RERA projects past their possession deadline
11,768 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 35 of 59
- Mangeshi City III4.2 yr overdueMangesh Dashrath Gaikar · Shree Complex Chowk, ThaneP51700016947· 45.5% built
- El-Homes4.2 yr overdueR D Deshpanday Developers Pvt Ltd · Opp PAN Card club, PuneP52100016546· 89.5% built· 5 complaints
- GLOBAL LIFESTYLE KHARADI4.2 yr overdueMIND SPACE SHELTERS LLP · NEAR EON IT PARKP52100016888· 77.3% built
- MAYURESH4.2 yr overdueARWADE KARANDIKAR ASSOCIATES · SOUTH SHIVAJI NAGAR, SangliP53100019329· 73.3% built
- SHREEJI ICONIC PHASE I4.2 yr overdueRAJ LAXMI DEVELOPERS · Badlapur (M Cl), ThaneP51700013918· 90.9% built
- Skyi Songbirds Phase D4.2 yr overdueEnerrgia Skyi Developers · Bhugaon, PuneP52100000764· filed Nov 2020 → now May 2022· 90.9% built· 7 complaints
- HIMBINDU4.2 yr overdueM/s. Sahajanand Developers · Goregaon West, Mumbai SuburbanP51800003502· filed Dec 2018 → now May 2022· 52.7% built· 5 complaints
- Skyi Songbirds Phase B4.2 yr overdueEnerrgia Skyi Developers · Bhugaon, PuneP52100001117· filed Nov 2020 → now May 2022· 85.7% built· 1 complaint
- MUKUNDA HEIGHTS4.2 yr overdueSai Mukunda Builder and Developers · Vasai, PalgharP99000000853· 46.4% built· 1 complaint
- KRIPA ALLURE4.2 yr overdueKRIPA ONENESS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800018912· 79.5% built
- GOKULDHAM APARTMENT4.2 yr overdueSHRINATHJI DEVELOPER · GANGAPUR ROAD, NashikP51600016370· 81.8% built
- Prime Builders4.2 yr overduePrime Builders and Developers · Andheri, Mumbai SuburbanP51800008911· filed Nov 2020 → now May 2022· 90.9% built· 1 complaint
- LODHA ETERNIS NATURA A4.2 yr overdueLODHA DEVELOPERS LIMITED · Andheri, Mumbai SuburbanP51800000345· 90.9% built
- Geras Imperium Rise4.2 yr overdueGera Developments Private Limited · Hinjewadi, PuneP52100001786· filed Dec 2020 → now May 2022· 90.9% built· 38 complaints
- ABHILASHA4.2 yr overdueKUDALE SABLE BUILDERS · Shirur, PuneP52100008268· filed Nov 2020 → now May 2022· 80% built
- Veera Residency4.2 yr overdueShree Ganesha Associates · Thane, ThaneP51700004004· 72.7% built
- MADHU MILIND RESIDENCY4.2 yr overdueMUKUND SHRIDHAR SHRIKHANDE · Thane, ThaneP51700021149· 90.9% built
- ABHIMAAN HOMES PHASE II4.2 yr overdueRISING PROPCON LLP · Shirgaon, PuneP52100000285· filed Dec 2019 → now May 2022· 88.9% built· 1 complaint
- Royal Bliss4.2 yr overdueJay Ganesh Associates · Kiwale, PuneP52100015623· filed Jun 2021 → now May 2022· 29.1% built
- M BARIA LAKE VIEW4.2 yr overdueMORESHWAR KRUSHNA BARIA · VIRAT NAGAR, PalgharP99000029111· 54.5% built
- IMPERIAL TOWER C WING4.2 yr overdueAGCONSTRUCTIONS · NIBM, PuneP52100019566· 28.2% built
- AZURE B4.2 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Tathwade, PuneP52100016218· 99.5% built
- SAHIL PRIDE4.2 yr overdueYOGESH OMPRAKASH AGARWAL · YEWALEWADI, PuneP52100005445· filed Dec 2020 → now Jun 2022· 10% built
- E Wing4.2 yr overdueVinayak Pandharinath Bhongale · Near Modern College of Pharmacy Borhadwadi Moshi Pune, PuneP52100019750· 14.5% built· 1 complaint
- DWARKESHDHAM APARTMENT4.2 yr overdueVAIDEHI CONSTRUCTION · NEAR MAHA BANG, NashikP51600010508· 81.8% built
