RERA projects past their possession deadline
12,128 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 35 of 61
- Majestic Pearl4.4 yr overdueVikas Narayan Virkar · Baner, PuneP52100007513· filed Jun 2019 → now May 2022· 36.4% built
- Skyi Songbirds Phase D4.4 yr overdueEnerrgia Skyi Developers · Bhugaon, PuneP52100000764· filed Nov 2020 → now May 2022· 90.9% built· 7 complaints
- SHREEJI ICONIC PHASE I4.4 yr overdueRAJ LAXMI DEVELOPERS · Badlapur (M Cl), ThaneP51700013918· 90.9% built
- SUVIDHA HARIPRASAD4.4 yr overdueSUVIDHA CONSTRO · MAYUR COLONY, PuneP52100021241· 40.9% built
- SAIDHAM4.4 yr overdueAnil Pandurang Mungaji · PUSHPAK NODE, RaigarhP52000020672· 9.1% built
- Skyi Songbirds Phase B4.4 yr overdueEnerrgia Skyi Developers · Bhugaon, PuneP52100001117· filed Nov 2020 → now May 2022· 85.7% built· 1 complaint
- Anand Swarup4.4 yr overdueAsha Vibhakar Khanvilkar · Marutimandir, RatnagiriP52800016504· 47.7% built
- ABHILASHA4.4 yr overdueKUDALE SABLE BUILDERS · Shirur, PuneP52100008268· filed Nov 2020 → now May 2022· 80% built
- Sejal Homes4.4 yr overdueSAUBHARI DEVELOPERS · CHAKAN, PuneP52100011006· 63.6% built
- Shindeshahi Residency4.4 yr overdueMaruti Narayan Shinde · Near Shakuntalnagar, SolapurP52600023067· 90.9% built
- GURUDEV PARK4.4 yr overdueGURUDEV ENTERPRISES · Pashane, RaigarhP52000012486· filed Nov 2020 → now May 2022· 90.9% built
- Prime Builders4.4 yr overduePrime Builders and Developers · Andheri, Mumbai SuburbanP51800008911· filed Nov 2020 → now May 2022· 90.9% built· 1 complaint
- Siddhi Homes4.4 yr overdueShree Ganesh Developers · Chakan (CT), PuneP52100009700· 47.3% built
- NEW PUSHPARAJ4.4 yr overdueYASH INFOMEDIA & ESTATE PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800001883· filed Sept 2019 → now May 2022· 50.5% built
- El-Homes4.4 yr overdueR D Deshpanday Developers Pvt Ltd · Opp PAN Card club, PuneP52100016546· 89.5% built· 5 complaints
- LODHA ETERNIS NATURA A4.4 yr overdueLODHA DEVELOPERS LIMITED · Andheri, Mumbai SuburbanP51800000345· 90.9% built· 1 complaint
- Mangeshi City III4.4 yr overdueMangesh Dashrath Gaikar · Shree Complex Chowk, ThaneP51700016947· 45.5% built
- DEEKAY ARIA4.4 yr overdueDEEKAY DEVELOPER · Ward ABCD, Mumbai CityP51900002895· filed Dec 2020 → now May 2022· 27.3% built
- GLOBAL LIFESTYLE KHARADI4.4 yr overdueMIND SPACE SHELTERS LLP · NEAR EON IT PARKP52100016888· 77.3% built
- DESTINATION KSHITIJ4.4 yr overdueD R GAVHANE DESTINATION · Haveli, PuneP52100014715· 33.2% built
- SIDDHIVINAYAK RESIDENCY4.4 yr overdueSUYASH SAHAKAR BUILDERS AND DEVELOPERS · PUSHPAK VAHAL ULWE, RaigarhP52000022815· 90.9% built
- Geras Imperium Rise4.4 yr overdueGera Developments Private Limited · Hinjewadi, PuneP52100001786· filed Dec 2020 → now May 2022· 90.9% built· 42 complaints
- SAVALI SAFFRON PHASE - I4.4 yr overdueSAPTSIDDHI ASSOCIATES · MUNDHWA, PuneP52100013111· 90.9% built· 1 complaint
- SAPPHIRE BUSINESS ANNEXE4.4 yr overdueSAPPHIRE DEVELOPERS · Kurla, Mumbai SuburbanP51800007622· filed Nov 2020 → now May 2022· 81.8% built
- SARA SANGAM PANCHGANGA BUILDING4.4 yr overdueJAGRUT SARA ASSOCIATES · BAJAJ NAGAR, AurangabadP51500024081· 90.9% built
