Delayed projects in Pune
3,375 MahaRERA-registered projects in Pune are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 12 of 17
- Urban Park3.6 yr overdueUrban Developers · Haveli, PuneP52100014555· 90.9% built
- ROYAL GRANDE3.6 yr overdueFive Star Construction Company · Bhumkar Nagar, Wakad, PuneP52100015350· 77.3% built
- NISARG3.6 yr overdueKULSWAMINI ASSOCIATES PROMOTOERS AND BUILDERS · chakan, PuneP52100002785· filed Dec 2018 → now Dec 2022· 90.9% built
- OLYMPIA PHASE 13.6 yr overdueOXFORD INFRA GROUP · Wakad, PuneP52100009480· filed Dec 2018 → now Dec 2022· 52.3% built· 15 complaints
- Akashparv A, B3.6 yr overdueSHARADA SHRIKALP PROMOTERS & BUILDERS · Bavdhan, PuneP52100003836· filed Dec 2019 → now Dec 2022· 90.9% built
- L Square3.6 yr overdueLODHA AND LALWANI ASSOCIATES · Sector 9, PuneP52100006914· 72.7% built· 1 complaint
- SHRIRAM CORNER3.6 yr overdueDG DEVELOPERS · DHAYARI, PuneP52100013792· 27.3% built
- SUHRUD3.6 yr overdueGANGOTREE GREENBUILD · Erandwane, PuneP52100013402· 90.9% built
- PRISTINE PURVRANG PART 13.6 yr overduePADMAVATI HOMES · Perane, PuneP52100001262· 80.3% built
- PARK EXPRESS PHASE III3.6 yr overduePARK EXPRESS JOINT VENTURE · BALEWADI, PuneP52100018658· 65.5% built
- Mont Vert Yolo3.6 yr overdueMont Vert Elegance · Bhugaon, PuneP52100007210· 24.7% built
- Rise Alta3.6 yr overdueM/s. Anand Developers · Tathawade, PuneP52100010096· filed Dec 2019 → now Dec 2022· 45.5% built
- PRADNYESH RESIDENCY3.6 yr overdueM\S PRADNYESH BUILDERS AND DEVELOPERS · ZAGADE WASTI, PuneP52100008874· 81.8% built
- Aapla Ghar Chakan Phase II Amenity Bldg A3.6 yr overdueMaple Estates · Nanekarwadi (CT), PuneP52100008123· 18.2% built
- HAPPYCITY TALEGAON3.6 yr overdueNAMRATA DEVELOPERS · Jijamata Chowk, PuneP52100017513· 90.9% built
- Shankeshwar Prestige3.6 yr overdueNitin Chhaganlal Jain · Moshi, PuneP52100017693· 90.9% built
- VENKATESH GRAFFITI ELITE PHASE 23.6 yr overdueSHREE VENKATESH DEVELOPERS · KESHAVNAGAR MUNDHWA, PuneP52100021796· 90.9% built
- PRIDE CORNER3.6 yr overduePRIDE CONSTRUCTIONS · ANANDNAGAR, PuneP52100032253· 27.3% built
- VED VIHAR3.6 yr overduePRAKASH BHONDWE · Pimpri Chinchawad (M Corp.), PuneP52100011964· filed Dec 2019 → now Dec 2022· 33.3% built
- GAYATRREE LANDMARK PHASE II3.6 yr overdueGAYATRREE SKYSCRAPERS · Dange chowk, PuneP52100007004· filed Dec 2018 → now Dec 2022· 44.8% built· 2 complaints
- INFINITY PLANET C AND D WING3.6 yr overdueTULIP PROPERTIES · MOSHI, PuneP52100019792· 82.7% built· 1 complaint
- Siddhivinayak Apartment3.6 yr overdueVinayak Developers · Sudarshan Nagar, Chinchwad, PuneP52100030041· 81.8% built
- OXY FLORA PHASE 23.6 yr overdueOXY FLORA PHASE 2 · LONIKAND, PuneP52100015940· filed Dec 2021 → now Dec 2022· 37.5% built
- RATANRAJ3.6 yr overdueRamnivas Gupta · Lokmanyanagar, PuneP52100034094· 80.9% built
- GREEN BASIL3.6 yr overdueSUMANA INFRA · DHANKUDE VASTI, PuneP52100030560· 81.8% built