- KEDAR RESIDENCY4.2 yr overdueGOURAV CONSTRUCTION · Gijavane, KolhapurP53000003979· filed Jun 2020 → now Jun 2022· 79.1% built
- REVELL ORCHID PHASE III BUILDING E4.2 yr overdueABHAY INDRABHAN FULFAGAR · LOHGAON, PuneP52100001549· 46.8% built
- CHAITANYA AAWAS4.1 yr overdueRAJENDRA MADHUKAR JOSHI · KARANJADE NAVI MUMBAI, RaigarhP52000016309· 90.9% built
- CHINMAY VAISHVA PHASE 24.1 yr overdueCHINMAY VISHWA · NEAR AMBEGAON PATHAR POLICE CHOWKI, PuneP52100027024· 72.7% built
- DHAWAL PARK4.1 yr overdueHEMCHANDRA RAMKRISHNA INGALE · BURHANAGR, AhmednagarP52200024450· 78.2% built
- Aaryavarta4.1 yr overdueDipti Spaces Pvt. Ltd. · Andheri, Mumbai SuburbanP51900002676· 90.9% built· 6 complaints
- PAWASKAR PARK4.1 yr overdueAKAR BUILDCON · NEAR AKASHWANI, SangliP53100010044· filed Dec 2018 → now Jun 2022· 81.4% built
- SHRINATH PARK4.1 yr overdueSHRI NATH VIHAR CONSTRUCTIONS · Pisadevi, AurangabadP51500006059· filed Dec 2021 → now Jun 2022· 81.8% built
- AVON VISTA PROJECT -14.1 yr overdueNAIKNAVARE PROFILE CONSTRUCTIONS PVT LTD · PUNE, PuneP52100000371· filed Dec 2020 → now Jun 2022· 87.9% built· 5 complaints
- Redevelopment of New Monalisa CHSL4.1 yr overdueShree Mahavir Estates · Mumbai, Mumbai SuburbanP51800001955· filed Dec 2020 → now Jun 2022· 34.4% built
- Redevelopment of Silverlight CHSL4.1 yr overdueShree Mahavir Estates · Mumbai, Mumbai SuburbanP51800002541· filed Dec 2020 → now Jun 2022· 36.2% built
- SHRIRANG4.1 yr overdueVIRENDRA NATWARLAL SHETH · Kurla, Mumbai SuburbanP51800004570· filed Jun 2020 → now Jun 2022· 90.9% built· 6 complaints
- Vishwa Vimal4.1 yr overdueVikrant Vishwasrao Jadhav · Kolhapur (M Corp.), KolhapurP53000009549· filed Nov 2020 → now Jun 2022· 66.8% built
- PARVATI HEIGHTS4.1 yr overdueLAXMINARAYAN CONSTRUCTIONS · Nashik, NashikP51600007938· filed Dec 2020 → now Jun 2022· 90.9% built
- Om Shyam4.1 yr overdueKurla, Mumbai SuburbanP51800002462· filed Apr 2021 → now Jun 2022· 90.9% built
- SAVITRI PEARL4.1 yr overdueMukesh BHOORMAL Jain · Alibag, RaigarhP52000010719· filed Jun 2021 → now Jun 2022· 90.9% built
- The Trees, Residential Phase 14.1 yr overdueGodrej Properties Limited · Kurla, Mumbai SuburbanP51800000165· 89.1% built· 5 complaints
- Rachana Park Wing I4.1 yr overdueShree Construction Builders and Developers · Off nagar Manmad Highway, AhmednagarP52200025216· 81.8% built
- KOHINOOR MAJESTY WING A4.1 yr overdueKOHINOOR MAJESTY · Varale, PuneP52100001379· 81.8% built
- PRATHAM RESIDENCY4.1 yr overdueDalvi Brothers Builders and Developers Pvt. Ltd. · Kudal (CT), SindhudurgP52900009895· 41.1% built
- SHREE TIRUMALA PARAMOUNT APARTMENT4.1 yr overdueROONGTA HOMES LLP · DEEPALI NAGAR, NashikP51600016034· 90.9% built
- Laxmi Residency4.1 yr overdueShivshakti Buildcon · kadwe nagar, NashikP51600010392· 90.9% built
- Jawale Bhuvan4.1 yr overduePrathamesh Developers & Project Consultants · Ward GNorth, Mumbai CityP51900001070· filed Mar 2021 → now Jun 2022· 90.9% built
- Anand Nagar Phase 14.1 yr overdueAnubhavshri Realty Pvt. Ltd. · Lonere, RaigarhP52000005747· filed Jun 2018 → now Jun 2022· 99.1% built· 15 complaints
- UMA IMPERIAL4.1 yr overdueMURUDESHWAR DEVELOPERS · NA, RaigarhP52000002083· filed Jun 2021 → now Jun 2022· 99.8% built
