Delayed projects in Raigarh
1,018 MahaRERA-registered projects in Raigarh are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 4 of 6
- ADINATH ASTHA4.6 yr overdueSHREE RIDDHI SIDDHI CONSTRUCTIONS · SECTOR-2A, RaigarhP52000014792· 90.9% built
- LAKE VIEW RESIDENCY4.6 yr overdueMAITREE DEVELOPERS · CHIKHALE, RaigarhP52000016746· 89.1% built
- SAI GANESH APARTMENT4.6 yr overdueNILESH PADMAKAR VAIDYA · Neral, RaigarhP52000014048· filed Dec 2018 → now Dec 2021· 27.3% built
- ADINATH ARADHANA4.6 yr overdueSHREE RIDDHI SIDDHI CONSTRUCTIONS · SECTOR 2A, RaigarhP52000014700· 90.9% built
- MARUTI SANKUL4.6 yr overdueOM SAI DEVELOPERS · Bopele, RaigarhP52000004469· filed May 2019 → now Dec 2021· 87% built
- Dreams Park - Blossom4.6 yr overdueDreamz Realty · Mamdapur, RaigarhP52000002069· 90.9% built
- PARADISO BAY4.6 yr overdueATHARVA REALTY PRIVATE LIMITED · -, RaigarhP52000012241· 28.8% built
- SAI ANGAN4.6 yr overdueWALMIK RAGHUNATH KHAIRNAR · Nevali, RaigarhP52000004010· filed Dec 2019 → now Dec 2021· 48.4% built· 1 complaint
- Nirman - Dinesh4.6 yr overdueNirman Construction · Roha Ashtami (M Cl), RaigarhP52000000597· 90.9% built
- Horizon Estate4.6 yr overdueGreenscape Kalpana Struct-Con · Uran, RaigarhP52000000107· 90.9% built
- IMPERIAL OASIS4.6 yr overdueImperial Developers · Ulawe, RaigarhP52000003298· 90.9% built
- WHISTLINGWOODSPARK4.6 yr overdueVELANI DEVELOPERS · SHELU, RaigarhP52000012731· 89.1% built
- KARTIKYA KUNJ 24.6 yr overdueSUNIL CHAMANLAL GUPTA · ULWE, RaigarhP52000014867· 72.7% built
- Hansprit Residancy4.6 yr overdueHPDEVELOPERS · Warasgaon, RaigarhP52000011732· 48.6% built
- Nirmal Arcade4.6 yr overdueAkshar Developers · NIRMAN NAGRI, RaigarhP52000009439· 90.9% built
- JEWEL RESIDENCY PHASE 14.6 yr overduePKDEVELOPERS · Nere, RaigarhP52000006943· 45.5% built· 3 complaints
- Retail A4.6 yr overduePersipina Developers Private Limited · Panvel, RaigarhP52000000436· 81.8% built
- AAKRUTI BUILDING NO.24.6 yr overdueAAKRUTI BUILDERS & DEVELOPERS · Pen (M Cl), RaigarhP52000012245· 54.1% built
- SHAGUN CORNER4.6 yr overdueJETHALAL RANCHHOD PATEL · Ulawe, RaigarhP52000002987· 50.9% built· 1 complaint
- SAI MANNAT4.6 yr overdueSWARAJ HOMES BUILDERS AND DEVELOPERS · KARANJADE, RaigarhP52000006287· 72.7% built
- SHREE SAMARTH KRUPA4.6 yr overdueJITENDRA SURYAKANT MANE · Mahad, RaigarhP51900009929· 72.7% built
- SIDDHIVINAYAK UTOPIA - C WING4.6 yr overdueSIDHIVINAYAK BUILTHOME SPECALITIES PRIVATE LIMITED · Panvel, RaigarhP52000009789· 30% built
- EUPHORIA4.6 yr overdueTODAY GLOBAL BUILDERS · Panvel, RaigarhP52000004727· filed Dec 2019 → now Dec 2021· 98.2% built
- National Harmony4.6 yr overdueSunny Housing [india] P Ltd · Panvel, RaigarhP52000002508· 90.9% built
- Mateshwari Desire4.6 yr overdueMateshwari Housing LLP · AKURLI VILLAGE, RaigarhP52000012066· filed Dec 2019 → now Dec 2021· 15.5% built· 1 complaint
