Delayed projects in Thane
1,619 MahaRERA-registered projects in Thane are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 8 of 9
- SILVER OAK APARTMENT1.5 yr overdueASHOKKUMAR TOPANLAL DEWANI · SHAHAPUR, ThaneP51700051210· 62.6% built
- AKSHAR ELITA1.5 yr overdueVAGAD CONSTRUCTIONS · NAVI MUMBAI, ThaneP51700005621· filed Dec 2019 → now Apr 2025· 96.8% built
- ASHTAVINAYAK1.5 yr overduePARISPARSH · SAI BABA MANDIR, ThaneP51700046185· 10% built
- Chandraprabhakar Co-operative Housing Society Limited1.5 yr overdueMellennium Homes · Garibcha wada Dombivli west, ThaneP51700048538· 87.3% built
- Runwal Shopping Arcade1.5 yr overdueRunwal Residency Private Limited · Dombivli, ThaneP51700026438· filed Apr 2024 → now Apr 2025· 90.9% built· 1 complaint
- KANHA RESIDENCY1.4 yr overdueKULKARNII BUILDER · BELAVALI GAON, ThaneP51700030985· 90.9% built
- Courtyard - Rozanne1.4 yr overdueCOURTYARD REAL ESTATE PRIVATE LIMITED · Thane, ThaneP51700006312· 88.6% built· 3 complaints
- Kamdhenu23-west1.4 yr overdueAccura Developers LLP · Thane, ThaneP51700025164· 75.5% built
- SAI HANUMAN TOWER B WING1.4 yr overdueOM SAI BABA BUILDERS · RAI, ThaneP51700048598· 89.1% built
- Paramount A1.3 yr overdueKalpataru Homes Private Limited · Thane, ThaneP51700004031· 93.9% built· 5 complaints
- HERITAGE GARDEN1.3 yr overdueHERITAGE GARDEN · Ulhasnagar, ThaneP51700054143· 53.6% built
- PATELS PRESTIGE1.3 yr overdueVRUDEE ASSOCIATES · AMBERNATH, ThaneP51700017035· filed Dec 2022 → now Jun 2025· 77% built
- ADITYA HEIGHTS1.3 yr overdueRATNAKAR DHARMA PATIL · MANDA, ThaneP51700048244· 90.9% built
- RUNWAL EIRENE - PART I1.3 yr overdueRUNWAL DEVELOPERS LIMITED · Thane, ThaneP51700004574· 99.3% built· 56 complaints
- RAUNAK CITY SECTOR IV - D41.3 yr overdueRAUNAK CORPORATION · KALYAN WEST, ThaneP51700019962· 90.9% built· 4 complaints
- NISARG GREENS Phase - 2 D1.3 yr overdueNND Ambernath LLP · Amberntah East, ThaneP51700031807· 63.6% built
- 27 East1.3 yr overdueRashi Developers · Sagaon, ThaneP51700028466· 65.3% built
- Paramount B1.3 yr overdueKalpataru Homes Private Limited · Thane, ThaneP51700004741· 93.4% built· 1 complaint
- Royal Palm1.3 yr overdueBuildcon Enterprises · Washind, ThaneP51700028329· filed Jun 2024 → now Jun 2025· 78.5% built
- Birla Vanya - Phase 11.3 yr overdueAditya Birla Real Estate Limited · Shahad, ThaneP51700019178· 99.2% built· 8 complaints
- NISARG GREENS Phase - 2 F1.3 yr overdueNND Ambernath LLP · Ambernath East, ThaneP51700031797· 72.7% built
- Prapti Heritage1.3 yr overdueTridev Enterprises · Manjarli Badlapur West, ThaneP51700025683· 90.9% built
- KYRAA PARK1.3 yr overdueKYRAA INFRA PROJECTS PRIVATE LIMITED · Thane, ThaneP51700005769· filed Dec 2023 → now Jun 2025· 67.3% built· 4 complaints
- PINNACLE ADARSH1.3 yr overduePINNACLE ENTERPRISES · BELAVLI BADLAPUR WEST, ThaneP51700050363· 90.9% built
- Paramount D1.3 yr overdueKalpataru Homes Private Limited · Thane, ThaneP51700021474· 81.1% built· 5 complaints