- PLUTO-B -SUNCITY HOUSING PHASE- I4.1 yr overdueSUNCITY COMPLEX · Kurla, Mumbai SuburbanP51800004553· filed Dec 2018 → now Jun 2022· 90.9% built
- SHREE GOPINATH SUBLIME4.1 yr overdueVEDANT CONSTRUCTION · Thane, ThaneP51700003177· 90.9% built
- 11 PARK STREET A WING4.1 yr overdueTRIMURTI HOUSING · Pisoli, PuneP52100003117· 90.9% built
- GLOBAL HEIGHTS4.1 yr overdueMD CREATION · CHARHOLI, PuneP52100007709· filed Dec 2020 → now Jun 2022· 90.9% built
- Cygnus4.1 yr overdueTrimity Developers Pvt Ltd · Mulund, Mumbai CityP51900005254· filed Oct 2018 → now Jun 2022· 62.3% built
- SHARADA MYRIA4.1 yr overdueSHARADA ERECTORS PRIVATE LIMITED · Haveli, PuneP52100012315· filed Dec 2020 → now Jun 2022· 86.8% built
- Rustomjee Aurelia 14.1 yr overdueKapstone Constructions Private Limited · Thane, ThaneP51700001516· 80.7% built· 2 complaints
- JP North Elara4.1 yr overdueJP Infra Realty Private Limited · Thane, ThaneP51700007001· 88.4% built· 2 complaints
- Rambaug4.1 yr overdueSuryanshu Properties Pvt Ltd · Phaltan (M Cl), SataraP52700000048· 90.9% built
- DREAM HOME PANNA4.1 yr overdueDREAM HOME BUILDERS · Hadapsar, PuneP52100006303· filed Dec 2017 → now Jun 2022· 90.9% built
- SHUBH CHINTAN4.1 yr overdueAUM ENTERPRISES · Kurla, Mumbai SuburbanP51800007195· 90.9% built
- Nathsagar residensy4.1 yr overdueSopan Radhakisan Andhale · Khalapur, RaigarhP52000013554· filed Dec 2018 → now Jun 2022· 79.1% built
- 1 Nere Residency4.1 yr overdueRajHeramb Landmarks · NERE, PuneP52100002517· filed Dec 2018 → now Jun 2022· 88.2% built· 2 complaints
- SUNFLOWER4.1 yr overdueShree Krishna Developers · Kurla, Mumbai SuburbanP51800006422· filed Dec 2018 → now Jun 2022· 90.9% built· 6 complaints
- The Trees Residential Phase 24.1 yr overdueGodrej Properties Limited · Kurla, Mumbai SuburbanP51800000161· 90.9% built· 1 complaint
- SIDDHI ELITE4.1 yr overduePatani Shah Associates · INDIRA NAGAR, NashikP51600005829· 90.9% built
- Samarth Krupa4.1 yr overdueShailendra Ramesh Vajaratkar · Kudal (CT), SindhudurgP52900012636· filed Jun 2019 → now Jun 2022· 65.8% built
- SHAMAL4.1 yr overdueMorajkar Estates LLP · Karanjade, RaigarhP52000019963· 90.9% built
- SAI KRUPA APARTMENT4.1 yr overdueVIJAN REALTY PRIVATE LIMITED · Nashik (M Corp.), NashikP51600004180· filed Mar 2018 → now Jun 2022· 90.9% built
- JANHAVI ENCLAVE4.1 yr overdueJANHAVI HOUSING DEVELOPERS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800009236· filed Jun 2021 → now Jun 2022· 52.5% built
- Ganga Paritosh B4.1 yr overdueGoel Mohata Associates · Sinhgad Road, PuneP52100001470· filed Jan 2021 → now Jun 2022· 76.4% built
- LAKE CITY PHASE-24.1 yr overdueSADANAND LAXMANRAO PATIL · Sudhagad, RaigarhP52000017801· 63% built
- Destination Ishanya B Wing4.1 yr overdueGavhane Realty · Haveli, PuneP52100020181· 78.2% built
- ALAG STELLA4.1 yr overdueALAG PROPERTY CONSTRUCTIONS PVT. LTD. · MULUND EAST, Mumbai SuburbanP51800018925· filed Jun 2021 → now Jun 2022· 82.3% built
- ABH SAMRUDDHI4.1 yr overdueTANU REALITY LLP · HANUMAN WADI, NashikP51600023767· 90.9% built
- ASHAPURA PRASAD4.1 yr overdueASHAPURA NIRMAN DEVELOPERS · Chikanghar, ThaneP51700014800· filed Dec 2018 → now Jun 2022· 61.8% built
