RERA projects past their possession deadline
11,768 MahaRERA-registered projects are past the possession date currently on file and still report under 100% construction progress. Both figures are the promoter's own disclosure to the regulator.
Page 34 of 59
- VASUNDHARA4.4 yr overdueRIDDHI SIDDHI DEVELOPERS · AMBEGAON KH, PuneP52100006501· 50% built
- LomateResidency4.4 yr overdueHemant Ramesh Lomte · Vatannagar, PuneP52100019013· 90.9% built
- Bhaveshwar Nagar Building No. 34.4 yr overdueYog Reality · Kurla, Mumbai SuburbanP51800003355· filed Mar 2019 → now Mar 2022· 99.5% built· 1 complaint
- TARANGAN APARTMENT4.4 yr overdueSTAR BUILDERS AND DEVELOPERS · PIMPALGAON BAHULA, NashikP51600025558· 57.3% built
- ADINATH PRESIDIO4.4 yr overdueADINATH REALTY · Aurangabad (M Corp.), AurangabadP51500003981· filed Mar 2020 → now Mar 2022· 90.9% built
- Signature Heights4.4 yr overdueSamruddhi Properties · Wakad, PuneP52100021583· 66.2% built
- PLATINUM PALLAZO4.4 yr overduePLATINUM SQUARE · Chichwad, PuneP52100008686· filed Mar 2020 → now Mar 2022· 81.8% built· 1 complaint
- VENKATESH GRAFFITI PHASE 54.4 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAV NAGAR MUNDHWA, PuneP52100018950· 90.9% built
- FORTUNE AVENUE4.4 yr overdueFORTUNE DEVELOPERS · BEHIND FORTUNE PLAZA, KolhapurP53000014570· 62.7% built
- SHONEST TOWER PHASE II4.4 yr overdueM/S SANSKRUTI AND ESSEN ASSOCIATES · Wakad, PuneP52100004000· filed Mar 2019 → now Mar 2022· 76.5% built
- Sadashanti4.4 yr overdueDigamber Parulekar · Kothrud, PuneP52100020351· 81.8% built
- KALP NISARG4.4 yr overdueBLS VENTURES · SHIRGAON, ThaneP51700015595· 90.9% built
- SAKAAR RESIDENCY4.4 yr overdueGALAXY BUILDCON · PANDURANG CHOWK, NashikP51600021319· 81.8% built
- OMKAR APARTMENTS4.4 yr overduePINNACLE LIFESPACES · BADLAPUR, ThaneP51700015525· 90.9% built
- BLDG NO-1 M.BARIA EVEREST4.4 yr overdueMORESHWAR KRUSHNA BARIA · Vasai, PalgharP99000004326· filed Dec 2017 → now Mar 2022· 90.9% built· 5 complaints
- PANCHARATNA COMPLEX4.4 yr overduePANCHARATNA DEVELOPERS · SHAHAPUR, KolhapurP53000016038· 72.7% built
- SAI ANKOOR4.4 yr overdueNarendra Jalinder Balwadkar · Balewadi, PuneP52100015931· 90.9% built· 1 complaint
- SHANKAR PARVATI RESIDENCY4.4 yr overdueR. S. Construction · pen, RaigarhP52000012212· 90.9% built
- FRESHIA4.4 yr overduekundan mehta kenjale jointventure · pune, PuneP52100012434· filed Jun 2021 → now Mar 2022· 90.9% built
- BLDG NO-3 ROSE4.4 yr overdueM/s AMEYA BUILDERS & PROPERTY DEVELOPERS · YASHWANT NAGAR, PalgharP99000008563· filed Mar 2019 → now Mar 2022· 90.9% built
- SAI HIGHLAND4.4 yr overdueSHREE SAIKRUPA DEVELOPERS · Badlapur (M Cl), ThaneP51700011261· 9.1% built
- Natures Blessings phase I4.4 yr overdueNagarkar Developers · GORHE BDK, PuneP52100006429· filed Sept 2019 → now Mar 2022· 90.9% built· 2 complaints
- NAMDEOWADI-14.4 yr overdueLAXMI BHAGWAN KSHIRSAGAR · LOKMANYA TILAK SCHOOL, WADI, NAGPUR, NagpurP50500015550· 41.4% built