- Ambika Niwas4.6 yr overdueLumbaram Modaram Patel · Pushpak Node, RaigarhP52000018656· 90.9% built
- QN GREENS PHASE 14.6 yr overdueQUALITAS NAMAN HOME MAKERS LLP · Panvel, RaigarhP52000007707· filed Dec 2019 → now Dec 2021· 81.1% built· 1 complaint
- VENKATESH NIWAS4.6 yr overdueGANPATI BUILDERS & DEVELOPERS · Karjat, RaigarhP52000007518· 64.3% built
- SPH ROYALE4.6 yr overduePARESH RANCHHOD PATEL · Panvel, RaigarhP52000015687· 0.9% built
- SHIV ORNATE4.6 yr overdueSHIVSHAKTI DEVELOPERS · Ulawe, RaigarhP52000004492· 55.5% built
- LAXMI CASTELLO PHASE-II, B1, A-WING, B2, B-WING4.6 yr overdueLAXMI GLOBAL · KARJAT, RaigarhP52000028993· 90.9% built
- PLATINUM4.6 yr overdueRND BUILDERS & DEVELOPERS · Uran, RaigarhP52000004590· filed Dec 2020 → now Jan 2022· 90.9% built· 1 complaint
- SHIV APARTMENTS4.5 yr overdueKESHAV BUILDCON · Deulwadi, RaigarhP52000011817· filed Feb 2020 → now Feb 2022· 55.3% built
- APOLLO 24.5 yr overdueM/S SHADOW BUILDERS AND DEVELOPERS PVT LTD · Panvel, RaigarhP52000007231· filed Dec 2018 → now Feb 2022· 46.2% built· 31 complaints
- ARIHANT ALOKI PHASE II4.4 yr overdueARIHANT AASHIYANA PRIVATE LIMITED · Karjat, RaigarhP52000006314· 41.5% built· 1 complaint
- LEVANTE4.4 yr overdueAVICON INFRA LLP · NEARBY RAMSETH THAKUR STADIUM, RaigarhP52000012320· filed Sept 2020 → now Mar 2022· 56.6% built
- SHIV SAGAR4.4 yr overdueMAHADEV VELJI PATEL · SECTOR 26, RaigarhP52000015315· 0% built
- Sai Prasad4.4 yr overduePRASAD ESTATE · Panvel, RaigarhP52000007874· filed Sept 2019 → now Mar 2022· 90.9% built
- FUTURE HEIGHTS4.4 yr overdueFUTURE HOMES CONSTRUCTIONS · Panvel, RaigarhP52000006255· 48.2% built· 1 complaint
- TULSI ALAYA4.4 yr overdueTULSI CONSTRUCTIONS · ULWE, RaigarhP52000002347· filed Sept 2020 → now Mar 2022· 72.7% built
- SHALOM ARCADE4.4 yr overdueJACOB GEORGE · Uran, RaigarhP52000009209· filed Mar 2020 → now Mar 2022· 90.9% built
- Mrudagandhar Phase 14.4 yr overdueThe United Group Of Builders And Developers · Ambeghar, RaigarhP52000000998· 31.4% built
- Retail C4.4 yr overduePersipina Developers Private Limited · Panvel, RaigarhP52000001411· 81.8% built
- Jayshree Ram4.4 yr overdueRachana Construction · Panvel, RaigarhP52000018164· 90.9% built
- Ashiyanas Lake View Building No 24.4 yr overdueAteeque Yusuf Khot · Khalapur, RaigarhP52000000361· 90.9% built
- SHANKAR PARVATI RESIDENCY4.4 yr overdueR. S. Construction · pen, RaigarhP52000012212· 90.9% built
- Shankar Parvati Residency Phase 24.4 yr overdueR. S. Construction · Pen (M Cl), RaigarhP52000013704· 90.9% built
- AAHVAAN AVENUE4.4 yr overdueAAHVAAN CONSTRUCTIONS · ULWE, RaigarhP52000016026· 90.9% built
- ARHAM VIEW4.4 yr overdueGALAXY ENTERPRISE · Uran, RaigarhP52000013784· 90.5% built
- DHRUV RESIDENCY-NX4.4 yr overdueKPZ ENTERPRISE · VANGANI WEST, RaigarhP52000014745· 81.8% built
