Delayed projects in Pune
3,402 MahaRERA-registered projects in Pune are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 14 of 18
- Godrej Rejuve2.5 yr overdueOXFORD REALTY LLP · Keshavnagar, PuneP52100018720· 90.9% built· 11 complaints
- NANDAN PROBIZ2.5 yr overdueNANDAN ASSOCIATES · BALEWADI, PuneP52100001376· filed Mar 2022 → now Mar 2024· 81% built· 7 complaints
- SARA CITY C82.5 yr overdueJagrutsara Structures LLP · KHARABWADI, PuneP52100015654· 90.9% built
- SARA CITY C102.5 yr overdueJagrutsara Structures LLP · KHARABWADI, PuneP52100015649· 90.9% built
- JAYHIND HILLSIDE2.5 yr overdueSAGAR JAYSING ERANDE · DUDULGAON, PuneP52100022761· 81.4% built
- Majestique City D Building2.5 yr overdueMANISH DWARKADAS MAHESHWARI · Pune-Nagar Road, PuneP52100019947· 90.9% built
- ALANKAPURAM PH 3 A BUILDING2.5 yr overdueR K Lunkad Housing corporation · WADMUKHWADI, PuneP52100027434· 81.8% built
- Shubh Aarambh2.5 yr overdueSHUBH ASSOCIATES · DADACHI WASTI, PuneP52100028760· 90.9% built
- ROHAN ABHILASHA 2 WING A2.5 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · Wagholi, PuneP52100025655· 80% built
- PAVILION2.5 yr overdueCERATEC GARIMA · KIWALE, PuneP52100047319· 72.7% built
- JAMDAR ERA2.5 yr overdueYogesh Suresh Dudhal · Baramati, PuneP52100048521· 90.9% built· 1 complaint
- ROYAL RESIDENCY2.5 yr overdueS J BUILDER & DEVELOPERS · PIMPRI CHINCHWAD, PuneP52100045783· 81.8% built
- SAMARTH VILLA2.5 yr overdueD.A.BORADE & SONS · VISHAL NAGAR, PuneP52100050168· 81.8% built
- ELEGANCE PARK2.5 yr overdueM/S RAMOLI SRUSHTI DEVELOPERS · near Sarpanch Vasti, PuneP52100013441· filed Sept 2023 → now Mar 2024· 75.2% built· 3 complaints
- VEDANT PRIDE2.5 yr overdueVEDANT CONSTRUCTIONS · OPP OJASWI APARTMENT, PuneP52100033002· 81.8% built
- DWARKAMAI HEIGHTS2.5 yr overdueDWARKAMAI ASSOCIATES · CHARHOLI BUDRUK, PuneP52100046861· filed Mar 2023 → now Mar 2024· 63.5% built
- DRUMADAL2.5 yr overdueRanjekar Realty LLP · Shivajinagar, Bhamburda, PuneP52100026105· filed Sept 2023 → now Mar 2024· 55.5% built
- MILLENNIUM PACIFIC2.5 yr overdueMillennium Developers · TATHAWADE, PuneP52100027204· 89.1% built
- SAI DWARKA PHASE 22.5 yr overdueMAA SANKALP BUILDCON · YAWALEWADI, PuneP52100004883· filed Dec 2019 → now Mar 2024· 42.3% built· 8 complaints
- ACE AURUM COMMERCIAL2.5 yr overdueAALIA HOMES · OPP. SENTOSA RESORT, NEAR MUKAI CHOWK RAVET, PuneP52100030450· 90.9% built
- SUKHMANI NIWAS2.5 yr overdueM/S PREETAM ASSOCIATES · PIMPRI, PuneP52100048054· 9.1% built
- SHUBHASHREE2.5 yr overdueKotibhaskar Infrastructures &Developers Pvt.Ltd. · PUNE, PuneP52100045350· 99.1% built
- Arunya2.5 yr overdueGM Buildcon · Haveli, PuneP52100014346· filed Dec 2020 → now Mar 2024· 45.5% built· 1 complaint
- KANAKMANGALA - GAJANAN2.5 yr overdueKanakmangala Properties · Haveli, PuneP52100034371· 31.8% built
- Ganganagar2.5 yr overdueSanjay Chandrakant Bafana · Shirur, PuneP52100022015· 90.9% built