- BALAJI HEIGHTS3.6 yr overdueYUVRAJ LANDMARK · BANER, PuneP52100033638· 41.8% built
- MAJESTIQUE TOWERS EAST PHASE 13.6 yr overdueM/S. SHARAD SHREE ENTERPRISES · WAGHOLI, PuneP52100015020· 92.9% built· 1 complaint
- MAHALAXMI HEIGHTS3.6 yr overduemahendra gulabchand rathod · MAMURDI, PuneP52100045405· 77.3% built
- INNARA RESIDENCY3.6 yr overdueSIDDHIDATA DEVELOPERS · NEAR BHUMKAR CHOWK, PuneP52100029850· 53.6% built
- Vtp Cygnus- Nation R1-Tower73.6 yr overdueAshdan Developers Private Limited · Manjri, PuneP52100009524· filed Jul 2021 → now Jan 2023· 90.9% built· 37 complaints
- Shiv Sai Parth Phase - II3.6 yr overdueS.R.P. Developers · Alefata (N.V.), PuneP52100005608· filed Jul 2019 → now Jan 2023· 70.9% built
- TCG PANORAMA PHASE-I BLDG - C3.6 yr overdueTHE CONSTRUCTION & DEVELOPMENT COMPANY · AMBEGAON K., PuneP52100001435· 90.9% built
- TCG PANORAMA PHASE-II BLDG - B3.6 yr overdueTHE CONSTRUCTION & DEVELOPMENT COMPANY · AMBEGAON B, PuneP52100001924· 90.9% built
- SWOJAS PRASHANT3.6 yr overdueSWOJAS PROPERTIES · ERANDWANA, PuneP52100020926· 90.9% built
- Aaroh3.6 yr overdueBhide Kulkarni Promoters and Builders · Behind Abhiruchi Mall, PuneP52100030828· 60.5% built
- SIDDHI TOWERS A WING3.6 yr overdueSATISH BASWANT PATIL · Haveli, PuneP52100007014· filed Dec 2019 → now Jan 2023· 58.2% built
- VTP Beaumonde-Nation R2 Tower43.6 yr overdueAshdan Developers Private ltd · manjri, PuneP52100009533· filed Apr 2021 → now Jan 2023· 90.9% built· 28 complaints
- SAMRUDDHI RESIDENCY3.5 yr overduePune City, PuneP52100006236· filed Jul 2019 → now Feb 2023· 81.8% built
- AJMERA EXOTICA3.5 yr overdueGopinath Developers LLP · Wagholi gaonthan, PuneP52100015618· 47.3% built
- CRYSTAL PARK3.5 yr overdueTRIMURTI DEVELOPERS · MOHOMMADWADI, PuneP52100019837· 31.4% built
- LIFE MAXIMA PHASE 23.5 yr overduePate Future Constructions LLP · Haveli, PuneP52100002233· filed Dec 2019 → now Feb 2023· 69% built· 1 complaint
- Centro MHADA3.5 yr overdueMahindra Lifespace Developers limited · Pimpri, PuneP52100030814· 62.7% built· 1 complaint
- VERDURA3.5 yr overdueSHUBHASHREE DEVELOPERS · DUDULGAON, PuneP52100024065· 81.8% built· 1 complaint
- MILESTONE3.4 yr overdueLAGAD PROPERTIES LLP · BUDRUK, PuneP52100022853· 81.8% built
- ADIRAJ BLISS3.4 yr overdueS K DEVELOPERS · BHUGAON, PuneP52100015487· filed Mar 2022 → now Mar 2023· 66.4% built
- Playtor Paud C- Phase 13.4 yr overdueSANGAM REALTY · Mulshi, PuneP52100004088· filed Mar 2019 → now Mar 2023· 54.5% built
- KAMAL GLORY3.4 yr overdueKAMAL REALTY · KONDHWA BK, PuneP52100007792· filed Mar 2022 → now Mar 2023· 37.3% built
- Rajyog Residency3.4 yr overdueRajyog Properties · Junnar, PuneP52100012213· filed Sept 2018 → now Mar 2023· 69.5% built· 1 complaint
- ASHIRWAD HOMES3.4 yr overdueBHARAT PREMCHAND KOTHARI · SR NO 275/1B, PLOT NO 05,DHORE WADA,NEAR RAILWY-STATION WADGAON MAWAL, PuneP52100025081· 90.9% built