- EAGLERIDGE WING B1.2 yr overdueROMA BUILDERS PRIVATE LIMITED · PATLIPADA, HIRANANDANI ESTATE, OFF GHODBUNDER ROAD, ThaneP51700017267· 90.9% built
- EAGLERIDGE WING A1.2 yr overdueROMA BUILDERS PRIVATE LIMITED · PATLIPADA, HIRANANDANI ESTATE, OFF GHODBUNDER ROAD, ThaneP51700019923· 90.9% built
- SARVODAY NAGAR SECTOR 11.2 yr overdueTHALIA INVESTMENT PRIVATE LIMITED · Ambarnath, ThaneP51700007690· 89.1% built· 1 complaint
- FULORA CO-OP HOUSING SOCIETY LTD1.2 yr overduePINNACLE CREATORS · BADLAPUR EAST, ThaneP51700046975· 90.9% built
- MAYURESH PLANET1.1 yr overdueSHREEGOPAL JUGALKISHORE BARASIA · Thane, ThaneP51700011665· 86.4% built
- Harikunj Enclave1.1 yr overdueSamir Shrinivas Kale · Brahman Society, Naupada, ThaneP51700047799· 80.9% built
- SKYRISE RESIDENCY1.1 yr overdueNISHITH SUBANDHU LUHAR · AMBERNATH, ThaneP51700051261· filed Jul 2025 → now Sept 2025· 81.8% built
- SNEHAM1.1 yr overdueParidhi Developers · Thane, ThaneP51700020410· filed Feb 2025 → now Sept 2025· 81.8% built
- VIVANTA MARVEL1.0 yr overdueTECHNO VISION REALTORS LLP · MIRA ROAD - EAST, ThaneP51700031458· 90% built· 1 complaint
- Maatr Skye1.0 yr overdueMaatr Ventures · Khadakpada, ThaneP51700028786· 90.9% built
- AYESHA GARDEN B WING1.0 yr overdueAZKA BUILDERS AND DEVELOPERS · KALYAN, ThaneP51700033810· filed Dec 2024 → now Sept 2025· 82.3% built
- RAM RIVERA1.0 yr overdueKULGAON BADLAPUR, ThaneP51700049706· 39% built
- Metropolis - Aquaris Phase 21.0 yr overdueANANT SQUARE · Kasarvadavli, ThaneP51700022959· 90.9% built
- PRISM INDUSTRIAL ESTATE11 mo overdueSPLENDOR SHELTERS PVT LTD · NEAR PENDHARKAR COLLEGE, ThaneP51700032231· 90.9% built
- PALAVA SERENITY A11 mo overdueLodha Developers Limited · Palava, ThaneP51700020155· 73.6% built
- Lodha Amara - Wing 40 and 4111 mo overdueLODHA DEVELOPERS LIMITED · Balkum, ThaneP51700020088· filed Nov 2024 → now Nov 2025· 81.6% built· 1 complaint
- Morivali Richmand Park10 mo overdueSHREE KHODIYAR BUILDCON · Mauje Morivali, ThaneP51700046687· filed Nov 2024 → now Nov 2025· 52.7% built
- IMPERIAL HEIGHTS PHASE I - A AND B WING9 mo overdueAKSHAR SHANTI REALTORS PRIVATE LIMITED · Thane, ThaneP51700006296· filed Dec 2024 → now Dec 2025· 99.1% built· 5 complaints
- North Barcelona9 mo overdueJP Infra Residency Private Limited · Near Vinay Nagar, ThaneP51700020082· 67.8% built· 3 complaints
- MM VALLEY A-19 mo overdueALFA ENTERPRISES · KAUSA-MUMBRA-THANE, ThaneP51700024240· 79.8% built· 1 complaint
- ARIHANT CITY PHASE-I BUIDING-A,B,C,D,D1,D2,H,H1,H2,F9 mo overdueARIHANT ENTERPRISES · Bhiwandi, ThaneP51700010884· 86.5% built
- Mahavir Spring - Daffodils - Phase 29 mo overdueVinayak developers · Pokhran Road No. 2, ThaneP51700022995· 79.5% built
- HUDA PARK9 mo overdueHUDA CONSTRUCTION · KAUSA MUMBRA, ThaneP51700016090· filed Dec 2024 → now Dec 2025· 81.8% built
- Immensa G9 mo overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700001083· 70.4% built· 14 complaints
