Delayed projects in Pune
3,375 MahaRERA-registered projects in Pune are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 5 of 17
- FAVOLOSA7.4 yr overdueABHILASHA DEVELOPERS · Pune (M Corp.), PuneP52100002469· 66.6% built
- ALFA LIFESCAPES PHASE 17.4 yr overdueTRINITY LANDMARKS · WAGHOLI, PuneP52100000749· 85.2% built
- Green Groves - Cilantro7.4 yr overdueKP-Rachana Real Estate LLP · WAGHOLI, PuneP52100012330· 86.8% built
- Golden Castle7.4 yr overdueFelix Associates · Pune, PuneP52100013780· 72.7% built
- BLISS AVENUE BUILDING B7.4 yr overdueLUNAWAT ASSOCIATES · Balewadi, PuneP52100001094· 90.9% built
- SURYASHRUSHTI7.4 yr overdueSURYAPUTRA DEVELOPERS · Junnar, PuneP52100003450· 90.9% built
- SHRIYOG7.4 yr overdueA & A ASSOCIATES · Katraj, PuneP52100001691· 90.9% built
- RAJ BLISS7.4 yr overdueAMIT RAJENDRA POKALE · Dhayari (Part), PuneP52100004860· 95.5% built
- Windermere Phase 27.4 yr overdueVascon Engineers Ltd · Haveli, PuneP52100002368· 80% built· 2 complaints
- Suyog Nisarg Phase III7.4 yr overdueSuyog Nisarg JV · WAGHOLI, PuneP52100003483· 84.5% built· 4 complaints
- SHRINIWAS Q HOMES7.4 yr overdueCUPID CONSTRUCTION LLP · Pune (M Corp.), PuneP52100011776· 81.8% built· 15 complaints
- THE BLUE MAJESTIC7.4 yr overdueBLUEBERRY DEVELOPERS · Somatane, PuneP52100012704· 90.9% built
- 33 MILESTONE PHASE IV7.4 yr overdueLABH PROMOTERS AND DEVELOPERS · Tathwade, PuneP52100013679· 52.7% built
- 33 MILESTONE PHASE III7.4 yr overdueLABH PROMOTERS AND DEVELOPERS · TATHAWADE, PuneP52100013749· 52.7% built
- TROPICAL SQUARE7.4 yr overdueOm Developers Project Green · Wakad, PuneP52100014854· 9.1% built· 1 complaint
- AERO NEST7.4 yr overdueGURUKRUPA BUILDCON · UNDRI, PuneP52100001596· 90.9% built
- KAMAL RESIDENCY7.4 yr overdueADITYA ASSOCIATES · Talegaon Dabhade (R), PuneP52100002337· 60.9% built
- ZIGGURAT H Building7.4 yr overdueM/S BUILT UP · Ambegaon, PuneP52100002178· 86.6% built
- 93 Avenue Phase-II7.4 yr overdueRAVIRAJ BOKADIA CREATIVE · Pune City, PuneP52100017392· 63.6% built
- Grande Ventila Phase 1 Wing B7.4 yr overdueSATAVDEVELOPERSANDBUILDERS · Wagholi, PuneP52100007686· 90.9% built
- Piyusha7.4 yr overdueAmol Ajit Ravetkar · Pune (M Corp.), PuneP52100002284· 60% built
- Park Marina Building B and C7.4 yr overdueSUJAY ASSOCIATES · Baner, PuneP52100004085· filed Mar 2018 → now Mar 2019· 40.9% built
- RMKNATURESCLASSIC7.4 yr overdueRANJEET RAMDAS KAKADE · Talegaon Dabhade (M Cl), PuneP52100001545· 61.6% built
- Saarrthi Serenity7.4 yr overdueSiddharth Real Ventures Limited Liability Partnership · Kothrud, PuneP52100001810· 90.9% built
