Delayed projects in Pune
3,402 MahaRERA-registered projects in Pune are past the possession date on file and still under 100% built. Where the promoter has formally revised the date, the original is shown alongside so you can see what changed.
Page 9 of 18
- VANTAGE-95.7 yr overdueSOHANLAL SHANKARLAL VISHNOI · Baner, PuneP52100003199· 90.9% built
- Tanai B5.7 yr overdueSurekha vishnu Kumbhar · Jalochi, PuneP52100003644· 72.7% built
- KRISHNA ICON5.7 yr overdueKRISHNA CONSTRUCTION COMPANY · charholi kh, PuneP52100004486· 85.2% built
- GRAND HERITAGE5.7 yr overdueUJJWALA SATISH HAWARE · Wakad, PuneP52100014251· 90.9% built
- NYATI UNITREE II5.7 yr overdueNYATI BUILDERS PRIVATE LIMITED · Pune City, PuneP52100001629· 37.4% built
- VENKATESH GRAFFITI PHASE 45.7 yr overdueSHREE VENKATESH BUILDCON PVT LTD · KESHAV NAGAR MUNDHWA, PuneP52100015461· 90.9% built
- DWARKA SAI5.7 yr overdueG K FORTUNE · Pimple Saudagar, PuneP52100001761· 81.8% built
- TRIMURTI5.7 yr overdueGruha Navnirman Developers · Pune (M Corp.), PuneP52100001969· filed Oct 2018 → now Feb 2021· 32.9% built
- Aabhas Phase I5.7 yr overdueVEDNIRMITEE REALITIES · medankarwadi, PuneP52100013811· 40.9% built
- SOLITAIRE PALMS C5.7 yr overdueRAJKUMARI GULAB CHOITHRAMANI · Borhadewadi, Moshi, PuneP52100002126· filed Aug 2019 → now Feb 2021· 27.3% built
- Gokul Residency5.6 yr overdueMEHTA BUILDERS · Suryanagari, PuneP52100016313· 90.9% built
- Shree Muktai Comlex5.6 yr overdueSAMARTH DEVELOPERS · Junnar, PuneP52100014225· 78.8% built
- INDRAPRASTHA5.6 yr overdueOMKAR DEVELOPERS · GAT NO 698/2/3, PuneP52100007400· filed Aug 2019 → now Feb 2021· 81.8% built
- Tinsel County Phase II5.6 yr overdueGrow India Realcon LLP · HINJEWADI, PuneP52100008206· 80.8% built
- SHIVAI 2 COOPERATIVE HOUSING SOCIETY5.6 yr overdueVISHWATAMAK ASSOCIATES · Parvati, PuneP52100003552· 51.8% built
- REGENT HILLS5.6 yr overdueRadheshyam Promoters and Builders · GHOTAWADE PHATA, PuneP52100003965· 90.9% built· 1 complaint
- Skyi Star Towers Phase II5.6 yr overdueEnerrgia Skyi Ventures · Bhukum, PuneP52100000690· 86.8% built· 1 complaint
- Divyatej5.6 yr overdueTejraj Promoters & Builders · Senapati Bapat Road, PuneP52100017295· 90.3% built
- SWOJAS VEDANT5.6 yr overdueASHISH RASIKLAL SHAH · ERANDVANA, PuneP52100017492· 8.2% built
- Rajashree Simandhar5.6 yr overdueRajashree Realty · Haveli, PuneP52100001297· 90.9% built
- SHREE SADGURU AUDUMBAR5.6 yr overdueSUNIL BAPUSAHEB SHINDE · RASTA PETH, PuneP52100018627· 81.8% built
- SHRAVANDHARA5.6 yr overdueKIRTIVARDHAN DEVELOPERS AND BUILDERS · Kothrud, PuneP52100002928· 72.7% built
- VISION ETERNITY5.6 yr overdueVISION DEVELOPERS · Marunji, PuneP52100002472· filed Aug 2019 → now Feb 2021· 90.9% built
- SWAPNASHILP5.6 yr overdueKALAJE ASSOCIATES · KALAJEWADI, PuneP52100002380· filed Sept 2019 → now Feb 2021· 72.7% built