- Godrej Alive C9 mo overdueModella Textile Industries Limited · Mulund Thane Circle, ThaneP51700009993· 0% built· 2 complaints
- RAUNAK HEIGHTS9 mo overdueUNNATHI ASSOCIATES · Thane, ThaneP51700000766· 90.9% built· 3 complaints
- Godrej Alive A9 mo overdueModella Textile Industries Limited · Mulund Thane Circle, ThaneP51700010303· 0% built· 2 complaints
- NICE CITY9 mo overdueNICE REALTY AND DEVELOPERS · Thane, ThaneP51700010742· 89.1% built
- Sunrise Parkview Phase I9 mo overdueSukham Corporation Proprietor Sunrise Lifespaces LLP · Padle Village, ThaneP51700021145· 86.4% built
- UNNATHI WOODS PHASE VII A9 mo overdueUNNATHI ESTATES · Thane, ThaneP51700000002· 90.9% built· 5 complaints
- MILLANO HEIGHTS9 mo overdueCHIMNANI CONSTRUCTIONS · Ulhasnagar, ThaneP51700047948· filed Dec 2024 → now Dec 2025· 86.8% built
- GLENDALE9 mo overdueROMA BUILDERS PRIVATE LIMITED · PATLIPADA, HIRANANDNAI ESTATE, OFF. G B ROAD, ThaneP51700019542· 90.9% built
- RAUNAK CITY SECTOR IV - D19 mo overdueRAUNAK CORPORATION · Kalyan, ThaneP51700003377· 90.9% built
- vedant nakshatra M phase 29 mo overdueMOHAN HARDASMAL THARWANI · Rameshwadi, ThaneP51700008414· 69.5% built
- Immensa D9 mo overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700000732· 89.8% built· 27 complaints
- GLENRIDGE9 mo overdueROMA BUILDERS PRIVATE LIMITED · PATLIPADA, HIRANANDANI ESTATE, OFF. G B ROAD, ThaneP51700019550· 90.9% built
- Immensa A9 mo overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700001039· 99.8% built· 24 complaints
- Godrej Alive B9 mo overdueModella Textile Industries Limited · Mulund Thane Circle, ThaneP51700005281· 0% built· 9 complaints
- Immensa E9 mo overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700000924· 89.7% built· 19 complaints
- JP North Imperia - Tower 19 mo overdueJP Infra Realty Private Limited · Near Vinay Nagar, ThaneP51700019613· 88% built· 1 complaint
- AMBER TARA9 mo overdueAMBERCORPORATION · TUKARAM NAGAR, ThaneP51700020065· 90.9% built
- JP North Imperia - Tower 29 mo overdueJP Infra Realty Private Limited · Near Vinay Nagar, ThaneP51700019783· 90.9% built
- RAUNAK CITY SECTOR IV - D29 mo overdueRAUNAK CORPORATION · Kalyan, ThaneP51700003210· 90.9% built
- SARVODAY SQUARE PHASE 2 BLDG NO 29 mo overdueSHREE SQUAREFEET ENTERPRISES LLP · Ambarnath, ThaneP51700018388· 90.9% built
- Godrej Alive E9 mo overdueModella Textile Industries Limited · Thane (M Corp.), ThaneP51700009992· 0% built· 1 complaint
- Immensa H9 mo overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700001310· 66.6% built· 20 complaints
- Immensa F9 mo overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700001278· 91.1% built· 25 complaints
- JP North Euphoria9 mo overdueJP Infra Realty Private Limited · Vinaynagar, ThaneP51700016290· 86.1% built· 2 complaints
- Immensa C9 mo overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700001040· 98.9% built· 24 complaints