- TRANQUIL PARK4.1 yr overdueLEGACY LANDMARKS PVT LTD · LOHGAON, PuneP52100002421· filed Mar 2020 → now Jun 2022· 75.9% built· 1 complaint
- SHUBHKALASH B WING4.1 yr overdueTulip Developers · Chikhali, PuneP52100002475· filed Dec 2020 → now Jun 2022· 90.9% built
- MINAKSHI HEIGHTS4.1 yr overdueVIJAYKUMAR KISANLAL GHODELLA · Nashik (M Corp.), NashikP51600010319· 55% built
- OMKARA4.1 yr overdueANH NIRMAN · Palghar, PalgharP99000016447· filed Dec 2020 → now Jun 2022· 56.8% built
- SUYOG CHS4.1 yr overdueADITYARAJ BUILDERS · Kurla, Mumbai SuburbanP51800004742· filed Feb 2021 → now Jun 2022· 72.7% built
- SWAMI NIWAS4.1 yr overdueSWAMI SAMARTH KRUPA INFRASTRUCTURE PRIVATE LIMITED · DABHA NAGPUR, NagpurP50500023460· 81.8% built
- LAXMI ANGAN D BUILDING4.1 yr overdueMALHAR ASSOCIATES · NEAR LAKE ROAD, AhmednagarP52200026168· 72.3% built
- GAJANANA4.1 yr overdueAMIT HARSHAVADAN AGASKAR · Palghar, PalgharP99000016205· filed Dec 2020 → now Jun 2022· 50% built
- Prakalp Pride4.1 yr overduePrakalp Infrabuild And Developers Pvt. Ltd. · Pune, PuneP52100001299· filed Dec 2019 → now Jun 2022· 81.8% built
- OM RESIDENCY4.1 yr overdueSHREE ASHAPURA COMBINES · adharwadi, ThaneP51700009448· filed Jun 2021 → now Jun 2022· 0% built· 1 complaint
- NEHRU NAGAR NISHIGANDHA CHS LTD4.1 yr overdueAISHWARYA BUILDERS & DEVELOPERS · Kurla, Mumbai SuburbanP51800002020· filed Dec 2019 → now Jun 2022· 90.9% built
- SAANJ CO OP HSG SOC Praposed4.1 yr overdueShrikrishna Ramchandra Marathe · Bramhan Ali, RaigarhP52000019822· 75.5% built
- Regent Heights-New Ganga Niwas CHSL4.1 yr overdueRDB Mumbai Infrastructures Private Limited · Andheri, Mumbai SuburbanP51800011798· filed Jun 2019 → now Jun 2022· 84.5% built
- Moreshwar tower4.1 yr overdueyashraj corporation · Kurla, Mumbai SuburbanP51800003786· filed Mar 2020 → now Jun 2022· 51.8% built
- Sanskruti Building A4.1 yr overduePushpam Infra LLP · Kashele, RaigarhP52000011794· filed Dec 2018 → now Jun 2022· 81.8% built· 1 complaint
- Yashodhan Daffodils4.1 yr overdueYASHODHAN DEVELOPMENT CORPORATION · Kondhwa BK., PuneP52100005635· filed Jul 2019 → now Jun 2022· 95.5% built· 3 complaints
- Royal Fantasy Phase I4.1 yr overdueRoyal Fantasy Constructions Private Limited · Andheri, Mumbai SuburbanP51800009606· filed Dec 2018 → now Jun 2022· 84.2% built· 5 complaints
- YOGESHWAR KRUPA CHS4.1 yr overdueJALARAM ASSOCIATES · NEAR TALUKA POLICE STATION, RaigarhP52000015656· 0.5% built
- Shree Nagri - 34.1 yr overdueSHAILESH KANTILAL SHAH · TALEGAON DABHADE, PuneP52100015639· 90.9% built
- Saptarshi Pride4.1 yr overdueSAPTARSHI REALTORS PRIVATE LIMITED · Karanje Tarf Satara (CT), SataraP52700013865· filed Dec 2019 → now Jun 2022· 88.6% built
- RAJ HEAVENS PHASE 1 C BUILDING4.1 yr overdueBURHANI TAMOS DEVELOPERS · BEHIND LIONS ENGLISH SCHOOL, Dadra & Nagar HaveliP49600000096· 90.9% built
- SUBHADRA APARTMENT4.1 yr overduePOTEAR ASSOCIATES · Baramati (M Cl), PuneP52100004395· filed Jun 2021 → now Jun 2022· 81.8% built
- Indiabulls Blu Tower D4.1 yr overdueIndiabulls Infraestate Limited · Ward GSouth, Mumbai CityP51900000871· 96.6% built· 2 complaints
- EVERSHINE CROWN4.1 yr overdueEVERSHINE BUILDERS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800003631· 80% built· 5 complaints