- NIRANKA COOP HSG SOC5.6 yr overdueRAJESH DINESH VYAS · IDEAL COLONY KOTHRUD, PuneP52100006326· 81.8% built
- GOKUL5.6 yr overdueHARICONSTRUCTION · rajland colony, PuneP52100017933· 81.8% built
- Manjri Green woods phase 2 H1 building5.6 yr overdueMaloji Constructions · Manjari Budruk, PuneP52100000613· 90.9% built
- VENKATESH ORCHID5.6 yr overdueM/S SHREE SAI DEVELOPERS · AMBEGAON Bk, PuneP52100011026· 13.6% built
- Nilaya5.5 yr overdueFour Seasons Holdings · Pune City, PuneP52100013216· 78.5% built
- SAISHRIYA SAMRUDDHI5.5 yr overdueSAI SHRIYA BUILDERS · WAGHOLI, PuneP52100005815· 24.8% built
- VENKATESH NANDANVAN D WING5.5 yr overdueSANJAY DNYANOBA JAGTAP · Sasvad (M Cl), PuneP52100009712· 44.5% built
- Beverly Hills - Building F5.5 yr overdueSheth Developers · Hinjewadi, PuneP52100008510· filed Mar 2020 → now Mar 2021· 38.2% built· 1 complaint
- SAROJ CHSL5.5 yr overdueAssociated Recons LLP · DAHANUKAR COLONY, PuneP52100014747· 81.8% built
- ROYAL RADIANCE5.5 yr overdueM/S.Five Star Shelters · RAHATANI, PuneP52100022253· 81.8% built
- VERTICA5.5 yr overdueINFINITY CORP · Mulshi, PuneP52100000863· 52.3% built
- TruSpace Prima Domus Phase 25.5 yr overdueAtharva Enterprises · Balewadi, PuneP52100016331· 45.9% built
- GANESH GALAXY5.5 yr overdueV.N.D CONSTRUCTION · PUNE, PuneP52100004383· filed Sept 2019 → now Mar 2021· 42.7% built
- CHRISHH FORTUNE5.5 yr overdueCHRISHH HOLDINGS · Talegaon Dabhade (M Cl), PuneP52100008612· 77.3% built
- RUNAL GATEWAY PHASE - II5.5 yr overdueRajendra Suresh Jain · Kiwale, PuneP52100019500· 90.9% built
- Unique Prospero5.5 yr overdueUnique Group Unit No. 4 · Haveli, PuneP52100013353· 86.8% built
- VENKATESH NANDANVAN C WING5.5 yr overdueSANJAY DNYANOBA JAGTAP · Sasvad (M Cl), PuneP52100011768· 41.8% built
- ROHAN LEHER 2 WING A5.5 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · Pune (M Corp.), PuneP52100000610· 86.4% built
- AKSHATA ANAND RESIDENCY5.5 yr overdueANAND CONTRACTORS AND DEVELOPERS · INDAPUR, PuneP52100016189· 90.9% built
- VISION INDRABHUMI5.5 yr overdueVISION INFRASTRUCTURE · DUDULGAON, PuneP52100018032· 90.9% built
- La Montana Phase III5.5 yr overdueTata Value Homes Limited · Mawal, PuneP52100000145· filed Sept 2019 → now Mar 2021· 90.9% built· 1 complaint
- SILVER OAK5.5 yr overdueSHREE SIDDHIVINAYAK CONSTRUCTION · PUNE, PuneP52100019281· 6.8% built
- ECSTASIA5.5 yr overdueA V BHAT BUILDERS PRIVATE LIMITED · Haveli, PuneP52100013096· filed Sept 2018 → now Mar 2021· 90.9% built
- SHIVNIL5.5 yr overdueSHIVKAILAS DEVELOPMENT CORPORATION · NEAR MOSHI TOLL PLAZA, PuneP52100023537· filed Dec 2020 → now Mar 2021· 81.8% built
- SHAGUN5.5 yr overdueSIDDHESH DEVELOPERS · Near Nal Stop , Karve Road , Erandwane, PuneP52100026627· 90.9% built
- SPLENDOUR GREENS SEETAI LAKE5.5 yr overdueJORI DAGADE ASSOCIAS · Bhugaon, PuneP52100005973· filed Aug 2019 → now Mar 2021· 99.1% built