- ORBIT CONSTRUCTION4.4 yr overdueAKSHAY ANIL JAIN · NIMBHORA, AmravatiP50300015171· 28.5% built
- CRD Gardenia Apartments 2 - Phase II4.4 yr overdueDr Chandrashekhar Raghunath Dound · Velgaon, PalgharP99000019691· 52.3% built
- MAULI APARTMENT4.4 yr overduePUSHPA DHANRAJ KHANDELWAL · FOREST COLONY, AmravatiP50300015336· 8.2% built
- PRABHUPAD HEIGHTS4.4 yr overdueAMIT DASHRATH JAGDALE · OPP SANGLIKAR MALA, SangliP53100015019· 45.5% built
- SHANTANIWAS CO-OP HOUSING SOCIETY4.4 yr overdueSAI CONSTRUCTION · DEOLALI NASHIK ROAD, NashikP51600017884· 90.9% built
- BLDG NO-16 VIOLET4.4 yr overdueM/s AMEYA BUILDERS & PROPERTY DEVELOPERS · Vasai, PalgharP99000002573· filed Mar 2018 → now Mar 2022· 87% built
- Vastu Pinnacle4.4 yr overdueSanwar M Khandelwal · Borivali, Mumbai SuburbanP51800004711· filed Mar 2020 → now Mar 2022· 90.9% built· 1 complaint
- KSHITHI4.4 yr overdueG AND S ASSOCIATES · BANER, PuneP52100000607· 81.8% built
- DELTA HIGH BLDG B PHASE I4.4 yr overdueSVASTI MAHAJAN REALTORS · BHUGAON, PuneP52100015089· 82.8% built· 1 complaint
- WATERS EDGE PHASE V4.4 yr overdueOM SAGAR DEVELOPERS · PIMPLE NILAKH, PuneP52100002038· 90.9% built
- SHREE SADGURU SADAN4.4 yr overduePRASHANT KASHINATH DONGRE · Thane, ThaneP51700020301· 55.3% built
- Shreeniwas4.4 yr overdueLAGOO APTE · Pune (M Corp.), PuneP52100014480· 35.3% built
- ARIHANT ALOKI PHASE II4.4 yr overdueARIHANT AASHIYANA PRIVATE LIMITED · Karjat, RaigarhP52000006314· 41.5% built· 1 complaint
- TIRUPATI HEIGHTS BUILDING A AND B4.4 yr overdueSAJANSING MOTILAL JARWAL · CIDCO Mahanagar 1, AurangabadP51500021589· 90.9% built
- MARATHE EMPIRE4.4 yr overdueSAIJI BUILDERS · Titwala, ThaneP51700009808· filed Sept 2020 → now Mar 2022· 90.9% built
- Tulsi Aadvik4.4 yr overdueRAJ GROUP · Kharvai, Badlapur - East, ThaneP51700015302· 66.2% built
- RAJLAKSHMI4.4 yr overdueAvinash Omprakash Yadav · Gandharv Nagari, NashikP51600023406· 90.9% built
- Atul Avenue-A4.4 yr overdueNeelabh Builders And Developers · Haveli, PuneP52100016664· 81.8% built
- MANORAMA NAGAR4.4 yr overdueARC ASSOCIATES · BADLAPUR, ThaneP51700021259· 39.8% built
- SWOJAS GAURI4.4 yr overdueSWOJAS ENTERPRISES · ERANDWANA, PuneP52100020353· 4.5% built
- SAT ANUPA CHS PHASE 14.4 yr overdueDISHA CONSTRUCTION · Andheri, Mumbai SuburbanP51800001640· filed Mar 2020 → now Mar 2022· 81.1% built· 1 complaint
- SHANTIVILLA4.4 yr overdueRIKHAV ASHIT SHAH · Vile Parle(West), Mumbai SuburbanP51800002468· 47.3% built
- SHRADDHA COLONY4.4 yr overdueNACHIKETA DEVELOPERS · Palshi, AurangabadP51500014546· 90.9% built
- NYATI ESTEBAN I4.4 yr overdueNYATI REALTORS LLP · Mohammaswadi, PuneP52100003767· filed Jun 2021 → now Mar 2022· 79% built· 14 complaints
- DHANLAXMI APARTMENT BLDG NO.1 D Wing4.4 yr overdueBhagwati Abhilasha Conventure · Kalyan, ThaneP51700009900· filed Mar 2020 → now Mar 2022· 51.8% built
- DSK GREEN4.4 yr overdueDSK INFRA PROJECT · NEW CHANDRAPUR, ChandrapurP50900002141· 50% built
- MICASAA PHASE 24.4 yr overdueGAGAN GLOBAL DEVELOPERS · Wagholi, PuneP52100004919· filed Sept 2020 → now Mar 2022· 90.9% built