- Immensa B9 mo overdueAgile Real Estate Pvt. Ltd. · Thane, ThaneP51700000927· 99% built· 25 complaints
- ORCHID SQUARE PHASE 49 mo overdueM/S SQUAREFEET ECO HOUSING LLP · Ambarnath, ThaneP51700022076· 81.8% built
- JP North Alexa9 mo overdueJP Infra Realty Private Limited · near Vinay Nagar, ThaneP51700016736· 81.8% built
- GLENWOOD9 mo overdueROMA BUILDERS PRIVATE LIMITED · PATLIPADA, HIRANANDANI ESTATE, OFF. G B ROAD, ThaneP51700019547· 90.9% built
- ATMIYA HEIGHTS9 mo overdueAKSHAR GROUP · SONIVALI, ThaneP51700015091· 83.3% built
- SHIVTEJ ASHIYANA9 mo overdueYOGESH RAMDAS SARJINE · Seawoods, ThaneP51700011753· filed Apr 2018 → now Dec 2025· 90.9% built
- KABINI9 mo overdueShree Shakti Developers · Chavindra, ThaneP51700010423· filed Dec 2021 → now Dec 2025· 90.9% built· 1 complaint
- AARADHYA HIGHPARK PROJECT III of PHASE 19 mo overdueMAN VASTUCON LLP · NEAR SINGAPORE INTERNATIONAL SCHOOL, ThaneP51700030611· 95% built· 2 complaints
- Shri Sai Mangal Co-Op Housing Society Ltd A Building9 mo overdueAMOGH ASSOCIATES · Village Chole , Thakurli, ThaneP51700050524· 84.1% built
- KATARIAS SHIV SHRISHTI9 mo overdueSHIV SAGAR DEVELOPERS AND BUILDERS · MORIVALI, ThaneP51700046409· 72.3% built
- Guru Ganesh CHS9 mo overdueVADNERE BUILDER & DEVELOPERS · Badlapur East, ThaneP51700049564· 81.8% built
- AMBER BLISS9 mo overdueM/S. AMBER COMBINES · DOMBIVLI WEST, ThaneP51700032492· 79.1% built
- SARVESH DREAM CITY WING D9 mo overdueSAI SHRADHA DEVELOPERS · JOVELI, ThaneP51700030642· 61.8% built
- GAYATRI NIWAS9 mo overdueGayatri Builders · CHIKANGHAR, ThaneP51700029816· 90.9% built
- Sai Pearl9 mo overdueM/S MITRA REALITY · Katrap, ThaneP51700030340· 86.4% built· 1 complaint
- JVMs Spectrum9 mo overdueJVM Spectrum LLP · Dhokali- Thane, ThaneP51700050671· 72.7% built
- SHARDA EMPORIO9 mo overdueSHARDA INFRA · NEAR AMAN TALKIES, ThaneP51700047731· 23.6% built
- MEERA SQUARE9 mo overdueSARASWATI CORP · BEHIND SHIV MANDIR, ThaneP51700053500· filed Jun 2025 → now Dec 2025· 71.6% built
- LAXMI NARAYAN CO OP HOUSING SOCIETY LTD9 mo overdueOJASS GOVIND INFRA LLP · NAUPADA, ThaneP51700049169· 74.3% built
- Ekatva Coral9 mo overdueSynergy Developers · Pancpakhadi, ThaneP51700049059· 66.8% built
- BALAJI EXOTICA BUILDING TYPE D PHASE III9 mo overdueBALAJI WORLD · CHIKANGHAR, ThaneP51700026674· filed Jun 2023 → now Dec 2025· 90.9% built· 1 complaint
- RAUNAK RESIDENCY9 mo overdueUNNATHI ESTATES · Thane, ThaneP51700009540· filed Jun 2024 → now Dec 2025· 69.5% built· 1 complaint
- Sai Heights Building No.1 B Wing9 mo overdueSai Siddhi Developers · Vithalwadi,, ThaneP51700032918· 90.9% built
- MANOHAR MAHAL9 mo overdueSHARDA VASTU NIRMITEE PVT. LTD. · PANCHPAKHADI, ThaneP51700048230· 81.8% built
- CHINTAMANI HABITAT JASMINE TYPE A-B-J9 mo overdueJASHNANI CONSTRUCTION PRIVATE LIMITED · SHAHAPUR, ThaneP51700034891· 81.8% built
- OMKAR RESIDENCY9 mo overdueM/s OMKAR ASSOCIATES · manda, ThaneP51700029285· 81.8% built
