Delayed projects in Mumbai Suburban
1,523 MahaRERA-registered projects in Mumbai Suburban are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 6 of 8
- Redevelopment of JUHU ANKUR CHS LTD2.8 yr overdueKDI HOLDINGS PVT. LTD. · Andheri, Mumbai SuburbanP51800004899· 90.9% built· 2 complaints
- ASHOK ODYSSEY - B WING2.8 yr overdueSANYAM REALTORS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800004418· 90.9% built· 5 complaints
- VASANT OASIS ZINNIA BLDG 172.8 yr overdueNEEPA REAL ESTATES PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800000980· 40.9% built· 7 complaints
- SRISHTI OASIS PH 2 WING B SANDS2.8 yr overdueSHIV KRUPA ENTERPRISE · Kurla, Mumbai SuburbanP51800005548· filed Dec 2022 → now Dec 2023· 90.9% built· 1 complaint
- PEARL PLATINUM2.8 yr overdueCHANDIWALA ENTERPRISES · Andheri, Mumbai SuburbanP51800004462· 42.7% built
- Kalpataru Woodsville2.8 yr overdueKalpataru Plus Sharyans · Kurla, Mumbai SuburbanP51800001512· 86.8% built· 1 complaint
- PEARL MAJESTIC2.8 yr overdueCHANDIWALA ENTERPRISES · Andheri, Mumbai SuburbanP51800015348· 90.9% built
- ARKADE EARTH - GARDENIA2.8 yr overdueArkade Developers Private Limited · Kanjurmarg East, Mumbai SuburbanP51800010074· 88.5% built
- SHATRUNJAY GIRIRAJ2.8 yr overduePRAMUKH REALTORS · Kurla, Mumbai SuburbanP51800009451· filed Dec 2022 → now Dec 2023· 82.9% built
- NAV-VISHWADHAM CHSL2.8 yr overdueWOLFPACK HOUSING CORPORATION · Andheri, Mumbai SuburbanP51800001669· 90.9% built
- ACROPOLIS2.8 yr overdueVORA ASSOCIATES · BORIVALI WEST, Mumbai SuburbanP51800004939· 90.5% built
- Whista 1st Street2.8 yr overdueNarang & Mahaveer Developers LLP · Andheri, Mumbai SuburbanP51800013101· 35.7% built
- Madhu Vasant CHS Ltd.2.8 yr overdueAmal Realtors Private Limited · Andheri, Mumbai SuburbanP51800000264· 78.2% built
- Golden Heights2.8 yr overdueGold Coin Builders · Andheri, Mumbai SuburbanP51800001552· 90.9% built
- Kalpataru Radiance C2.8 yr overdueKeyana Estate LLP · Borivali, Mumbai SuburbanP51800000482· filed Jun 2022 → now Dec 2023· 97% built· 37 complaints
- Kalpataru Radiance A2.8 yr overdueKeyana Estate LLP · Borivali, Mumbai SuburbanP51800000591· filed Jun 2022 → now Dec 2023· 98.3% built· 27 complaints
- Emerald Isle - T152.8 yr overdueLarsen & Toubro Ltd. (Realty Division) · Kurla, Mumbai SuburbanP51800013214· 90.2% built· 5 complaints
- Emerald Isle - T102.8 yr overdueLarsen & Toubro Ltd. (Realty Division) · Kurla, Mumbai SuburbanP51800013052· 72.5% built· 4 complaints
- PRATHMESH DARSHAN2.8 yr overdueJAYDEEP MAHALAXMI CONSTRUCTION · Kurla, Mumbai SuburbanP51800009248· 72.2% built· 4 complaints
- AURIS SERENITY TOWER 22.8 yr overdueTRANSCON-SHETH CREATORS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800001413· 72.7% built· 18 complaints
- TERRAFORM DWARKA2.8 yr overdueMoney Magnum Nest Pvt Ltd · Kurla, Mumbai SuburbanP51800002718· 91.2% built· 2 complaints
- SHUBH AANGAN WING B2.8 yr overdueG D REALTORS PVT LTD · BHANDUP EAST, Mumbai SuburbanP51800029568· 90.9% built
- VARDHMAN CASTLE PHASE I2.8 yr overdueVENUS DEVELOPMENT CORPORATION · SANTACRUZ WEST, Mumbai SuburbanP51800033033· 0.2% built
- SEYCHELLES2.8 yr overdueSHUBHAM ENTERPRISES · Andheri, Mumbai SuburbanP51800033314· 87.5% built