- SHASHWAT PARK - PHASE I- BUILDING 2 WING C D,BUILDING 3 WING E F, BUILDING 4 WING G H4.4 yr overdueSHASHWAT HOMES · Badlapur (M Cl), ThaneP51700008430· 81.5% built
- EMPIRE SQUARE PHASE II4.4 yr overdueEMPIRE PROPERTIES · Haveli, PuneP52100005190· filed Sept 2020 → now Mar 2022· 97% built· 1 complaint
- Shree Shambhavi Residency4.4 yr overdueRSDevelopers · Jule Solapur, SolapurP52600013062· 82.5% built
- Shree Residency4.4 yr overdueSHREE DEVELOPERS · Kolhapur (M Corp.), KolhapurP53000001228· 61.8% built
- PATELS SIGNATURE4.4 yr overdueSERENE INFRATECH CO · Ambarnath, ThaneP51700001172· 38.2% built
- Ashiyanas Lake View Building No 24.4 yr overdueAteeque Yusuf Khot · Khalapur, RaigarhP52000000361· 90.9% built
- TULSI ALAYA4.4 yr overdueTULSI CONSTRUCTIONS · ULWE, RaigarhP52000002347· filed Sept 2020 → now Mar 2022· 72.7% built
- PAYAL PRIDE4.4 yr overdueMIT ENTERPRISES · Thane, ThaneP51700016608· 81.8% built
- PLATINUM TOWER - 14.4 yr overdueAKSHAY GRUHPRAVESH LLP · Andheri, Mumbai SuburbanP51800000487· filed Mar 2020 → now Mar 2022· 90.9% built· 1 complaint
- Aldea Espanola Phase V4.4 yr overduePuranik Buildcon Private Limited · Mahalunge, PuneP52100000572· 90.9% built
- LAMBODAR SECOND HOMES4.4 yr overdueSATISH RAMCHANDRA PARIT · BHAGAWATI NAGAR, RatnagiriP52800015583· 40.9% built· 1 complaint
- FUTURE HEIGHTS4.4 yr overdueFUTURE HOMES CONSTRUCTIONS · Panvel, RaigarhP52000006255· 48.2% built· 1 complaint
- NEW CUFFE PARADE -LODHA ALTIA4.4 yr overdueLODHA DEVELOPERS LIMITED · Ward FNorth, Mumbai CityP51900000629· 81.8% built· 5 complaints
- AZHAAN RESIDENCY4.4 yr overdueBLUE PEARL DEVELOPERS · Ward E, Mumbai CityP51900009229· filed Sept 2020 → now Mar 2022· 82.7% built
- SAI HEIGHTS4.4 yr overdueKULSWAMINI MAHALAXMI DEVELOPERS · Vasai-Virar City (M Corp), PalgharP99000012928· filed May 2018 → now Mar 2022· 30.3% built
- REDEVELOPMENT OF NAVCHANDRAKUNJ CHSL4.4 yr overduePRANAV CONSTRUCTIONS LIMITED · Borivali, Mumbai SuburbanP51800016377· 39.5% built
- KOLOSUS GREEN CITY PHASE 14.4 yr overdueLEBBERTY PROMOTERSS AND BUILDERS · Pimpri Chinchawad (M Corp.), PuneP52100009898· filed Sept 2020 → now Mar 2022· 86% built
- MUKTA AASHIYANA4.4 yr overdueMukta Builder · Thane, ThaneP51700004190· 87.3% built
- SHANKHESHWAR PLATINUM PHASE 24.4 yr overdueSHANKHESHWAR KREATERS · Kalyan-Dombivali (M Corp.), ThaneP51700013669· 90.9% built
- POLITE HARMONY COMMERCIAL CENTRE4.4 yr overduePOLITE PROMOTERS AND BUILDERS · CHIKHALI, PuneP52100024722· 90.9% built
- XRBIA EIFFEL CITY CHAKAN PH24.4 yr overdueXRBIA CHAKAN DEVELOPERS PRIVATE LIMITED · Chakan, PuneP52100003059· filed Sept 2020 → now Mar 2022· 86.8% built· 46 complaints
- Sandesh Dawa Bazar4.4 yr overdueSandes Infrastructures Pvt Ltd · Nagpur (M Corp.), NagpurP50500009347· 81.8% built
- Cosmos Meluha4.4 yr overdueConcorde Realty · Thane, ThaneP51700009729· 64.8% built
- GANRAJ ARCADE4.4 yr overdueG G DEVELOPERS · BADLAPUR VILLAGE, ThaneP51700023490· 63.6% built