- SAMARTH CARINA7.4 yr overdueMAHESH ZUMBARLAL KHINVASARA · Thergaon, PuneP52100009646· 19.1% built
- Ganga Sagar - Phase II7.4 yr overdueCHAITALI BUILDERS AND DEVELOPERS · Daund, PuneP52100001623· 36.4% built
- KAMAL RESIDENCY7.4 yr overdueRAJENDRANATH GORAKHNATH KALOKHE · Talegaon Dabhade (M Cl), PuneP52100011471· 27.3% built
- PLANET97.4 yr overdueShree Sai Developers · Hinjavadi (CT), PuneP52100001880· 90.9% built
- ADORA7.4 yr overdueNEST KRISALA ASSOCIATES · Pimpri Chinchawad (M Corp.), PuneP52100003141· 81.8% built
- KRUPASINDHU II7.4 yr overduePRITHVI PROPERTIES AOP · BANER, PuneP52100015321· 90.9% built
- SAI ESHANYA7.4 yr overdueMANIKCHAND VASUDHA DEVELOPERS · BANER, PuneP52100002815· filed Mar 2018 → now Mar 2019· 90.9% built· 1 complaint
- ASTON PLAZA PHASE I7.4 yr overdueSKP Corp Private Limited · Ambegaon, PuneP52100013383· 49.1% built
- MANTRI ALPINE C PART7.4 yr overdueOMEGA PREMISES PVT LTD · BAVDHAN BK, PuneP52100011683· filed Mar 2018 → now Mar 2019· 81.4% built
- SAI VRUNDAVAN7.4 yr overduePRABHAKAR BABURAO THORAT · Ambegaon, PuneP52100007037· 84.8% built
- Aarohi S7.4 yr overdueTeirth Developers and Suyojit Infrastructure Ltd · Sus, PuneP52100008608· 81.8% built
- GAGAN CEFIRO PHASE 27.4 yr overdueGAGAN UNNATI PROMOTERS · Undri, PuneP52100002365· 90.9% built
- PRATIBHA SADAN CO. OP. HSG. SOC.7.4 yr overdueVYAS BUILDCON PVT. LTD. · Kothrud, PuneP52100002624· filed Mar 2018 → now Mar 2019· 85.5% built
- N B Square7.4 yr overdueGanesh Developers & Company · AMBEGAON Bk, PuneP52100013282· 59.1% built
- NANDADEEP APARTMENT7.4 yr overdueSHREE YASH DEVELOPERS · kondhwa BK, PuneP52100012358· filed Apr 2018 → now Mar 2019· 79.2% built
- SAI MALHAR7.4 yr overdueSai Associates · Pimpri Chinchawad (M Corp.), PuneP52100013695· 80.9% built
- Konark Tower7.4 yr overdueKonark Developers · Baner, PuneP52100008532· 63.6% built
- SWISS PLAZA7.4 yr overdueMOTI UDHARAM PANJABI · THERGAON, PuneP52100016426· 61.6% built
- BLUE BELLS AURA7.4 yr overdueRainbow Construction · PASHAN, PuneP52100009029· 90.9% built
- SHRADHHA RESIDENCY7.4 yr overdueM/S VIJAYRAJ ASSOCIATES · Haveli, PuneP52100001915· 60.9% built
- ALCON STYLUS7.4 yr overdueALCON LANDMRKS · kondhwa BK, PuneP52100001398· 76.8% built
- YASHLAXMI COMPLEX7.4 yr overdueAMODH ASSOCIATES · Daund, PuneP52100013503· 45.5% built
- 93 AVENUE PHASE- 17.4 yr overdueRAVIRAJ BOKADIA CREATIVE · Pune City, PuneP52100015538· 81.8% built
- Kingston Atlantis B1 and B2 Building7.4 yr overdueVedant Landmarks · MOHAMMADWADI, PuneP52100011904· 99.5% built· 1 complaint
- SENTOSA PALM7.4 yr overdueSRI SAINATH INFRA · Wakad, PuneP52100013778· 90.9% built
- LAXMI BHAKTI7.4 yr overdueL S MEHETRE & SUKHWANI SHELTERS · RAHATNI, PuneP52100008310· 86.4% built