- Rite Civis2.8 yr overdueYashodanand Developers · Bhandup West, Mumbai SuburbanP51800030301· 42.3% built· 2 complaints
- MARY VILLA2.8 yr overdueH&D PROJECTS · Borivali, Mumbai SuburbanP51800031597· 81.8% built
- SWASTIK ELEGANCE2.8 yr overdueSwastik Realtors · Swastik park Chembur, Mumbai SuburbanP51800031928· 90.9% built
- STERLING COURT WING D2.8 yr overdueAPRAULIC CONSTRUCTION INVESTMENT AND FINANCE PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800002160· filed Sept 2020 → now Dec 2023· 90.9% built
- SWASTIK PHASE 12.8 yr overdueDISHA CONSTRUCTION · Andheri, Mumbai SuburbanP51800002197· filed Dec 2019 → now Dec 2023· 49.2% built· 1 complaint
- Sunrise Orlem 2B Phase 32.8 yr overdueDhaval Housing AOP · Borivali, Mumbai SuburbanP51800006843· filed Jun 2021 → now Dec 2023· 83.6% built· 1 complaint
- AURA APARTMENTS - PHASE 2 11TH FLOOR2.8 yr overdueBHOLENATH DEVELOPERS LTD. · GHATLA, Mumbai SuburbanP51800009179· filed Oct 2018 → now Dec 2023· 54.5% built
- KANDIVALI BASANT BAHAR2.8 yr overdueWESTIN SANKALP DEVELOPERS · KANDIVALI WEST, MUMBAI, Mumbai SuburbanP51800031940· 40% built
- Sahil Exotica2.8 yr overdueBOMBAY CONSTRUCTION & INFRAPROJECTS PVT LTD · Andheri, Mumbai SuburbanP51800003978· filed Jun 2019 → now Dec 2023· 87.3% built· 1 complaint
- MDM Zion2.8 yr overdueMDM REALTY LLP · Andheri West, Mumbai SuburbanP51800029740· 90.9% built
- Suprabha-Shivam Lifestyle2.8 yr overdueShivam Lifestyle · Chembur, Mumbai SuburbanP51800029652· 90.9% built
- PRIME GROUP PROJECT GRAND SLAM2.8 yr overduePRIME GROUP · Dahisar, Mumbai SuburbanP51800034404· 90.9% built
- ARIHANT ENCLAVE2.8 yr overdueM/s Arihant Enterprise · Andheri, Mumbai SuburbanP51800030594· 23.6% built
- ASHWA PLATINUM2.8 yr overdueASHWA PLATINUM · Kurla, Mumbai SuburbanP51800005636· filed Nov 2020 → now Dec 2023· 84.1% built· 10 complaints
- Athena2.7 yr overdueM/s. Sahajanand Developers · Goregaon West, Mumbai SuburbanP51800003330· filed Mar 2020 → now Jan 2024· 62.7% built· 10 complaints
- CITI CHALET2.7 yr overdueBASONS CONSTRUCTIONS · Andheri, Mumbai SuburbanP51800046606· 90.9% built
- Puneet Sanjivani Phase 3 Floor 21 to Floor 232.7 yr overduePuneet Developers · Kurla, Mumbai SuburbanP51800017800· 90.9% built
- Puneet Sanjivani Phase 2 Floor 17 to Floor 202.7 yr overduePuneet Developers · Kurla, Mumbai SuburbanP51800017842· 90.9% built
- Laxmi Sanskruti2.7 yr overdueLAXMIDEVI DEVELOPERS · Jawahar Nagar, Goregaon West, Mumbai SuburbanP51800034219· 52.7% built
- Redevelopment of Om Divya Apartments Co-operative Housing Society Limited2.6 yr overdueM/s Shanti Developers · Borivali, Mumbai SuburbanP51800005768· filed Feb 2021 → now Feb 2024· 90.5% built
- Swashraya Andheri CHS Ltd2.6 yr overdueDEM CONSTRUCTIONS LLP · nr Juhu Lane, Mumbai SuburbanP51800030781· 67.4% built
- KHAR HIRA PREMISES CO OP SOCIETY LTD2.6 yr overdueL NAGPAL DEVELOPERS · Andheri, Mumbai SuburbanP51800031276· 78.2% built
- RISHABRAJ VICINIA2.6 yr overdueH RISHABRAJ DEVELOPERS · GHATKOPAR EAST, Mumbai SuburbanP51800026330· 90.9% built
- GOREGAON RASIK CO OP HSG SOCIETY LTD2.6 yr overdueAAKAR REAL ESTATE DEVELOPERS · GOREGAON WEST, Mumbai SuburbanP51800007636· filed Mar 2019 → now Mar 2024· 90.9% built