- MANOHAR VIKAS SHREEJI PARAISO PHASE 14.4 yr overdueDEEPLAXMI DEVELOPERS · Ambarnath, ThaneP51700002188· 90.9% built
- GALAXY AVENUE4.4 yr overduePARSHWANATH REALTORS · rajnagar, PalgharP99000010944· filed Jun 2019 → now May 2022· 90.9% built
- Veera Residency4.4 yr overdueShree Ganesha Associates · Thane, ThaneP51700004004· 72.7% built
- MAYURESH4.4 yr overdueARWADE KARANDIKAR ASSOCIATES · SOUTH SHIVAJI NAGAR, SangliP53100019329· 73.3% built
- KRIPA ALLURE4.4 yr overdueKRIPA ONENESS PRIVATE LIMITED · Andheri, Mumbai SuburbanP51800018912· 79.5% built
- MUKUNDA HEIGHTS4.4 yr overdueSai Mukunda Builder and Developers · Vasai, PalgharP99000000853· 46.4% built· 1 complaint
- M BARIA LAKE VIEW4.4 yr overdueMORESHWAR KRUSHNA BARIA · VIRAT NAGAR, PalgharP99000029111· 54.5% built
- Royal Bliss4.4 yr overdueJay Ganesh Associates · Kiwale, PuneP52100015623· filed Jun 2021 → now May 2022· 29.1% built
- ABHIMAAN HOMES PHASE II4.4 yr overdueRISING PROPCON LLP · Shirgaon, PuneP52100000285· filed Dec 2019 → now May 2022· 88.9% built· 1 complaint
- AZURE B4.4 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Tathwade, PuneP52100016218· 99.5% built
- E Wing4.4 yr overdueVinayak Pandharinath Bhongale · Near Modern College of Pharmacy Borhadwadi Moshi Pune, PuneP52100019750· 14.5% built· 1 complaint
- IMPERIAL TOWER C WING4.4 yr overdueAGCONSTRUCTIONS · NIBM, PuneP52100019566· 28.2% built
- SAHIL PRIDE4.4 yr overdueYOGESH OMPRAKASH AGARWAL · YEWALEWADI, PuneP52100005445· filed Dec 2020 → now Jun 2022· 10% built
- DWARKESHDHAM APARTMENT4.4 yr overdueVAIDEHI CONSTRUCTION · NEAR MAHA BANG, NashikP51600010508· 81.8% built
- KEDAR RESIDENCY4.4 yr overdueGOURAV CONSTRUCTION · Gijavane, KolhapurP53000003979· filed Jun 2020 → now Jun 2022· 79.1% built
- REVELL ORCHID PHASE III BUILDING E4.4 yr overdueABHAY INDRABHAN FULFAGAR · LOHGAON, PuneP52100001549· 46.8% built
- CHAITANYA AAWAS4.4 yr overdueRAJENDRA MADHUKAR JOSHI · KARANJADE NAVI MUMBAI, RaigarhP52000016309· 90.9% built
- CHINMAY VAISHVA PHASE 24.4 yr overdueCHINMAY VISHWA · NEAR AMBEGAON PATHAR POLICE CHOWKI, PuneP52100027024· 72.7% built
- DHAWAL PARK4.4 yr overdueHEMCHANDRA RAMKRISHNA INGALE · BURHANAGR, AhmednagarP52200024450· 78.2% built
- Aaryavarta4.4 yr overdueDipti Spaces Pvt. Ltd. · Andheri, Mumbai SuburbanP51900002676· 90.9% built· 6 complaints
- PAWASKAR PARK4.4 yr overdueAKAR BUILDCON · NEAR AKASHWANI, SangliP53100010044· filed Dec 2018 → now Jun 2022· 81.4% built
- SHRIRANG4.4 yr overdueVIRENDRA NATWARLAL SHETH · Kurla, Mumbai SuburbanP51800004570· filed Jun 2020 → now Jun 2022· 90.9% built· 6 complaints
- SHRINATH PARK4.4 yr overdueSHRI NATH VIHAR CONSTRUCTIONS · Pisadevi, AurangabadP51500006059· filed Dec 2021 → now Jun 2022· 81.8% built
- Redevelopment of New Monalisa CHSL4.4 yr overdueShree Mahavir Estates · Mumbai, Mumbai SuburbanP51800001955· filed Dec 2020 → now Jun 2022· 34.4% built
- AVON VISTA PROJECT -14.4 yr overdueNAIKNAVARE PROFILE CONSTRUCTIONS PVT LTD · PUNE, PuneP52100000371· filed Dec 2020 → now Jun 2022· 87.9% built· 5 complaints
- Redevelopment of Silverlight CHSL4.4 yr overdueShree Mahavir Estates · Mumbai, Mumbai SuburbanP51800002541· filed Dec 2020 → now Jun 2022· 36.2% built