- DISHA PARADISE7.4 yr overdueJAY GANESH EMPIRE · Shirur, PuneP52100003596· 42.7% built
- LIFE VILLE7.4 yr overdueBHARAT SITARAM KATE · Pimpale Saudagar, PuneP52100003879· 30.2% built
- EMPPIRE ETERNITY7.4 yr overdueEMPPIRE PROPERTIES · Pune (M Corp.), PuneP52100003185· 41.8% built
- Marvel Brisa7.4 yr overdueMARVEL REALTORS AND DEVELOPERS LTD · Pune (M Corp.), PuneP52100001627· 91.2% built· 22 complaints
- Akshar Height7.4 yr overdueAkshar Venture · Opposite Manohanr Nagar Gate, PuneP52100006726· 88.2% built
- ROSHAN ONE WING C7.4 yr overdueRAHUL BHAGWANDAS SANKLA · Varale, PuneP52100006758· filed Dec 2018 → now Mar 2019· 81.8% built
- ASHTHAVINAYAK7.4 yr overdueUNITY GROUP BUILDERS AND DEVELOPERS · Tandulwadi, PuneP52100010511· 13.8% built
- PRISTINE VIVA7.4 yr overdueSACHIN ISHWARCHAND GOYAL · MOHAMMADWADI, PuneP52100002319· 90.9% built
- DNV ELVIRA A7.4 yr overdueDNV REALTY · NEAR AKSHARA SCHOOL, PuneP52100001240· 72.7% built
- Athashri Xion7.4 yr overduePSC Pacific · Hinjavadi (CT), PuneP52100000051· 88.6% built
- GAJSHEELA7.4 yr overdueSHASHIKANT LAXMAN BHAGAT · Talegaon Dabhade (M Cl), PuneP52100002285· 38.6% built
- DREAM CITY7.4 yr overdueTANAJI SADASHIV PANSARE · Jalochi, PuneP52100005463· 90.9% built· 1 complaint
- Mauli Residency7.4 yr overdueVraj Ratan Home Makers (I) Pvt Ltd · Wakad, PuneP52100010200· filed Mar 2018 → now Mar 2019· 88.6% built
- Manhattan7.4 yr overdueMajestique Housing LLP · WAGHOLI, PuneP52100000291· 93.2% built
- GRUKRUPA7.4 yr overdueGURUKRUPA ASSOCIATES · Wadagaon (CT), PuneP52100013430· 48.2% built
- Jaymala Business Court7.4 yr overdueSatyam Constructions · mANJRI, PuneP52100002339· 81.8% built
- Bhagyam Residency7.4 yr overdueZende Reality · kondhwa BK, PuneP52100003512· 52.7% built
- Sukhwani Gracia Phase-2 B Wing7.4 yr overduePrime properties · Sus Pune, PuneP52100007297· 90.9% built
- Manjri Green Annexe - B1, B2, B37.4 yr overdueY Associates · Gopalpatti, PuneP52100000538· 90.9% built
- SHUBHARAMBHA SKY7.4 yr overdueSHUBHARAMBHA DEVELOPERS · NARHE, PuneP52100013417· 90.9% built· 1 complaint
- RAJ ANGAN7.4 yr overdueBATHUWEL UTTAMRAO BALID · Pimpri Chinchawad (M Corp.), PuneP52100012828· 72.7% built· 1 complaint
- DEVGHAR7.3 yr overdueBagwan Infratech · ADARSHNAGAR, PuneP52100014545· 9.1% built
- SILVER CREST7.3 yr overduePRIDE HOMES · Wakad, PuneP52100007038· 63.6% built
- SAARVI NISARG7.3 yr overdueSAARVI HOME MAKERS · Alefata (N.V.), PuneP52100004502· 60.5% built
- Regency Orion7.3 yr overdueREGENCY HOUSING · Baner, PuneP52100020102· 81.8% built