- Shiv Paradise9 mo overdueShiv Corporation · Shirgaon, ThaneP51700046607· 90.9% built
- Vakratunda CHS9 mo overdueARYA ENTERPRISES · THANE, ThaneP51700049403· 45.5% built
- JVMs Magnum9 mo overdueJVM Spectrum LLP · Dhokali- Thane, ThaneP51700052431· 78.2% built
- Shivam Homes Wing A and B9 mo overdueShivam Homes · Badlapur East, ThaneP51700048026· 81.8% built
- Anjani Pride9 mo overdueGeeta Developers · Mira Road (East), ThaneP51700024335· filed Jul 2025 → now Dec 2025· 88.6% built
- AUROVILLE A AND B WING9 mo overdueARYA CONSTRUCTION · SANDAP, ThaneP51700047056· 81.8% built
- Sai Heritage9 mo overdueShashank Enterprises · Ambernath, ThaneP51700053065· 80.5% built
- MAXIMUS9 mo overdueGURUVIDHA ENTERPRISES · BHAYANDAR, ThaneP51700045811· 0.9% built
- ISKCON RESIDENCY PHASE 19 mo overdueIskcon Realtors · AMBERNATH, ThaneP51700051160· 59.1% built
- Gaurang Apartment9 mo overdueGanesha Developers · Opp to State Bank of India, ThaneP51700048961· filed Dec 2024 → now Dec 2025· 90.9% built
- SUKH SAGAR CO-OP HSG SOCIETY9 mo overdueNOBLE INFRASTRUCTURE BUILDER AND DEVELOPERS · KATRAP, ThaneP51700051135· 72.7% built
- Balaji Heritage9 mo overdueBalaji Developers · Belavali, ThaneP51700048085· filed Dec 2024 → now Dec 2025· 79.5% built
- KOEL9 mo overdueShree Shakti Developers · Chavindra, ThaneP51700007920· filed Dec 2021 → now Dec 2025· 90.9% built
- Lakeview Co Operative Housing Limited9 mo overdueGP Infra · Neelkanthnagar, Kalyan, ThaneP51700049612· 81.8% built
- SAI MAJESTIC PARK8 mo overdueMARUTI DEVELOPERS · ROOM NO 362 SHEET NO 42, ThaneP51700050235· 43.6% built
- Amber Galaxy C Wing7 mo overduePANDHARINATH SITARAM PATIL · VITAWA, ThaneP51700024773· filed Jan 2024 → now Mar 2026· 26.8% built· 1 complaint
- SURYA EXCELLENCY7 mo overdueSURYAKANT MANGALDAS SAMANI AND CHAMPABEN VASANJI MASHRU · NARPOLI, ThaneP51700015832· 86.2% built
- SAI VIJAY HERITAGE7 mo overdueVIJAY LALSINGH THAKUR · Ulhasnagar, ThaneP51700034485· filed Mar 2025 → now Mar 2026· 51.8% built
- SUMITRA HEIGHTS7 mo overdueSWAMI NARAYAN ENTERPRISES · KALYAN DOMBIVLI M CORP, ThaneP51700052785· 90.9% built
- M M CITY7 mo overdueFINE CONSTRUCTION COMPANY · NEW SHILL, ThaneP51700022075· 84.1% built
- KAPIL BLING6 mo overdueTRIDENT BUILDERS AND DEVELOPERS · BHIWANDI, ThaneP51700032751· filed Dec 2024 → now Mar 2026· 27.3% built
- NIRMAN SIGNATURE6 mo overdueSHREE SHA DEVELOPERS · Badlapur (W), ThaneP51700050640· 81.8% built
- EMPIRE TOWERS6 mo overdueLAKHANI REALTY LLP · Naupada Thane, ThaneP51700005215· filed Jul 2024 → now Mar 2026· 38.2% built· 2 complaints
- SATISH OAK HEIGHT6 mo overdueSHREE SAI PRATHAMESH DEVELOPERS · BADLAPUR WEST, ThaneP51700030403· 36.4% built
- SAURABH HEIGHTS6 mo overdueS K DEVELOPERS · Badlapur, ThaneP51700051500· 90.9% built
- SAI WORLD6 mo overduePINNACLE CORPORATION · BORADPADA ROAD, ThaneP51700034155· 90.9% built
- Gayatri CHS LTD6 mo overdueShree Angarak Enterprises Builders and Developers · Thane, ThaneP51700032690· filed Dec 2023 → now Mar 2026· 81.8% built
