, Mumbai SuburbanP51800047524· 80.5% built
- Govind Nagar SRA CHS Ltd.1.0 yr overdueDrishti Developers II · mahakali, Mumbai SuburbanP51800010475· filed Sept 2022 → now Sept 2025· 98.7% built
- MAYA MAMTA1.0 yr overdueGREENBUILDING LIFESCAPES LLP · Borivali WEST, Mumbai SuburbanP51800045381· 0% built
- JADE GARDENS TOWER C11 mo overdueJAIRAJHAPPYHOMES · Pant Nagar Ghatkopar East, Mumbai SuburbanP51800033954· 81.8% built
- Crest Parkview11 mo overdueCREST VENTURES LIMITED · Bandra West, Mumbai SuburbanP51800045968· 80.9% built
- JADE GARDENS TOWER A11 mo overdueJAIRAJHAPPYHOMES · Pant Nagar Ghatkopar East, Mumbai SuburbanP51800033601· 61.4% built
- Jade Gardens Tower B11 mo overdueJAIRAJHAPPYHOMES · Pant Nagar Ghatkopar East, Mumbai SuburbanP51800033945· 79.1% built
- DIVUM11 mo overdueDYNAMIX CONTRACTORS & BUILDERS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800018784· filed Sept 2024 → now Oct 2025· 83.9% built· 2 complaints
- SKYVIEW CHS10 mo overdueHIRANIMANTHAN BUILDERS AND DEVELOPERS · Nehru Nagar, Mumbai SuburbanP51800008227· filed Dec 2019 → now Nov 2025· 90.9% built· 1 complaint
- HARI NIWAS10 mo overdueTORAL RAJ DEVELOPERS · BORIVALI EAST, Mumbai SuburbanP51800053673· 72.7% built
- SHREE KRUSHNA TOWER10 mo overdueMAGNAACASA REALTY PVT. LTD. · Tambe Nagar, Mulund West, Mumbai SuburbanP51800022998· filed Dec 2024 → now Dec 2025· 83.5% built· 1 complaint
- Neelyog Virat -B Wing10 mo overdueNeelyog Construction Pvt Ltd · Borivali, Mumbai SuburbanP51800003560· 99.9% built
- SHAKTI TROMBAY 889 mo overdueVASHU RAHEJA SONS REALTY LLP · Kurla, Mumbai SuburbanP51800049964· filed Jun 2025 → now Dec 2025· 97.7% built
- Nirmaan Heena9 mo overdueM/s. Ramkripa Enterprises · Vile Parle East, Mumbai SuburbanP51800056079· 90.9% built
- AIM Platinum9 mo overdueAIM REALTORS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800023249· 96.8% built
- WORLIWALA CHSL9 mo overdueSHAMIK & SANGHVI DEVELOPERS LLP · VILE PARLE (EAST), Mumbai SuburbanP51800047017· 90.9% built
- TRISHABH GREENS - WING A9 mo overdueRISHABH ENTERPRISES · CHEMBUR NAKA, CHEMBUR EAST, Mumbai SuburbanP51800018331· 90.9% built
- PLATINUM LIFE9 mo overdueSAMUDRA DARSHAN GRUHPRAVESH LLP · ANDHERI WEST, Mumbai SuburbanP51800014518· 90.7% built· 15 complaints
- NEHRU NAGAR GURUPRASAD CO-OPERATIVE HOUSING SOCIETY LIMITED9 mo overdueDERAIYA REALTORS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800023015· 90.9% built· 2 complaints
- ROMELL DIVA PHASE II - 17TH TO 20TH FOOR9 mo overdueROMELL REAL ESTATE PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800014389· 82.3% built
- Hubtown Sunstone A wing9 mo overdueSunstone Developers Joint Venture · Andheri, Mumbai SuburbanP51800000183· 98.2% built· 2 complaints
- ROMELL DIVA PHASE III - 21ST TO 23RD FLOOR9 mo overdueROMELL REAL ESTATE PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800014484· 82.3% built· 1 complaint
- TRISHABH GREENS - WING B9 mo overdueRISHABH ENTERPRISES · CHEMBUR NAKA, CHEMBUR EAST, Mumbai SuburbanP51800018350· 81.8% built