- CASA RAMIRO2.6 yr overduePRESCOTT HOUSING LLP · Andheri, Mumbai SuburbanP51800033552· 90.9% built
- VISHNU BHASKAR CHS LTD2.6 yr overdueSUDHANSHU INFRASTRUCTURES PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800015748· filed Sept 2019 → now Mar 2024· 90.9% built· 1 complaint
- AIM Residency Phase I2.5 yr overdueA M ENTERPRISES · Andheri, Mumbai SuburbanP51800015762· 90% built
- Makarani Pada Phase 12.5 yr overdueK D Builders · Borivali, Mumbai SuburbanP51800008606· 24.2% built· 1 complaint
- Maruti Bhuvan2.5 yr overdueSuresh Prabhushankar Sharma · Mogra, Mumbai SuburbanP51800005335· filed Mar 2019 → now Mar 2024· 72.7% built
- MARUTI2.5 yr overdueINVENTION REALTORS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800012405· 86.8% built
- AURUS2.5 yr overdueKINGSTAY REAL ESTATE PRIVATE LIMITED · MUMBAI, Mumbai SuburbanP51800015024· 90.9% built
- THE METROPOLE2.5 yr overdueRaveshia Realtors · GHATKOPAR, Mumbai SuburbanP51900026208· 81.4% built· 14 complaints
- REDEVELOPMENT OF BORIVALI SHIVDARSHAN CHSL2.5 yr overduePRANAV CONSTRUCTIONS LIMITED · BORIVALI WEST MUMBAI, Mumbai SuburbanP51800026908· 86.7% built
- MAYA HARMONY2.5 yr overdueMAYA DEVELOPERS · Kurla, Mumbai SuburbanP51800009358· filed Nov 2020 → now Mar 2024· 74.1% built
- LABH SAMARTH HEIGHT2.5 yr overdueM.V. LABH ASSOCIATES · Andheri, Mumbai SuburbanP51800011676· filed Dec 2018 → now Mar 2024· 90.9% built
- Prem Zephyr2.5 yr overdueAshwin Enterprises · Mulund West, Mumbai SuburbanP51800029011· 90.9% built
- Motivilla2.5 yr overdueAAKAR SHIV INFRA VENTURE · Goregaon West, Mumbai SuburbanP51800033793· 90.9% built
- Vidya Nidhi2.5 yr overdueLaxmi Aakar Realty · Goregaon West, Mumbai SuburbanP51800033588· 90.9% built
- ACCORD CLASSIC2.5 yr overdueSUYOJANA IMPEX PVT. LTD · Borivali, Mumbai SuburbanP51800007765· filed Mar 2022 → now Mar 2024· 81.8% built
- REDEVELOPMENT OF SILVERENE CHSL2.5 yr overduePRANAV CONSTRUCTIONS LIMITED · MUMBAI, Mumbai SuburbanP51800031840· 90.9% built
- ROMELL CORNERSTONE2.5 yr overdueROMELL REAL ESTATE PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800032709· 90.9% built
- SHREE SIDDHI BLDG NO 692.5 yr overdueHIRANIMANTHAN BUILDERS AND DEVELOPERS · Kurla, Mumbai SuburbanP51800003413· filed Mar 2020 → now Mar 2024· 90.9% built
- THE JAMBLI GALLI CHS LTD2.5 yr overdueMAHAVIR CORPORATIONS · BORIVALI WEST, Mumbai SuburbanP51800045335· 81.8% built
- PREETI SANGAM CHS2.5 yr overdueKANDIVALI PRITI SANGAM CO-OP HOS SOC LTD · Borivali, Mumbai SuburbanP51800011235· filed Jul 2022 → now Mar 2024· 30.2% built· 3 complaints
- MAYAANK HEIGHTS2.5 yr overdueN. K. LIFESTYLE · Borivali, Mumbai SuburbanP51800030223· 90.9% built
- KRUPA2.5 yr overdueAASAMANTA REALTY · GOREGAON EAST, Mumbai SuburbanP51800032389· 90.9% built
- Shikhar2.5 yr overduePTR Universal · Andheri, Mumbai SuburbanP51800020732· 97.3% built
- SHEETAL DHARMARAJ2.5 yr overdueD.G.LAND DEVELOPERS PRIVATE LIMITED · MARVE ROAD, Mumbai SuburbanP51800027915· 0% built· 1 complaint
- SURYADARSHAN CHS LTD2.5 yr overdueH&D PROJECTS · Borivali, Mumbai SuburbanP51800046756· 70.5% built
- KUKREJA GARDENS WING A2.5 yr overdueTOLARAM AND CO · BHANDUP WEST, Mumbai SuburbanP51800020817· 73.3% built· 1 complaint