- SIGNATURE PARK C AND D BUILDING2.5 yr overdueSHREE SONIGARA REALCON · THERGAON, PuneP52100020943· 42.3% built· 66 complaints
- KUMAR PEBBLE PARK KHUSHI 2- D22.5 yr overdueKumar Construction and Properties Pvt Ltd · HANDEWADI, PuneP52100020421· 49.1% built
- SIGNATURE PARK G AND H BUILDING2.5 yr overdueSHREE SONIGARA REALCON · THERGAON, PuneP52100019960· 45.5% built· 89 complaints
- SWANANDI RESIDENCY2.5 yr overdueAMIT SANJAY CHAKANKAR · DHAYARI, PuneP52100031935· filed Dec 2023 → now Apr 2024· 97.7% built
- BALEWADI 372.5 yr overdueNitin Shamrao Patil · BALEWADI, PuneP52100028844· 72.7% built
- VEDANT DEVELOPERS2.5 yr overdueVEDANT DEVELOPERS · TAL- HAVELI, DISTRICT PUNE, PuneP52100048105· filed Dec 2023 → now Apr 2024· 36.8% built
- Vtp Beaumonde- Nation R2 Tower52.5 yr overdueAshdan Developers Private Limited · Manjri, PuneP52100007384· filed Jul 2022 → now Apr 2024· 90.9% built· 33 complaints
- Boulevard part of Towers Phase 12.5 yr overdueBramhacorp Limited · Pune City, PuneP52100004150· 81.8% built· 1 complaint
- Kumar Prospera - A3, A4 and A52.5 yr overdueKumar Agro Products Pvt Ltd - Kumar Company (Now known as Kumar Construction and Properties Pvt Ltd) JV · Magarpatta, PuneP52100022619· 88.1% built· 1 complaint
- BLUE ROOF SERA2.5 yr overdueRainbow Construction · SUS, PuneP52100024232· 72.9% built
- Poorti2.5 yr overdueRahul Ramesh Shah · Gultekadi, PuneP52100032542· 90.9% built
- FORTUNE SHUBHAN PHASE 2 BUILDING D2.5 yr overdueFORTUNE COPORATION · Pune (M Corp.), PuneP52100006125· filed Jun 2019 → now Apr 2024· 90.9% built
- SHREE DREAMS2.5 yr overdueRAFIK AKBAR MULLA · Shirur, PuneP52100001844· filed Feb 2020 → now Apr 2024· 90.9% built
- NYATI ELAN SOUTH I2.5 yr overduePSQUARE BUILDERS LLP · WAGHOLI, PuneP52100029008· 86.4% built
- BALKRUSHNA AND NANDALAL2.5 yr overdueVAINATEYA BUILD PRIVATE LIMITED · PUNE, PuneP52100004293· filed Dec 2019 → now Apr 2024· 90.9% built
- Annapurna Smruti2.5 yr overdueGokhale Empires LLP · Shukrawar Peth, PuneP52100026504· 81.8% built· 1 complaint
- NYATI ELAN CENTRAL I2.5 yr overduePSQUARE BUILDERS LLP · WAGHOLI, PuneP52100029005· 86.4% built· 1 complaint
- Mayuri Infinity2.5 yr overdueMAYURI LANDMARKSLLP · TATA inora park, PuneP52100015703· filed Apr 2021 → now Apr 2024· 66.7% built· 1 complaint
- Mont Vert Grande Bldg Type G plot 22.5 yr overdueNiraj Kumar Associates Pvt Ltd · Pashan, PuneP52100020880· 90.9% built
- TRIDENT2.4 yr overdueDEU ASSOCIATES · PIMPLE NILKH, PuneP52100026732· 36.4% built
- Avani II2.4 yr overdueKamal Promoters & Builders. · Mohammadwadi chowk, PuneP52100015958· 51.8% built· 1 complaint
- Chinmay Pride2.4 yr overdueChinmay Pride · Mahavir Nagar, PuneP52100031331· 63.6% built
- VENKATESH GRAFFITI ELAN PHASE 12.4 yr overdueSHREE VENKATESH BUILDCON PVT LTD · Keshav Nagar, Mundhwa, PuneP52100023431· 90.9% built
- SAWALI APARTMENTS2.4 yr overduePARMAR REALTY · PARVATI, PuneP52100032232· 53.6% built
- RAGHUNANDAN KASTURI/ KAMTHE PATIL BUSINESS CENTER2.4 yr overdueRAGHUNANDAN ASSOCIATES · KONDHWA BK, PuneP52100020129· 81.8% built