- TULSI SHAKUNTALA KANADE NAGAR7.3 yr overdueM/s. TULSI DEVELOPERS · KANADE NAGAR, PuneP52100008932· filed Apr 2018 → now Apr 2019· 68.6% built· 1 complaint
- BELLAVISTA G BUILDING7.3 yr overdueAVNEE AND CONCORD ASSOCIATES · Pune City, PuneP52100001389· filed Apr 2018 → now Apr 2019· 60.3% built
- TRUSPACE PALOMA7.3 yr overdueTruSpace · VIJAYANAGAR COLONY, PuneP52100001474· 65.5% built
- NAVALAI HEIGHTS7.3 yr overdueVIVEK VIJAY SAWANT · Pune City, PuneP52100010137· 46.4% built
- Anand Shree Society7.3 yr overdueNS Landmarks · Parvati, PuneP52100005478· filed Apr 2018 → now Apr 2019· 90.9% built
- VARAD SUKRITI7.3 yr overdueNEHA DREAM HOMES LLP · Mukund Nagar, PuneP52100003495· 58.2% built
- Namo Panchratna Residency7.3 yr overdueShital Samir Oswal · Wadagaon (CT), PuneP52100013359· 51.4% built
- AISHWARYAM HAMARA MHADA7.3 yr overdueSAI ESSEN DEVELOPERS · CHIKHALI, PuneP52100016065· 36.8% built
- Heritage7.3 yr overdueGalaxy Realty · Wakad, PuneP52100001845· filed Jun 2018 → now Apr 2019· 51.5% built· 1 complaint
- 41 ESTERA7.3 yr overdueSAMARTTHA TRIMURTI PROPERTIES · PUNAWALE, PuneP52100003574· filed Jul 2018 → now Apr 2019· 81.8% built· 2 complaints
- Aditya Pristine7.3 yr overdueATUL ARVIND BHOSLE · Mohannagar baner, PuneP52100001573· filed May 2018 → now Apr 2019· 80.2% built
- SARA A BUILDING7.3 yr overdueAnshul Megaprojects LLP · Baner, PuneP52100002199· 90.9% built
- Nandini Orchid Phase 17.3 yr overdueNandini Group Promoters And Builders · Wadki, PuneP52100014245· 81.8% built· 7 complaints
- Aeropolis Phase II7.3 yr overdueKrishna developers · LOHGAON, PuneP52100003798· 90.9% built
- HILLVIEW RESIDENCY PHASE I7.2 yr overdueKUMAR BEHARAY PROPERTIES LLP · KOTHRUD, PuneP52100001962· 93.2% built· 1 complaint
- Goodwill Nirmiti B Building7.2 yr overdueUnique Choice Ventures · LOHGAON, PuneP52100003051· 58.2% built
- Vastu Nirvana7.2 yr overdueNirvana Builders · Pune City, PuneP52100002857· 65.5% built
- Amrutvilla7.2 yr overdueM/s Abhiraj Builders · Chakankar mala, PuneP52100005156· 81.8% built
- Rucha Phase II7.2 yr overdueKEDAR RANADE · Punawale, PuneP52100001692· 81.8% built
- GURU PRAJAKTA7.2 yr overduePRAJ DEVELOPERS · Lohgaon, PuneP52100001792· 81.4% built
- GRAND ICON7.2 yr overdueTRIMURTI DEVELOPERS · NEAR TRIMURTI CHOWK, PuneP52100006202· 56.4% built
- SAMARTH DHANVATIKA7.2 yr overdueSWAMI SAMARTH DEVELOPERS · Wadagaon (CT), PuneP52100005854· 39.1% built
- Park Infinia Phase III7.2 yr overdueKumar Properties and Real Estate Pvt. Ltd. · Haveli, PuneP52100000084· 89.1% built
- NAVASHISH7.2 yr overdueKEDAR RANADE · TULSHIBAUGWALE COLONY, PuneP52100001911· 90.9% built
- Sarovar Residency7.2 yr overdueChandrakant Shankar Bhide · Talegaon Dabhade (M Cl), PuneP52100008917· 82.7% built