- ACE AURUM - II PHASE 014.4 yr overdueAALIA HOMES · RAVET, PuneP52100015591· 90% built
- NIRMAN AAKASH4.4 yr overdueDEEPAK SHANKAR YASHWANTE · Kalyan, ThaneP51700011174· filed Oct 2018 → now Mar 2022· 78.9% built· 4 complaints
- Skyi Star Town Phase III4.4 yr overduePate Life Melange Developers Pvt Ltd · Bhukum, PuneP52100016286· 90.9% built· 1 complaint
- COLLINA4.4 yr overdueBHARUCHA & SONS REALTORS & DEVELOPERS PVT LTD · Kanhe, PuneP52100002704· 89.1% built· 2 complaints
- NYATI ELYSIA I4.4 yr overdueNITIN DWARKADAS NYATI · KHARADIP52100000860· 82.2% built
- DANDEKAR RESIDENCY4.4 yr overdueJAYANT VISHNU DANDEKAR · NEAR VIJAYA BANK, PalgharP99000019704· 81.8% built
- KAPADIA AVENUE4.4 yr overdueL J ENTERPRISE · Borivali, Mumbai SuburbanP51800012139· filed Mar 2019 → now Mar 2022· 90.9% built
- SAI PLAZA4.4 yr overdueSAI MIRACLE DEVELOPERS · Haveli, PuneP52100009664· 79.5% built
- ARIHANT ANMOL PHASE II4.4 yr overdueARIHANT VATIKA REALTY PRIVATE LIMITED · Ambarnath, ThaneP51700003112· filed Sept 2020 → now Mar 2022· 90.9% built· 4 complaints
- NYATI ELAN SOUTH EAST I4.4 yr overduePSQUARE BUILDERS LLP · WAGHOLI, PuneP52100016232· 78.8% built
- MITHILA DHAM4.4 yr overdueNAVAL RAMBAHADUR SINGH · Palghar, PalgharP99000006624· 61.8% built
- Swiss Boulevard4.4 yr overdueChaurang Associates · Kurla, Mumbai SuburbanP51700000636· 93.9% built
- SETHIA SEA VIEW C AND D WING4.4 yr overduePrathamesh Land Developers · Borivali, Mumbai SuburbanP51800002308· filed Mar 2019 → now Mar 2022· 90.9% built· 6 complaints
- WONDER RESIDENCY C WING BUILDING NO 24.4 yr overdueNEW GALAXY ENTERPRISES · GOKHIVIRE, VASAI, PalgharP99000020475· 90.9% built
- SAPPHIRE4.4 yr overdueSai Nisarg Developers LLP · Pimpri Chinchawad (M Corp.), PuneP52100008695· 74.5% built
- BENCHMARK4.4 yr overdueNG RATHI DEVELOPERS · UNDRI, PuneP52100015705· filed Mar 2021 → now Mar 2022· 90.9% built· 1 complaint
- Retail C4.4 yr overduePersipina Developers Private Limited · Panvel, RaigarhP52000001411· 81.8% built
- PARSHVA RESIDENCY WING D4.4 yr overduePARSHVA REALTORS · DIPALI PARK, ThaneP51700022768· 29.1% built
- Sunrise Charkop Wing C4.4 yr overdueDhaval Housing AOP · Borivali, Mumbai SuburbanP51800004387· 88.6% built
- TREEKAYA4.4 yr overdueSHREE PADMAMBA ASSOCIATE · Kolhapur (M Corp.), KolhapurP53000001913· 80.9% built
- Anjani Enclave4.4 yr overdueGeeta Developers · Mira Road East, ThaneP51700014453· 81.8% built
- SHREE GANESH KRUPA4.4 yr overdueSHREE GAJANAN BUILDERS AND REALTORS · ANAND NAGAR, NashikP51600024064· 63.6% built
- SHALOM ARCADE4.4 yr overdueJACOB GEORGE · Uran, RaigarhP52000009209· filed Mar 2020 → now Mar 2022· 90.9% built
- Jayshree Ram4.4 yr overdueRachana Construction · Panvel, RaigarhP52000018164· 90.9% built
- Shankar Parvati Residency Phase 24.4 yr overdueR. S. Construction · Pen (M Cl), RaigarhP52000013704· 90.9% built
- Sai Prasad4.4 yr overduePRASAD ESTATE · Panvel, RaigarhP52000007874· filed Sept 2019 → now Mar 2022· 90.9% built