- MUKUND2.4 yr overdueKotibhaskar Infrastructures &Developers Pvt.Ltd. · MAHARSHI KARVENAGAR, PuneP52100045860· 90% built
- WESTBROOK2.4 yr overdueTara Constructions · AMBEGAON, PuneP52100003178· filed Sept 2020 → now May 2024· 68% built· 14 complaints
- Felicia2.4 yr overdueAryavedant promoters & builders · Balewadi, PuneP52100046927· 89.5% built
- Blue Ridge Project E Land T24 and T252.4 yr overdueParanjape Schemes (Construction) Ltd. · Hinjewadi, PuneP52100016328· 99.9% built· 1 complaint
- SOHAM GALAXY2.4 yr overdueNANDU NARHARI JAGTAP · PUNE, PuneP52100029013· filed Dec 2023 → now Jun 2024· 10% built
- KUTUMB PRIME2.3 yr overdueNAIKNAVARE BUILDCON PVT LTD · Mawal, PuneP52100002348· filed Jun 2019 → now Jun 2024· 60.5% built
- Three Jewels2.3 yr overdueSnowflower Properties Private Limited · Kondhwa, PuneP52100006160· filed Dec 2023 → now Jun 2024· 71.8% built
- Swapnalok Nagari, Building No -32.3 yr overdueSWAPNALOK DEVELOPERS · Bhor, PuneP52100017102· 81.8% built
- Sai Sparsh-A1, A22.3 yr overdueJalan Associates · Bhor, PuneP52100003561· filed Dec 2018 → now Jun 2024· 99.1% built
- Megapolis Saffron - A3 to A92.3 yr overduePegasus Properties Pvt. Ltd. · Rajiv Gandhi Infotech Park, Phase 3, PuneP52100018779· 89.1% built
- SPRING GARDENS PHASE - I2.3 yr overdueAchalare Realtors Private Limited · BORHADEWADI, PuneP52100026121· 90.9% built
- PALAASH SADAPHULI PHASE 2 A1 WING2.3 yr overdueGS ASSOCIATES · Varale, PuneP52100005853· filed Apr 2018 → now Jun 2024· 81.8% built· 20 complaints
- BHALCHANDRA PROSPERA2.3 yr overdueN B BHONDAVE PROMOTERS · RAVET, PuneP52100031692· 89.2% built· 1 complaint
- Sukhniwas2.3 yr overdueAmol Ajit Ravetkar · Shivajinagar, PuneP52100009654· filed Feb 2021 → now Jun 2024· 90.9% built
- SUKHWANI NYSA2.3 yr overdueSUKHWANI LANDMARK · RAVET, PuneP52100026493· 81.6% built
- PLATINUM TOWERS2.3 yr overdueLaxman Sopanrao Nimhan · wakad, PuneP52100016501· 90.9% built
- SAPPHIRE TOWERS 22.3 yr overdueCHAURANG VENTURES · CHARHOLI PHATA, CHOVISAWADI, PuneP52100031392· 89.5% built
- PALAASH SADAPHULI2.3 yr overdueGS ASSOCIATES · Varale, PuneP52100003228· filed Apr 2018 → now Jun 2024· 90.9% built· 21 complaints
- Dynamic Grandeur2.3 yr overdueDYNAMIC REALTY ENTERPRISES · Undri, PuneP52100005396· 85% built
- Borawake Shilp2.3 yr overdueUrban Creations · Satavvadi, PuneP52100028860· 77.3% built
- VENKATESH GRAFFITI ELAN PHASE 22.3 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAVNAGAR MUNDHWA, PuneP52100026737· 90.9% built
- KASTURI2.3 yr overdueMORYA LANDMARKS · BEHIND SEASONS HOTEL NEAR CROMA MALL AUNDH, PuneP52100048116· filed Jan 2024 → now Jun 2024· 63.6% built
- GREENVILLE BUILDING A42.3 yr overdueVision Realtors · HADAPSAR, PuneP52100052689· 90.9% built
- NYATI ELITE2.3 yr overdueNITIN DWARKADAS NYATI · UNDRI VILLAGE, PuneP52100045651· 83.5% built
- GOKHALE SERENITY2.3 yr overdueSUDHIR MAHADEV GOKHALE · DHAYRI, PuneP52100028814· 73.3% built