- Kohinoor3.4 yr overdueOxford Properties ( Kondhwa Project) · KONDHWA, PuneP52100013890· 67.3% built
- SHREE GANESH ACE ARCADE3.4 yr overdueGOBIND BUILDERS & DEVELOPERS · RAHATNI, PuneP52100015738· 81.7% built
- Playtor Rajgurunagar- Phase 23.4 yr overduePLAYTOR RAJGURUNAGAR DEVELOPERS PRIVATE LIMITED · Khed, PuneP52100006327· filed Sept 2018 → now Mar 2023· 60% built· 2 complaints
- Playtor Paud B3.4 yr overduePLAYTOR PAUD HOMES PRIVATE LIMITED · Mulshi, PuneP52100001949· filed Sept 2018 → now Mar 2023· 60.2% built· 1 complaint
- AKSHAY SRUSHTI3.4 yr overdueRAJENDRA RAMANLAL LUNAKD · WADMUKHWADI, PuneP52100015477· 81.8% built
- Celestial City Phase II Building A, E, H3.4 yr overdueRAMA SYNERGY SPACES · S No 78 P and 86/2 P, Ravet Aundh Road, Near Expressway, Ravet, Pimpri Chichwad, Pune, MH, PuneP52100022487· 97% built
- KUMAR PRATIK B BUILDING3.4 yr overdueKumar Construction and Properties Pvt Ltd · SINHGAD ROAD, PuneP52100020450· 0% built· 1 complaint
- RUDRA DESIRE3.4 yr overdueRADHAKRUSHANA MADHUKAR KALE · AMBEKAR MALA BABURAO NAGAR, PuneP52100023077· 63.6% built
- SILVER BROOK WING A3.4 yr overdueBehede Properties LLP · BAVDHAN KR, PuneP52100024383· 48.6% built
- Mukti Nakshatra D and F type Building3.4 yr overdueMukti Township Development & Construction Co. Pvt. Ltd. · Near Nakshatra Garden, PuneP52100022494· filed Mar 2022 → now Mar 2023· 95.5% built
- Swaroop Enclave3.4 yr overdueAMS LANDMARKS CO. · Mitramandal Co Op Hsg Society, PuneP52100019957· 90.9% built
- N B PEARL PHASE III3.4 yr overdueGanesh developers & co · NAVLE BRIDGE, PuneP52100015948· 95.5% built
- ALIVE SKYPARK3.4 yr overdueNIMANI CONSTRUCTIONS · BANER, PuneP52100020379· 81.8% built
- BELLEZA C WING3.4 yr overdueVISHAL ASSOCIATES · MALWADI, PuneP52100022719· 90.9% built
- Princetown Royal - B23.4 yr overdueManikchand Kumar Properties · Undri, PuneP52100018309· 90.9% built
- KRISHNAS BLESSING D BUILDING3.4 yr overdueVISHAL INFRACON · MANJRI BK, PuneP52100022987· 1.8% built
- The Bzone3.4 yr overdueOxford Properties ( Kondhwa Project) · KONDVA, PuneP52100013641· 79.5% built· 1 complaint
- RAINBOW GRACE3.4 yr overdueRAINBOW REALTY · WAGHOLI, PuneP52100008364· filed Mar 2020 → now Mar 2023· 90.9% built
- SHIVTEERTH LEGACY A WING3.4 yr overdueSHIVTEERTH PROPERTIES · DUDALGAON, PuneP52100020486· 9.1% built
- ANP - LANDMARK3.4 yr overdueFive Star Construction Company · Near Bhumkar Chowk, PuneP52100023061· 81.8% built
- Meera Heights3.4 yr overdueMoraya Realty · Chikhali, PuneP52100015269· 72.7% built
- DISCOVERY PHASE - II3.4 yr overdueS2 REALTY AND DEVELOPERS PRIVATE LIMITED · KUNENAMA, KUNEGAON, PuneP52100002302· filed Oct 2018 → now Mar 2023· 81.8% built· 1 complaint
- AMENITY BUILDING COMMERCIAL HONEYDEW SHOPPING PLAZA3.4 yr overdueRajendra Jindatt Achalare · NEAR RANILAXMI BAI SANIKI SCHOOL, PuneP52100031170· 80.9% built