- Vishwa Vimal4.4 yr overdueVikrant Vishwasrao Jadhav · Kolhapur (M Corp.), KolhapurP53000009549· filed Nov 2020 → now Jun 2022· 66.8% built
- GAGANGIRI VIHAR COMPLEX4.4 yr overdueCRESCENT INFRASTRUCTURE & DEVELOPING COMPANY · Khalapur, RaigarhP52000003647· filed Dec 2019 → now Jun 2022· 78.6% built
- Regency Classic Wing B24.4 yr overdueREGENCY NIRMAN LTD · Pune (M Corp.), PuneP52100005014· 60.9% built
- Joyville Virar Phase 14.4 yr overdueJoyville Shapoorji Housing Private Limited · Vasai, PalgharP51900000444· 72.7% built· 1 complaint
- KANJUR MATRUCHHAYA CHS LTD4.4 yr overdueSUNIL DINKAR SHINDE · Kurla, Mumbai SuburbanP51800015513· 90.9% built
- VENKATES RESIDENCY PHASE II4.4 yr overdueTIRUPATI BUILDERS AND DEVELOPERS · Aurangabad (M Corp.), AurangabadP51500004159· filed Mar 2019 → now Jun 2022· 40.9% built
- SHREENIWAS APARTMENT4.4 yr overdueKRISHNA CONSTRUCTION · WADALA SHIWAR, NashikP51600022902· 90.9% built
- REGENCY ANTILIA PHASE IV4.4 yr overdueREGENCY NIRMAN LTD · Ulhasnagar, ThaneP51700023854· 81.8% built
- DOSTI WEST COUNTY - DOSTI OAK4.4 yr overdueDOSTI ENTERPRISES · balkum, ThaneP51700006565· 90.9% built· 5 complaints
- ALANKAPURISHREE CO.OP.HSG.SOC.LTD.4.4 yr overdueVYAS BUILDCON PVT. LTD. · RAMBAUG COLONY, PuneP52100018752· 81.8% built
- Royale Residences B And C Wing4.4 yr overdueM/S Rani Creators , Consultant And Service Providers · Kurla, Mumbai SuburbanP51800005315· filed Dec 2019 → now Jun 2022· 49.7% built
- SATYAM RESIDENCY4.4 yr overdueMahalaxmi builders and Developers · Pisadevi, AurangabadP51500004520· filed Jul 2019 → now Jun 2022· 78.6% built
- AADESHWAR-24.4 yr overdueSHREE ADESHWAR BUILDCOM · Palghar, PalgharP99000011704· filed Dec 2020 → now Jun 2022· 90.9% built
- Royal Orange County C Wing4.4 yr overdueNavras Sthapatya LLP · Pimpri Chinchawad (M Corp.), PuneP52100003764· 90.9% built
- Moreshwar tower4.4 yr overdueYashraj Corporation · Kurla, Mumbai SuburbanP51800003786· filed Mar 2020 → now Jun 2022· 51.8% built
- PLUTO-B -SUNCITY HOUSING PHASE- I4.4 yr overdueSUNCITY COMPLEX · Kurla, Mumbai SuburbanP51800004553· filed Dec 2018 → now Jun 2022· 90.9% built
- RAYANSH BLOSSOM4.4 yr overdueVEENA DEVELOPERS · KALWA, THANE, ThaneP51700019266· 42.7% built
- SUMATI SADAN4.4 yr overdueMARK LIFE SPACE · MALAD (W), Mumbai SuburbanP51800021758· 81.8% built
- Krishna Pride4.4 yr overdueGajanan Krupa Developers · CHANAKYA NAGAR, ThaneP51700011439· 90.9% built
- Pushpendra City- Mahalakshmi Enclave4.4 yr overduePushpendra Real Construction Private Limited · Khedshi, RatnagiriP52800001072· 90.9% built
- Gandharva Excellence Project III H Building Part 24.4 yr overdueVinayak Pandharinath Bhongale · Borhadewadi Moshi, PuneP52100026673· 36.4% built· 1 complaint
- SHEETAL DWAR4.4 yr overdueSHEETAL ENTERPRISES · Borivali, Mumbai SuburbanP51800003724· filed Dec 2019 → now Jun 2022· 35.7% built
- Shree Hari Industrial Estate4.4 yr overdueParul and Mona Associates · Chinchpada, PalgharP99000026567· 45.5% built
- SAI VAIBHAV PARADISE4.4 yr overdueSHREE SAI DEVELOPERS · SHRIDHAR MHATRE CHOWK, ThaneP51700025525· 39.1% built