- NISARG4.1 yr overdueIndiapride Infraspaces · Neral, RaigarhP52000002022· filed Dec 2020 → now Jun 2022· 90.9% built
- Spring Valley Phase II4.1 yr overdueSHUBH GANESH PROPERTIES · CHAROLI, PuneP52100013807· filed Jun 2021 → now Jun 2022· 99.1% built· 2 complaints
- EMIRUS G4.1 yr overdueG M KENJALE DEVELOPERS · BANER, PuneP52100005651· filed Jun 2021 → now Jun 2022· 85.9% built· 1 complaint
- Grishma Heights4.1 yr overdueRIGHT CHANNEL CONSTRUCTION PVT LTD · kandivali west, Mumbai SuburbanP51800012108· filed Dec 2018 → now Jun 2022· 97.7% built
- Regency Classic Wing B24.1 yr overdueREGENCY NIRMAN LTD · Pune (M Corp.), PuneP52100005014· 60.9% built
- BT SUJATA CHSL4.1 yr overdueC H PATIL AND SONS LLP · Borivali, Mumbai SuburbanP51800003936· filed Jan 2021 → now Jun 2022· 63.6% built
- SAI SARTHAK4.1 yr overduePRAVIN MAHARUDRA NAGARGOJE · AURANGABAD, AurangabadP51500014639· filed Dec 2020 → now Jun 2022· 18.2% built
- BUSINESS BAY4.1 yr overdueSHIVDATTA ASSOCIATES · NEAR ADITYA CORNERP53000018067· 81.8% built
- Pushpendra City- Mahalakshmi Presidency4.1 yr overduePushpendra Real Construction Private Limited · Khedshi, RatnagiriP52800000951· filed Dec 2020 → now Jun 2022· 90.9% built
- Woodsville Phase 3 Cluster C4.1 yr overduePharande Promoters and Builders · Moshi, PuneP52100015970· 85.1% built
- RAMALAY APARTMENT4.1 yr overdueM/S SHREERAM BUILDERS · NEAR GAJANAN MAHARAJ MATH, PuneP52100017117· 81.8% built
- Kalpataru Radiance E4.1 yr overdueKeyana Estate LLP · Borivali, Mumbai SuburbanP51800013245· 46.9% built
- RENUKA DARSHAN4.1 yr overdueRENUKA DEVELOPERS · VIHITGAON, NashikP51600004063· filed Dec 2020 → now Jun 2022· 48.2% built· 1 complaint
- THE EMPIRE4.1 yr overdueWESTIN INFRA · TARABAI PARK, KolhapurP53000002901· filed Jan 2019 → now Jun 2022· 81.8% built
- SIMRAH PARADISE4.1 yr overdueARYAN DEVELOPERS · Pune (M Corp.), PuneP52100014597· 81.4% built
- OM HEIGHTS4.1 yr overdueYOGESH WADNERE AND KISHOR WADNERE · Nashik, NashikP51600012257· 90.9% built
- SHUBH AANGAN4.1 yr overdueG D REALTORS PVT LTD · Kurla, Mumbai SuburbanP51800005320· filed Jun 2021 → now Jun 2022· 90.9% built
- REGENCY ANTILIA PHASE IV4.1 yr overdueREGENCY NIRMAN LTD · Ulhasnagar, ThaneP51700023854· 81.8% built
- RAINBOW CLASSIC4.1 yr overdueEFFICIENT PROPERTIES · Lonavala (M Cl), PuneP52100010619· filed Mar 2018 → now Jun 2022· 90.9% built
- Mukta Lake City4.1 yr overdueKANAK REALTORS · Thane, ThaneP51700014979· filed Jun 2021 → now Jun 2022· 90.9% built· 3 complaints
- SHREE DEEPLAXAMI4.1 yr overduePURO CONSTRUCTIONS · Kurla, Mumbai SuburbanP51800009423· filed Dec 2019 → now Jun 2022· 24% built
- Mont Vert Belbrook4.1 yr overdueMont Vert Elegance · Mulshi, PuneP52100002449· filed Dec 2018 → now Jun 2022· 93.9% built
- KANJUR MATRUCHHAYA CHS LTD4.1 yr overdueSUNIL DINKAR SHINDE · Kurla, Mumbai SuburbanP51800015513· 90.9% built
- Marvel Castella A And B Building4.1 yr overdueMARVEL SIGMA HOMES PRIVATE LIMITED · Balewadi, PuneP52100002438· 0% built· 6 complaints
- JD GREEN PARADISE4.1 yr overdueDATTATRAYA GULABRAO KHANDAVE · LOHGAON, PuneP52100004183· 35.9% built