- Arun Viva5.5 yr overdueCelesta Developers · Pune, PuneP52100013048· 90.9% built
- KRUPACHHATRA COMPLEX5.5 yr overdueMEHTA BUILDERS · Jalochi, PuneP52100013921· 90.9% built
- ECO SHOPPY5.5 yr overdueNAMRATA DEVELOPERS PVT. LTD · s, PuneP52100015225· 80% built
- PANCHAVATI NEST5.5 yr overduePANCHAVATI DEVELOPERS · chikhali, PuneP52100005358· 81.8% built
- Sanvi Marvel5.5 yr overdueMeghraj Spaces Private Limited · Khed, PuneP52100007075· filed Oct 2019 → now Apr 2021· 27.1% built· 3 complaints
- SINHGAD PLANET B WING5.5 yr overdueANANT NARAYAN GANDALE · NARHE, PuneP52100003473· filed Oct 2019 → now Apr 2021· 27.3% built
- VARDHAMAN PEARL-ABOLI5.5 yr overdueVardhman Pearl · Raghav nagar, PuneP52100000751· filed Oct 2019 → now Apr 2021· 90.9% built
- KATE VRUNDAVAN5.5 yr overdueVRUNDAVAN DEVELOPERS · Haveli, PuneP52100000189· 48% built
- NIRVANA BEYOND A WING5.3 yr overdueDiamond Nexus Properties · KATALE VASTI, PuneP52100015425· 90.5% built
- SIDDHESHWAR ARAMBHA5.3 yr overdueSIDDHESHWAR DEVELOPERS AND BUILDERS · MOSHI GAOTHAN, PuneP52100016365· 27.3% built
- Silver Treasure Wing B5.3 yr overdueMark Bulidcon · Vadgaon Phata, PuneP52100013384· 61.8% built
- Courtyard One phase 25.3 yr overdueSIGMA ONE DHOOT VENTURES Previously Sigmaone Remonesa Ventures · WAKAD, PuneP52100004083· 87.3% built
- Rajyog Royal5.3 yr overdueRajyog Builders and Developers · Haveli, PuneP52100013691· 80.5% built
- Vistaara Residences5.3 yr overdueVistaara Lifespaces LLP · Gultekdi Pune, PuneP52100015297· 81.8% built
- Sun Exotica Phase 25.3 yr overdueJindal Mittal Graha Nirman Pvt. Ltd. · S. No. 10/2/4, PuneP52100018347· 93.3% built
- 32 Pinewood Drive -Phase 15.3 yr overdueS S Properties · Hingewadi Phase 3, PuneP52100001171· 79.1% built
- GANESH EMERALD B WING5.3 yr overdueEKDANTA NEST LLP · CHIKHALI, PuneP52100019225· 72.3% built
- FUSION TOWERS PHASE I5.3 yr overdueRAMA SYNERGY SPACES · Hinjawadi - Phase III, PuneP52100018013· 95.5% built· 3 complaints
- Building D Voyage5.3 yr overdueKasturi Shelters · Borhadewadi, PuneP52100006188· 99.8% built
- VRUNDAVAN PARK5.1 yr overdueShree Saishraddha Developers & Builders · Shirur, PuneP52100018019· 18.2% built
- PRASANNA I SQUARE5.1 yr overduePRASANNA DEVELOPERS · Chakan (CT), PuneP52100011288· filed Dec 2017 → now Sept 2021· 90.9% built
- MELANGE RESIDENCES - PHASE III5.0 yr overdueRAMA SYNERGY SPACES · Hinjawadi Phase III, PuneP52100017090· 94.5% built
- GREEN GLORY B WING5.0 yr overdueShree Mahalaxmi Group · Mawal, PuneP52100002374· filed Mar 2019 → now Sept 2021· 73.5% built
- Sukhwani Coloronic Phase II5.0 yr overdueS. S. D. Construction · Ravet, PuneP52100019968· 88% built
- Shree Samarth Krupa5.0 yr overdueShri Labsons Builders and Developers Pvt Ltd · Vinayak nagar , Moshi, PuneP52100010272· filed Dec 2018 → now Oct 2021· 76.4% built
- SAIDHAM5.0 yr overdueRajmata Construction · Baramati (M Cl), PuneP52100003158· 90.9% built