- Rozi Pushpa Sagar4.4 yr overdueROZI CONSTRUCTION AND DEVELOPERS · Chiplun (M Cl), RatnagiriP52800006682· filed Mar 2021 → now Jun 2022· 34.3% built
- AKSHAY VILLA4.4 yr overdueAKSHAY INFRASTRUCTURE PVT LTD · AMBEGAON Bk, PuneP52100007501· filed Apr 2020 → now Jun 2022· 72.7% built
- 10 Square4.4 yr overdueVIJAY KAMDAR · Andheri, Mumbai SuburbanP51800004094· filed Jun 2018 → now Jun 2022· 82.7% built· 2 complaints
- RAMALAY APARTMENT4.4 yr overdueM/S SHREERAM BUILDERS · NEAR GAJANAN MAHARAJ MATH, PuneP52100017117· 81.8% built
- PLATINUM TOWER - 314.4 yr overdueMANAS GRUHPRAVESH LLP · Andheri, Mumbai SuburbanP51800001759· 85.4% built
- ASHAPURA PRASAD4.4 yr overdueASHAPURA NIRMAN DEVELOPERS · Chikanghar, ThaneP51700014800· filed Dec 2018 → now Jun 2022· 61.8% built
- SKYLINE PRIDE4.4 yr overdueSKYLINE DEVELOPERS · Charathe, SindhudurgP52900009098· filed Mar 2019 → now Jun 2022· 85% built
- SAI SANSKRUTI4.4 yr overdueSAI RACHANA LIFE SPACES · yevalewadi, PuneP52100007881· filed Jun 2021 → now Jun 2022· 81.8% built
- Cygnus4.4 yr overdueTrimity Developers Pvt Ltd · Mulund, Mumbai CityP51900005254· filed Oct 2018 → now Jun 2022· 62.3% built
- MANHAR RESIDENCY4.4 yr overdueSHLOK ENTERPRISES (MANHAR) · Dahisar west, Mumbai SuburbanP51800002057· filed Dec 2019 → now Jun 2022· 90.8% built
- PRATHAM RESIDENCY4.4 yr overdueDalvi Brothers Builders and Developers Pvt. Ltd. · Kudal (CT), SindhudurgP52900009895· 41.1% built
- Sai Sneh Phase-I4.4 yr overdueGS DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100004300· 72.7% built
- Anandam Vihar Phase I WING A4.4 yr overdueSV SMART CITY DEVELOPERS · Gandhinagar, SolapurP52600013748· filed Mar 2020 → now Jun 2022· 90.9% built
- SAI KRUPA APARTMENT4.4 yr overdueVIJAN REALTY PRIVATE LIMITED · Nashik (M Corp.), NashikP51600004180· filed Mar 2018 → now Jun 2022· 90.9% built
- MINAKSHI HEIGHTS4.4 yr overdueVIJAYKUMAR KISANLAL GHODELLA · Nashik (M Corp.), NashikP51600010319· 55% built
- F Residences T84.4 yr overdueBramhacorp Limited · VadgaonsheriP52100002099· 96.4% built
- ALAG STELLA4.4 yr overdueALAG PROPERTY CONSTRUCTIONS PVT. LTD. · MULUND EAST, Mumbai SuburbanP51800018925· filed Jun 2021 → now Jun 2022· 82.3% built
- OM RESIDENCY4.4 yr overdueSHREE ASHAPURA COMBINES · adharwadi, ThaneP51700009448· filed Jun 2021 → now Jun 2022· 0% built· 1 complaint
- GAJANANA4.4 yr overdueAMIT HARSHAVADAN AGASKAR · Palghar, PalgharP99000016205· filed Dec 2020 → now Jun 2022· 50% built
- Regent Heights-New Ganga Niwas CHSL4.4 yr overdueRDB Mumbai Infrastructures Private Limited · Andheri, Mumbai SuburbanP51800011798· filed Jun 2019 → now Jun 2022· 84.5% built
- BT SUJATA CHSL4.4 yr overdueC H PATIL AND SONS LLP · Borivali, Mumbai SuburbanP51800003936· filed Jan 2021 → now Jun 2022· 63.6% built
- SUNFLOWER4.4 yr overdueShree Krishna Developers · Kurla, Mumbai SuburbanP51800006422· filed Dec 2018 → now Jun 2022· 90.9% built· 6 complaints
- SUYOG CHS4.4 yr overdueADITYARAJ BUILDERS · Kurla, Mumbai SuburbanP51800004742· filed Feb 2021 → now Jun 2022· 72.7% built
- OM SAI PLAZA4.4 yr overdueOM DEVELOPERS · DAMODAR NAGAR, NashikP51600022335· 90.9% built