- FORTUNE DP NANO4.4 yr overdueG B & ASSOCIATES · Daman, DamanP49500000001· filed Sept 2020 → now Mar 2022· 75.2% built
- UNIQUE CORNER BUILDING NO 2 B WING4.4 yr overdueUNIQUE LAND REALTY PVT LTD · STELLA, VASAI WEST, PalgharP99000023334· 54.5% built
- ASTERIA HEIGHTS4.4 yr overdueSONA DEVELOPERS · Ward GNorth, Mumbai CityP51900002210· 90% built· 1 complaint
- M/s SIMCO JYOTI4.4 yr overdueSURESH MITHALAL JAIN · Kamatghar, ThaneP51700013727· filed Sept 2019 → now Mar 2022· 90.9% built
- Roha Prime Square4.4 yr overduePrime Square Properties · Ashtami, RaigarhP51900014230· filed Dec 2020 → now Mar 2022· 90.9% built
- NAMAN SUDARSHAN4.4 yr overdueNaman Developers · SHIVAJINAGAR BHAMBURDA, PuneP52100030266· 86.4% built
- JISHA ORCHID4.4 yr overdueYASH BUILDERS · RAHATANI, PuneP52100029044· 81.8% built
- Riddhivinayak Apartment4.4 yr overdueJai Bajarang Construction · Navali, PalgharP99000014934· filed Nov 2019 → now Mar 2022· 87.7% built
- KAMAL CLASSIC4.4 yr overdueVENKATESHWARA BUILDCON · OLD SANGVI, PuneP52100029717· 70% built
- KULSWAMINI APARTMENT4.4 yr overdueOM DEVELOPERS · SINNER FATA, NashikP51600011503· filed Jul 2021 → now Mar 2022· 53.6% built
- The Wave Phase 14.3 yr overdueJineshwar Constructions · Nashik (M Corp.), NashikP51600010965· 90.9% built
- MANHATTAN4.3 yr overdueMAJESTIQUE HOUSING LLP · Wagholi, PuneP52100001192· 97.6% built
- POORVA AANGAN4.3 yr overduePOORVA ASSOCIATES · Walhe, PuneP52100013892· 81.8% built
- MADHUBANAPARTMENT4.3 yr overdueGAURAV VISHVANATH AWATI · THATTE GROUND, AhmednagarP52200015569· 90.9% built
- SHARAD APARTMENTS CHS LTD4.3 yr overdueAAKAR CONSTRUCTIONS · Borivali, Mumbai SuburbanP51800003282· filed Dec 2017 → now Apr 2022· 90.9% built· 1 complaint
- Saidatta Developers Project Saidham4.3 yr overdueSai Datta Developers · mauje saturna, AmravatiP50300016082· 81.8% built
- CONSTRUCTION OF 448 TS EWS UNDER PMAY AND 32 SHOPS4.3 yr overdueNASHIK HOUSING AND AREA DEVELOPMENT BOARD · NEAR NEW ENGLISH SCHOOL, NashikP51600010485· 90.9% built
- Aditi Empire4.3 yr overdueRakhumai Developers · Vasai, PalgharP99000010761· 20% built
- ZEN COUNTY4.3 yr overdueZEN COUNTY · Sudhagad, RaigarhP52000004949· filed Oct 2020 → now Apr 2022· 81.8% built· 1 complaint
- Laxmi Chayya4.3 yr overdueLaxmikripa Developers · Nashik, NashikP51600008182· filed Oct 2020 → now Apr 2022· 22.7% built
- Nisarg Shrushti Phase-14.3 yr overdueArvel Realtors · Behind Mahavir Garden, PalgharP99000009330· filed Oct 2020 → now Apr 2022· 90.9% built
- SAIKRUPA HEIGHTS4.3 yr overdueVIKRAM SANJAY POL · MALKAPUR, SataraP52700022390· 27.3% built
- Acropolis 24.3 yr overdueMillennium Developers · Vinode Wasti, PuneP52100015821· 90.9% built
- SILVER OAKS VILLAS4.3 yr overdueNAVKAR CONSTRUCTION · NEAR MIT COLLEGE, AurangabadP51500020485· 90.9% built
- Aria4.3 yr overdueParinee Realtors Pvt. Ltd. · Andheri, Mumbai SuburbanP51800003167· filed Dec 2020 → now Apr 2022· 87.7% built
- VASANT NIWARA4.3 yr overdueM/s Niwara Builders & Developers · Kasaba Bawada, KolhapurP53000000207· 90.9% built