- DESTINATION EL PROGRESO2.3 yr overdueEL PROGRESO VENTURES · MOSHI PRADHIKARAN, PuneP52100026761· 57.6% built
- Mangalam homes2.3 yr overdueYashashree Group · Dudulgoan Moshi, PuneP52100021772· 61.4% built
- Sai Sanskruti2.3 yr overdueHORIZON REALTY · Kharadi, PuneP52100025975· 90.9% built
- AURORA2.3 yr overdueMagnum Developers · GAT NO.927 PART, PuneP52100030790· 81.8% built
- ADI AVENTURA2.3 yr overdueADI HOMES · RAVET, PuneP52100016461· 87.9% built
- BHALCHANDRA VIHAR PHASE - IV/M32.3 yr overdueN B BHONDVE BUILDERS · RAVET, PuneP52100047005· 81.8% built
- SPECTRUM2.3 yr overdueJOSHI BUILDCON LANDMARKS · Shivajinagar, PuneP52100032621· 68.2% built
- GREENVILLE BUILDING A12.3 yr overdueVision Realtors · Hadapsar, PuneP52100028126· 90% built· 1 complaint
- SAPPHIRE TOWERS2.3 yr overdueCHAURANG VENTURES · CHOVISAWADI, PuneP52100027242· 89.5% built
- MILESTONE RKD DEVELOPERS2.3 yr overdueRKD DEVELOPERS · BANER, PuneP52100030844· 75.9% built
- NANDANVAN2.3 yr overduePENTAGON PROPERTIES · Haveli, PuneP52100008374· filed Sept 2021 → now Jun 2024· 95.5% built
- Laxmi Homes2.3 yr overduePokar Realty · Haveli, PuneP52100025463· filed Jul 2023 → now Jun 2024· 72.7% built
- GOLDEN WINDS Building D Phase 52.3 yr overdueGOLDEN BRICKS DEVELOPERS · Opposite D Y Patil Knowledge City Off Porwal Road, PuneP52100027754· 81.8% built
- Aldea Espanola Phase VI2.3 yr overduePuranik Buildcon Private Limited · Mahalunge, PuneP52100000537· 90.6% built· 1 complaint
- Savannah2.3 yr overdueSim Properties · wagholi, PuneP52100027297· 51.5% built
- ACORN PARK PHASE I2.3 yr overduePANTHEON ASSOCIATES LLP · wakad, PuneP52100028087· 86.4% built
- YAHAVI-TOWER-1-OAK2.3 yr overdueIMAGE REALTY PRIVATE LIMITED · OXFORD GOLF COURSE, PuneP52100028031· 81.8% built· 1 complaint
- DEVRAJ NISSARG2.3 yr overdueDEVRAJ BUILDERS AND DEVELOPERS · Baramati (M Cl), PuneP52100010031· filed Feb 2021 → now Jun 2024· 79.5% built· 1 complaint
- GANDHI TOWERS2.3 yr overdueJAYSHREE SATISH GANDHI · DAUND, PuneP52100016096· 36.4% built
- Green park2.3 yr overdueAnishka Developers Pvt. Ltd. · Kondhwa Bk, PuneP52100000501· filed Dec 2022 → now Jun 2024· 98.2% built
- SHERLYN AVENUE2.3 yr overdueSHARAD SOPAN SHENDE · Pisoli, PuneP52100001087· filed Feb 2021 → now Jun 2024· 66.1% built
- Swapnalok Nagari Commercial Building2.3 yr overdueSWAPNALOK DEVELOPERS · Bhor, PuneP52100017103· 81.8% built
- LAXMI AVENUE2.3 yr overdueLAXMAN SAIBANA MEHETRE · NEAR PRISTINE PROLIFE PHASE III, PuneP52100024445· 86.4% built
- Guardian Cityscapes Phase 12.3 yr overdueGuardian Homes Private Limited · Dattawadi, PuneP52100003214· 75.2% built· 4 complaints
- CASA ABRIGO2.3 yr overdueTECHSTONE CONSTRUCTIONS LLP · HADAPSAR, PuneP52100026227· 90.9% built
- GAYATRREE LEGACY2.3 yr overdueGAYATRREE PROPERTIES · Chikhali, PuneP52100013335· filed Dec 2018 → now Jun 2024· 69.7% built· 5 complaints
- Splendid Lake view2.3 yr overdueYASHADA HOMES · PASHAN, PuneP52100021727· 90.9% built