- KAMGAR PANCH GANGA SRAPHASE 1 CHSPROPOSED2.5 yr overduePAYAL J SHAH · Borivali, Mumbai SuburbanP51800008400· filed Aug 2018 → now Apr 2024· 99.1% built· 1 complaint
- EKTA VERVE2.5 yr overdueEKTA WORLD PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800021089· 87% built· 3 complaints
- KRISHNA KOYNA2.4 yr overdueJKD ENGINEERS AND INFRASTRUCTURE PRIVATE LIMITED · SHIMPOLI, Mumbai SuburbanP51800027749· 20.6% built
- Bhagwati Ashish2.4 yr overduePritesh Damji Savla · Andheri, Mumbai SuburbanP51800010515· filed Nov 2020 → now May 2024· 88.6% built· 4 complaints
- Dreamsville2.4 yr overdueParadiso Builders Private Limited · Borivali, Mumbai SuburbanP51800046670· 81.8% built
- RISHABRAJ SURAJ2.4 yr overdueH RISHABRAJ REALTY · BORIVALI WEST, Mumbai SuburbanP51800029277· 90.9% built
- EXPRESS ZONE MALL2.3 yr overdueCELLO SONAL CONSTRUCTION · Andheri, Mumbai SuburbanP51800002490· 81.8% built· 3 complaints
- ACE AVENUE2.3 yr overdueAce properties · MULUND WEST, Mumbai SuburbanP51800033494· 90.9% built
- Oshi2.3 yr overdueSahyog Homes Limited · Oshiwara, Mumbai SuburbanP51800002965· filed Dec 2022 → now Jun 2024· 92.7% built· 8 complaints
- Kanchan Sheila CHS2.3 yr overdueYug Developers · Mulund West, Mumbai SuburbanP51800033242· filed Mar 2024 → now Jun 2024· 64.6% built
- EXPRESS ZONE B WING2.3 yr overdueCELLO SONAL CONSTRUCTION · Andheri, Mumbai SuburbanP51800005634· 54.5% built
- DAHISAR SHIVANGAN WING A2.3 yr overdueYASH ENTERPRISES · DAHISAR EAST, Mumbai SuburbanP51800028519· 40% built· 3 complaints
- 127 UPPER EAST2.3 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Andheri, Mumbai SuburbanP51800000454· filed Dec 2019 → now Jun 2024· 56.4% built· 1 complaint
- Ajit Mulund CHS2.3 yr overdueYug Developers · Mulund, Mumbai SuburbanP51800032940· filed Mar 2024 → now Jun 2024· 64% built
- Skyline viha Wing B2.3 yr overdueAnkit Overseas · Kurla, Mumbai SuburbanP51800002495· filed Dec 2018 → now Jun 2024· 82.6% built· 1 complaint
- GOREGAON SUKHNIWAS CO-OPERATIVE HOUSING SOCIETY LIMITED2.3 yr overdueDILIP DOSHI · Borivali, Mumbai SuburbanP51800028730· 91.8% built
- Arkade Serene2.3 yr overdueArkade Developers Private Limited · Sunder Nagar Malad West, Mumbai SuburbanP51800029961· 74.5% built
- BALI LAXMI2.3 yr overdueBALI SPACES LLP · Borivali, Mumbai SuburbanP51800027818· 90.9% built
- SOSAR SOLITAIRE2.3 yr overdueSOSAR ENTERPRISES · Andheri, Mumbai SuburbanP51800025925· 81.8% built
- VIRESHWAR DARSHAN CHS LTD2.3 yr overdueVIRESHWAR DARSHAN CHS LTD · VILE PARLE EAST, Mumbai SuburbanP51800049312· 70% built
- NIDHAAN CLOVER - A2.3 yr overdueNIDHAAN BUILDCON PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800019932· 86.4% built
- OMKAR CHS LTD2.3 yr overdueLAKSHMI BUILDERS AND DEVELOPERS · Andheri, Mumbai SuburbanP51800003558· filed Jul 2023 → now Jun 2024· 90.9% built
- NL TAKSASILA2.3 yr overdueNAHALCHAND LALOOCHAND PVT. LTD. · KANDIVALI (WEST), Mumbai SuburbanP51800025643· 90.9% built
- Supreme Evana2.3 yr overdueSupreme Mega Constructions LLP · Bandra West, Mumbai SuburbanP51800033931· 90% built