- WISTERIA C BUILDING PHASE 17.2 yr overdueMR DILIP KANAIYALAL TILWANI · chikhali Bk, PuneP52100007292· 90.9% built
- THE HOUSE OF LORDS7.2 yr overdueTHE HOUSE OF LORDS · Pune (M Corp.), PuneP52100006066· filed Jun 2018 → now May 2019· 68.2% built
- MADHUMITA7.2 yr overdueKEDAR RANADE · MAHAGANESH COLONY, PuneP52100001656· 90.9% built
- ANIKA ARCADE7.2 yr overdueArun Pitamber Sheth · PISOLI, PuneP52100018361· 55.5% built
- Rucha Phase I7.2 yr overdueKEDAR RANADE · NEAR BLUE WATER HOTEL, PuneP52100001941· 81.8% built
- Green Republic7.2 yr overdueSamrat Buildcon · Wagholi, PuneP52100009638· 90.9% built· 2 complaints
- Sopan Residency7.2 yr overdueMauli Enterprises · Haveli, PuneP52100007906· 72.7% built
- Anand Gold Coin7.2 yr overdueAnand Infra · Baramati (M Cl), PuneP52100007171· 74.5% built
- KAKADE PROPERTIES7.2 yr overdueKUNAL PRAKASH KAKADE · Pimpri Chinchawad (M Corp.), PuneP52100010667· 11.8% built
- Rutuja Heights7.2 yr overdueOm Developers · Pimpri Chinchawad (M Corp.), PuneP52100009892· 63.6% built
- DWARKA RESIDENCY WING-A7.2 yr overdueSHRI PANDURANG MARUTI KACHARE · JALOCHI TALUKA BARAMATI, PuneP52100015319· 54.5% built
- Sapphire Greens7.2 yr overdueShreem Corporation · Waksai, PuneP52100002171· filed Jun 2018 → now Jun 2019· 78.2% built
- UTSAV RESIDENCY7.2 yr overdueROYAL DEVELOPERS · WAGHOLI, PuneP52100006886· 81.8% built
- Sugam Cooperative Housing Society Limited7.2 yr overdueKotibhaskar Infrastructures &Developers Pvt.Ltd. · Erandwane, PuneP52100012123· 90.9% built
- Jai Ganesh7.2 yr overdueVastushri construction · Vadgaon Mawal, PuneP52100011271· filed Jun 2018 → now Jun 2019· 81.8% built
- 1 Hallmark Avenue Phase I7.1 yr overdueRajHeramb Properties · Ravet, PuneP52100002760· filed Jun 2018 → now Jun 2019· 89.1% built
- Sari Oshiya Park7.1 yr overdueVijaykumar Fulchand Bafna · kondhwa BK, PuneP52100011977· 78.2% built
- SAHIL HEIGHTS7.1 yr overdueVAISHNAVI PROMOTERS AND DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100010663· 56.1% built· 2 complaints
- ATLANTA II PHASE I7.1 yr overdueGKWONDERS · Wakad, PuneP52100001073· 90.9% built
- Ceratec Greens7.1 yr overdueanand dayanand agarwal · Pune (M Corp.), PuneP52100000432· 90.9% built
- GALAXEE APARTMENT7.1 yr overdueHASMUKH INDRADEV GUPTA · LONAVALA, PuneP52100014995· 90.9% built
- RHYTHM PARK7.1 yr overdueOM VENTURES · -, PuneP52100016489· 83.6% built
- NAVKAR - B building7.1 yr overdueMAJESTIQUE LIFESPACES LLP · Kondhwa BK, PuneP52100001335· 99.5% built
- INFINITY TOWER - B WING7.1 yr overdueTULIP DEVELOPERS · Punawale, PuneP52100004824· 77.7% built