- 1 Nere Residency4.4 yr overdueRajHeramb Landmarks · NERE, PuneP52100002517· filed Dec 2018 → now Jun 2022· 88.2% built· 2 complaints
- Nathsagar residensy4.4 yr overdueSopan Radhakisan Andhale · Khalapur, RaigarhP52000013554· filed Dec 2018 → now Jun 2022· 79.1% built
- INSIGNIA4.4 yr overdueULTRA SPACE DEVELOPERS PRIVATE LIMITED · Kalina, Mumbai SuburbanP51800002313· filed Apr 2020 → now Jun 2022· 96.1% built· 64 complaints
- LAKE CITY PHASE-24.4 yr overdueSADANAND LAXMANRAO PATIL · Sudhagad, RaigarhP52000017801· 63% built
- RAJ HEAVENS PHASE 1 C BUILDING4.4 yr overdueBURHANI TAMOS DEVELOPERS · BEHIND LIONS ENGLISH SCHOOL, Dadra & Nagar HaveliP49600000096· 90.9% built
- AVADHUT VIHAR A WING4.4 yr overdueAVADHUT BUILDERS · -, SataraP52700014055· filed Dec 2018 → now Jun 2022· 66.4% built
- SIMRAH PARADISE4.4 yr overdueARYAN DEVELOPERS · Pune (M Corp.), PuneP52100014597· 81.4% built
- PARVATI HEIGHTS4.4 yr overdueLAXMINARAYAN CONSTRUCTIONS · Nashik, NashikP51600007938· filed Dec 2020 → now Jun 2022· 90.9% built
- GRAND VIEW4.4 yr overdueSQUARE PROPERTIES · Sangli Miraj Kupwad (M Corp.), SangliP53100003046· filed Jan 2021 → now Jun 2022· 27.3% built
- UMA IMPERIAL4.4 yr overdueMURUDESHWAR DEVELOPERS · NA, RaigarhP52000002083· filed Jun 2021 → now Jun 2022· 99.8% built· 1 complaint
- Kalpataru Radiance E4.4 yr overdueKeyana Estate LLP · Borivali, Mumbai SuburbanP51800013245· 46.9% built
- Kashmiri Heights4.4 yr overdueM.K.Enterprises · Andheri, Mumbai SuburbanP51800008802· 74.5% built· 2 complaints
- Rachana Park Wing I4.4 yr overdueShree Construction Builders and Developers · Off nagar Manmad Highway, AhmednagarP52200025216· 81.8% built
- Marvel Castella A And B Building4.4 yr overdueMARVEL SIGMA HOMES PRIVATE LIMITED · Balewadi, PuneP52100002438· 0% built· 6 complaints
- JP North Elara4.4 yr overdueJP Infra Realty Private Limited · Thane, ThaneP51700007001· 88.4% built· 3 complaints
- HILL GALAXY4.4 yr overdueR R BUILDERS · MIRA ROAD, ThaneP51700012160· filed Dec 2018 → now Jun 2022· 53.2% built
- FLORENCIA PHASE 14.4 yr overdueSHUBHAM ASSOCIATES · Wakad, PuneP52100002881· filed Jan 2021 → now Jun 2022· 72.7% built
- MIDTOWN SQUARE - PHASE I4.4 yr overdueLOTUS EMPIRE · OPP ORDNANCE FACTORY, ThaneP51700014394· 50.4% built
- SHREE TIRUMALA PARAMOUNT APARTMENT4.4 yr overdueROONGTA HOMES LLP · DEEPALI NAGAR, NashikP51600016034· 90.9% built
- EMIRUS G4.4 yr overdueG M KENJALE DEVELOPERS · BANER, PuneP52100005651· filed Jun 2021 → now Jun 2022· 85.9% built· 1 complaint
- Sanskruti Building A4.4 yr overduePushpam Infra LLP · Kashele, RaigarhP52000011794· filed Dec 2018 → now Jun 2022· 81.8% built· 1 complaint
- OM HEIGHTS4.4 yr overdueYOGESH WADNERE AND KISHOR WADNERE · Nashik, NashikP51600012257· 90.9% built
- MOUNTSCAPE4.4 yr overdueNAYAN BUILDCON · Pisoli, PuneP52100006878· filed Jun 2021 → now Jun 2022· 79.5% built
- Lodha Kolshet Plot A - Tower K4.4 yr overdueLODHA DEVELOPERS LIMITED · Thane, ThaneP51700015040· 81.8% built· 5 complaints
- NEELAYA PROJECT 24.4 yr overdueNAIKNAVARE BUILDCON PVT LTD · TALEGAON, PuneP52100021179· 79.5% built· 1 complaint