- Anandam Vihar Phase I WING A4.1 yr overdueSV SMART CITY DEVELOPERS · Gandhinagar, SolapurP52600013748· filed Mar 2020 → now Jun 2022· 90.9% built
- LODHA AZZURO4.1 yr overdueLodha Developers Limited · Ward FSouth, Mumbai CityP51900000828· 90.9% built· 15 complaints
- DOSTI WEST COUNTY - DOSTI OAK4.1 yr overdueDOSTI ENTERPRISES · balkum, ThaneP51700006565· 90.9% built· 5 complaints
- Krishna Pride4.1 yr overdueGajanan Krupa Developers · CHANAKYA NAGAR, ThaneP51700011439· 90.9% built
- AADESHWAR-24.1 yr overdueSHREE ADESHWAR BUILDCOM · Palghar, PalgharP99000011704· filed Dec 2020 → now Jun 2022· 90.9% built
- SHREEJI HEIGHTS4.1 yr overdueSHUBH BUILDCON · BADLAPUR EAST, ThaneP51700015270· 75.7% built
- Hrishita Apartment4.1 yr overdueHrishita Buildcon & Infrastructures Pvt. Ltd · SHIVAR, NashikP51600011155· filed Aug 2018 → now Jun 2022· 23.5% built
- VISION INDRATEJ4.1 yr overdueVISION BUILDCON · TATHAWADE, PuneP52100019399· 90.9% built
- Neelmohar E4.1 yr overdueAshoka Township (AOP) · SinnarP51600012230· filed Dec 2020 → now Jun 2022· 27.3% built
- CYPRUS4.1 yr overdueBENCHMARK TOWN PLANNING LLP · Punawale, PuneP52100000561· 40% built· 1 complaint
- MANHAR RESIDENCY4.1 yr overdueSHLOK ENTERPRISES (MANHAR) · Dahisar west, Mumbai SuburbanP51800002057· filed Dec 2019 → now Jun 2022· 90.8% built
- INSIGNIA4.1 yr overdueULTRA SPACE DEVELOPERS PRIVATE LIMITED · Kalina, Mumbai SuburbanP51800002313· filed Apr 2020 → now Jun 2022· 96.1% built· 64 complaints
- Royal Orange County C Wing4.1 yr overdueNavras Sthapatya LLP · Pimpri Chinchawad (M Corp.), PuneP52100003764· 90.9% built
- NEELAYA PROJECT 24.1 yr overdueNAIKNAVARE BUILDCON PVT LTD · TALEGAON, PuneP52100021179· 79.5% built· 1 complaint
- MAYUR HEIGHTS4.1 yr overdueREAL VALUE BUILDERS AND DEVELOPERS · MOHANE VILLAGE, ThaneP51700015724· filed Jun 2021 → now Jun 2022· 90.9% built
- Gandharva Excellence Project III H Building Part 24.1 yr overdueVinayak Pandharinath Bhongale · Borhadewadi Moshi, PuneP52100026673· 36.4% built· 1 complaint
- Allure4.1 yr overdueDreamland Venture · Wagholi, PuneP52100002402· filed Mar 2019 → now Jun 2022· 86.4% built
- AKSHA VASANT PARK4.1 yr overdueUNITED PROPERTIES · Pimpri Chinchawad (M Corp.), PuneP52100009433· filed Dec 2019 → now Jun 2022· 90.9% built
- Lodha Kolshet Plot A - Tower K4.1 yr overdueLODHA DEVELOPERS LIMITED · Thane, ThaneP51700015040· 81.8% built· 5 complaints
- The Address - 24.1 yr overdueSOL Developers · MOSHI, PuneP52100007886· filed Jun 2020 → now Jun 2022· 82.8% built
- SATYAM RESIDENCY4.1 yr overdueMahalaxmi builders and Developers · Pisadevi, AurangabadP51500004520· filed Jul 2019 → now Jun 2022· 78.6% built
- HILL GALAXY4.1 yr overdueR R BUILDERS · MIRA ROAD, ThaneP51700012160· filed Dec 2018 → now Jun 2022· 53.2% built
- Rozi Pushpa Sagar4.1 yr overdueROZI CONSTRUCTION AND DEVELOPERS · Chiplun (M Cl), RatnagiriP52800006682· filed Mar 2021 → now Jun 2022· 34.3% built
- ALANKAPURISHREE CO.OP.HSG.SOC.LTD.4.1 yr overdueVYAS BUILDCON PVT. LTD. · RAMBAUG COLONY, PuneP52100018752· 81.8% built
- royale residences b and c wing4.1 yr overduem/s rani creators , consultant and service providers · Kurla, Mumbai SuburbanP51800005315· filed Dec 2019 → now Jun 2022· 49.7% built