- Shree Ram Radha Damodar6 mo overdueADITYA BUILDCON · Near Aditya Mangal Karyalaya, ThaneP51700050634· 72.7% built
- Sukoon Heights6 mo overdueVIRANI CONSTRUCTION COMPANY · Thane, ThaneP51700004837· 97% built
- 24 HIGH6 mo overdueDREAM APEX REALTIES LIMITED · OPP DY PATIL STADIUM, ThaneP51700025150· 60.9% built· 1 complaint
- JANKI LEGACY6 mo overdueMihir Nandkumar papaiya · Mira Road East, ThaneP51700020239· 42.7% built
- YOGI NIWAS5 mo overdueELITE INFRASTRUCTURE · AMBERNATH, ThaneP51700015565· 1.8% built
- SAI WORLD LEGEND5 mo overdueParadise Lifestyles Private Limited · Ulhasnagar, ThaneP51700025002· 45.8% built
- Terraform K - Residences5 mo overdueMoney Magnum Constructions · Thane, ThaneP51700002673· filed Sept 2023 → now May 2026· 90.9% built
- ISHWAR SARASWATI PALACE5 mo overdueISHWAR REALITY · KANSAI, ThaneP51700051501· filed May 2025 → now May 2026· 72.3% built
- ISHWAR NEW AMIT5 mo overdueISHWAR DEVELOPERS · VADAVALI, ThaneP51700050877· filed May 2025 → now May 2026· 81.4% built
- Sarthi Emrald5 mo overdueSarthi Developers · Dombivli, ThaneP51700049548· filed May 2024 → now May 2026· 90.9% built
- Sai Ganesh Co-Operative Housing Society Ltd4 mo overdueShree Vyankatesh Enterprises · Dombivli West, ThaneP51700051405· 59.1% built
- SAI SHARADA CHS LTD4 mo overdueM SQUARE DEVELOPERS · GANESH NAGAR, ThaneP51700051917· 75% built
- Mangeshi Marvel4 mo overdueMangesh Dashrath Gaikar · Kalyan West, ThaneP51700034332· 63.2% built
- Navkamal Pushpa CHS4 mo overdueDream Realtors · Naupada, Thane West, ThaneP51700056041· 27.3% built
- UMA KUNJ COOPERATIVE HOUSING SOCIETY LIMITED4 mo overduePravin Arvind Apte · Badlapur, ThaneP51700033015· filed Dec 2025 → now May 2026· 90.9% built
- VRINDAVAN4 mo overdueSHIVRAJ DEVELOPERS · Kalyan, ThaneP51700020946· filed Jul 2024 → now May 2026· 86.4% built
- Mangeshi Royale4 mo overdueMangesh Dashrath Gaikar · Kalyan West, ThaneP51700034444· 0% built
- Rajas Leela4 mo overdueNakhye's Everest Estate Private Limited · Navagaon, ThaneP51700050538· 81.8% built
- SARVODAY AANAND4 mo overdueOM SAI LAND DEVELOPERS · Kalyan, ThaneP51700000725· filed Dec 2020 → now Jun 2026· 76.4% built
- BUILDING A1-SHREE KRUPA HEIGHTS3 mo overdueSHREE KRUPA BUILDERS AND DEVELOPERS · TISGAON, ThaneP51700025692· filed Jun 2022 → now Jun 2026· 90.9% built
- Kohinoor Eden B63 mo overdueKGI REALTY PRIVATE LIMITED · Kalyan East, ThaneP51700052179· 57.3% built
- GAURAV SAFFRON3 mo overdueRavi Developments · Thane, ThaneP51700003472· filed Dec 2022 → now Jun 2026· 69.9% built· 42 complaints
- SEA GREEN PALACIA3 mo overdueSEA GREEN PALACIA · Ulhasnagar, ThaneP51700055526· 54.5% built
- SAGAR HEIGHTS3 mo overdueAADINATH DEVELOPERS · KHADAKPADA, ThaneP51700051990· filed Dec 2025 → now Jun 2026· 90.5% built
- THARWANI ARIANA PHASE IV3 mo overdueANIL HARDASMAL THARWANI · CHIKLOLI, ThaneP51700047534· 36.6% built