- Yes Residency2.3 yr overdueYemul& Sancheti Associates · Hadapsar, PuneP52100010630· filed Dec 2018 → now Jun 2024· 79.5% built· 2 complaints
- AMEY2.3 yr overdueRanjekar Realty LLP · Kothrud, Pune, PuneP52100026733· 89.1% built
- ARCHANA PARADISE WING A2.3 yr overdueKANIFNATH REALITY · MOHAMMADWADI, PuneP52100026701· 51.4% built
- Gagan Utopia2.3 yr overdueGAGAN BUILDSCAPES LLP · Mundhwa, PuneP52100005074· filed Dec 2019 → now Jun 2024· 63.3% built· 2 complaints
- PRAYEJA CITY2.3 yr overduePRAYEJA CITY · Wadgaon Budruk, PuneP52100010668· filed Nov 2018 → now Jun 2024· 85.5% built· 12 complaints
- MANTRA CITY 360 PHASE042.3 yr overdueMANTRA ISLAND HOMES TALEGAON LLP · TALEGAON, PuneP52100001457· filed Oct 2019 → now Jul 2024· 90.9% built· 5 complaints
- 41 EVOKE PHASE 12.3 yr overdueKRIASLA ASSOCIATES · KOHALI GAS SERVICE, PuneP52100026277· 45.2% built· 2 complaints
- Vtp Cygnus- Nation R1-Tower 82.3 yr overdueAshdan Developers Private Limited · Manjri, PuneP52100007722· filed Jul 2023 → now Jul 2024· 90.9% built· 24 complaints
- Saarrthi Swadesh2.2 yr overdueSiddharth Properties · Mawal, PuneP52100003849· filed Sept 2018 → now Jul 2024· 90.9% built· 3 complaints
- Metro Life Bizz Bay2.2 yr overdueRAMA SYNERGY SPACES · Next to Indira College of Commerce and Science, PuneP52100022156· filed Jul 2023 → now Jul 2024· 90.9% built· 2 complaints
- Sanghavi Paradise A Building2.2 yr overdueSanjay Walchand Sanghavi · Sanghavi Nagar, PuneP52100017993· filed Sept 2023 → now Jul 2024· 90.9% built
- TRIDENT2.2 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Wakad, PuneP52100004511· filed Jul 2023 → now Jul 2024· 92.5% built· 2 complaints
- NYATI EMBRACE I2.2 yr overdueNITIN DWARKADAS NYATI · UNDRI, PuneP52100002290· 39.4% built
- Shravan Corner2.2 yr overdueSuraj Buildcon · Pimpri Chinchawad (M Corp.), PuneP52100013651· filed Oct 2018 → now Jul 2024· 60% built
- LOTUS AVENUE2.2 yr overdueMAULI DEVELOPERS · CHOVISWADI, PuneP52100022298· 81.4% built
- LEGACY IVY2.2 yr overdueLEGACY LIFESPACES LLP · Punawale, PuneP52100029412· 77% built
- Sun-Srushti Greens2.2 yr overdueSRUSHTI DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100009844· filed Dec 2019 → now Aug 2024· 80% built
- Eden Spaces Phase 22.2 yr overdueElysian Realty · Kiwale, PuneP52100025591· filed Jun 2023 → now Aug 2024· 86.4% built
- DOLPHIN GARIMA2.2 yr overdueDOLPHIN VASTU · RAVET, PuneP52100030737· filed Dec 2023 → now Aug 2024· 81.8% built
- Bhakti Park2.1 yr overduePravin Haibatrao Shinde · Ambegaon, PuneP52100024924· filed Dec 2023 → now Aug 2024· 28.2% built
- VENTURE CITY A AND D WING2.1 yr overdueVENTURE GROUP · DUDULGAON, PuneP52100019311· filed Dec 2022 → now Aug 2024· 90.9% built· 1 complaint
- REAL DREAM HOMES WING A AND B2.1 yr overdueREAL BUILDCON BUILDERS AND DEVELOPERS · GANESH NAGAR, PuneP52100021993· 99.5% built
- United Athashri2.1 yr overdueTen Corner Developers LLP · Lohegaon, PuneP52100033894· filed Mar 2024 → now Aug 2024· 65.5% built