- REDEVELOPMENT OF KHATRI APARTMENTS COOPERATIVE HOUSING SOCIETY LIMITED2.3 yr overdueSRP REALTORS PRIVAYE LIMITED · Borivali, Mumbai SuburbanP51800009333· filed Dec 2019 → now Jun 2024· 90.9% built
- RAJAN DINAKAR PHATAK AND OTHERS2.3 yr overdueWESTIN SANKALP DEVELOPERS · Borivali, Mumbai SuburbanP51800028236· 89.1% built
- Bhoomi Samarth B Wing2.3 yr overdueSamarth Erectors & Developers · Borivali, Mumbai SuburbanP51800026289· 50.9% built
- SAI SOLITARE2.3 yr overdueSamrudhi Associates · Kurla, Mumbai SuburbanP51800006560· filed Jun 2021 → now Jun 2024· 89.5% built· 1 complaint
- Saraswati Sadan2.3 yr overdueLAKSHMI BUILDERS AND DEVELOPERS · Vile Parle East, Mumbai SuburbanP51800026655· 90.9% built
- Acharat Baug2.3 yr overdueAnkur Premises Developers LLP · Andheri, Mumbai SuburbanP51800034682· 39.1% built
- Prem Belaire2.3 yr overdueM/s Aryan Infra · Kurla, Mumbai SuburbanP51800003675· filed Feb 2019 → now Jul 2024· 90.8% built· 1 complaint
- DEVCHHAYA2.3 yr overdueHARSHAL ENTERPRISES · RAWALPADA DAHISAR EAST, Mumbai SuburbanP51800015406· filed Mar 2024 → now Jul 2024· 90.9% built
- SHYAM KUNJ2.2 yr overdueBASONS CONSTRUCTIONS · Andheri, Mumbai SuburbanP51800046209· 90.9% built
- Altavista - Phase 12.2 yr overdueSPENTA ENCLAVE PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800001050· filed Dec 2019 → now Jul 2024· 90.9% built· 18 complaints
- AMARDEEP ALLIANCE2.2 yr overdueALLIANCE CITY DEVELOPERS REALTORS PVT LTD · St. Pius Church Mulund West, Mumbai SuburbanP51800024225· 90.9% built· 2 complaints
- NIDHI TOWERS2.2 yr overdueRAJAN KUMAR MANCHANDA · Andheri, Mumbai SuburbanP51800008893· filed Jul 2022 → now Jul 2024· 90.9% built· 3 complaints
- PEARL RESIDENCY - WING-B, RESIDENTIAL PHASE - III2.2 yr overdueGIRIRAJ ENTERPRISES · Andheri, Mumbai SuburbanP51800006592· 52.7% built
- Shree Swami Samarth Krupa2.2 yr overdueShoreline Builders Pvt Ltd · Kurla, Mumbai SuburbanP51800018673· 19.8% built· 3 complaints
- THE VILE PARLE MEGHALAYA CHSL2.1 yr overdueDHRUV INFRASTRUCTURE · VILE PARLE EAST, Mumbai SuburbanP51800033919· 90.9% built
- RISHABRAJ SUJAI2.1 yr overdueRISHABRAJ ESTATE DEVELOPERS PVT LTD · MALAD EAST, Mumbai SuburbanP51800031075· 90.9% built
- Chaitanya Anand - Lunkhod CHSL2.1 yr overdueChaitanya Developers · Andheri West, Mumbai SuburbanP51800029553· filed May 2024 → now Aug 2024· 90.9% built
- RISHABRAJ RAMESHWAR2.1 yr overdueH RISHABRAJ REALTY · Borivali, Mumbai SuburbanP51800030723· 90.9% built
- OM TRIMURTI2.1 yr overdueJE AND VEE INFRASTRUCTURE · OPP OBEROI MALL, Mumbai SuburbanP51800020394· filed Dec 2023 → now Aug 2024· 85.5% built· 1 complaint
- 52 PARK AVENUE2.1 yr overdueDAN KUTIR CHSL · Andheri, Mumbai SuburbanP51800032136· 90.9% built
- RISHABRAJ AGNEL2.1 yr overdueRISHABRAJ ESTATE DEVELOPERS PVT LTD · Borivali, Mumbai SuburbanP51800030530· 90.9% built
- SANTACRUZ ANURAG MANDIR CHSL2.1 yr overdueS M CONSTRUCTIONS · SANTACRUZ, Mumbai SuburbanP51800050095· 90.9% built· 1 complaint
- Supreme Elenor2.1 yr overdueSupreme Mega Constructions LLP · Kurla, Mumbai SuburbanP51800030270· 70.9% built
- ACE FLORENCE2.1 yr overdueAce properties · MULUND WEST, Mumbai SuburbanP51800034518· 90.9% built
- IZARRA2.0 yr overdueORNO INFRAPROJECTS PVT LTD · Andheri, Mumbai SuburbanP51800018888· filed Dec 2022 → now Sept 2024· 90.9% built· 2 complaints