- Roha Prime Square4.4 yr overduePrime Square Properties · Ashtami, RaigarhP51900014230· filed Dec 2020 → now Mar 2022· 90.9% built
- ZEN COUNTY4.4 yr overdueZEN COUNTY · Sudhagad, RaigarhP52000004949· filed Oct 2020 → now Apr 2022· 81.8% built· 1 complaint
- Keru Mata Niwas4.3 yr overdueShree Ambika Builders & Developers · Pushpak New, RaigarhP52000018652· filed Oct 2020 → now Apr 2022· 90.9% built· 1 complaint
- Ornate Heights4.3 yr overdueSADGURU BUILDERS & DEVELOPERS · Panvel, RaigarhP52000010371· filed May 2019 → now Apr 2022· 99.7% built
- SECTOR 37 TALOJA (RENAMED) /SECTOR 29 TALOJA (OLD)4.3 yr overdueCITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED · SECTOR 29, RaigarhP52000017447· filed Oct 2021 → now Apr 2022· 78.2% built
- Sector 40 Kharghar4.3 yr overdueCity and Industrial Development Corporation Of Mahrastra Ltd · Kharghar, RaigarhP52000017448· filed Oct 2021 → now Apr 2022· 78.2% built
- Cluster G4.3 yr overdueShibam Associates · Neral, RaigarhP52000009953· 56.8% built
- Konnark Gardens4.3 yr overdueNinath Bhausaheb Shingade · Chindran, RaigarhP52000009416· 70.3% built· 1 complaint
- DOSTY HERITAGE4.2 yr overdueDOSTY INFRA · KARANJADE, RaigarhP52000016408· 0% built
- SIDDHIVINAYAK RESIDENCY4.2 yr overdueSUYASH SAHAKAR BUILDERS AND DEVELOPERS · PUSHPAK VAHAL ULWE, RaigarhP52000022815· 90.9% built
- GURUDEV PARK4.2 yr overdueGURUDEV ENTERPRISES · Pashane, RaigarhP52000012486· filed Nov 2020 → now May 2022· 90.9% built
- SAIDHAM4.2 yr overdueAnil Pandurang Mungaji · PUSHPAK NODE, RaigarhP52000020672· 9.1% built
- CHAITANYA AAWAS4.2 yr overdueRAJENDRA MADHUKAR JOSHI · KARANJADE NAVI MUMBAI, RaigarhP52000016309· 90.9% built
- jewel heaven phase 14.1 yr overdueJewel Builders and Infraprojects Ltd · Neral, RaigarhP52000015976· filed Jun 2021 → now Jun 2022· 90.9% built
- SAANJ CO OP HSG SOC Praposed4.1 yr overdueShrikrishna Ramchandra Marathe · Bramhan Ali, RaigarhP52000019822· 75.5% built
- Nathsagar residensy4.1 yr overdueSopan Radhakisan Andhale · Khalapur, RaigarhP52000013554· filed Dec 2018 → now Jun 2022· 79.1% built
- LAKE CITY PHASE-24.1 yr overdueSADANAND LAXMANRAO PATIL · Sudhagad, RaigarhP52000017801· 63% built
- UMA IMPERIAL4.1 yr overdueMURUDESHWAR DEVELOPERS · NA, RaigarhP52000002083· filed Jun 2021 → now Jun 2022· 99.8% built· 1 complaint
- SIGNATURE DESIRE4.1 yr overdueSATYAM HOMES · Karjat, RaigarhP52000001892· filed May 2020 → now Jun 2022· 79.7% built
- Hari Om Nagar CHS4.1 yr overdueVASTU INFRA BUILDERS & DEVELOPERS · Panvel, RaigarhP52000007638· filed Jun 2019 → now Jun 2022· 90.9% built
- Anand Nagar Phase 14.1 yr overdueAnubhavshri Realty Pvt. Ltd. · Lonere, RaigarhP52000005747· filed Jun 2018 → now Jun 2022· 99.1% built· 15 complaints
- SHREE NEMINATH HEIGHTS4.1 yr overdueSHREE NEMINATH CONSTRUCTION CO · Karjat, RaigarhP52000002465· 90.9% built