- pollens luxuria4.3 yr overdueSiddhivinayak infra · kalepadal, PuneP52100016336· 93.9% built· 1 complaint
- Laxmi Paresh Complex4.3 yr overdueManisha Nandkumar Phadke · Satara, SataraP52700004272· 38.2% built
- SIDDHIVINAYAK COMPLEX4.3 yr overdueUSHA PRASAD TANPURE · RAHURI, AhmednagarP52200016389· 55.9% built
- Kalpataru Avenue4.3 yr overdueNeo Pharma Private Limited · Borivali, Mumbai SuburbanP51800003417· filed Jun 2021 → now Apr 2022· 76.3% built· 1 complaint
- RACHANA ASHWINI4.3 yr overdueRachana Developers · BESIDE FIRE ENGINEERING COLLEGE JAGDISH NAGAR BOREGAON, NagpurP50500020724· 90.9% built
- ANSHUL CASA G BUILDING4.3 yr overdueM/S ANSHUL SIDDHI PROMOTERS AND BUILDERS · Wakad, PuneP52100001429· 90.9% built
- SIDDHIVINAYAK HEIGHTS4.3 yr overdueNIRMITI INFRAA · MALKAPUR, SataraP52700021933· 27.3% built
- Vishwa Vastu Apartments4.3 yr overduePatki-Joshi Engineers and Contractors Pvt. Ltd. · Nagala Park, KolhapurP53000020255· 90.9% built
- Rajwada Nx4.3 yr overdueBhandari Limaye Developers & Contractors · Satara, SataraP52700011395· 90.9% built· 1 complaint
- ECO VALLEY PLUS4.3 yr overdueNAMRATA JALAN VENTURES · Kanhe, PuneP52100016509· 90.9% built
- Laxmi Vyankatesh Complex4.3 yr overdueNandkumar Vinayak Phadke · Satara, SataraP52700006159· 38.2% built
- SECTOR 37 TALOJA (RENAMED) /SECTOR 29 TALOJA (OLD)4.3 yr overdueCITY AND INDUSTRIAL DEVELOPMENT CORPORATION OF MAHARASHTRA LIMITED · SECTOR 29, RaigarhP52000017447· filed Oct 2021 → now Apr 2022· 78.2% built
- Constuction of 56 flats under EWS and 21 LIG at S.No. 11-12/3 at Mouza- Wanjara, Nagpur4.3 yr overdueMHADA (Nagpur Board) · North Nagpur, NagpurP50500002554· 86.4% built
- Pancham Phase II at Nanded City4.3 yr overdueNanded City Development & Construction Co. Ltd. · Nanded City, PuneP52100000288· 99.2% built
- Kalpataru Yashodhan4.3 yr overdueKalpataru Property Ventures LLP · Andheri, Mumbai SuburbanP51800000442· 86.3% built· 2 complaints
- INDRAPRASTH COMPLEX4.3 yr overdueSWASTIK DEVELOPERS · Palghar, PalgharP99000001847· filed Jan 2019 → now Apr 2022· 90.9% built
- SUMANGAL PRIDE4.3 yr overdueSANDEEP SUDHAKAR KODGULE · SHANIWAR PETH, SataraP52700018807· 81.4% built
- Sector 40 Kharghar4.3 yr overdueCity and Industrial Development Corporation Of Mahrastra Ltd · Kharghar, RaigarhP52000017448· filed Oct 2021 → now Apr 2022· 78.2% built
- Heramb Prime4.3 yr overdueMangesh Vitthal Wadekar · Satara, SataraP52700009659· 90.9% built
- Bhandari Plaza4.3 yr overdueABHISHEK RADHESHYAM BHANDARI · Satara, SataraP52700009431· 90.5% built
- TULJA NEST4.3 yr overdueTULJA BUILDERS · Sawantwadi (M Cl), SindhudurgP52900007799· 61.6% built
- Ornate Heights4.3 yr overdueSADGURU BUILDERS & DEVELOPERS · Panvel, RaigarhP52000010371· filed May 2019 → now Apr 2022· 99.7% built
- Devakinagar4.3 yr overdueEmpire Developers · Palghar, PalgharP99000003256· filed Feb 2019 → now Apr 2022· 90.9% built
- Anant Vihar4.3 yr overdueQuality Developers · Satara, SataraP52700011558· 81.8% built