- Venkatesh Imperia Phase II4.1 yr overdueRajHeramb Properties · Punawale, PuneP52100002301· filed Dec 2018 → now Jun 2022· 90.9% built
- SHREENIWAS APARTMENT4.1 yr overdueKRISHNA CONSTRUCTION · WADALA SHIWAR, NashikP51600022902· 90.9% built
- GAGANGIRI VIHAR COMPLEX4.1 yr overdueCRESCENT INFRASTRUCTURE & DEVELOPING COMPANY · Khalapur, RaigarhP52000003647· filed Dec 2019 → now Jun 2022· 78.6% built
- PALAVA CLUSTER 2-06 - A - G, I - N4.1 yr overdueLodha Developers Limited · Kalyan, ThaneP51700000802· 78.2% built· 2 complaints
- ACE ALMIGHTY COMMERCIAL4.1 yr overdueM/S. ACE ALMIGHTY · TATHWADE, PuneP52100019488· 99.5% built
- AVADHUT VIHAR A WING4.1 yr overdueAVADHUT BUILDERS · -, SataraP52700014055· filed Dec 2018 → now Jun 2022· 66.4% built
- Vrundavan Residency4.1 yr overdueSwamiraj Developers LLP · Haveli, PuneP52100028242· 75.9% built
- EELA Phase-III4.1 yr overdueM/s. Siddhashila Developers · Punawale, PuneP52100024257· 90.9% built
- Sara Metroville A phase II4.1 yr overdueSara Infrastructures · Punawale, PuneP52100002174· filed Jun 2021 → now Jun 2022· 81.8% built
- EKDANT DEVELOPERS4.1 yr overdueEKDANT DEVELOPERS · Kalyan, ThaneP51700001682· 90.9% built
- Puneville Phase I4.1 yr overdueBENCHMARRK REALTY PRIVATE LIMITED · Punawale, PuneP52100000441· filed Dec 2020 → now Jun 2022· 89.1% built
- MIDTOWN SQUARE - PHASE I4.1 yr overdueLOTUS EMPIRE · OPP ORDNANCE FACTORY, ThaneP51700014394· 50.4% built
- VIMACO GULMOHAR CONDOMINIUM4.1 yr overdueABBASALI AHTESHAM HUSAIN HAJI · Amravati (M Corp.), AmravatiP50300006416· filed Dec 2020 → now Jun 2022· 9.1% built
- SHREE SWAMI ANANT SHRUSHTI4.1 yr overdueSHIVSAI PROPERTIES LLP · kirkatwadi, PuneP52100009187· filed Dec 2018 → now Jun 2022· 81.8% built
- PLATINUM TOWER - 314.1 yr overdueMANAS GRUHPRAVESH LLP · Andheri, Mumbai SuburbanP51800001759· 85.4% built
- DUDHWALA COMPLEX-PHASE 24.1 yr overdueROCK CORNER DEVELOPER PRIVATE LIMITED · Ward E, Mumbai CityP51900003621· filed Dec 2020 → now Jun 2022· 99% built
- SWARGANDHAR PHASE 2 A1,A2,A3,B1,B2,B3,B4,B5,C14.1 yr overdueVAIBHAV CLASSIC BUILDERS AND DEVELOPERS · Uruli Kanchan, PuneP52100004672· filed Dec 2019 → now Jun 2022· 48.1% built
- SIDDHANT RUTURANG4.1 yr overdueCHAITANYA BUILDCON · Haveli, PuneP52100005960· filed Dec 2019 → now Jun 2022· 90.9% built
- OM SAI PLAZA4.1 yr overdueOM DEVELOPERS · DAMODAR NAGAR, NashikP51600022335· 90.9% built
- MOUNTSCAPE4.1 yr overdueNAYAN BUILDCON · Pisoli, PuneP52100006878· filed Jun 2021 → now Jun 2022· 79.5% built
- jewel heaven phase 14.1 yr overdueJewel Builders and Infraprojects Ltd · Neral, RaigarhP52000015976· filed Jun 2021 → now Jun 2022· 90.9% built
- FORTUNE PLAZA PHASE II4.1 yr overdueVENKATESH LAXMI DEVELOPERS ·P52100009565· filed Dec 2018 → now Jun 2022· 42.3% built
- Vijayalakshmy Residency4.1 yr overdueSaanvi Landmarks Pvt.Ltd · DhanoriP52100046262· 90% built· 1 complaint
- Abhidarshan Homes4.1 yr overdueAbhidarshan Combines · Kalyan, ThaneP51700007573· filed Jun 2020 → now Jun 2022· 89.3% built
- INDU RESIDENCY4.1 yr overdueSURESH KHIMJIBHAI BORSANIYA · BORGAON, NagpurP50500014852· 90.9% built
- GRAND VIEW4.1 yr overdueSQUARE PROPERTIES · Sangli Miraj Kupwad (M Corp.), SangliP53100003046· filed Jan 2021 → now Jun 2022· 27.3% built