- PEARL HANS RESIDENCY - G WING9 mo overdueHARI OM CONSTRUCTION · KURLA WEST, Mumbai SuburbanP51800022670· 90.9% built
- TruEarth Views9 mo overdueTRUEARTH DEVELOPERS PVT LTD · Vikhroli (East), Mumbai SuburbanP51800024328· 28.7% built· 7 complaints
- Aveza Phase 29 mo overdueTata Housing Development Company Limited · Mulund East, Opp Navghar Police Station, MHADA Colony, Mulund East,, Mumbai SuburbanP51900007740· 0% built
- TRILOK PARK9 mo overdueRAJESH TRILOKCHAND CHOPRA · KANDIVALI WEST, Mumbai SuburbanP51800033509· filed Dec 2024 → now Dec 2025· 86.4% built
- ASHAR MAPLE BIRCH9 mo overdueMs ASHAR REALTORS · VAISHALI NAGAR, Mumbai SuburbanP51800023941· 66.8% built· 1 complaint
- PEARL HANS RESIDENCY - H WING9 mo overduePEARL HANS RESIDENCY - H WING · Kurla, Mumbai SuburbanP51800022506· 90.9% built
- AURIS BUSINESS CENTRE9 mo overdueDev Pooja Builders Pvt Ltd · SHIMPOLI, BORIVALI WEST, Mumbai SuburbanP51800034380· filed Dec 2024 → now Dec 2025· 63.2% built
- Hubtown Sunstone B Wing9 mo overdueSunstone Developers Joint Venture · Andheri, Mumbai SuburbanP51800000186· 89.1% built· 1 complaint
- PRIME LEGACY9 mo overduePRIME GROUP · Dahisar, Mumbai SuburbanP51800046428· filed Dec 2024 → now Dec 2025· 81.8% built
- La Charmaine CHSL9 mo overdueJDN DEVELOPERS · Malad West, Mumbai SuburbanP51800051287· 63.6% built
- CHOICE AMBE DARSHAN9 mo overdueCHOICE DEVELOPER · PANT NAGAR GHATKOPAR (E) MUMBAI, Mumbai SuburbanP51800045613· 90.9% built
- Manisha Prime9 mo overdueMANISHA ELITE REALTY PRIVATE LIMITED · Mulund East, Mumbai SuburbanP51800047877· 89.1% built
- CHARKOP SHWETAMBARA CO OPERATIVE HOUSING SOCIETY LIMITED9 mo overdueCHARKOP SHWETAMBARA COOPERATIVE HOUSING SOCIETY LIMITED · CHARKOP KANDIVALI WEST, Mumbai SuburbanP51800029344· 90.9% built· 1 complaint
- EKTA CREST9 mo overdueEKTA HOUSING PRIVATE LIMITED · CHEMBUR, Mumbai SuburbanP51800046149· 93.9% built
- Park View9 mo overduePinak Enterprises · Mulund West, Mumbai SuburbanP51800033996· 89.1% built· 1 complaint
- Hetali Vishnu Bhavan9 mo overdueJayesh Pandya · Akurli, Kandivali East, Mumbai SuburbanP51800034561· 63% built
- Rolex SRA CHS9 mo overdueSQUARE CONSTRUCTIONS · Andheri, Mumbai SuburbanP51800011887· filed Mar 2019 → now Dec 2025· 90.9% built
- PERRY APARTMENT9 mo overduePANKAJ SHANTILAL PARIKH · ORLEM MALAD WEST MUMBAI, Mumbai SuburbanP51800077645· 90.9% built· 1 complaint
- Vindhyagiri9 mo overdueGio Properties · Pahadi Eksar and Pahadi Goregaon East, Mumbai SuburbanP51800034813· filed Feb 2025 → now Dec 2025· 71.9% built
- Sharon Rose CHSL9 mo overdueM/s JDN REALTY LLP · MALAD WEST, Mumbai SuburbanP51800033903· 84.1% built
- AXIOM CAPITOL9 mo overdueAXIOM REFAB CONSTRUCTION (INDIA) PVT LTD · Kurla, Mumbai SuburbanP51800034787· 34.1% built
- PARIJAT CHS SRA LTD9 mo overdueGloriosa Infra and Consultants Private Limited · ANDHERI WEST, Mumbai SuburbanP51800047617· 72.7% built
- Arkade Prime9 mo overdueM/s. Arkade Developers Pvt Ltd. · Andheri East, Mumbai SuburbanP51800047081· 78.6% built