- The Trees, Residential Phase 14.4 yr overdueGodrej Properties Limited · Kurla, Mumbai SuburbanP51800000165· 89.1% built· 5 complaints
- MAYURESH PRIDE4.4 yr overdueSANTOSH DATTATRAY BIDKAR · BEHIND TALATHI OFFICE, SangliP53100016193· 90.9% built
- SIDDHANT RUTURANG4.4 yr overdueCHAITANYA BUILDCON · Haveli, PuneP52100005960· filed Dec 2019 → now Jun 2022· 90.9% built
- Samarth Krupa4.4 yr overdueShailendra Ramesh Vajaratkar · Kudal (CT), SindhudurgP52900012636· filed Jun 2019 → now Jun 2022· 65.8% built
- Ganga Paritosh B4.4 yr overdueGoel Mohata Associates · Sinhgad Road, PuneP52100001470· filed Jan 2021 → now Jun 2022· 76.4% built
- Ananta Apartments4.4 yr overdueSMARTSOLUTIONS · Vileparle east, Mumbai SuburbanP51800023422· 55.6% built
- PARK IVORY PHASE II4.4 yr overdueSUNGUARD BUILDERS LLP · KALEWADI PHATA, PuneP52100015699· 90.9% built
- EVERSHINE CROWN4.4 yr overdueEVERSHINE BUILDERS PRIVATE LIMITED · Borivali, Mumbai SuburbanP51800003631· 80% built· 5 complaints
- SHUBH AANGAN4.4 yr overdueG D REALTORS PVT LTD · Kurla, Mumbai SuburbanP51800005320· filed Jun 2021 → now Jun 2022· 90.9% built
- MEGHASRUSHTI4.4 yr overdueSIDDHI PROMOTERS · KOTHRUD, PuneP52100010408· filed Dec 2019 → now Jun 2022· 90% built
- Apna Ghar Phase-II Plot-B4.4 yr overdueSeven Eleven Construction Private Limited · Thane, ThaneP51700007988· 90.9% built· 3 complaints
- NEHRU NAGAR NISHIGANDHA CHS LTD4.4 yr overdueAISHWARYA BUILDERS & DEVELOPERS · Kurla, Mumbai SuburbanP51800002020· filed Dec 2019 → now Jun 2022· 90.9% built
- OMKARA4.4 yr overdueANH NIRMAN · Palghar, PalgharP99000016447· filed Dec 2020 → now Jun 2022· 56.8% built
- GLOBAL HEIGHTS4.4 yr overdueMD CREATION · CHARHOLI, PuneP52100007709· filed Dec 2020 → now Jun 2022· 90.9% built
- SUBHADRA APARTMENT4.4 yr overduePOTEAR ASSOCIATES · Baramati (M Cl), PuneP52100004395· filed Jun 2021 → now Jun 2022· 81.8% built
- Laxmi Residency4.4 yr overdueShivshakti Buildcon · kadwe nagar, NashikP51600010392· 90.9% built
- SHRI SWAMI SAMARTH MAULI4.4 yr overdueSHREE SWAMI SAMARTH ENTERPRISES · Karvanchiwadi, RatnagiriP52800002926· filed Mar 2019 → now Jun 2022· 18.2% built
- KOHINOOR MAJESTY WING A4.4 yr overdueKOHINOOR MAJESTY · Varale, PuneP52100001379· 81.8% built
- The Address - 24.4 yr overdueSOL Developers · MOSHI, PuneP52100007886· filed Jun 2020 → now Jun 2022· 82.8% built
- RENUKA DARSHAN4.4 yr overdueRENUKA DEVELOPERS · VIHITGAON, NashikP51600004063· filed Dec 2020 → now Jun 2022· 48.2% built· 1 complaint
- Mahavir Niwas A4.4 yr overdueRAJESH ENTERPRISES · Palghar, PalgharP99000021942· 90.9% built
- SHAMAL4.4 yr overdueMorajkar Estates LLP · Karanjade, RaigarhP52000019963· 90.9% built
- INDU RESIDENCY4.4 yr overdueSURESH KHIMJIBHAI BORSANIYA · BORGAON, NagpurP50500014852· 90.9% built
- Rustomjee Aurelia 14.4 yr overdueKapstone Constructions Private Limited · Thane, ThaneP51700001516· 80.7% built· 2 complaints
- MIRAYA4.4 yr overdueAMIT HARSHAVADAN AGASKAR · MAHIM, PalgharP99000016401· filed Dec 2020 → now Jun 2022· 49.1% built
- Saptarshi Pride4.4 yr overdueSAPTARSHI REALTORS PRIVATE LIMITED · Karanje Tarf Satara (CT), SataraP52700013865· filed Dec 2019 → now Jun 2022· 88.6% built