- SHAMAL4.1 yr overdueMorajkar Estates LLP · Karanjade, RaigarhP52000019963· 90.9% built
- Sanskruti Building A4.1 yr overduePushpam Infra LLP · Kashele, RaigarhP52000011794· filed Dec 2018 → now Jun 2022· 81.8% built· 1 complaint
- GAGANGIRI VIHAR COMPLEX4.1 yr overdueCRESCENT INFRASTRUCTURE & DEVELOPING COMPANY · Khalapur, RaigarhP52000003647· filed Dec 2019 → now Jun 2022· 78.6% built
- NISARG4.1 yr overdueIndiapride Infraspaces · Neral, RaigarhP52000002022· filed Dec 2020 → now Jun 2022· 90.9% built
- YOGESHWAR KRUPA CHS4.1 yr overdueJALARAM ASSOCIATES · NEAR TALUKA POLICE STATION, RaigarhP52000015656· 0.5% built
- SAVITRI PEARL4.1 yr overdueMukesh BHOORMAL Jain · Alibag, RaigarhP52000010719· filed Jun 2021 → now Jun 2022· 90.9% built
- Ashray Apartment4.1 yr overdueVINOD BALARAM PATIL · Pushpak New, RaigarhP52000021755· filed Jun 2021 → now Jun 2022· 9.1% built
- MANGALMURTI KRUPA4.1 yr overdueMANGALMURTI CONSTRUCTIONS · PARDESHI ALI, RaigarhP52000018542· 90.9% built
- JAI GANESH4.1 yr overdueAtharv Construction and Developers · Khalapur, RaigarhP52000003906· 63.6% built
- SHREE GANESH NAGAR4.1 yr overdueSHREE GANESH LIFESPACES LLP · Anjap, RaigarhP52000000683· 21.2% built
- VAASTU ADARSH4.1 yr overdueVAASTU Builders & Developers · Ulwe, RaigarhP52000017291· 54.5% built
- Udaan Avenue4.1 yr overdueUDAAN DEVELOPERS · NERAL, RaigarhP52000012197· 85.5% built
- VIDYA HEIGHTS4.0 yr overdueLandmark Builders And Developers · PANVEL, RaigarhP52000017850· 27.3% built
- SUYOG4.0 yr overdueB.Kalyanji Realty · KATANG, RaigarhP52000026252· 90.9% built
- SHREE SAI APARTMENT4.0 yr overdueS K DEVELOPERS · Karjat, RaigarhP52000008128· 47.3% built
- SAI PARADISE4.0 yr overdueS K DEVELOPERS · Karjat, RaigarhP52000005424· 57.7% built
- SUNRISE SEVEN4.0 yr overdueSUNRISE BUILDERS AND DEVELOPERS · KARANJADE, RaigarhP52000020814· 67.3% built
- SECTOR 15 ROADPALI KALAMBOLI3.9 yr overdueCity and Industrial Development Corporation Of Mahrastra Ltd · Roadpali, RaigarhP52000017437· filed Mar 2021 → now Sept 2022· 78.2% built
- SECTOR 21 TALOJA3.9 yr overdueCITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED · SECTOR 21 TALOJA, RaigarhP52000017439· filed Dec 2020 → now Sept 2022· 78.2% built
- PLOT NO 68 SECTOR 12 DRONAGIRI3.9 yr overdueCITY AND INDUSTRIAL DEVELOPEMENT CORPORATION OF MAHARASHTRA LTD · Uran, RaigarhP52000017368· filed Mar 2021 → now Sept 2022· 78.2% built
- SPANDAN APARTMENT3.9 yr overdueSUBODH RAMCHANDRA BHOSALE · Sudhagad, RaigarhP52000025690· 66.8% built
- PLOT NO 01 SECTOR 11 DRONAGIRI3.9 yr overdueCITY AND INDUSTRIAL DEVELOPEMENT CORPORATION OF MAHARASHTRA LTD · DRONAGIRI, RaigarhP52000017480· filed Dec 2020 → now Sept 2022· 78.2% built
- DISHA APARTMENT3.9 yr overdueNORTH POINT HOME · ULWE NAVI MUMBAI, RaigarhP52000021949· 27.3% built
- SPAN EXOTICA3.9 yr overdueSPAN STRUCTURES · Ulawe, RaigarhP52000008675· 90.9% built· 1 complaint