- AYANA9 mo overdueARMAAN REAL ESTATE PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800032667· 90.9% built
- ACE AMBIENCE9 mo overdueAce properties · MULUND WEST, Mumbai SuburbanP51800034328· 70.9% built
- PREESHA PARADISE9 mo overdueVASTU REALTORS AND DEVELOPERS · Borivali west, Mumbai SuburbanP51800050024· 71.8% built
- Mehta Premiere-Residential9 mo overdueAsiatic Trading and Construction Company · Magathane, Mumbai SuburbanP51800033388· 99.5% built
- Gagan 459 mo overdueGagangiri Developers · Kurla, Mumbai SuburbanP51800033764· 90.9% built
- Tricity Natraj9 mo overdueTricity Realty LLP · Wadhavali, Chembur, Mumbai SuburbanP51800050160· 77% built
- SPLENDOUR9 mo overdueSUNNY DEVELOPERS & BUILDERS LLP · MULUND WEST, Mumbai SuburbanP51800045467· 63.6% built
- Kaveri Tower9 mo overdueGnanesh Virendra Lakhia · Andheri West, Mumbai SuburbanP51800051955· 77.7% built
- SAUJANYA RACHANAA9 mo overdueTERRAFERMA DEVELOPERS LLP · ANDHERI, Mumbai SuburbanP51800046295· 91.8% built
- Apollo Heights9 mo overdueJASANI REALTY PVT.LTD · Khar (West), Mumbai SuburbanP51800008154· filed Jul 2022 → now Dec 2025· 67.5% built
- MULUND GIRIRAJ CHSL9 mo overdueANON DEVELOPERS · MULUND WEST, Mumbai SuburbanP51800050695· 65.5% built
- ACE INFINIA9 mo overdueAce properties · MULUND WEST, Mumbai SuburbanP51800051062· 44.5% built
- KHANOLKAR BHAVAN CHSL - PARADISE9 mo overdueC H PATIL AND SONS LLP · GOREGAON EAST, Mumbai SuburbanP51800046246· 9.1% built
- Borivli Vasundhara CHS Ltd.9 mo overdueShree Sai Shraddha Developers · Borivali East, Mumbai SuburbanP51800006294· filed Jan 2020 → now Dec 2025· 72.7% built
- SHRADDHA ELITE9 mo overdueSHRADDHA DEVELOPERS & REALTORS · BORIVALI WEST, Mumbai SuburbanP51800045452· 90.5% built
- GLORY APARTMENTS9 mo overdueAdnani Constructions · BORIVALI WEST, Mumbai SuburbanP51800048855· filed Dec 2024 → now Dec 2025· 72.7% built
- Silver Crest9 mo overdueGold Coin Builders · Andheri, Mumbai SuburbanP51800030332· 83.3% built
- SANSKAR9 mo overdueSANSKAR DWELLINGS LLP · Andheri, Mumbai SuburbanP51800046200· 83.2% built
- MOHAMMEDIMANZIL9 mo overdueJEM DEVELOPERS AND BUILDERS · Andheri, Mumbai SuburbanP51800034489· 55.5% built
- TIARA by Swastik Empire9 mo overdueM/s SWASTIK EMPIRE DEVELOPERS LLP · PANTNAGAR, Mumbai SuburbanP51800034308· 90.4% built
- ANTARIKSH AVALON9 mo overdueANTARIKSH REALTORS PRIVATE LIMITED · PANTNAGAR GHATKOPAR EAST, Mumbai SuburbanP51800030439· 87.7% built
- KRISHNA NIWAS9 mo overdueK.PATELAND CO · Goregaon East, Mumbai SuburbanP51800033756· 90.9% built
- VRINDAVAN9 mo overdueDINESH AMRUTLAL THAKKAR · Borivali, Mumbai SuburbanP51800032747· 90.9% built
- Aayush Ayaansh9 mo overdueAayush Developers · Chembur East, Mumbai SuburbanP51800051964· 86.4% built
- Marina Enclave Wings Q and R with Kindergarten Phase - IV9 mo overdueGURUKRUPA DEVELOPERS D N NAGR PROJECT · Malvani Malad West, Mumbai SuburbanP51800032847· 71.4% built
- SHRADDHA PEARL9 mo overdueSHRADDHA LANDMARK PRIVATE LIMITED · VILLAGE HARIYALI, Mumbai SuburbanP51800046124· 76.2% built