- CHANDAN HIRA2.0 yr overdueBALI SHELTERS LLP · GOREGAON WEST, Mumbai SuburbanP51800033253· 90.9% built
- School View Shreyas CHS Ltd2.0 yr overdueMAJESTIC ROYALE DEVELOPERS · MUMBAI, Mumbai SuburbanP51800046219· 54.5% built
- AIM Avenue2.0 yr overdueAIM REALTORS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800028763· 77.7% built
- REDEVELOPMENT OF POPULAR TERRACE CHSL2.0 yr overduePRANAV CONSTRUCTIONS LIMITED · BORIVALI WEST MUMBAI, Mumbai SuburbanP51800029351· 90.9% built
- REDEVELOPMENT OF GALA APARTMENTS CHSL2.0 yr overduePRANAV CONSTRUCTIONS LIMITED · MALAD EAST, Mumbai SuburbanP51800029415· 90.9% built· 1 complaint
- EMPIRE TOWERS2.0 yr overdueSahakar Ventures · Borivali, Mumbai SuburbanP51800026306· 87.3% built
- Avenue Park - I2.0 yr overdueCB Enterprises · pathanwadi, Mumbai SuburbanP51800005425· filed Jun 2022 → now Sept 2024· 73.5% built· 1 complaint
- PARLE NIMESH CO-OP. HSG. SOC. LTD.2.0 yr overdueCHINTAMANI COMMERCIAL VENTURES · VILE PARLE EAST, Mumbai SuburbanP51800030964· 90% built
- REDEVELOPMENT OF TIARA CHSL2.0 yr overduePRANAV CONSTRUCTIONS LIMITED · MALAD WEST, Mumbai SuburbanP51800034818· 90.9% built
- PARLASHRAY CHSL2.0 yr overdueSai Ganesh Properties and Holdings LLP · VILE PARLE EAST, Mumbai SuburbanP51800033078· filed Mar 2024 → now Oct 2024· 90.9% built
- SAMARA2.0 yr overdueCharisma Builders Ltd · Chembur, Mumbai, Mumbai SuburbanP51800020854· filed Mar 2024 → now Oct 2024· 81.8% built
- CRYSTAL PARADISE RESIDENCES1.9 yr overduePrithvi Sthapti LLP · Andheri, Mumbai SuburbanP51800015472· filed Jun 2024 → now Nov 2024· 72.3% built
- Gagan 1391.9 yr overdueGagangiri Constructions · Kurla, Mumbai SuburbanP51800029662· 90.9% built
- SWANAND BLDG NO 331.9 yr overdueHIRANIMANTHAN BUILDERS AND DEVELOPERS · Kurla, Mumbai SuburbanP51800004914· filed Dec 2019 → now Nov 2024· 90.9% built
- HERITAGE HOUSE1.8 yr overdueGreen Tree Lifescapes LLP · Andheri, Mumbai SuburbanP51800033917· 0.9% built
- CELESTIAL HEIGHTS1.8 yr overdueAYYAPPA DEVELOPERS PVT. LTD. · Borivali, Mumbai SuburbanP51800005812· filed Jan 2021 → now Dec 2024· 46.4% built· 16 complaints
- SILVER SCAPE/SILVER ENCLAVE1.8 yr overdueMalde Properties LLP · MULUND WEST, Mumbai SuburbanP51800009210· filed Dec 2023 → now Dec 2024· 45.5% built
- KINGS PRIDE1.8 yr overdueNilesh Laxmikant Kudalkar · GOVANDI EAST, MUMBAI, Mumbai SuburbanP51800023958· filed Dec 2023 → now Dec 2024· 82.5% built
- Mulund Om CHS Ltd1.8 yr overdueSUNRISE HOUSING · Nahur Village Mulund - West, Mumbai SuburbanP51800022406· 81.8% built
- DOSHI TARACHAND VALAMJI VANIK NIWAS1.8 yr overdueSHREE CUTCHI DASHA SHRIMALI VANIK GNYATI · Chembur, Mumbai SuburbanP51800045888· filed Dec 2023 → now Dec 2024· 90.9% built
- Kalpataru Radiance B1.8 yr overdueKeyana Estate LLP · Borivali, Mumbai SuburbanP51800000810· filed Jun 2022 → now Dec 2024· 95.5% built· 33 complaints
- CELESTIAL1.8 yr overdueSU SHARDA EDIFICE LLP · Kurla, Mumbai SuburbanP51800001768· 99.7% built· 3 complaints
- Hubtown Seasons - Daintree1.8 yr overdueJoynest Premises Private Limited · Kurla, Mumbai SuburbanP51800002373· 81.8% built· 7 complaints