- Dixit Sneh Sankul Phase 12.1 yr overdueSahasrabudhe & Kanitkar Associates · Nene Ghat, PuneP52100032280· filed Apr 2024 → now Aug 2024· 83.9% built
- Construction of 760 EWS tenaments on survey No 12 part at Talegaon Dabhade2.1 yr overduePUNE HOUSING AND AREA DEVELOPMENT BOARD · Joshiwada, PuneP52100019009· filed Jun 2022 → now Aug 2024· 86.8% built
- Legacy Celestia2.1 yr overdueLegacy Lifespaces LLP · Wakad, PuneP52100030612· 90.9% built
- Nakshatra2.1 yr overdueANGAL & CO · Nimhan Mala, PuneP52100019074· 90.9% built· 5 complaints
- Mi Casa2.1 yr overdueMarimagnum Constructions · UNDRI, PuneP52100009650· filed Mar 2020 → now Sept 2024· 96.4% built
- TROVE2.0 yr overdueKALASH PROPERTIES · BANER, PuneP52100031289· filed Sept 2023 → now Sept 2024· 95.5% built
- VJ Town Centre2.0 yr overdueVilas Javdekar Eco Shelters Private Limited · Near Indira College, Wakad, PuneP52100028755· 84.1% built· 3 complaints
- 27TH AVENUE2.0 yr overdueBLUE CONSTRUCTION COMPANY · BAVDHAN BUDRUKH, PuneP52100023239· filed Mar 2024 → now Sept 2024· 81.8% built
- PRISM CITY-INDIGO2.0 yr overdueSWASTIK DIAMOND REALTY · CHARHOLI, PuneP52100030026· 88.2% built
- Sukhwani Araya2.0 yr overdueSukhwani Associates · Rahatani, PuneP52100031415· 81.8% built
- AAKANKSHA RESIDENCY2.0 yr overdueSHARVIN BUILDERS LLP · KATRAJ, PuneP52100033307· filed Dec 2023 → now Sept 2024· 58.2% built
- NYATI EVOLVE II2.0 yr overdueNYATI GEETA ASSOCIATES · MUNDHWA, PuneP52100022029· 85.1% built
- VJ IndiLife2.0 yr overdueVILAS JAVDEKAR GREENSCAPE DEVELOPERS LLP · Pashan, PuneP52100028030· 86.8% built· 2 complaints
- NYATI EVOLVE I2.0 yr overdueNYATI GEETA ASSOCIATES · MUNDHWA, PuneP52100022030· 93.5% built
- NYATI EMPRESS2.0 yr overdueNYSHAA BUILDERS LLP · LOHEGAON, PuneP52100022492· 81.8% built
- NYATI EVOLVE III2.0 yr overdueNYATI GEETA ASSOCIATES · MUNDHWA, PuneP52100026448· 96.2% built
- Devanshi Nirmiti2.0 yr overdueNirmiti Realty · Galinde nagar, PuneP52100045661· 81.8% built
- Park Infinia - L2, L3, L4, K4, K5 and J42.0 yr overdueKumar Properties and Real Estate Pvt. Ltd. · Hadapsar, PuneP52100026185· 87.6% built
- DHANASHREE AANAND 12.0 yr overdueAtria Constructions · HANDEWADI CHOWK, PuneP52100031055· 90.9% built
- Megapolis Saffron - A10 to A142.0 yr overduePegasus Properties Pvt. Ltd. · Rajiv Gandhi Infotech Park Phase 3, PuneP52100021609· 90.7% built
- NANAWAREGADHAVERESIDENCY2.0 yr overdueSHRI DEVELOPERS · GAT NO-123 PLOT NO-11, PuneP52100024766· 27.3% built
- Madhukosh2.0 yr overdueKakkad Housing · Balewadi, PuneP52100019179· 74.1% built
- UDYAM BIZ CASA2.0 yr overdueKADU PROPERTIES LLP · Saswad, PuneP52100026231· filed Jun 2024 → now Sept 2024· 81.8% built
- VENKATESH GRAFFITI GLOVER PHASE 12.0 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAV NAGAR MUNDHWA, PuneP52100025621· 90.9% built
- AMOGH HEIGHTS2.0 yr overdueAMOGH PROMOTERS & BUILDERS · PARVATI, PuneP52100025019· 50.9% built
- SUVIDHA SHARADA VIHAR2.0 yr overdueSUVIDHA SCHEMES · 1639A SADASHIV PETH, PuneP52100031448· 81.8% built