- SHREE GANESH TOWER - UNIT E3.4 yr overduePOLITE DEVELOPERS · SECTOR NO 4, MOSHI-PCNTDA, PuneP52100032436· 63.6% built
- VISHWARAJ RESIDENCY3.4 yr overdueM/S. ANAND DEVELOPERS · WAGHOLI, PuneP52100014591· filed Jun 2020 → now Mar 2023· 51.5% built
- Jai Rajkiran Cooperative Housing Society3.4 yr overdueCitadel Landmarks · Walvekar Nagar, PuneP52100019450· filed Sept 2022 → now Mar 2023· 55% built
- 7SKYE3.4 yr overdueSUPREME VISION VENTURES · BANER, PuneP52100032077· 90.9% built
- TULJAI CLASSIC3.4 yr overdueTULJAI ASSOCIATES LLP · RAVET, PuneP52100032661· 71.8% built
- MAGIA AVENUE3.4 yr overdueOM TIRUPATI DEVELOPERS · SAI-NAGAR, PuneP52100003261· filed May 2019 → now Apr 2023· 81.8% built
- KUBER AANGAN3.3 yr overdueKUBER BUILDERS · Kolhemala, PuneP52100001638· filed Apr 2022 → now Apr 2023· 84.5% built
- Honeydew Wing B3.3 yr overdueRajendra Jindatt Achalare · Mulshi, PuneP52100016440· 90.9% built
- GANGA AMBER PH I3.3 yr overdueSHRI SIDDHIVINAYAK DEVELOPERS · Tathawade, PuneP52100002620· filed Jun 2022 → now Apr 2023· 90.9% built· 22 complaints
- THE WORK CLUB PHASE I3.3 yr overdueRavima Developer · Pimpri Waghere, PuneP52100021171· 85% built
- TCG COROLLA3.3 yr overdueTHE CONSTRUCTION & DEVELOPMENT COMPANY · Pune (M Corp.), PuneP52100001737· 81.8% built
- Laxmi Horizon3.3 yr overdueLAXMAN SAIBANA MEHETRE · NEAR PCMC WATER TANK, PuneP52100000397· filed Sept 2019 → now Apr 2023· 86.4% built
- KUMAR PEBBLE PARK ANAND 3- A1 CORE33.3 yr overdueKumar Construction and Properties Pvt Ltd · Handewadi, PuneP52100016951· 79.5% built
- addressOne - Phase 23.3 yr overduePeninsula Land Limited · Nr Maharashtra Cricket Association Stadium Gahunje Pune, PuneP52100015747· 78.2% built· 5 complaints
- GARLI HERITAGE3.3 yr overdueVSQUARE INCORP · PIMPRIGAON, PuneP52100029334· 52.3% built
- GULAB COURT3.2 yr overdueBUTTEPATIL PROPERTIES · Haveli, PuneP52100026687· 81.8% built· 1 complaint
- Vithal Niwas3.2 yr overdueM/S SHREERAM BUILDERS · Pune City, PuneP52100024779· 81.8% built
- SHIVYOG3.2 yr overdueSHIV DEVEOPERS · MHETRE PARK, PuneP52100014794· 84.8% built
- K-SQUARE-BALEWADI3.2 yr overdueANKIT CONSTRUCTION · Haveli, PuneP52100003794· filed May 2022 → now May 2023· 90.8% built· 3 complaints
- Trident Commercial and MHADA3.2 yr overduePARANJAPE SCHEMES (CONSTRUCTION) LTD · Wakad, PuneP52100019023· 9.1% built
- addressOne - Phase 33.2 yr overduePeninsula Land Limited · Near Maharashtra Cricket Association Stadium Gahunje Pune, PuneP52100015779· 81.8% built· 1 complaint
- GULAB BHAKTI NIWAS3.2 yr overdueBUTTEPATIL PROPERTIES · Haveli, PuneP52100026603· 81.8% built
- 41 ELITE A BUILDING PHASE 23.2 yr overdueM/S KRISALA ENTERPRISES · JEEVAN NAGAR, PuneP52100021234· 47.7% built
- GOLDEN NEST3.2 yr overdueSAH DEVELOPERS · Wakad, PuneP52100029184· 80.7% built
- Mont Vert Sonnet3.2 yr overdueGreenlife Constructions · Wakad, PuneP52100004227· filed Dec 2022 → now May 2023· 86.8% built