- Jaliyan Heights Borivali4.1 yr overdueJaliyan Developer · Borivali, Mumbai SuburbanP51800012925· filed Jul 2021 → now Jun 2022· 67.5% built· 1 complaint
- SIGNATURE DESIRE4.1 yr overdueSATYAM HOMES · Karjat, RaigarhP52000001892· filed May 2020 → now Jun 2022· 79.7% built
- Ashray Apartment4.1 yr overdueVINOD BALARAM PATIL · Pushpak New, RaigarhP52000021755· filed Jun 2021 → now Jun 2022· 9.1% built
- Pushpendra City- Mahalakshmi Enclave4.1 yr overduePushpendra Real Construction Private Limited · Khedshi, RatnagiriP52800001072· 90.9% built
- Joyville Virar Phase 14.1 yr overdueJoyville Shapoorji Housing Private Limited · Vasai, PalgharP51900000444· 72.7% built· 1 complaint
- Gagan Adira Phase 14.1 yr overdueTopaz Homes LLP · Wagholi, PuneP52100001048· filed Dec 2020 → now Jun 2022· 64.4% built· 15 complaints
- Ananta Apartments4.1 yr overdueSMARTSOLUTIONS · Vileparle east, Mumbai SuburbanP51800023422· 55.6% built
- SAI VAIBHAV PARADISE4.1 yr overdueSHREE SAI DEVELOPERS · SHRIDHAR MHATRE CHOWK, ThaneP51700025525· 39.1% built
- Avant Heritage I4.1 yr overdueAishwarya Avant Builders LLP · Andheri, Mumbai SuburbanP51800009299· filed Dec 2018 → now Jun 2022· 90.9% built· 27 complaints
- KIPL Morya4.1 yr overduekhade Infrastructre Pvt. Ltd. · VADAWALI, ThaneP51900010004· filed Jun 2021 → now Jun 2022· 78.4% built· 5 complaints
- Sai-Sanjay Residency4.1 yr overdueSaipuja Buildcon · PuneP52100024996· 90.9% built
- AKSHAY VILLA4.1 yr overdueAKSHAY INFRASTRUCTURE PVT LTD · AMBEGAON Bk, PuneP52100007501· filed Apr 2020 → now Jun 2022· 72.7% built
- SUNSHINE ELEGANCE4.1 yr overdueSUNSHINE ENTERPRISES · DOMBIVLI, ThaneP51700004045· filed Dec 2019 → now Jun 2022· 71.8% built
- SKYLINE PRIDE4.1 yr overdueSKYLINE DEVELOPERS · Charathe, SindhudurgP52900009098· filed Mar 2019 → now Jun 2022· 85% built
- BASERA ETERNITY4.1 yr overdueSANJEEVKUMAR RAMESHCHANDRA AGARWAL · Rajiv Gandhi Infotech Park, PuneP52100008447· filed Dec 2019 → now Jun 2022· 81.8% built· 1 complaint
- SHEETAL DWAR4.1 yr overdueSHEETAL ENTERPRISES · Borivali, Mumbai SuburbanP51800003724· filed Dec 2019 → now Jun 2022· 35.7% built
- Shankar Heights Phase 44.1 yr overdueLaxmi Kamal Associates · Ambarnath, ThaneP51700002953· filed Jun 2021 → now Jun 2022· 67.1% built
- Akash Towers A and B4.1 yr overdueLunkad Builders LLP · Pimple Nilakh, PuneP52100019140· 86.4% built· 1 complaint
- SHREE NEMINATH HEIGHTS4.1 yr overdueSHREE NEMINATH CONSTRUCTION CO · Karjat, RaigarhP52000002465· 90.9% built
- MIRAYA4.1 yr overdueAMIT HARSHAVADAN AGASKAR · MAHIM, PalgharP99000016401· filed Dec 2020 → now Jun 2022· 49.1% built
- Mahavir Niwas A4.1 yr overdueRAJESH ENTERPRISES · Palghar, PalgharP99000021942· 90.9% built
- Apna Ghar Phase-II Plot-B4.1 yr overdueSeven Eleven Construction Private Limited · Thane, ThaneP51700007988· 90.9% built· 2 complaints
- SHRI SWAMI SAMARTH MAULI4.1 yr overdueSHREE SWAMI SAMARTH ENTERPRISES · Karvanchiwadi, RatnagiriP52800002926· filed Mar 2019 → now Jun 2022· 18.2% built
- Puraniks Abitante Phase 1A4.1 yr overduePuranik Buildcon Private Limited · Bavadhan BK, PuneP52100000437· 90.9% built· 3 complaints
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.