- EPITOME9 mo overdueTHOROUGHBRED REALTY LLP · GARODIA NAGAR, Mumbai SuburbanP51800034589· 99.5% built
- Redevelopment of Gurudeo Geetanjali CHS Ltd.9 mo overdueHeritage Lifestyles LLP · Chembur, Mumbai SuburbanP51800034564· 90.9% built
- SARTHAK HEIGHTS9 mo overdueSarthak Developers · Andheri, Mumbai SuburbanP51800007127· filed Nov 2019 → now Dec 2025· 80.6% built· 16 complaints
- SHEETAL VAIBHAV9 mo overdueD.G.S TOWNSHIP PRIVATE LIMITED · KHAR WEST, Mumbai SuburbanP51800019010· filed May 2022 → now Dec 2025· 89.5% built
- VISTA9 mo overdueSARVSHUBH ENTERPRISES · MULUND EAST, Mumbai SuburbanP51800045286· 44.6% built
- SHIVBLISS9 mo overdueRUSHI BUILDER & DEVELOPER · Kurla, Mumbai SuburbanP51800011156· filed Dec 2018 → now Dec 2025· 77.3% built· 10 complaints
- RISHABRAJ PARK VISTAS9 mo overdueH RISHABRAJ REALTY · BORIVALI WEST, Mumbai SuburbanP51800033442· 59.1% built
- Kohinoor City Residential Phase 2 Block 29 mo overdueKohinoor Developers · Kurla, Mumbai SuburbanP51800003258· filed Dec 2019 → now Dec 2025· 89.1% built· 79 complaints
- SHRADDHA PRIVILEGE9 mo overdueSHRADDHA LANDMARK PRIVATE LIMITED · KANNAMWAR NAGAR VIKHROLI EAST, Mumbai SuburbanP51800033921· 82.7% built
- Construction of MIG t/s on open plot on land bearing S.No.01 pt. on CTS No. 1/3 village kopari powai9 mo overdueMHADA · Near Shipping corporation india, opposite powai lake, Mumbai SuburbanP51800077430· 98.5% built
- 72 CORP9 mo overdueSKYBLU DEVELOPERS · SAKINAKA, Mumbai SuburbanP51800021663· filed Dec 2024 → now Dec 2025· 98.8% built
- ONE MERAKI - Wing A & Wing B9 mo overdueMeraki Habitats LLP · CHEMBUR, Mumbai SuburbanP51800011606· filed Dec 2023 → now Dec 2025· 99.5% built
- Shraddha Panache9 mo overdueShraddha Landmark Private Limited · Village Hariyali, Mumbai SuburbanP51800046277· 81.8% built
- ARKADE CROWN9 mo overdueArkade Developers Private Limited · Borivali, Mumbai SuburbanP51800045342· 71.1% built
- REDEVELOPMENT OF KESAR NIKETAN CHSL9 mo overduePRANAV CONSTRUCTIONS LIMITED · BORIVALI EAST, Mumbai SuburbanP51800046669· 91.8% built
- EKAM7 mo overdueA P PROPERTIES · Andheri, Mumbai SuburbanP51800002628· filed Mar 2025 → now Mar 2026· 72.6% built
- MAHESHWAR KRIPA CHSL7 mo overdueMAHESHWAR KRIPA C0-OPERATIVE HOUSING SOCIETY LIMITED · GHATKOPAR EAST, Mumbai SuburbanP51800033398· filed Mar 2025 → now Mar 2026· 81.8% built
- JEEVAN SHOBHA CHSL AND BHANSALI CHSL6 mo overdueHIRANI REALTORS LLP · BORIVALI EAST, Mumbai SuburbanP51800047979· 81.8% built
- ZEE ASHTAVINAYAK6 mo overdueZEE LAND DEVELOPMENT SERVICES · ANDHERI WEST, Mumbai SuburbanP51800045964· 90.9% built· 2 complaints
- ACHARYA ASHRAM SAHAKARI GRIHA RACHANA SANSTHA MARYADIT6 mo overdueVASTU DARSHAN DEVELOPERS LLP · OPP DON BOSCO SCHOOL, VAZIRA, BORIVALI WEST, Mumbai SuburbanP51800027379· filed Oct 2023 → now Mar 2026· 90.9% built
- West Winds6 mo overdueGhatkopar Neelkanth Kunj CHSL · GHATKOPAR EAST, Mumbai SuburbanP51800045813· 75% built
- Rose Garden6 mo overdueVinayaka Realtors and Developers · Andheri, Mumbai SuburbanP51800022587· filed Dec 2023 → now Mar 2026· 90.9% built