- SHAMBHAVI PALACE3.2 yr overdueN K COMPANY · WAGHOLI, PuneP52100012814· filed Mar 2018 → now May 2023· 90.9% built· 1 complaint
- Sai Nandan3.2 yr overdueVeena Constructions · Near Sai Mandir, PuneP52100034152· 81.8% built
- KSHITIJ3.2 yr overdueRVK REALTY · NEAR SONAL HALL KARVE ROAD, PuneP52100017003· 81.8% built
- VTP Alpine3.2 yr overdueNNP BUILDCON PVT. LTD · mhalunge, PuneP52100007943· filed Jun 2022 → now Jun 2023· 79.8% built· 2 complaints
- Axisa3.2 yr overdueMaheshwari Developers · Pimpri Chinchawad (M Corp.), PuneP52100003153· filed Mar 2019 → now Jun 2023· 90.9% built
- Princeville - A2, C2 and Conv Shop 23.2 yr overdueKumar Agro Products Pvt Ltd · Moshi, PuneP52100018603· 90.9% built
- KUTUMB PRIME3.2 yr overdueNAIKNAVARE BUILDCON PVT LTD · Mawal, PuneP52100002090· filed Mar 2019 → now Jun 2023· 58.2% built· 4 complaints
- KUTUMB PRIME3.2 yr overdueNAIKNAVARE BUILDCON PVT LTD · Mawal, PuneP52100003209· filed Mar 2019 → now Jun 2023· 53.4% built
- Playtor Paud D- Phase 13.2 yr overdueSANGAM REALTY · Next to Tehsil Office, PuneP52100002705· filed Jun 2019 → now Jun 2023· 25.4% built· 3 complaints
- Joyville Hinjawadi - I, Phase 43.1 yr overdueJoyville Shapoorji Housing Private Limited · Man Village, PuneP52100016786· 90.9% built· 1 complaint
- Royal Residency3.1 yr overdueRoyal Eterprises · Krupasinndhu Park, PuneP52100033743· 90.9% built
- Sukhwani Euphoria3.1 yr overdueSukhwani Buildtech · Near Kapil Akhila, PuneP52100028123· 87.3% built
- Aaradhyam Phase II3.1 yr overdueJairaj Developers Unit 11 · Tilekarnagar, PuneP52100027545· 86.4% built
- Lunawat Apex3.1 yr overdueNavya Prem Developers LLP · Aundh, PuneP52100025503· 81.8% built
- AAKAR INDIGO 23.1 yr overdueAAKAR REALTIES · CHOVISAWADI, PuneP52100025648· 90.9% built
- VISHNU KRUPA3.1 yr overdueA S ASSOCIATES · Uravade, PuneP52100004048· filed Jul 2020 → now Jun 2023· 58.2% built
- Hillside Apartment 4th Floor3.1 yr overduePratik Chandrakant Bhide · Talegaon Dabhade, PuneP52100027682· 94.5% built
- GANADHISH SANKUL B WING3.1 yr overdueM.S.PATIL AND ASSOCIATES · Pune City, PuneP52100021788· 90.9% built
- Spring Field3.1 yr overdueSoham Developers · Haveli, PuneP52100027261· 90% built
- Akshara Platinum3.1 yr overdueGARVE DEVELOPERS · Mulshi, PuneP52100023153· 90.9% built· 3 complaints
- UDYAM BIZBAY3.1 yr overdueKADU REALTY · Saswad, PuneP52100026686· 90.9% built
- AMAR ORNATE-II3.1 yr overdueMALOJI AND SONS · HADAPSAR, PuneP52100027186· 81.8% built
- YASH3.1 yr overdueRANJEKAR REALTY · Kothrud, PuneP52100030981· 81.8% built
- Joyville Hinjawadi - I, Phase 13.1 yr overdueJoyville Shapoorji Housing Private Limited · Man Village, PuneP52100016131· 90.9% built
- SAHIL YASHIKA3.1 yr overdueYOGESH OMPRAKASH AGARWAL · KONDWA(BK), PuneP52100029680· 63.6% built
- Florida Water Color II3.1 yr overdueONE EARTH · MUNDHAWA, PuneP52100000946· 63.6% built