- Emvis Tower C3.8 yr overdueM/S Emerald Developers · Mahadik Wadi Behind Pen Court, RaigarhP52000025984· 90.9% built
- VINAYAK SANKUL PHASE I3.8 yr overdueM/S VINAYAK ASSOCIATES · Dahivali Tarfe Need, RaigarhP52000016291· 90.9% built
- KVK ARUM3.8 yr overdueM/S. KVK BUILDERS & DEVELOPERS · VADAGHAR, RaigarhP52000015928· 90.9% built
- Pacific3.7 yr overduePrashant Madhusudan Naik · Alibag, RaigarhP52000007367· 81.8% built
- Madhav Ganga3.7 yr overdueDolphin Developers · Khalapur, RaigarhP52000003944· 90.9% built
- RS EXOTICA3.7 yr overdueRS BUILDERS & DEVELOPERS · Panvel, RaigarhP52000006872· filed Dec 2021 → now Dec 2022· 61.8% built
- PRAYAG MEADOWS PHASE - l3.7 yr overduePRAYAG BUILDERS AND DEVELOPERS · VICHUMBE, RaigarhP52000017065· 90.9% built
- Neelkanth Co.Op.Soc.3.7 yr overdueswapnil mohan kalyankar · Khalapur, RaigarhP52000009820· 84.8% built
- MARATHON NEXZONE AVIOR -23.6 yr overdueSANVO RESORTS PVT. LTD. · PALASPE PHATA, RaigarhP52000000713· filed Jun 2021 → now Dec 2022· 72.7% built· 6 complaints
- Pratik Residency3.6 yr overdueM/s Pratik constructions · Panvel, RaigarhP52000007028· 97.5% built
- The Serenes Villa No 213.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012819· 40.9% built
- The Serenes Villa No 203.6 yr overdueMahindra Lifespace Developers limited · NAGAON, RaigarhP52000012522· 40.9% built
- SHANTI HARMONY3.6 yr overdueSHANTI DEVELOPERS · VAKADI, RaigarhP52000015820· 86.4% built
- DEV LUXURIA3.6 yr overdueDevkrupa Enterprises · Uran, RaigarhP52000004220· filed Jun 2021 → now Dec 2022· 96.4% built
- SHIV SHAMBHO COMPLEX3.6 yr overdueMAITREE ASSOCIATES · USARLI, RaigarhP52000019349· 61.8% built
- APEX SHUKAN3.6 yr overdueAPEX BUILDCON · PUSHPAK, RaigarhP52000021219· 81.8% built
- Krushna Apartment3.6 yr overdueDATTA KRUPA ENTERPRISES · Pushpak New, RaigarhP52000021703· 55.5% built
- The Serenes Villa No 133.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012781· 81.8% built
- EXCEL GALAXY3.6 yr overdueEXCEL CONSTRUCTIONS · ULWE, RaigarhP52000017632· 90.9% built
- The Serenes Villa No 193.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000013839· 40.9% built
- ALANKAAR RESIDENCY3.6 yr overdueS P DEVELOPERS · HOC COLONY, RaigarhP52000014698· 90.9% built
- The Serenes Villa No 223.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012523· 40.9% built
- Indiabulls Greens - 43.6 yr overdueLucina Land Development Limited · Panvel, RaigarhP52000002658· filed Jun 2021 → now Dec 2022· 99.5% built· 7 complaints
- PRAMUKH NARAYAN3.6 yr overduePRAMUKH DEVELOPERS · TALOJA NEW, RaigarhP52000019977· 90.9% built
- PRAYAG YASH PHASE ll3.6 yr overduePRAYAG PROPERTIES · Near ZP School, RaigarhP52000016045· 90.9% built
- Jupiter Prime3.6 yr overdueArjun Ashok Tarachandani · Pushpak New, RaigarhP52000018263· 53.6% built
- M P Keshav3.6 yr overdueM P Construction · Pushpak New, RaigarhP52000019549· 90.9% built