- NISHCHAY WING F1.8 yr overdueSHREERAJ DEVELOPER LLP · Borivali, Mumbai SuburbanP51800009954· 87.7% built· 1 complaint
- Godrej RKS1.8 yr overdueGodrej Projects Development Limited · Chembur, Mumbai SuburbanP51800023915· 78.4% built· 8 complaints
- SWASTIK PEARL1.8 yr overdueSUVASYA BUILDERS AND DEVELOPERS LLP · Kurla, Mumbai SuburbanP51800024910· 75.5% built
- Puneet Sanjivani Phase 1 Floor 0 to Floor 161.8 yr overduePuneet Developers · Kurla, Mumbai SuburbanP51800015397· 90.9% built
- Jaliyan Heights Goregaon1.8 yr overdueJaliyan Developer · Goregaon East, Mumbai SuburbanP51800012880· filed Dec 2022 → now Dec 2024· 84.5% built· 2 complaints
- SAIKRUPA CHSL1.8 yr overdueC H PATIL AND SONS LLP · Near Eksar Talao, Mumbai SuburbanP51800011410· 69.5% built
- Neelkanth Jyot CHS LTD.1.8 yr overdueSchemaatics · Ghatkopar, Mumbai SuburbanP51800022558· 41.4% built
- Hubtown Seasons - Ecuador Cloud1.8 yr overdueJoynest Premises Private Limited · Chembur East, Mumbai SuburbanP51800004432· 81.8% built
- Supreme Headquarter Bandra1.8 yr overdueSupreme Heights LLP · Near Link Square Mall, Mumbai SuburbanP51800025298· 90% built
- SHUBHAM AURA1.8 yr overdueAVVAD REALTTY LLP · Kurla, Mumbai SuburbanP51800021965· 90.9% built
- AARADHYA EASTWIND1.8 yr overdueMICL DEVELOPERS LLP · Kurla, Mumbai SuburbanP51800020183· 90.9% built
- VASUNDHARA HEIGHTS1.8 yr overdueVASUNDHARA MRK PROPERTIES PVT LTD · MULUND WEST, Mumbai SuburbanP51800019256· 90.9% built
- Sorrento1.8 yr overdueHGP Community Pvt. Ltd. · Kurla, Mumbai SuburbanP51800021706· 90.9% built
- NISHCHAY - WING E1.8 yr overdueSHREERAJ DEVELOPER LLP · REVENUE MAJUE DAHISAR, Mumbai SuburbanP51800015985· 89.5% built
- PEARL OASIS1.8 yr overdueBAHIST ENTERPRISES PVT LTD · PATHANWADI, Mumbai SuburbanP51800016403· 79.5% built
- LA PRENDA1.8 yr overdueD M LIFESPACES · Andheri, Mumbai SuburbanP51800022314· 88.6% built
- Mayfair The View1.8 yr overdueMAYFAIR HOUSING · Kurla, Mumbai SuburbanP51800020140· 82.6% built
- Lotus Residency1.8 yr overdueLotus Logistics and Developers pvt ltd · Mumbai, Mumbai SuburbanP51800006322· filed Jun 2021 → now Dec 2024· 80.9% built· 2 complaints
- ADVENT NEEL1.8 yr overdueREGENT ASSOCIATES · Andheri, Mumbai SuburbanP51800032332· 78.9% built
- Pragati Revanta1.8 yr overduePragati Enterprises · Ghatkopar, Mumbai SuburbanP51800032025· 90.9% built
- PUSHP-VATIKA1.8 yr overdueANISH SHAH & MANISH SHAH · Andheri, Mumbai SuburbanP51800031796· 85% built
- MATRUCHHAYA1.8 yr overdueM/s. Rishabraj Balaji Infra · BORIVALI EAST, Mumbai SuburbanP51800034195· 0% built· 1 complaint
- SHANTI HEIGHTS1.8 yr overdueSUNNY DEVELOPERS · MULUND WEST, Mumbai SuburbanP51800032643· 97.7% built
- Shree Rajrajeshwari Chhaya Chs Ltd.1.8 yr overdueSUNIL DINKAR SHINDE · Bhandup East, Mumbai SuburbanP51800032685· 90.9% built
- Rajshree Eleven East1.8 yr overduePanchsheel 1 Upgrade LLP · Kurla, Mumbai SuburbanP51800030117· 85.4% built
- RISHABRAJ GARDENIA1.8 yr overdueH RISHABRAJ REALTY · Andheri, Mumbai SuburbanP51800035106· 89.1% built
- RISHABRAJ VILLA STELLA1.8 yr overdueH RISHABRAJ REALTY · Borivali, Mumbai SuburbanP51800034790· 72.7% built
- RENDEZVOUS PREMISES CO-OP SOCIETY LTD1.8 yr overdueJGB BUILDERS LLP (CA to Owner) · Mumbai, Mumbai SuburbanP51800033783· 95.5% built