- SHASHWAT PARK Z-5 A and B WING APARTMENT3 mo overdueSHASHWAT HOMES · BADLAPUR WEST, ThaneP51700050263· filed Jun 2025 → now Jun 2026· 90.9% built
- VISHNU BLISS3 mo overdueLEGACY BUILDERS & INNOVATORS · ., ThaneP51700055630· filed Dec 2025 → now Jun 2026· 79.6% built· 1 complaint
- SANGHVIS SHRI PARRSSSVA CITY 15-163 mo overdueSANGHVI PREMISES PRIVATE LIMITED · Atgaon, ThaneP51700007140· filed Dec 2019 → now Jun 2026· 16.4% built
- BSC IT PARK3 mo overdueBansal Steel Corporation · Thane, ThaneP51700045736· filed Jun 2024 → now Jun 2026· 90.9% built
- ISHWAR BLOSSOM3 mo overdueISHWAR LIFESPACE · KANSAI SECTION, ThaneP51700049361· filed Dec 2024 → now Jun 2026· 72.3% built
- NITIN ENCLAVES3 mo overdueNITIN ENCLAVES · Thane, ThaneP51700004830· filed Jun 2018 → now Jun 2026· 90.9% built· 8 complaints
- REGENCY SAPPHIRE3 mo overdueREGENCY NIRMAN LTD · DOMBIVALI, ThaneP51700053596· 59.1% built
- SHREE SAMARTH KRUPA PRASAD CO OPERATIVE HOUSING SOCIETY LIMITED3 mo overdueRAJLAXMI SAMARTH DEVELOPERS · AMBERNATH, ThaneP51700032714· filed Dec 2025 → now Jun 2026· 90.9% built
- The Icon Phase 23 mo overdueLeading Frontier Private Limited · Dhokali, ThaneP51700028535· 88.1% built· 1 complaint
- 24 EAST3 mo overdueMALHAR DEVELOPERS · Thane, ThaneP51700049178· 96.4% built
- PLUTONIUM BUSINESS PARK3 mo overduePLUTONIUM BUSINESS SOLLUTION PRIVATE LIMITED · Thane, ThaneP51700025606· 74.1% built
- SUNRAJ SUPREME3 mo overdueVASHDEV BACHOMAL KHUSHALANI · DOMBIVILI EAST, ThaneP51700026868· 90.9% built
- NICE GARDEN 13 mo overdueABHA CONSTRUCTIONS · SHILL, ThaneP51700026058· 81.8% built
- SARVODAY SQUARE PHASE 3 BLDG NO 13 mo overdueSHREE SQUAREFEET ENTERPRISES LLP · Ambarnath, ThaneP51700027546· 81.8% built
- Vraj Vatika3 mo overdueVraj Vatika · Thane, ThaneP51700025676· 36.4% built
- Godrej Emerald Thane3 mo overdueGodrej Greenview Housing Private Limited · Thane, ThaneP51700000120· filed Dec 2024 → now Jun 2026· 99.6% built· 30 complaints
- SAKET WORLD3 mo overdueAnand Associates · Near Chetana School, ThaneP51700024797· 11.3% built
- Shree Prasad CHSL3 mo overdueLcon Infra LLP · Naupada, ThaneP51700055985· 63.8% built
- Aarambh - C3 mo overdueM/s. Annapurna Lifespaces LLP · Thane, ThaneP51700000940· 90.9% built· 1 complaint
- Nida Amisha Heights3 mo overdueSAI KRUPA DEVELOPERS · MIRA BHAYANDAR, ThaneP51700009395· 64.5% built· 3 complaints
- New Kirtikar Proposed3 mo overdueNew Kirtikar Proposed · Thane, ThaneP51700004963· 49.5% built
- GANESH DARSHAN3 mo overdueJ.V. REALTY · PENKARPADA MAHAJANWADI, ThaneP51700047281· 27.3% built
- URBAN Villa3 mo overdueYASH INFRA · Thane, ThaneP51700015488· filed Dec 2022 → now Jul 2026· 90.9% built
- Mangeshi Ambar3 mo overdueMangesh Dashrath Gaikar · Gandhare, ThaneP51700047989· 0% built
- Veer Galaxy3 mo overdueYash Infra · near vandana depo, ThaneP51700051438· filed Jul 2025 → now Jul 2026· 66.8% built
- SAIRAJ AVENUE WING B2 mo overdueVIRENDRA ATMARAM SALUNKHE · BEHIND SHREE COMPLEX BADLAPUR WEST, ThaneP51700049787· filed May 2024 → now Jul 2026· 90.9% built