- Shivalay4.3 yr overdueKedar Developers · MANJARI Bk, PuneP52100008842· 56.4% built
- SHREE LAXMI NABHANGAN4.3 yr overdueBHAGYALAXMI ENTERPRISES · Near Ram Mandir, PuneP52100016414· 73.5% built
- Mohak City Florence4.3 yr overdueV.M.S Enterprises · Vasai, PalgharP99000011207· filed Oct 2020 → now Apr 2022· 90.9% built
- HORIZON PALMS II4.3 yr overdueK M DEVELOPERS · OWALE, ThaneP51700011148· 88.3% built
- Keru Mata Niwas4.3 yr overdueShree Ambika Builders & Developers · Pushpak New, RaigarhP52000018652· filed Oct 2020 → now Apr 2022· 90.9% built· 1 complaint
- VRUNDAVAN NAGARI4.3 yr overdueRUKMANI BUILDERS AND DEVELOPERS · BEHIND MANTRI PARK, WashimP50200018767· 87.3% built
- S K RESIDENCY4.3 yr overdueITTEHAD BUILDERS AND DEVELOPERS · Thane, ThaneP51700009469· filed Apr 2021 → now Apr 2022· 98.5% built
- The Oasis4.3 yr overdueM/s. Universal Infra Developers · Thane, ThaneP51700004362· filed Apr 2020 → now Apr 2022· 87.3% built· 5 complaints
- Radha Classic4.3 yr overdueRadha Housing · Vadgaon Anand.(Aalephata), PuneP52100017411· filed Oct 2020 → now Apr 2022· 60% built
- SHREE TIRUMALA REGENCY APARTMENT4.3 yr overdueROONGTA HOMES LLP · DEEPALI NAGAR, NashikP51600016235· 81.8% built
- Prathmesh Mangal4.3 yr overdueVivek Shankarrao Nikam · Satara, SataraP52700002519· 90.9% built
- VERDE RESIDENCE COLLECTION4.3 yr overdueSTRATFORD REALTY LLP · Yerwada, PuneP52100004841· filed Oct 2020 → now Apr 2022· 88.6% built· 1 complaint
- Tulsi Sharnam4.3 yr overdueTulsi Infratech · Chikhloli west, ThaneP51700017417· 90.9% built
- Muktanand Co-op Housing Society4.3 yr overdueKuldeep s Pednekar · Kurla, Mumbai SuburbanP51800006384· filed May 2018 → now May 2022· 53.6% built· 2 complaints
- The Palms4.3 yr overdueKetsun Enterprises · Pune (M Corp.), PuneP52100008404· filed Jun 2018 → now May 2022· 72.6% built
- YOGA YOG CHS - CREST4.3 yr overdueHariom Sayaji Properties LLP · Andheri, Mumbai SuburbanP51800001550· 72.7% built· 1 complaint
- Vainta Residency4.3 yr overdueSthapatya Realtors · Kankavali, SindhudurgP52900007947· filed Jun 2018 → now May 2022· 90.9% built
- The Ghatkopar Nilkantha Chs Ltd4.3 yr overdueSchemaatics · Kurla, Mumbai SuburbanP51800012450· filed Jan 2021 → now May 2022· 90.9% built
- JD Villas4.2 yr overdueJD Villas · SATARA AREA, AurangabadP51500034527· 90.9% built
- Datta Digambar Apartment4.2 yr overdueManish Bhaskar Danke · In front of Vishrambag railway station, SangliP53100018975· 81.8% built
- Cluster G4.2 yr overdueShibam Associates · Neral, RaigarhP52000009953· 56.8% built
- NAGESHWAR PROPERTIES4.2 yr overdueSAMBHAJI BABAN BORADE · Haveli, PuneP52100006098· 90.9% built
- Chirag Infotech4.2 yr overdueAarsh Construction · Thane, ThaneP51700019942· 90.9% built
- VARAD IMPERIA4.2 yr overdueNAKSHATRA INFRA · NEAR LAMXI MANDIR, SangliP53100021313· 81.8% built
- SIDDHI HERITAGE4.2 yr overdueDOSTI DEVELOPERS · JALGAON, RatnagiriP52800016717· filed Dec 2021 → now May 2022· 90.9% built