- The Serenes Villa No 43.6 yr overdueMahindra Lifespace Developers limited · Nagaon, RaigarhP52000012795· 38.2% built
- The Serenes Villa No 173.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012537· 40.9% built
- The Serenes Villa No 473.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000017563· 40.9% built
- MOHAN RESIDENCY3.6 yr overdueSAIRAJ ENTERPRISES · Panvel, RaigarhP52000012544· 90.9% built
- The Serenes Villa No 113.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012524· 40.9% built
- GANESHMURTI APARTMENT3.6 yr overdueNOOR MOHAMMED IDRIS JALGAONKAR · SECTOR R4 PUSHPAK, RaigarhP52000021824· 90.9% built
- Building no. 1 , Uptown Avenue3.6 yr overdueSimran Enterprises · Sai Nagar, RaigarhP52000016037· 90.9% built
- Nirman Vimla Kanti3.6 yr overdueNirman Construction · Roha Ashtami (M Cl), RaigarhP52000003155· 90% built
- The Serenes Villa No 73.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012867· 40.9% built
- AVIGHNA3.6 yr overdueV.S.CONSTRUCTIONS · Panvel, RaigarhP52000013885· 90.9% built
- Mohnesh3.6 yr overdueMotwani International Services · Kalundre (CT), RaigarhP52000012024· filed Dec 2019 → now Dec 2022· 67.7% built
- NANDADEVI GALAXY3.6 yr overdueAAIJI GROUP · KARANJADE, RaigarhP52000009334· 86.4% built
- HILLSIDE SPACE3.6 yr overdueSPACE HOUSING · Karjat, RaigarhP52000006003· 79.5% built
- SEA REGENCY3.6 yr overdueSUREKHA TUKARAM DUDHE · Navi Mumbai, RaigarhP52000010351· filed Dec 2021 → now Dec 2022· 98.2% built· 3 complaints
- The Serenes Villa No 93.6 yr overdueMahindra Lifespace Developers limited · Nagaon, RaigarhP52000012915· 35.5% built
- SHREE RAM KRUPA APARTMENT3.6 yr overdueVISHAL DILIP DOSHI · NEAR UBHA MARUTI, RaigarhP52000017712· 90.9% built
- Dwarka3.6 yr overdueMorajkar Estates LLP · Karanjade, RaigarhP52000020710· 78.2% built
- Mahaavir Majesty - Phase II3.6 yr overdueMahaavir Impex · Near Taloja Phase II, RaigarhP52000016434· 90.9% built
- SADANAND SHILP3.6 yr overdueDEVYANI HARISHCHANDRA ULWEKAR · Kalundre, RaigarhP52000013481· 82.3% built
- SAROVAR3.6 yr overdueS D Buildcon · Uran, RaigarhP52000001908· 70.5% built
- DEVIKE CONSTRUCTION3.6 yr overdueSURESH GANPAT MORE · PANCHIL NAGAR, RaigarhP52000015551· 75.5% built
- MIDAS RESIDENCY -23.6 yr overdueMIDAS TOUCH INFRA · PRABHAT COLONY MAHAD CITY, RaigarhP52000015215· 81.8% built
- Haware Meadows Phase 13.6 yr overdueHAAAS Corporation Private Limited · Mamdapur, RaigarhP52000015126· 90.9% built
- BHAKTI NIWAS3.6 yr overdueVISHAL RATANSHI PATEL · Panvel, RaigarhP52000015471· 90.9% built
- SIDDHIVINAYAK PRATIMA3.6 yr overdueSIDDHIVINAYAK HOMES · Koyana Velhe, RaigarhP52000015123· 90.9% built
- The Serenes Villa No 103.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000013927· 40.9% built
- Anant Sapphire3.6 yr overdueAnant Realty · Adai, RaigarhP52000017134· 90.9% built