- ANUSHRI KLASSIC5.0 yr overdueBalaji Developers · Kalas, PuneP52100015672· 81.8% built
- PARIJATAK, MADHUBAN PHASE 55.0 yr overdueSAHYADRI PROPERTIES · Haveli, PuneP52100010997· filed Sept 2019 → now Oct 2021· 50% built
- EKTARA5.0 yr overdueArtharaj Realtors · Haveli, PuneP52100006129· filed Oct 2019 → now Oct 2021· 90.9% built
- Dreams Avani C wing5.0 yr overdueDreams Corporation Pvt Ltd · Manjari, PuneP52100000157· filed Jun 2019 → now Oct 2021· 65.9% built· 11 complaints
- BALAJI VISHWA5.0 yr overdueBALAJI DEVELOPERS · NARHE, PuneP52100013310· 90.9% built
- Perfect 10 Phase III5.0 yr overdueShagun Manav Spaces LLP · Balewadi, PuneP52100001096· 90.9% built
- Hi Face5.0 yr overdueMBM Developers · Pimpale Saudagar, PuneP52100004321· filed Oct 2018 → now Oct 2021· 55.7% built· 7 complaints
- The Legend5.0 yr overdueShree Sankalp Associates · Hinjawadi, PuneP52100007333· filed Dec 2020 → now Oct 2021· 18.2% built· 1 complaint
- SAI SHIVAM5.0 yr overdueS.R. DEVELOPERS · Navlakh Umbre, PuneP52100012266· filed Apr 2019 → now Oct 2021· 81.8% built
- Skyways Esfera 15.0 yr overdueMoze Associates · Lohegaon, PuneP52100018128· 90.9% built
- ROYAL MYSTIC5.0 yr overdueFive Star Construction Company · RAHATANI,, PuneP52100016160· 81.8% built
- BHAGYASHREE5.0 yr overdueRANJEKAR REALTY · KOTHRUD, PuneP52100015709· 36.4% built
- PARSHWA GOLD COUNTY WING A5.0 yr overduePARSHWA PROPERTIES · charohli, PuneP52100000180· 90.9% built
- SHIVAM GREENCOURT5.0 yr overdueSHIVAM DEVELOPERS PVT. LTD. · Mahalunge, PuneP52100010035· 90.9% built
- Gulmohar Apartment5.0 yr overdueM/S SHREERAM BUILDERS · OPP SHINDE HIGH SCHOOL, PuneP52100017155· 81.8% built
- PGD Pinnacle5.0 yr overduePGD Land LLP · Keshavnagar, PuneP52100002015· 90.9% built
- Zinnia Row Houses5.0 yr overdueMagarpatta Township Development & Construction Co. Ltd. · Haveli, PuneP52100018373· 87.1% built
- Rajyog annexe5.0 yr overdueJhala and kodre associates · Wadgaon Khurd, PuneP52100000570· filed Oct 2019 → now Oct 2021· 90.9% built
- K52 Building A5.0 yr overdueM/S Shri Sairaj Associates · Pune City, PuneP52100019093· 90.9% built
- MANTRA CITY 360 PHASE035.0 yr overdueMANTRA ISLAND HOMES TALEGAON LLP · TALEGAON, PuneP52100002880· filed Oct 2019 → now Oct 2021· 88.2% built
- GATHA HEIGHTS5.0 yr overdueOMGATHA BUILDERS AND DEVELOPERS PVT LTD · CHOVISAWADI, PuneP52100026233· filed Jan 2021 → now Oct 2021· 72.7% built
- Audumber5.0 yr overdueOmChidanand · Haveli, PuneP52100014216· 17.6% built
- Kumar Sanctum - A1 and B14.9 yr overdueKumar Govind J V · Ivory Estate, PuneP52100004814· filed Nov 2019 → now Nov 2021· 82.6% built
- VINAYAK154.9 yr overdueBADHEKAR DEVELOPERS · Rambaug Colony, PuneP52100007478· 81.8% built
- VIVANTA LIFE VERONIKA4.9 yr overdueVIVANTA REALTY · Pimpale Saudagar, PuneP52100002206· 90.9% built