- KK SHRIRAM7.1 yr overdueKOKANE BUILDERS · Pimpri Chinchawad (M Corp.), PuneP52100011061· 90.9% built
- PRERANA7.1 yr overdueBPN ASSOCIATES · Pune (M Corp.), PuneP52100004966· 52.7% built· 1 complaint
- SIROCCO GRANDE7.1 yr overdueBENCHMARK TOWN PLANNING LLP · Punavale, PuneP52100000326· 75.3% built· 11 complaints
- DAYALHEIGHTS7.1 yr overdueVINOD PREMCHAND CHANDWANI · Haveli, PuneP52100000191· 90.9% built
- Venkatesh Imperia Phase I7.1 yr overdueRajHeramb Properties · PCMC, PuneP52100002796· filed Jun 2018 → now Jun 2019· 90.9% built
- NEELKAMAL7.1 yr overduenilkanth associates · Talegaon Dabhade (M Cl), PuneP52100011030· 90.5% built
- Greens Centre7.1 yr overdueAMJ Land Developers · Chinchwad, PuneP52100013159· 81.8% built
- TANISHQ CASITA7.1 yr overdueNAVKAAR ASSOCIATES · AMBEGAON Bk, PuneP52100013979· 93.9% built
- NYATI EVARA I7.1 yr overdueNYATI BUILDERS PRIVATE LIMITED · UNDRI, PuneP52100000455· 89.2% built· 2 complaints
- GREEN PARK PHASE 37.1 yr overdueRAJENDRA VASANTRAO INGOLE · Rui, PuneP52100008361· 81.8% built
- The Address - 17.1 yr overdueSOL Developers · MOSHI, PuneP52100007674· 90.9% built
- Blue Bell7.1 yr overdueAbhaysinh Dhadve Patil Constructions Private Limited · Baner, PuneP52100008278· 88.2% built· 9 complaints
- Yashwin Anand7.1 yr overdueVilas Javdekar & Sanjeevani Developers LLP · Sus, PuneP52100000012· 90.9% built
- SHREE SIDDHI RESIDENCY7.1 yr overdueGANGADHAR RAMESH BHALEKAR · Pimpri Chinchawad (M Corp.), PuneP52100012836· 76.8% built
- Navkar A building7.1 yr overdueMAJESTIQUE LIFESPACES LLP · Kondhwa BK, PuneP52100001901· 99.5% built
- SHREEJI DREAMS7.1 yr overdueSHREEJI DEVELOPERS · Bhosari, PuneP52100003437· 43.6% built
- APPLE AROMA7.1 yr overdueAPPLE BUILDCON · Man, PuneP52100001186· 8.6% built
- BHAKTI SAPPHIRE7.1 yr overdueDHAVAL BUILDERS · Pune City, PuneP52100000646· 58.3% built
- INFINITY TOWER A WING7.1 yr overduePURPLE BUILDCON · Punawale, PuneP52100002680· 75.7% built
- Golden Empire7.1 yr overdueS K Developers · Baner, PuneP52100011647· 90.9% built
- Lotus Laxmi 27.1 yr overdueSURYA PROPERTIES · Pimpri Chinchawad (M Corp.), PuneP52100001075· 90.9% built
- LAXMI NARAYAN HEIGHTS7.1 yr overduePARTH SHREE DEVELOPERS · SASWAD VILLAGE, PuneP52100014603· 90.9% built
- AMITs COLORI Phase-II H and I Building7.1 yr overdueAMIT ENTERPRISES HOUSING LIMITED · Undri, PuneP52100001940· 95.5% built· 2 complaints
- RKL Complex B Building7.1 yr overdueRKL Complex · CHARHOLI, PuneP52100000266· 90.9% built
- Spectra7.1 yr overdueSaarrthi Blue Ventures Limited Liability Partnership · Kothrud, PuneP52100014363· 90.9% built· 1 complaint