- KAKADE- SANJEEVANI3.1 yr overdueBMK PROPERTIES PRIVATE LIMITED · NEAR BALADOR, PuneP52100028898· 70.5% built· 3 complaints
- THE EVOQ3.1 yr overdueFUTURISTIC HOMES · ASHOK THEATRE, PuneP52100027486· 81.8% built
- LINEA3.1 yr overdueRajeev Shivnath Sonkar · Hadapsar, PuneP52100002743· 45.8% built· 1 complaint
- YASHRAJ PRADAKSHINA3.1 yr overdueRAJENDRA MURLIDHAR GODBOLE · Haveli, PuneP52100000633· filed Jan 2021 → now Jun 2023· 90.9% built
- Goodwill Unique Zest County Phase 23.1 yr overdueZENITH BUILDCON · Lohegaon, PuneP52100023942· 90.9% built
- Florida Water Color I3.1 yr overdueONE EARTH · Mundhawa, PuneP52100000870· 90.9% built
- Avika Periwinkle3.1 yr overdueM/S Avika Buildcon Pvt Ltd · Baner, PuneP52100029015· 90.9% built
- 24 SILVER SPRING3.1 yr overdueMARUTI BUILDCON · Talegaon Dabhade (M Cl), PuneP52100009224· 27.3% built
- Ekdant Wing D3.1 yr overdueHemant Thombare · kothrud, PuneP52100015134· 33.6% built
- Altura3.1 yr overdueSigma Housing · Baner, PuneP52100028192· 60.6% built
- Park Infinia - I1, I2, I3, J2, J3 and K13.1 yr overdueKumar Properties and Real Estate Pvt. Ltd. · Hadapsar, PuneP52100017239· 89.1% built
- Dynamic Oasis3.1 yr overdueRajeev Shivnath Sonkar · Undri, PuneP52100001931· 64.1% built· 3 complaints
- NAKSHATRA3.1 yr overduePADMAVATI LANDMARKS · Pune City, PuneP52100030557· 9.1% built
- Anil3.1 yr overdueGokhale Housing LLP · Subhash Nagar Shukrawar Peth, PuneP52100022240· 81.8% built
- THE CENTRUM3.1 yr overdueMANSION CREATORS · OPP SKYSCRAPER, PuneP52100027662· 30.5% built
- Swaraj Phase IV TUV3.1 yr overdueSim Realty · Borhadewadi Moshi, PuneP52100015606· 93.9% built
- Kanakshree Apartments3.1 yr overdueKanak Developments · undri, PuneP52100003928· filed Dec 2018 → now Jun 2023· 90.9% built
- KUL Utsav Phase I -Building G3.1 yr overdueKumar Builders · kondhwa BK, PuneP52100003489· filed May 2019 → now Jun 2023· 49.3% built
- SWAPNASHILP3.1 yr overdueUday Pandurang Dalvi · GHORPADI, PuneP52100020665· filed Dec 2022 → now Jun 2023· 43.4% built
- Shubh Aarambh3.1 yr overdueSIDDHIVINAYAK DEVELOPERS · alandi, PuneP52100020376· 95.5% built
- Rahul Residency3.1 yr overdueSiddh Construction and Developers · Parvati, PuneP52100019158· filed Sept 2020 → now Jun 2023· 81.8% built
- TRIDENT BUSINESS CENTER3.1 yr overdueSHIRISH BHASKAR JADHAV · Haveli, PuneP52100008007· filed Jul 2020 → now Jun 2023· 81.8% built
- GULAB SADAN3.1 yr overdueBUTTEPATIL PROPERTIES · Haveli, PuneP52100029801· 81.8% built
- SAI PRASAD3.1 yr overdueUNITY CONSTRUCTIONS · ERANDWANA, PuneP52100026161· 59.1% built
- VARAD VIRAJ3.1 yr overdueSHRIKANT HIRALALJI UNECHA · DHAYARI PUNE, PuneP52100025846· 90% built
- BHALCHANDRA VIHAR PHASE - II / C3.1 yr overduePOLITE BUILDTECH · RAVET, PuneP52100029204· 74.5% built
- RKL Anand ph13.1 yr overdueLUNKAD GRUH NIRMAN COMPANY · Tathawade, PuneP52100023493· 90.9% built
- Joyville Hinjawadi - I, Phase 23.1 yr overdueJoyville Shapoorji Housing Private Limited · Man Village, PuneP52100016252· 90.9% built