- KAMALJA3.6 yr overdueM/S. SAIVIJAY BUILDERS AND DEVELOPERS JADHAV KADU · ULWE, RaigarhP52000017514· 81.8% built
- SUKHADA CO-OP HOUSING SOCIETY3.6 yr overdueKAUSTUBH JEEVAN KULKARNI · VIDYANAGAR EAST, RaigarhP52000021391· 90.9% built
- The Serenes Villa No 83.6 yr overdueMahindra Lifespace Developers limited · Nagaon, RaigarhP52000012883· 34.4% built
- The Serenes Villa No 163.6 yr overdueMahindra Lifespace Developers limited · nagaon, RaigarhP52000012788· 40.9% built
- SANSKRUTI3.6 yr overdueM/S. V.R. BUILDERS · Sector 19, RaigarhP52000014578· 90.9% built
- SAUSHILYA3.6 yr overdueSILVER LEAF REALTY · Mamdapur, RaigarhP52000004115· 90.9% built
- R.K. MAJESTIC3.6 yr overdueR K CONSTRUCTION · -, RaigarhP52000020806· 9.1% built
- SIDDHESHWAR RESIDENCY3.6 yr overdueSIDDHIVINAYAK ASSOCIATES · NEAR SIDDHESHWAR TEMPLE, RaigarhP52000016759· 82.2% built
- MARATHON NEXZONE ALTIS -23.6 yr overdueSANVO RESORTS PVT. LTD. · PALASPE PHATA, RaigarhP52000000677· filed Jun 2021 → now Dec 2022· 72.7% built· 1 complaint
- REDWOOD LANDMARK3.6 yr overdueREDWOOD DEVELOPERS · NEAR CARMEL SCHOOL, RaigarhP52000012810· filed Dec 2021 → now Dec 2022· 90.9% built
- Anant Sakshi3.6 yr overdueAnant Builders · Sakshi Nagar, RaigarhP52000019773· 57.3% built
- Keshar Kunj3.6 yr overdueKeshar Realities · Panvel, RaigarhP52000008372· 55.1% built
- Ramrai Kunj3.6 yr overdueSantosh Ramchandra Karavkar · Panvel, RaigarhP52000011536· 90.9% built
- GALAXY APARTMENTS3.6 yr overdueDIVINE DOLPHIN ENTERPRISES · Ulwe (New), RaigarhP52000018320· 90.9% built· 1 complaint
- SHREE GANESH3.6 yr overdueSHREE ENTERPRISES · SECTOR 5A, RaigarhP52000020556· 81.8% built
- Eternia Space3.6 yr overduePLANET SPACE · Karjat, RaigarhP52000008057· 81.8% built· 1 complaint
- REWILLAX TANISHQ3.6 yr overdueREWILLAX BUILDCON · Karjat, RaigarhP52000002166· filed Dec 2020 → now Dec 2022· 90.9% built
- ONE KIYO PHASE-I3.6 yr overdueONEARTH CREATORS LLP · MAMDAPUR, RaigarhP52000002212· filed Dec 2020 → now Dec 2022· 65.7% built
- SERENA3.6 yr overdueMAVERICK DEVELOPERS DRONAGIRI · Uran, RaigarhP52000009481· filed Dec 2021 → now Dec 2022· 59.9% built
- ORCHID PARK3.6 yr overdueUNITED ONE REALTY LLP · MAMDAPUR, RaigarhP52000016238· filed Dec 2019 → now Dec 2022· 86.8% built
- AVIVA APARTMENT3.6 yr overdueSHRINE ENTERPRISES · Mamdapur, RaigarhP52000009385· filed Dec 2018 → now Dec 2022· 72.7% built
- TARAMATI TOWER WING I AND J3.6 yr overdueVAST CONSTRUCTION · PEN, RaigarhP52000021617· 53% built
- Alibag Horizon3.5 yr overdueACORP · vidyanagar, RaigarhP52000019811· 90.9% built
- Konnark Heavens3.4 yr overdueNinath Bhausaheb Shingade · Panvel, RaigarhP52000003634· filed May 2022 → now Mar 2023· 89.1% built· 3 complaints
- ROSEWOOD BUILDING NO. 13.4 yr overdueSVS GROUPS · Karjat, RaigarhP52000011741· filed Mar 2022 → now Mar 2023· 73.1% built