- Apple Tree Cottage7.1 yr overdueSaraswati Constructions · pune, PuneP52100003385· 72.6% built
- Alankar E building7.1 yr overdueR K Lunkad Housing Company · charoli, PuneP52100000231· 81.8% built
- PAPA MAMTA RESIDENCY7.1 yr overdueANUP indrapal BASHANI · Wadagaon (CT), PuneP52100005206· 30.5% built
- BON VIVANT7.1 yr overdueMALKANI PROPERTIES · Mundhawa-Keshavnagar, PuneP52100000944· 63.3% built
- Eastwoods7.1 yr overdueSRS PROJECTS JV · kondhwa khurd, PuneP52100001430· filed Jun 2018 → now Jun 2019· 90.9% built
- Prudentia - Phase 17.1 yr overdueVilas Javdekar Eco Shelters Private Limited · Wakad, PuneP52100000114· 66.7% built
- Riddhi Siddhi Enclave7.1 yr overdueSNEHA CONSTRUCTIONS · Pune City, PuneP52100004206· filed Jun 2018 → now Jun 2019· 67.7% built· 1 complaint
- Girisparsh7.1 yr overdueEnvision Landmarks LLP · Haveli, PuneP52100001354· 90.9% built
- S3 PRIME7.1 yr overdueS-3 PROPERTIES · Sus, PuneP52100002314· 60% built
- NIVASA UDAAN7.1 yr overdueNIVASA REALTY · LOHGAON, PuneP52100006335· 51.8% built
- Twin Tower7.1 yr overdueRoyal Unicorn · Bhumkar Vasti, PuneP52100008672· 90.9% built
- LALI RESIDENCY7.1 yr overdueARCHANA DEVELOPERS · GULTEKADI PUNE, PuneP52100008977· 81.8% built
- LODHA BELMONDO AUGUSTA B7.1 yr overdueLodha Developers Limited · Gahunje, PuneP52100000406· 90.9% built· 2 complaints
- XRBIA HINJEWADI ROAD/RIVERFRONT-PH-17.1 yr overdueXrbia North Hinjewadi Developers Private Limited · Bebad Ohol, PuneP52100012738· 90.9% built· 2 complaints
- Vibha7.1 yr overdueBKP Infraa · NARHE, PuneP52100005970· filed Jun 2018 → now Jun 2019· 42% built
- Samarth Nilaya7.1 yr overdueShree Samarthkrupa Associates · Haveli, PuneP52100001584· 72.7% built
- TANVI RESIDENCY7.1 yr overdueARM ENGINEERS · Shirur, PuneP52100003796· 90.9% built
- FLORIDA RIVER BANK7.1 yr overdueONE EARTH · Mundhawa, PuneP52100000236· 90.9% built
- Akshay Classic7.1 yr overdueAkshay Skyscrapers LLP · Pimplesaudagar, PuneP52100007968· 86.4% built
- Konark Orchid I and J7.1 yr overdueKaria Realty · Wagholi, PuneP52100016266· 90.9% built
- Varad Residency - Building B7.1 yr overdueDigambar Laxman Kumbhar · Jijamata nagar, PuneP52100015132· 0.5% built
- GILT RESIDENCES7.1 yr overdueSAMRAT SPACES · Pune (M Corp.), PuneP52100001614· filed Jun 2018 → now Jun 2019· 18.2% built
- Eves Garden Phase V7.1 yr overdueSancheti Properties · Mundhwa, PuneP52100004610· 50% built
- VIVAAN7.1 yr overduePADALE CONSTRUCTIONS PVT LTD · Mahalunge, PuneP52100007627· 18.9% built
- SINDHU SRUSHTI7.1 yr overdueSHREE VIGHNAHAR PROMOTERS AND BUILDERS PVT LTD · Junnar, PuneP52100005663· 78% built
- Highrise Galaxy7.1 yr overdueHIGHRISE BUILDCON · AMBEGAON Bk, PuneP52100012996· 72.7% built