- AXIS VERTIGA4.9 yr overdueAXIS LIFESPACES LLP · PUNE, PuneP52100003159· filed Nov 2019 → now Nov 2021· 90.9% built
- DB Commercial Phase I4.9 yr overduePune Buildtech Private Limited · Yerawada, PuneP52100004589· filed Dec 2019 → now Nov 2021· 62.3% built· 7 complaints
- Mantra Moments Phase 64.9 yr overdueMANTRA PROPERTIES · Pimpri Chinchawad (M Corp.), PuneP52100014375· 27.3% built· 2 complaints
- VIDYA VILAS4.9 yr overdueRajyog Builders through its Proprietor Vinayak Alias Prakash Shankar Manohar · Mulshi, PuneP52100013901· 90.9% built
- SUYOG AMARDHAN4.9 yr overdueSUYOG STAR DEVELOPERS · Parvati, PuneP52100010912· filed Nov 2019 → now Nov 2021· 90.9% built
- VINAYAKA BLISS4.9 yr overdueVinayaka Developers · Pimpri Chinchawad (M Corp.), PuneP52100014359· filed Jul 2019 → now Nov 2021· 95.5% built
- SHIVSAGAR PLATINUM4.9 yr overdueSABLE ASSOCIATES · Haveli, PuneP52100003789· filed Mar 2018 → now Nov 2021· 89.5% built
- Shankeshwar Darshan4.8 yr overdueShankeshwar Developers · Haveli, PuneP52100000830· filed Dec 2019 → now Dec 2021· 81.8% built
- NEST4.8 yr overdueSKYLINE ENTERPRISES · NEAR ORCHID SCHOOL, PuneP52100026122· 72.7% built
- Westernhills V1 - V94.8 yr overdueHigh Seas Properties Private Limited · Sus, PuneP52100002728· filed Dec 2019 → now Dec 2021· 89.1% built
- BA IRIS4.8 yr overdueBhandari Patel Venture · Moze Engineering College, PuneP52100013967· 90.9% built
- BHAKTI MEERA4.8 yr overdueMEGHASWANA BHONGADE ASSOCIATES · Varale, PuneP52100003491· filed Dec 2019 → now Dec 2021· 9.3% built
- TROODOS HEIGHTS4.8 yr overdueSHIVGANGA DEVELOPERS · Shewalewadi, PuneP52100007606· filed Dec 2019 → now Dec 2021· 81.8% built
- PRIVIA 94.8 yr overduePRIVIA BUILDERS LLP · MOSHI, PuneP52100007271· 90.9% built
- Runal Gateway Phase 14.8 yr overdueRajendra Suresh Jain · Kiwale, PuneP52100002021· filed Dec 2019 → now Dec 2021· 90.3% built· 2 complaints
- AUM TRIMURTI C BUILDING4.8 yr overdueM/S BUILT UP · Haveli, PuneP52100001581· filed Dec 2019 → now Dec 2021· 90% built
- Trade Park Phase14.8 yr overdueVTP Mohite Associates · UNDRI, PuneP52100000518· filed Dec 2019 → now Dec 2021· 90.9% built
- Park Land - 1 - i4.8 yr overdueYashvastu Developers · Pune City, PuneP52100002945· filed Dec 2019 → now Dec 2021· 74.4% built
- NAMRATA BUSINESS CENTRE4.8 yr overdueNAMRATA DEVELOPERS · -, PuneP52100017272· 81.8% built
- CORNER VIEW RESIDENCY4.8 yr overdueKACHA BUILDERS & DEVELOPERS · BEHIND VISHAL LAWNS, PuneP52100022330· 90.9% built
- DHRUVA4.8 yr overdueSANJEEVANI LANDSCAPE DHRUVA · PUNAWALE, PuneP52100000555· 42.5% built
- VISTAS CENTREPOINT4.8 yr overdueCavalcade Properties Private Limited · MOHAMMADWADI, PuneP52100016359· 81.8% built· 1 complaint
- SANSKRITI-NAVYANGAN4.8 yr overdueM/S. AVIOR MERLIN BUILDCON LLP · Mulshi, PuneP52100000213· filed Mar 2020 → now Dec 2021· 87.9% built· 2 complaints
- NEO CITY PART 24.8 yr overdueMAHALAXMI SHELTERS · Near JSPM College, PuneP52100001867· 90.9% built· 1 complaint