- VTP Beaumonde-Nation R2 T12.0 yr overdueAshdan Developers Private Limited · Manjri, PuneP52100009535· filed Jan 2022 → now Oct 2024· 88% built· 25 complaints
- AASARA Crystal Heights2.0 yr overdueSandeep Shivaji Tapkir · Dehu Phata, PuneP52100022365· filed Oct 2023 → now Oct 2024· 90.5% built
- Godrej Hillside 12.0 yr overdueMahalunge Township Developers LLP · Mahalunge, PuneP52100022099· 81.8% built· 5 complaints
- Kalpataru Serenity - Bldg. 22.0 yr overdueKalpataru Gardens Pvt. Ltd. · PUNE, PuneP52100015855· 89.5% built· 1 complaint
- Tara Towers2.0 yr overdueHublikar Constructions · Baner Residency Sakal Nagar, PuneP52100049226· 51.8% built
- Divyash Residency2.0 yr overdueNihar Estates LLP · Baner, PuneP52100053119· 78.2% built
- Godrej Hillside 22.0 yr overdueMahalunge Township Developers LLP · Mahalunge, PuneP52100022153· 81.8% built· 3 complaints
- PLOT NO. 10, VIVA,PIRANGUT,PUNE2.0 yr overduePACT REAL ESTATE PRIVATE LIMITED · Pirangut, PuneP52100002702· 72.1% built
- SHREERAM VRUNDAVAN2.0 yr overdueSHREERAM EMPIRE · JIJAMATA CHOWK, PuneP52100034163· 81.8% built
- VISION ACE PHASE II2.0 yr overdueVISION ACE · OPP INDIRA SCHOOL NEAR AKSHRA SCHOOL TATHAWADE, PuneP52100022545· 94.8% built
- Usha Enclave2.0 yr overduePATWARDHAN PROJECTS · Bhide Bag Behind Abhiruchi mall Vadgaon, PuneP52100031888· 73.6% built· 1 complaint
- AIKYAM2.0 yr overdueSHREENATH ASSOCIATES · NEAR VENKATESH IMPERIYA, PuneP52100048456· 55.5% built
- CAPITAL ONE2.0 yr overdueSWOJAS ICON CONSTRUCTIONS LLP · BHAMBURDA SHIVAJINAGAR, PuneP52100033168· 81.8% built
- ADORN ALCAZAR-I1.9 yr overdueHASIB AHMED SHAIKH · KONDHWA BUDRUK, PuneP52100019924· 90.9% built
- Chinmay Heritage Phase 21.9 yr overdueChinmay Heritage · Niranjan Society, PuneP52100028113· 63.6% built
- PLOT NO 8, VIVA, PIRANGUT1.9 yr overduePACT REAL ESTATE PRIVATE LIMITED · Mulshi, PuneP52100002113· 78.2% built
- Aditya Apartments Condominium1.9 yr overdueKelkar Housing LLP · Mahaganesh Colony, Kothrud, PuneP52100035170· filed Sept 2024 → now Nov 2024· 90.9% built
- ARUNODAY CLASSIC1.9 yr overdueVAISHNAVI GROUP OF CONSTRUCTION · TALEGAON STATION, PuneP52100021781· filed Dec 2023 → now Nov 2024· 54.1% built
- PLANNING DESIGNING OBTAINING APPROVALS AND CONST OF 680 MIG TS ON S NO 126,127,1 TATHAWADE PUNE PH I1.8 yr overduePune Housing & Area Development Board · Bapu Buwaji Nagar, PuneP52100031648· 90.9% built· 1 complaint
- AMBAR RESIDENCY B BUILDING1.8 yr overdueMEHTA BUILDERS · JALOCHI, PuneP52100033604· 56.8% built
- AMRUT AURA1.8 yr overdueSIMMONI DEVELOPERS · MOSHI, PuneP52100032317· filed Dec 2023 → now Dec 2024· 80.9% built
- SAHARA EMERALD1.8 yr overdueSAHARA BUILDERS · BHEKRAINAGAR, PuneP52100033675· 9.4% built· 1 complaint
- ANAND EXCLUSIVE1.8 yr overdueANAND CONTRACTORES AND DEVELOPERS · BABRAS MALA INDAPUR, PuneP52100025418· 90.9% built
- Chaitanya Srusti1.8 yr overdueCHAITANYA DEVELOPERS · Daund, PuneP52100003910· filed Feb 2021 → now Dec 2024· 63.6% built