- ANAND TARANG B1 AND B27.1 yr overdueR K LUNKAD BUILDERS AND PROMOTERS · Charoli Phata, PuneP52100000126· 90.9% built
- Regalia Residency7.1 yr overdueRajHeramb Properties · Bavdhan, PuneP52100001872· filed Jun 2018 → now Jun 2019· 90.9% built
- SAI SADAN RESIDENCY 17.1 yr overdueSACHIN GANPATRAO TAWARE · Baramati (M Cl), PuneP52100008043· 90.9% built
- Vertical Oriana Phase II7.1 yr overdueVertical Infra · Mundhwa, PuneP52100003699· 33.9% built
- Rolling Hills7.1 yr overdueSHIVNERI ASSOCIATES · Haveli, PuneP52100001755· 81.8% built
- ARTEMIS7.1 yr overdueCALYX ESTATES · Wadgaon Bk, PuneP52100002256· filed Jun 2018 → now Jun 2019· 90.9% built· 3 complaints
- SWAPNASHILP7.1 yr overdueSHREEJI DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100011002· 86.4% built
- VARDHAMAN RESIDENCY7.1 yr overdueVARDHAMAN ASSOCIATES · Wakad, PuneP52100001375· 70.5% built
- JAI RESIDENCY7.1 yr overdueRAJWADE DEVELOPERS · Ambegaon Budruk, PuneP52100010647· 90.9% built
- ELLANZA PHASE-A7.1 yr overdueMAHESH VITTHAL · WADGAON BUDRUK, PuneP52100003171· 74.4% built
- Abhimanyu Nagari7.1 yr overdueAbhimanyu Group · Baramati (M Cl), PuneP52100010222· 77.3% built
- K K SUNDARBAN BUILDING A17.1 yr overdueK K DEVELOPERS · Girim, PuneP52100008965· 42.7% built
- EMERALD PH-IV7.1 yr overdueGAWADE CONSTRUCTION COMPANY · Wakad, PuneP52100001028· 76.4% built
- VIMAL KASTURI7.1 yr overdueAISHWARYA VIMAL BUILDERS · Haveli, PuneP52100009078· 90.9% built
- NEELKANTH RESIDENCY7.1 yr overdueSHIVSHAKTI ASSOCIATES · Chikhali Bk., PuneP52100011342· filed Jun 2018 → now Jun 2019· 56.4% built
- PRISTINE VILLAS PHASE II7.1 yr overdueATHARV DEVELOPERS · Karla, PuneP52100004703· 23.6% built
- OAKWOOD HILLS7.1 yr overdueSHARAD SOPAN SHENDE · Baner, PuneP52100001235· 39.5% built
- ORCHID CITY BUILDING A7.1 yr overdueS S ASSOCIATES · Baramati (M Cl), PuneP52100004953· filed Jun 2018 → now Jun 2019· 63.2% built
- SONA ESTATE7.1 yr overdueGHARKUL DEVELOPERS · Baramati (M Cl), PuneP52100013167· 68.3% built
- Alankapuram ph 2 D building7.1 yr overdueR K Lunkad Housing corporation · CHARHOLI, PuneP52100000334· 81.8% built
- Dreamcastle7.1 yr overdueSancheti Space · Wakad, PuneP52100002264· 84.8% built
- HOLLYHOCK CITY7.1 yr overdueKate Moze Associates · LOHGAON, PuneP52100013107· 70.2% built
- Venkatesh Galaxy7.1 yr overdueVenkatesh Associates · Tilekar Nagar, PuneP52100006088· 51.1% built
- VISHWA LAXMI7.1 yr overdueSANTOSH RAMCHANDRA JAGTAP · Trishul Housing Society, PuneP52100010518· 90.9% built
- WATER EDGE7.1 yr overdueRAYKAR MARATHE DEVELOPERS · PUNE, PuneP52100008074· 11.8% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.