- SHIV VIHAR4.8 yr overdueROYAL CONSTRUCTION · CHARHOLI KHURD, PuneP52100016068· 18.2% built
- VASTUVAIBHAV4.8 yr overdueMaheshdada Devlopers · CHIKHALI, PuneP52100014728· 55.9% built
- ARV Newtown4.8 yr overdueVedant Infracon · Pisoli, PuneP52100002738· 90.9% built
- KESHAV VATIKA4.8 yr overdueUDAY INFRA · MAVAL, PuneP52100007032· filed Mar 2019 → now Dec 2021· 78.8% built
- Building D3 Eon Homes4.8 yr overdueHinjawadi Infradevelelopment Private Limited · Hinjwadi Ph-3, PuneP52100001860· 81.8% built
- Atrium Skyward4.8 yr overdueATRIUM HOMES LLP · Hole Vasti, PuneP52100002923· 90.9% built· 1 complaint
- MULIK LUXURIA - E WING4.8 yr overdueTUKARAM SOPANRAO MULIK · WAGHOLI, PuneP52100017442· 41.8% built
- BRAMHA SKY ONE4.8 yr overdueB & G DEVELOPERS · UNDRI, PuneP52100012500· filed Dec 2019 → now Dec 2021· 90.9% built
- Sai Pearl Phase 24.8 yr overdueSSD PROMOTERS AND BUILDERS · Pimpale Saudagar, PuneP52100000868· 69.3% built
- EPIC PHASE II4.8 yr overdueSHIVSAGAR PROMOTERS & DEVELOPERS · Wagholi, PuneP52100005410· 73% built
- SHREE SAIDATTA4.8 yr overdueSHREE SAIDATTA DEVELOPERS · Baramati (M Cl), PuneP52100011346· 27.9% built
- Kiarah Terrazo4.8 yr overdueWellwisher Apartment · Haveli, PuneP52100002327· filed Dec 2019 → now Dec 2021· 57.7% built· 4 complaints
- ETASHA4.8 yr overdueKRISALA LIMAN LANDMARKS LIMITED LIABILITY PARTNERSHIP · Pimpri Chinchawad (M Corp.), PuneP52100012581· 90.9% built
- ARADHYAM B WING4.8 yr overdueDHANESHWAR VISION DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100014371· 90.9% built
- MONTECITO Phase II - E Building4.8 yr overdueAmit Vastu Ventures LLP · Parvati, PuneP52100002014· filed Jun 2019 → now Dec 2021· 93.2% built· 1 complaint
- Westen Tower4.8 yr overdueKalbhor and Lanke Birje Associates · Wakad, PuneP52100016419· 90.9% built
- Building A2 Eon Homes4.8 yr overdueHinjawadi Infradevelelopment Private Limited · Hinjwadi Ph-3, PuneP52100006888· 81.8% built
- BLOOM RESIDENCY C BUILDING AND COMMERCIAL4.8 yr overdueBLOOM INFRASTRUCTURE · charholi kh, PuneP52100004126· 23.2% built· 1 complaint
- LALBAG PRESTIGE BUILDING B4.8 yr overdueRELIABLE CONSTRUCTION · Ambegaon, PuneP52100010952· filed Dec 2019 → now Dec 2021· 81.8% built
- SONIGARA PRATIK4.8 yr overdueSHANKHESHWAR CONSTRUCTIONS AND DEVELOPERS · KIWALE, PuneP52100013672· 90.9% built
- STERLING SHELTERS4.8 yr overdueICON DEVELOPERS · Haveli, PuneP52100022411· 81.8% built
- Golden Treasures Wing A4.8 yr overdueVINAYAK KISHOR GARVE · Punawale, PuneP52100001868· filed Dec 2019 → now Dec 2021· 90.9% built
- SOMANI DREAM HOME PHASE - 14.8 yr overdueFAST REALTY PVT LTD · Punawale, PuneP52100002272· 32.5% built
- PHASE I VISION CITY4.8 yr overdueSHUBBAN PROPERTIES VISION CITY · jambhul, PuneP52100011209· filed Dec 2018 → now Dec 2021· 89.1% built· 9 complaints