- AKSHA VASANT PARK4.4 yr overdueUNITED PROPERTIES · Pimpri Chinchawad (M Corp.), PuneP52100009433· filed Dec 2019 → now Jun 2022· 90.9% built
- VIMACO GULMOHAR CONDOMINIUM4.4 yr overdueABBASALI AHTESHAM HUSAIN HAJI · Amravati (M Corp.), AmravatiP50300006416· filed Dec 2020 → now Jun 2022· 9.1% built
- ABH SAMRUDDHI4.4 yr overdueTANU REALITY LLP · HANUMAN WADI, NashikP51600023767· 90.9% built
- SHREE GOPINATH SUBLIME4.4 yr overdueVEDANT CONSTRUCTION · Thane, ThaneP51700003177· 90.9% built
- DUDHWALA COMPLEX-PHASE 24.4 yr overdueROCK CORNER DEVELOPER PRIVATE LIMITED · Ward E, Mumbai CityP51900003621· filed Dec 2020 → now Jun 2022· 99% built
- Avant Heritage I4.4 yr overdueAishwarya Avant Builders LLP · Andheri, Mumbai SuburbanP51800009299· filed Dec 2018 → now Jun 2022· 90.9% built· 27 complaints
- Akash Towers A and B4.4 yr overdueLunkad Builders LLP · Pimple Nilakh, PuneP52100019140· 86.4% built· 1 complaint
- YOGESHWAR KRUPA CHS4.4 yr overdueJALARAM ASSOCIATES · NEAR TALUKA POLICE STATION, RaigarhP52000015656· 0.5% built
- Mont Vert Belbrook4.4 yr overdueMont Vert Elegance · Mulshi, PuneP52100002449· filed Dec 2018 → now Jun 2022· 93.9% built
- MAYUR HEIGHTS4.4 yr overdueREAL VALUE BUILDERS AND DEVELOPERS · MOHANE VILLAGE, ThaneP51700015724· filed Jun 2021 → now Jun 2022· 90.9% built
- THE EMPIRE4.4 yr overdueWESTIN INFRA · TARABAI PARK, KolhapurP53000002901· filed Jan 2019 → now Jun 2022· 81.8% built
- SHREE NEMINATH HEIGHTS4.4 yr overdueSHREE NEMINATH CONSTRUCTION CO · Karjat, RaigarhP52000002465· 90.9% built
- ACE ALMIGHTY COMMERCIAL4.4 yr overdueM/S. ACE ALMIGHTY · TATHWADE, PuneP52100019488· 99.5% built
- SHUBHKALASH B WING4.4 yr overdueTulip Developers · Chikhali, PuneP52100002475· filed Dec 2020 → now Jun 2022· 90.9% built
- RAINBOW CLASSIC4.4 yr overdueEFFICIENT PROPERTIES · Lonavala (M Cl), PuneP52100010619· filed Mar 2018 → now Jun 2022· 90.9% built
- Puneville Phase I4.4 yr overdueBENCHMARRK REALTY PRIVATE LIMITED · Punawale, PuneP52100000441· filed Dec 2020 → now Jun 2022· 89.1% built
- Sara Metroville A phase II4.4 yr overdueSara Infrastructures · Punawale, PuneP52100002174· filed Jun 2021 → now Jun 2022· 81.8% built
- Abhidarshan Homes4.4 yr overdueAbhidarshan Combines · Kalyan, ThaneP51700007573· filed Jun 2020 → now Jun 2022· 89.3% built
- SBI Staff Trinity CHS Ltd4.4 yr overdueRajshree Enterprise · Borivali, Mumbai SuburbanP51800008470· filed Dec 2019 → now Jun 2022· 37% built
- 11 PARK STREET A WING4.4 yr overdueTRIMURTI HOUSING · Pisoli, PuneP52100003117· 90.9% built
- Hrishita Apartment4.4 yr overdueHrishita Buildcon & Infrastructures Pvt. Ltd · SHIVAR, NashikP51600011155· filed Aug 2018 → now Jun 2022· 23.5% built
- SHARADA MYRIA4.4 yr overdueSHARADA ERECTORS PRIVATE LIMITED · Haveli, PuneP52100012315· filed Dec 2020 → now Jun 2022· 86.8% built
- Anand Nagar Phase 14.4 yr overdueAnubhavshri Realty Pvt. Ltd. · Lonere, RaigarhP52000005747· filed Jun 2018 → now Jun 2022· 99.1% built· 15 complaints
- VISION INDRATEJ4.4 yr overdueVISION BUILDCON · TATHAWADE, PuneP52100019399· 90.9% built
- SUNSHINE ELEGANCE4.4 yr overdueSUNSHINE ENTERPRISES · DOMBIVLI, ThaneP51700004045· filed Dec 2019 → now Jun 2022· 71.8% built