- STERLING BLOOMS3.1 yr overdueYASHADA GOVIND CITY CORPORATION · Pimpri Chinchawad (M Corp.), PuneP52100003148· filed Jun 2022 → now Jun 2023· 97% built
- YASHODA AANGAN3.1 yr overdueKONARK ASSOCIATES · Thergaon, PuneP52100006664· filed Dec 2019 → now Jun 2023· 76.6% built· 1 complaint
- Ananta3.1 yr overdueNDG Projects LLP · Right Bhusari Colony, PuneP52100031934· filed Dec 2022 → now Jun 2023· 72.7% built
- Revanta3.1 yr overdueP4 PROPERTIES · RAVET, PuneP52100014793· 77.3% built
- CORAL PARK PHASE 23.1 yr overdueENKAY LIFE RELATORS PVT LTD · CHOVISAWADI, PuneP52100027697· 90.9% built
- Konark Virtue3.1 yr overdueKonark Builders · kESHAVNAGAR, PuneP52100001587· filed Dec 2022 → now Jun 2023· 78.5% built· 3 complaints
- SAMRAJYA3.1 yr overdueGARVE PATIL CONSTRUCTION COMPANY · Haveli, PuneP52100014056· filed Dec 2019 → now Jun 2023· 60% built· 1 complaint
- AVIOR-AATMAN PHASE - III3.1 yr overdueAVIORENTERPRISES LLP · Pune City, PuneP52100029907· 81.8% built
- Joyville Hinjawadi - I, Phase 33.1 yr overdueJoyville Shapoorji Housing Private Limited · Man Village, PuneP52100016775· 90.9% built
- AUDUMBER WING B3.1 yr overdueGPL SANKALP ASSOCIATES · Pune City, PuneP52100032612· 90.9% built
- Atharva Patson Phinix PH II3.1 yr overdueM/S SAMRAT ATHARVA PATSON BUILDERS AND DEVELOPERS · Chakan (CT), PuneP52100006867· 7.9% built
- SKYSCRAPER PHASE 13.1 yr overdueVISHAL PROPERTIES · Tathwade, PuneP52100008605· 90.9% built· 1 complaint
- Princetown Tower - C33.1 yr overdueManikchand Kumar Properties · Undri, PuneP52100009077· 90.9% built
- VISION STARWEST PHASE - 13.1 yr overdueVISION CREATIVE INFRA · TATHAWADE, PuneP52100024346· 90.9% built
- METRO LIFE MAXIMA RESIDENCES PHASE I3.1 yr overdueRAMA SYNERGY SPACES · Next to Indira College of Commerce and Science, PuneP52100022178· 90.9% built· 26 complaints
- Vikrant3.1 yr overduePate P Square Developers LLP · Navi Peth, PuneP52100021513· 90.9% built
- Hubtown Countrywoods Building 53.1 yr overdueHubtown Limited · Tilekar Nagar Kondhwa Budruk, PuneP52100002695· 51.5% built
- 74DownTown3.1 yr overdueAura Realtors · Baner Shroff Road Pune 411045, PuneP52100025327· 90.9% built
- Atharva Heights3.1 yr overdueAtharva Developers · INFRONT MARKET YARD, PuneP52100007912· 73.1% built
- SAI KUNJ3.1 yr overdueCHOULWAR CONSTRUCTION · BAVDHAN, PuneP52100025939· filed Jan 2023 → now Jul 2023· 56.4% built
- 75 WESTGATE3.1 yr overdueSIDDHARTH RAMESH BANSAL · RAVET, PuneP52100021442· 1.8% built
- RKH Blessings B andd C building3.1 yr overdueRKH DEVELOPERS · Moshi, PuneP52100006496· 21.1% built
- ALANKAPURI3.0 yr overdueLAIGUDE DEVELOPERS · wadgaon, PuneP52100010797· 67.5% built
- WEST AVENUE3.0 yr overdueRAINBOW CONSTRUCTIONS · PANDI BHIMSEN KALAMANDIR, PuneP52100016725· filed Feb 2023 → now Aug 2023· 38% built
- TWIN TOWERS3.0 yr overdueGAYATRI PROPERTIES · MANJARI Bk, PuneP52100005036· filed Aug 2022 → now Aug 2023· 81.8% built