- ROHAN MADHUBAN II WINGS A B C4.8 yr overdueRohan Promoters & Developers · Pune City, PuneP52100002297· 90.9% built
- Palmspring Bungalows - E1 to E64.8 yr overdueKUMAR KERING DEVELOPERS LLP · MOHAMMEDWADI, PuneP52100015961· 78.2% built
- Maithili Empire4.8 yr overdueShree Ganesh Associates · Pimpri Chinchawad (M Corp.), PuneP52100010136· 90.9% built· 1 complaint
- Panache4.8 yr overdueTRIMURTI SAI NATH INFRAS LLP · KATRAJ, PuneP52100016181· 9.1% built
- RICH COUNTY- C & D WING4.8 yr overdueSWASTIK PROMOTERS & BUILDERS · PUNE, PuneP52100006337· filed Jun 2019 → now Dec 2021· 92.1% built
- INDRAA PARK4.8 yr overdueS K BUILDCON · AADARSH NAGAR, PuneP52100004605· 90.9% built
- AUSTIN PLAZA4.8 yr overdueAUSTIN REAL INFRA LLP · MAHATHOBA CHOWK, PuneP52100003698· 78.6% built
- Aarohi H4.8 yr overdueTeirth Developers and Suyojit Infrastructure Ltd · -, PuneP52100007298· 0% built
- POWER BOULEVARD4.8 yr overdueSAPRA PROPERTIES & INVESTMENTS · GANESH BAUG, PuneP52100002004· 81.8% built
- NANDANVAN COLINA4.8 yr overdueSAI SANKALP DEVELOPERS · AMBEGAON BK, PuneP52100014132· filed Mar 2021 → now Dec 2021· 39% built
- Omega Paradise Wing L Phase 24.8 yr overdueGarve Buildcon · WAKAD, PuneP52100004943· filed Dec 2019 → now Dec 2021· 90.9% built
- GANGA GLITZ F. BLDG4.8 yr overdueLegends County Landmark Pvt Ltd · Pune City, PuneP52100000259· 88.4% built
- SANTOSH DREAMS4.8 yr overdueMANAS PROMOTERS & DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100006993· filed Dec 2019 → now Dec 2021· 81.6% built
- SWASTIK SHRUSHTI4.8 yr overdueSWASTIK ASSOCIATES · Pimpri Chinchawad (M Corp.), PuneP52100002248· filed Dec 2019 → now Dec 2021· 14.7% built· 1 complaint
- SAMRUDHA COMPLEX4.8 yr overdueRAVI SOMJIBHAI PATEL · Junnar, PuneP52100021049· 81.8% built
- RIDDHI SIDDHI AVENUE4.8 yr overdueR R LUNKAD BUILDCON · Kaspate Vasti, PuneP52100015078· 90.9% built
- Grande View 7 Phase III Building K4.8 yr overdueChirag Developers · AMBEGAON bk, PuneP52100013947· 90.9% built
- Premier Tower - Solitaire World4.8 yr overdueClassic Promoters and Builders Private Limited · Pune, PuneP52100013951· 81.8% built· 2 complaints
- NOTTING HILL PHASE I4.8 yr overdueJaikul Associates · CHARHOLI, PuneP52100001939· 81.8% built· 4 complaints
- Aapla Ghar Lonikand4.8 yr overdueMIA Properties · Haveli, PuneP52100008033· filed Dec 2019 → now Dec 2021· 87.9% built· 4 complaints
- Vrindavan4.8 yr overdueGiriraj Associates · Pimpri Chinchawad (M Corp.), PuneP52100004464· filed Dec 2019 → now Dec 2021· 45.5% built
- JEWELS ROYALE4.8 yr overdueJEWEL DEVELOPMENT CORP · GANESH BAUG, PuneP52100002343· 90.9% built
- PRESTIGE GOLD4.8 yr overdueSHAH PRATHAMESH CONSTRUCTIONS · Mundhawa, PuneP52100001263· 54.8% built
- OXFORD PARADISE4.8 yr overdueROHAN ANIRUDHA SEOLEKAR · Sus, PuneP52100000867· 79% built
- AVALON CITY C-34.8 yr overdueClassic Promoters and Builders Private Limited · Haveli, PuneP52100003105· filed Dec 2019 → now Dec 2021· 81.8% built· 1 complaint