- SWAMI NIWAS4.4 yr overdueSWAMI SAMARTH KRUPA INFRASTRUCTURE PRIVATE LIMITED · DABHA NAGPUR, NagpurP50500023460· 81.8% built
- SAIRAJ PHASE 2-WING-A4.4 yr overdueBHASKAR JAYWANT KALE · MANDAVGAN ROAD, AhmednagarP52200026159· 81.8% built
- WHISTLING WINDS4.4 yr overdueNarendra Shantilal Bhandari · Near Balaji Hotel, PuneP52100007671· filed Jun 2019 → now Jun 2022· 55.5% built
- Yashodhan Daffodils4.4 yr overdueYASHODHAN DEVELOPMENT CORPORATION · Kondhwa BK., PuneP52100005635· filed Jul 2019 → now Jun 2022· 95.5% built· 3 complaints
- Sai-Sanjay Residency4.4 yr overdueSaipuja Buildcon · PuneP52100024996· 90.9% built
- Allure4.4 yr overdueDreamland Venture · Wagholi, PuneP52100002402· filed Mar 2019 → now Jun 2022· 86.4% built
- JANHAVI ENCLAVE4.4 yr overdueJANHAVI HOUSING DEVELOPERS PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800009236· filed Jun 2021 → now Jun 2022· 52.5% built
- LAXMI ANGAN D BUILDING4.4 yr overdueMALHAR ASSOCIATES · NEAR LAKE ROAD, AhmednagarP52200026168· 72.3% built
- SAI SYMPHONY4.4 yr overdueSainath Realtors · Kurla, Mumbai SuburbanP51800000842· filed Dec 2018 → now Jun 2022· 92.3% built
- DREAM HOME PANNA4.4 yr overdueDREAM HOME BUILDERS · Hadapsar, PuneP52100006303· filed Dec 2017 → now Jun 2022· 90.9% built
- Shiv Pride4.4 yr overdueJagdish Babubhai Kothiya · Pathardi, NashikP51600013284· 90.9% built
- EKDANT DEVELOPERS4.4 yr overdueEKDANT DEVELOPERS · Kalyan, ThaneP51700001682· 90.9% built
- Venkatesh Imperia Phase II4.4 yr overdueRajHeramb Properties · Punawale, PuneP52100002301· filed Dec 2018 → now Jun 2022· 90.9% built
- Prakalp Pride4.4 yr overduePrakalp Infrabuild And Developers Pvt. Ltd. · Pune, PuneP52100001299· filed Dec 2019 → now Jun 2022· 81.8% built
- Gagan Adira Phase 14.4 yr overdueTopaz Homes LLP · Wagholi, PuneP52100001048· filed Dec 2020 → now Jun 2022· 64.4% built· 15 complaints
- Vrundavan Residency4.4 yr overdueSwamiraj Developers LLP · Haveli, PuneP52100028242· 75.9% built
- GAIA Shrushti4.4 yr overdueZambad Disha Pride Infrastructure LLP · Satara Parisar, AurangabadP51500027185· 90.9% built
- Neelmohar E4.4 yr overdueAshoka Township (AOP) · SinnarP51600012230· filed Dec 2020 → now Jun 2022· 27.3% built
- SHREE DEEPLAXAMI4.4 yr overduePURO CONSTRUCTIONS · Kurla, Mumbai SuburbanP51800009423· filed Dec 2019 → now Jun 2022· 24% built
- Royal Orange County D wing4.4 yr overdueNavras Sthapatya LLP · Pimpri Chinchawad (M Corp.), PuneP52100004820· 90.9% built
- Shree Nagri - 34.4 yr overdueSHAILESH KANTILAL SHAH · TALEGAON DABHADE, PuneP52100015639· 90.9% built
- Vijayalakshmy Residency4.4 yr overdueSaanvi Landmarks Pvt.Ltd · DhanoriP52100046262· 90% built· 1 complaint
- NISARG4.4 yr overdueIndiapride Infraspaces · Neral, RaigarhP52000002022· filed Dec 2020 → now Jun 2022· 90.9% built
- Mukta Lake City4.4 yr overdueKANAK REALTORS · Thane, ThaneP51700014979· filed Jun 2021 → now Jun 2022· 90.9% built· 3 complaints
- LODHA AZZURO4.4 yr overdueLodha Developers Limited · Ward FSouth, Mumbai CityP51900000828· 90.9% built· 15 complaints
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.