- Sai City1.8 yr overdueRaju Dnyandev Gaikwad · Daund, PuneP52100003598· filed Dec 2022 → now Dec 2024· 90.9% built
- SOLITAIRE BUSINESS HUB KALYANINAGAR1.8 yr overdueCLASSIC PROMOTERS & BUILDERS PVT LTD · YERWADA, PuneP52100014846· filed Jun 2023 → now Dec 2024· 68% built· 7 complaints
- GULMOHAR PARK B PHASE 21.8 yr overdueMercury Artharaj Landmarks AOP · DEHU, PuneP52100023073· filed Dec 2023 → now Dec 2024· 90.9% built
- Shree Ganesh Heights1.8 yr overdueShree Ganesh Developers · Haveli, PuneP52100051487· filed Dec 2023 → now Dec 2024· 90.9% built
- Madhuvan 4 76B1.8 yr overdueMagarpatta City Development Co. Pvt. Ltd. · Mohammadwadi, PuneP52100025447· 9% built
- SUKHWANI ASPIRE1.8 yr overdueBasant - Sukhwani · Kiwale, PuneP52100030795· 82.3% built
- PRISTINE GREENS PHASE III1.8 yr overduePRISTINE PROPERTIES · PUNE, PuneP52100024045· 98.2% built· 2 complaints
- KUMAR SELENA A BUILDING1.8 yr overdueKumar Construction and Properties Pvt Ltd · PASHAN, PuneP52100023773· 63.6% built
- SPLENDID HOMES1.8 yr overdueSAGAR SHANTILALJI BHATEWARA · BANER PUNE, PuneP52100033350· filed Dec 2023 → now Dec 2024· 80% built
- AKSHAY GALAXY - BUILDING B1.8 yr overdueA. P. BHANDARI DEVELOPERS · Yewalewadi, PuneP52100028684· 61.8% built
- PROJECT AT S.NO 168 H NO 7/A/B/C/28B/30/8/29/3F/3Y1.8 yr overdueSUNGRACE INFRA PROJECTS · Ambegaon, PuneP52100007062· 68.2% built
- Mont Vert Grande Plot 4 Bldg D1.8 yr overdueNiraj Kumar Associates Pvt Ltd · Pashan, PuneP52100020690· 90.9% built
- Periwinkle1.8 yr overdueAJIT GIRDHARILAL NAHAR · -, PuneP52100017310· 86.4% built
- RANGAI RESIDENCY1.8 yr overdueRAJRATNA PROMOTORS AND BUILDERS · BHOSARI, PuneP52100013661· filed Dec 2022 → now Dec 2024· 90.9% built
- MHADA - Yashwin Encore1.8 yr overdueVilas Javdekar Lifestyle Developers Pvt. Ltd. · Opposite Sayaji Hotel, PuneP52100020924· 90.9% built
- Yashwin SukhNiwas1.8 yr overdueGROWISA ADVISORS · Hinjawadi, PuneP52100025982· 90.1% built
- VJ Grand Central1.8 yr overdueVilas Javdekar Eco Shelters Private Limited · Wakad, PuneP52100026304· 89.5% built· 1 complaint
- Legacy Aeon1.8 yr overdueLegacy Homes · Near Kalyan Bhel, PuneP52100020258· 77.3% built
- Kalpataru Jade Residences E1.8 yr overdueAstrum Developments Private Limited · Haveli, PuneP52100001392· 73.5% built· 1 complaint
- ACE AURUM III TOWER 061.8 yr overdueJHAMTANI REALTY PRIVATE LIMITED · RAVET, PuneP52100025056· 50.2% built
- W-BIZ1.8 yr overdueAdi Siddhashila Associates · Wakad, PuneP52100024521· 53.9% built
- VRINDAVAN1.8 yr overdueSOHAIL ISAQUE (ISAK) BAGWAN AND ISAQUE(ISAK) IBRAHIM BAGWAN · Jalochi, PuneP52100010752· 70.5% built
- GANGA SERIO E F BUILDING1.8 yr overdueGOEL GANGA LANDMARKS LLP · KHARADI, PuneP52100023713· 90.9% built· 3 complaints
- Aero East PH II1.8 yr overdueM/S MIRACLE GURUKRUPA DEVELOPERS · Undri, PuneP52100018765· 81.8% built
- Yashwin Encore1.8 yr overdueVilas Javdekar Lifestyle Developers Pvt. Ltd. · Opposite Sayaji Hotel, PuneP52100017756· 95.6% built· 3 complaints
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.