- VASTUVARAD4.2 yr overdueVASTUSHRDDHA BUILDERS · GOVT. COLONY, SangliP53100022472· 81.8% built
- Konnark Gardens4.2 yr overdueNinath Bhausaheb Shingade · Chindran, RaigarhP52000009416· 70.3% built· 1 complaint
- Westernhills D 64.2 yr overdueHigh Seas Properties Private Limited · Pune, PuneP52100001257· filed Jan 2021 → now May 2022· 90.9% built
- Mahalaxmi City Phase II4.2 yr overdueGRUHLAXMI LIFE SPACE PRIVATE LIMITED · Bokhara, NagpurP50500002647· filed Nov 2020 → now May 2022· 52% built
- Ratnadeep4.2 yr overdueAnkur Premises Developers LLP · Andheri, Mumbai SuburbanP51800007115· 81.8% built
- Panvelkar Estate - Stanford - Phase-II4.2 yr overduePanvelkar Infrastructures Private Limited · Mankivali, ThaneP51700014842· 90.9% built· 2 complaints
- Sejal Homes4.2 yr overdueSAUBHARI DEVELOPERS · CHAKAN, PuneP52100011006· 63.6% built
- NEW PUSHPARAJ4.2 yr overdueYASH INFOMEDIA & ESTATE PRIVATE LIMITED · Kurla, Mumbai SuburbanP51800001883· filed Sept 2019 → now May 2022· 50.5% built
- SIDDHIVINAYAK RESIDENCY4.2 yr overdueSUYASH SAHAKAR BUILDERS AND DEVELOPERS · PUSHPAK VAHAL ULWE, RaigarhP52000022815· 90.9% built
- GURUDEV PARK4.2 yr overdueGURUDEV ENTERPRISES · Pashane, RaigarhP52000012486· filed Nov 2020 → now May 2022· 90.9% built
- MANOHAR VIKAS SHREEJI PARAISO PHASE 14.2 yr overdueDEEPLAXMI DEVELOPERS · Ambarnath, ThaneP51700002188· 90.9% built
- SUVIDHA HARIPRASAD4.2 yr overdueSUVIDHA CONSTRO · MAYUR COLONY, PuneP52100021241· 40.9% built
- MOTIRAM PURAM4.2 yr overdueNAYAN DILIP DALAL · Ambarnath, ThaneP51700001387· 18.2% built
- SARA SANGAM PANCHGANGA BUILDING4.2 yr overdueJAGRUT SARA ASSOCIATES · BAJAJ NAGAR, AurangabadP51500024081· 90.9% built
- DEEKAY ARIA4.2 yr overdueDEEKAY DEVELOPER · Ward ABCD, Mumbai CityP51900002895· filed Dec 2020 → now May 2022· 27.3% built
- Prime Builders and Developers - SadhuAdarsh4.2 yr overduePrime Builders and Developers · Andheri, Mumbai SuburbanP51800007720· filed Nov 2020 → now May 2022· 69.1% built
- GALAXY AVENUE4.2 yr overduePARSHWANATH REALTORS · rajnagar, PalgharP99000010944· filed Jun 2019 → now May 2022· 90.9% built
- Anand Swarup4.2 yr overdueAsha Vibhakar Khanvilkar · Marutimandir, RatnagiriP52800016504· 47.7% built
- SAPPHIRE BUSINESS ANNEXE4.2 yr overdueSAPPHIRE DEVELOPERS · Kurla, Mumbai SuburbanP51800007622· filed Nov 2020 → now May 2022· 81.8% built
- SAVALI SAFFRON PHASE - I4.2 yr overdueSAPTSIDDHI ASSOCIATES · MUNDHWA, PuneP52100013111· 90.9% built· 1 complaint
- Shindeshahi Residency4.2 yr overdueMaruti Narayan Shinde · Near Shakuntalnagar, SolapurP52600023067· 90.9% built
- SAIDHAM4.2 yr overdueAnil Pandurang Mungaji · PUSHPAK NODE, RaigarhP52000020672· 9.1% built
- DESTINATION KSHITIJ4.2 yr overdueD R GAVHANE DESTINATION · Haveli, PuneP52100014715· 33.2% built
- Majestic Pearl4.2 yr overdueVikas Narayan Virkar · Baner, PuneP52100007513· filed Jun 2019 → now May 2022· 36.4% built
- Siddhi Homes4.2 yr overdueShree Ganesh Developers · Chakan (CT), PuneP52100009700· 47.3% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.