- SHREEJI MEADOWS2 mo overdueDEEPLAXMI DEVELOPERS · BELAVLI, ThaneP51700031453· 81.8% built
- PREMSADAN CHS2 mo overdueNAMRATA REALTORS · G B PATHARLI, ThaneP51700047653· filed Jul 2025 → now Jul 2026· 67.3% built
- BALAJI ESTATE2 mo overdueM/s. Sai Balaji Buildcon · Umbroli, ThaneP51700027980· filed Jun 2025 → now Jul 2026· 85.8% built· 10 complaints
- RAJ SILVERSTONE PHASE-22 mo overdueSKYSPACE BUILTEK · BELAVALI BADLAPUR WEST, ThaneP51700047261· filed Jul 2025 → now Jul 2026· 71.4% built
- SHREEJI GREENS2 mo overdueDEEP LAXMI ASSOCIATES · BADLAPUR, ThaneP51700046293· 81.8% built
- SAVALIYA RESIDENCY2 mo overdueShree Savaliya Housing LLP · Mira Road East, ThaneP51700027312· filed Jun 2025 → now Jul 2026· 75.9% built
- Swastik Paradise2 mo overdueGHUDE ENTERPRISES · Chikhaloli, ThaneP51700056372· filed Dec 2025 → now Jul 2026· 81.5% built
- Anantsavitri Ratna Heights2 mo overdueKrisha Realty · Near Maxus Mall, ThaneP51700032014· filed Dec 2024 → now Aug 2026· 90.9% built
- 127 RAJ HOMES A WING2 mo overdueRAJ HOMES · Penkar Pada ( Mahajanwadi), ThaneP51700034776· filed Sept 2025 → now Aug 2026· 90.9% built
- Bhairav Enclave2 mo overdueLeena Estate Venture · Thane, ThaneP51700028700· 90.9% built
- GLOBE BUSINESS SQUARE1 mo overdueGLOBE REALTY · Kalyan, ThaneP51700020338· filed Apr 2026 → now Aug 2026· 72.7% built
- HILL SPRING1 mo overdueASHA INFRATECH · BHADVAD, ThaneP51700004477· filed Dec 2023 → now Aug 2026· 90.9% built· 4 complaints
- AVIGHNA KARAN WING C1 mo overdueAVIGHNA KARAN · Kalyan east, ThaneP51700030327· filed Dec 2024 → now Aug 2026· 72.7% built
- Samarth Shivani Co-Operative Housing Society Limited1 mo overdueGURURAJ ENTERPRISES BUILDERS AND DEVELOPERS · Shirgaon, ThaneP51700052991· filed Aug 2025 → now Aug 2026· 70.9% built
- RASHMI PRIYA CO-OP HSG SOC LTD1 mo overdueSHREE RIDDHI SIDDHI INFRAPROJECT · NEAR MODEL SCHOOL, ThaneP51700050768· filed May 2025 → now Aug 2026· 81.8% built
- UMA RESIDENCY, PHASE I1 mo overdueADARSH INFRA DEVELOPERS · NA, ThaneP51700011302· filed Jun 2021 → now Aug 2026· 48.8% built
- Swami Datta Krupa1 mo overdueDinesh Laxman Sonawane · Kalyan, ThaneP51700077368· 27.3% built· 4 complaints
- SAI KANHUJIPOLICE SANKUL1 mo overdueHarshad Balu Gawade · BALYANI GAON, ThaneP51700016588· filed May 2024 → now Sept 2026· 80% built
- BEAUMONDE0 mo overdueKANUNGO PROPERTY · KANUNGO GARDEN CITY, MIRA ROAD EAST, ThaneP51700049442· filed Mar 2026 → now Sept 2026· 90.9% built
- PARSHURAM TOWER0 mo overdueMORESHWAR CONSTRUCTIONS · TALUKA KALAYN, ThaneP51700025480· filed Sept 2025 → now Sept 2026· 71.5% built
- Sky Gardens at Godrej Vihaa0 mo overdueK. R. REAL ESTATE PVT. LTD. · Ambarnath, ThaneP51700013329· filed Dec 2023 → now Sept 2026· 84.7% built· 1 complaint
- SKY HEIGHT0 mo overdueMango Enterprises · Valivali Village, ThaneP51700045826· filed May 2026 → now Sept 2026· 83.6% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.