- SULOCHAN PARK3.0 yr overdueASHWAMEDH SPACES PRIVATE LIMITED · Vanaj Paramhansnagar, PuneP52100029020· 90% built
- Legacy Millennia3.0 yr overdueINFINITY DEVELOPERS · Punawale, PuneP52100022379· 81.8% built
- Ceratec Avika3.0 yr overdueAnand Dayanand Agarwal · Yewalewadi, PuneP52100013774· 14.1% built
- Aqua Millennium3.0 yr overdueMILLENNIUM LEGACY DEVELOPERS · RAVET, PuneP52100022420· 81.8% built
- KUMAR PALMCREST A4 BUILDING3.0 yr overdueKUMAR PROPERTIES AND PROMOTERS PRIVATE LIMITED · PISOLI, PuneP52100022295· 61.8% built
- addressOne - Phase 43.0 yr overduePeninsula Land Limited · Near Maharashtra Cricket Association Stadium Gahunje Pune, PuneP52100015803· 78.2% built· 4 complaints
- Skyi Star Town Commercial3.0 yr overduePate Life Melange Developers Pvt Ltd · Bhukum, PuneP52100013211· filed Feb 2021 → now Aug 2023· 90% built· 4 complaints
- VIRAJ HEIGHTS3.0 yr overdueVENKATESH DEVELOPERS · DHANORI, PuneP52100026384· 90.9% built· 1 complaint
- NALANDA GARDEN B WING2.9 yr overdueM D CONSTRUCTIONS · HAVELI BANER, PuneP52100031155· filed Sept 2022 → now Sept 2023· 81.8% built
- T-Villa2.9 yr overduePanchshil Infrastructure Holdings Pvt Ltd · WAGHOLI, PuneP52100010632· 11.4% built
- WATERS EDGE PHASE VI2.9 yr overdueOM SAGAR DEVELOPERS · Pimple Nilakh, PuneP52100001427· filed Sept 2022 → now Sept 2023· 75.5% built
- PRIMUS2.9 yr overdueRANADE BAGADE CONSTRUCTIONS · BANER, PuneP52100026980· 90.9% built
- NB Coral2.9 yr overdueGanesh Associates · Saswad, PuneP52100026536· 88.2% built
- Shankeshwar Wisdom2.9 yr overdueNitin Chhaganlal Jain · Moshi, PuneP52100023359· 81.8% built
- VRINDAVAN HEIGHTS PHASE II2.9 yr overdueKWALITY WORLD DEVELOPERS (AOP) · HADAPSAR, PuneP52100016466· 94.3% built
- VENKATESH GRAFFITI GLOVER PHASE 3 - MHADA2.9 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAV NAGAR MUNDHWA, PuneP52100027217· 90.9% built
- NEXUS GULMOHAR WING C2.9 yr overdueDIAMOND NEXUS ASSOCIATES · CHARHOLI, PuneP52100022264· 81.8% built
- Joyville Hinjawadi - I, Phase 52.9 yr overdueJoyville Shapoorji Housing Private Limited · Man Village, PuneP52100018500· 90.9% built· 2 complaints
- Joyville Hinjawadi - I, Phase 62.9 yr overdueJoyville Shapoorji Housing Private Limited · Man Village, PuneP52100018502· 90.9% built
- GULMOHAR2.9 yr overdueVAASTU VISHWA BUILDCON · Jalochi, PuneP52100020209· 61.8% built
- Sai Millenium AS2.9 yr overdueSHIV CONSTRUCTIONS · Punawale, PuneP52100022267· 81.8% built
- Zinnea Housing and Commercial2.9 yr overdueSURANA BHANSALI NATEKAR · Chandani Chowk, PuneP52100006078· filed Mar 2021 → now Sept 2023· 97.7% built
- ADISHREE2.9 yr overdueMAHALAXMI DEVELOPERS AND BUILDERS · AMBEGAON BK, PuneP52100014388· filed Mar 2021 → now Sept 2023· 65.9% built
- Nikunj2.9 yr overdueDMBhosale · Haveli, PuneP52100027080· 47.3% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.