- Mam Trilok6 mo overdueLEELA ENTERPRISES · Kurla, Mumbai SuburbanP51800011162· filed Sept 2020 → now Mar 2026· 90.9% built
- SAYBA ELEGANT6 mo overdueSAYBA ELEGANT · Kurla, Mumbai SuburbanP51800051973· 90.9% built
- SHAMIKH BUILDING6 mo overdueTAMOS ASSOCIATES · ANDHERI EAST, Mumbai SuburbanP51800048394· 82.3% built
- Navratna6 mo overdueOm Navratna Enterprises LLP · Vileparle, Mumbai SuburbanP51800050281· 90.9% built
- Smriti6 mo overdueMahesh Balkrishna Sambhus · GOREGAON EAST, Mumbai SuburbanP51800050592· 81.8% built
- Horizon Heights6 mo overdueI.R.Developers LLP · Sher-E-Punjab Colony, Andheri East, Mumbai SuburbanP51800050202· 0% built· 1 complaint
- Merushikhar6 mo overdueSavvy Infrastructure Private Limited · Mogra, Andheri East, Mumbai SuburbanP51800049155· 55% built· 1 complaint
- Kalpataru Magnus6 mo overdueKalpataru Properties Pvt. Ltd. · Andheri, Mumbai SuburbanP51800004029· filed Jun 2024 → now Mar 2026· 83.9% built· 64 complaints
- JITEN CHS6 mo overdueM/s Keytech · ANDHERI WEST, Mumbai SuburbanP51800032184· filed Dec 2024 → now Mar 2026· 99.8% built
- Pant Nagar Gulmohar Chs Ltd6 mo overduePragati Developers · Ghatkopar, Mumbai, Mumbai SuburbanP51800026241· filed Dec 2024 → now Mar 2026· 81.8% built
- PHOENIX6 mo overdueNEMINATH CORP · Borivali, Mumbai SuburbanP51800029237· filed Mar 2025 → now Mar 2026· 90.9% built
- BORIVALI SAGAR CHSL6 mo overdueMAHAVIR INFRAPROJECTS · BORIVALI WEST, Mumbai SuburbanP51800052089· 60.5% built
- WEST AVENUE6 mo overdueM/s Dhabalia Enterprises · Borivali (West), Mumbai SuburbanP51800051576· 90.9% built
- MANASAROVAR6 mo overdueHARASIDDH PROJECTS · Kandivali (W), Mumbai SuburbanP51800078732· 98.2% built
- DEM ICON6 mo overdueDEM Developers LLP · Charkop, Mumbai SuburbanP51800050731· 86.6% built
- PAREKH RADIANCE6 mo overduePAREKH BUILDPROJECTS PRIVATE LIMITED · KANDIVALI WEST, Mumbai SuburbanP51800046909· 81.8% built
- saroj sadan CHSL6 mo overduePritesh Damji Savla · Kurar, Mumbai SuburbanP51800012908· filed Dec 2018 → now Apr 2026· 90.9% built· 1 complaint
- KUSH AVENUEE5 mo overdueKUSH AVENUEE · Kurla, Mumbai SuburbanP51800052873· 68.2% built
- NAVRANG NAVKAR5 mo overdueOXFORD NAVRANG REALTY LLP · Borivali, Mumbai SuburbanP51800047342· filed Oct 2025 → now Apr 2026· 81.8% built
- YASHOMATI CHSL5 mo overdueSAMRAT ENTERPRISE · Kurla, Mumbai SuburbanP51800023057· filed Dec 2022 → now Apr 2026· 99.1% built
- HIRANI VILLA5 mo overdueAMI INFRA PROJECTS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800026708· filed Mar 2023 → now May 2026· 90.9% built· 1 complaint
- Garnet Paladium5 mo overdueGarnet Construction Limited · Andheri, Mumbai SuburbanP51800005369· filed Dec 2018 → now May 2026· 90.9% built· 2 complaints
- Sigma Pearl5 mo overdueAshapura Shelters Private Limited · Andheri, Mumbai SuburbanP51800050197· filed May 2025 → now May 2026· 90.9% built
- Chandraprabha4 mo overdueManisha Supreme Realty LLP · Kurla, Mumbai SuburbanP51800048875· 87.3% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.