- Laxmi Kunj1.8 yr overdueGeeCee Ventures Limited · Andheri, Mumbai SuburbanP51800046721· 88.2% built
- Bileshwar Darshan CHSL1.8 yr overdueM/s. Desai Residency Private Limited · Vile Parle East, Mumbai SuburbanP51800047797· 90.9% built
- SEQUOIA1.8 yr overdueAUM PRIMA LLP · Andheri, Mumbai SuburbanP51800032970· 56.8% built
- ALAG ARANYA1.8 yr overdueALAG AARCHIE LLP · Panth Nagar, Mumbai SuburbanP51800032034· 90.9% built
- BORIVALI SHALIMAR CO-OPERATIVE HOUSING SOCIETY LIMITED1.8 yr overdueTASMAI SHREE · Borivali, Mumbai SuburbanP51800045551· 90.9% built
- ALAG ARTIS1.8 yr overdueALAG LIFESPACE LLP · GHATKOPAR EAST, Mumbai SuburbanP51800032385· 84.5% built
- PLATINUM PARK1.8 yr overdueshreeji Developers · Andheri, Mumbai SuburbanP51800008722· filed Jun 2021 → now Dec 2024· 85.9% built· 22 complaints
- AUDUMBAR APARTMENTS CHS LTD1.8 yr overdueMASAKIN DEVELOPERS · MALAD WEST MUMBAI, Mumbai SuburbanP51800034993· 90.9% built
- Apoorva Rise1.8 yr overdueApoorva Housing · Chembur, Mumbai SuburbanP51800031714· 97.7% built
- BHOOMI CELESTIA - A WING1.8 yr overdueSASHWAT CONSTRUWELL PRIVATE LIMITED · Librity Garden, Opp. S.N.D.T. Girls Collage, Mumbai SuburbanP51800011623· filed Dec 2022 → now Dec 2024· 30.5% built
- JOSEPH VILLA1.8 yr overdueK.PATELAND CO · GOREGAON EAST, Mumbai SuburbanP51800045891· 72.7% built
- DP STAR TRIVENI1.8 yr overdueDP BUILDHOMES LLP · BHANDUP WEST, Mumbai SuburbanP51800004550· filed Dec 2021 → now Dec 2024· 85.5% built
- CITI NEST1.8 yr overdueBasons Investments Private Limited · ANDHERI - EAST, Mumbai SuburbanP51800049340· 36.8% built
- STAR CHS LTD1.8 yr overdueHEALTH COLONIES & CONSTRUCTION PVT.LTD. · POWAI, Mumbai SuburbanP51800035098· 23.6% built
- SATRA ONE1.8 yr overdueBLEU NOIR INFRASTRUCTURE DEVELOPMENT PVT. LTD. · GOREGAON WEST, Mumbai SuburbanP51800032891· 46.2% built· 1 complaint
- SHUBHAM AVALON CO-OPERATIVE HOUSING SOCIETY LIMITED1.8 yr overdueAVVAD HOUSING LLP · GHATKOPAR EAST, Mumbai SuburbanP51800045851· 90.9% built
- ALAG ASHTAPAD1.8 yr overdueCONTOUR DEVELOPERS LLP · Kurla, Mumbai SuburbanP51800031922· 90.9% built
- Anjani Tirth1.8 yr overdueGeeta Space Realtors · Borivali (West), Mumbai SuburbanP51800033828· 90.9% built
- VARDHMAN PEARL1.8 yr overdueDIWALI DEVELOPERS · MALAD WEST, Mumbai SuburbanP51800032809· 36.4% built
- SHEEL APARTMENTS BY MAYFAIR1.8 yr overdueMAYFAIR HOUSING PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800031040· 82.7% built
- ALAG OLIVE1.8 yr overdueALAG OLIVE LLP · GHATKOPAR EAST, Mumbai SuburbanP51800032510· 89.5% built
- ANNAVISTA1.8 yr overdueTRISONS BUILDERS · BANDRA WEST, Mumbai SuburbanP51800034372· 74.1% built
- HS ALAG1.8 yr overdueHS ALAG REALTY LLP · Kurla, Mumbai SuburbanP51800031693· 90.9% built
- SUPREME MADHUKAR1.8 yr overdueSUPREME ENTERPRISE · BORIVALI, Mumbai SuburbanP51800032692· 86.8% built
- BORIVALI NEELKANTH NAGAR CHS LTD1.7 yr overdueMAHAVIR INFRASTRUCTURE · Borivali, Mumbai SuburbanP51800006154· filed Dec 2020 → now Jan 2025· 90.9% built
- GHATKOPAR PARK VIEW CHS LIMITED1.7 yr overdueEV AND SARAF REALTY · KURLA, Mumbai SuburbanP51800014255· filed Dec 2019 → now Jan 2025· 86.4% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.