- GAURISUTA3.4 yr overdueSAI DEVELOPERS · NEAR KARNALA SPORTS ACADEMY, RaigarhP52000018222· 54.7% built
- APEX AURA3.4 yr overdueAPEX BUILDCON · DRONAGIRI, RaigarhP52000019129· 90.9% built
- SAI AASTHA3.4 yr overdueYASH RAJ DEVELOPERS · SECTOR 4, RaigarhP52000015632· 90.9% built
- KANKESHWAR VRINDAVAN3.4 yr overdueKANKESHWARA BUILDCON PRIVATE LIMITED · ALIBAG, RaigarhP52000000991· filed Mar 2020 → now Mar 2023· 90.9% built
- AAKRUTI BUILDING NO. 4 AND 53.4 yr overdueAAKRUTI BUILDERS & DEVELOPERS · Pen (M Cl), RaigarhP52000005056· filed Jun 2021 → now Mar 2023· 63.2% built
- MAITRI3.4 yr overdueMAITRI ENTERPRISES · DRONAGIRI, RaigarhP52000030192· 90.9% built
- SHREE SWAMI SAMARTH APARTMENT3.4 yr overduePRAVIN LALCHAND JAIN LALCHAND TESHU DEVELOPERS · MG ROAD MAHAD, RaigarhP52000018419· filed Dec 2021 → now Apr 2023· 90.9% built
- Vesta3.3 yr overduePersipina Developers Private Limited · Bhokarpada, RaigarhP52000001078· 95% built
- QUALCON PALMS3.3 yr overdueQualcon Ecostar Realty LLP · Panvel, RaigarhP52000015616· 25.2% built
- The Habitat3.2 yr overdueARP INFRA · Khopoli, RaigarhP52000021010· 84.5% built
- SATYAM PEARL3.2 yr overdueSATYAM GROUP · Panvel, RaigarhP52000026688· 90.9% built
- J K PARAMOUNT3.2 yr overdueJ.K.INFRA BUILDERS & DEVELOPERS · PUSHPAK NODE, RaigarhP52000029517· 81.8% built
- DIVINE COMPLEX3.2 yr overdueDIVINE BUILDERS & DEVELOPERS · CHIKHALE, RaigarhP52000014112· filed Jan 2020 → now Jun 2023· 47.6% built
- AADAR DEVELOPERS3.2 yr overdueAADAR DEVELOPERS · Raigad, RaigarhP52000008366· filed Dec 2019 → now Jun 2023· 27.3% built
- SHIV RESIDENCY3.2 yr overdueSHIVKRUPA COLOSSAL LLP · SECTOR 3, RaigarhP52000019162· 90.9% built
- VAKRATUNDA RESIDENCY3.2 yr overdueGREENFIELD DEVELOPERS · KHANDAD, RaigarhP52000028328· 80.9% built
- TULSI CHHAYA3.2 yr overdueTULSI UNISON · Karjat, RaigarhP52000003264· filed Dec 2019 → now Jun 2023· 87.6% built
- Sai Residency3.2 yr overdueSatguru Construction and Developers · Utekhol, RaigarhP52000011265· filed Aug 2019 → now Jun 2023· 90.9% built
- Shivam Complex Phase - 13.1 yr overdueManoj Ramanand Prajapati · Lodhivali, RaigarhP52000015165· filed Dec 2020 → now Jun 2023· 90.9% built
- PADMAVATI DARSHAN BUILDING NO 23.1 yr overduePADMAVATI CONSTRUCTION · NANDIMAL NAKA, RaigarhP52000026108· 18.2% built
- APEX ADDRESS3.1 yr overdueAPEX BUILDCON · NODE PUSHPAK, RaigarhP52000021012· 81.8% built
- OMKAR HEIGHTS3.1 yr overdueANIKET TANAJI CHAVAN · PUSHPAK NODE, RaigarhP52000027718· 27.3% built
- AYESHA PLANET3.1 yr overdueANISA SUBHAN PATEL · TALOJA, RaigarhP52000027819· 81.8% built
- Sai Aangan3.1 yr overdueVIR Enterprises · Panvel, RaigarhP52000004701· filed Mar 2020 → now Jun 2023· 90.9% built· 1 complaint
- Mahalaxmi Nivara3.1 yr overdueMAHALAXMI BUILDTECH LLP · Mangaon, RaigarhP51900007332· filed Jun 2021 → now Jun 2023· 77.1% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.