- Bhagyoday Residency Wing B4.8 yr overdueK C B Builders · Pimpri Chinchawad (M Corp.), PuneP52100001551· filed Dec 2019 → now Dec 2021· 50% built
- AKSHAY GALAXY4.8 yr overdueA. P. BHANDARI DEVELOPERS · YEWALEWADI, PuneP52100001730· 97.3% built· 3 complaints
- PARVATARA PHASE 14.8 yr overdueSaakshi Constructions · Haveli, PuneP52100002385· 92.7% built
- SPLENDID COUNTY4.8 yr overdueYASHADA BUILDERS · LOHGAON, PuneP52100001057· 90.9% built
- SKY POINT-PHASE I-A WING4.8 yr overdueShubh Enterprises · KESHAVNAGAR, PuneP52100009213· 69.1% built
- SAI PARADISE4.8 yr overdueHaresh Premchand Chandwani · Baner, PuneP52100002660· 72.6% built
- Atmosphere - C Wing4.8 yr overdueJRS Associates · AMBEGAON, PuneP52100000821· filed Dec 2019 → now Dec 2021· 90.9% built· 23 complaints
- GANGA KINGSTON BUILDING G4.8 yr overdueVEDANT CONSTRUCTION · Mohammadwadi, PuneP52100015357· 23.6% built
- GANRAJ HEIGHTS4.8 yr overdueBHUDHAN CONSTRUCTION · Haveli, PuneP52100004465· filed Dec 2019 → now Dec 2021· 90.9% built
- PALAASH RHYTHM4.8 yr overdueSPBDEVELOPER · chinchwad, PuneP52100002524· 9.1% built
- MILLENNIUM PARAMOUNT4.8 yr overdueMillennium Superstructures LLP · CHIKHALI, PuneP52100018086· 81.8% built
- Ganraya Mall phase1 wing B4.8 yr overduePrakash Realty · Daund (M Cl), PuneP52100005707· filed Dec 2019 → now Dec 2021· 72.7% built
- RUTURANG SHRAVAN BUILDING G4.8 yr overdueA.K.SURANA DEVELOPERS-G · PARVATI, PuneP52100003075· 99.9% built
- Sara Metroville C phase III4.8 yr overdueSara Infrastructures · Punawale, PuneP52100004198· 89.1% built
- Mount Castel4.8 yr overdueSancheti Space · WAGHOLI, PuneP52100003062· 90.9% built
- PEARL SQUARE4.8 yr overduePearl Developers · Hadapsar, PuneP52100007357· filed Dec 2018 → now Dec 2021· 90.9% built
- The Crown Greens4.8 yr overdueInternational Biotech Park Limited · Maan, Hinjawadi, PuneP52100001864· 99.9% built· 1 complaint
- ATRIA GRANDE PROJECT B4.8 yr overdueAtria Constructions · Handewadi, PuneP52100015620· 72.7% built
- Chitamani Nivas4.8 yr overdueKrishna Haribhau Lohokare · NEAR STATE BANK COLONY, PuneP52100014967· 90.9% built
- Dreams Carnival-A building4.8 yr overdueSam Developers · Charholi Phata, PuneP52100004235· 90.9% built
- EMEZEKA PARK4.8 yr overdueINDRA PROPERTIES · Jadhavwadi, PuneP52100002604· 90.9% built· 1 complaint
- Geras Isle Royale Tower 2 and 34.8 yr overdueGera Developments Private Limited · Bavdhan, PuneP52100009870· 77.7% built
- IONIA4.8 yr overdueAmit Developers · -, PuneP52100001255· filed Dec 2019 → now Dec 2021· 81.8% built
- Saarrthi Savvy Homes4.8 yr overdueSiddharth Value Homes Limited Liability partnership · Hinjavadi (CT), PuneP52100001288· filed Dec 2019 → now Dec 2021· 90.9% built· 3 complaints
- VASTUSHRI4.8 yr overdueBENKAR PROPERTIES · Dhayari (Part), PuneP52100004924· filed Dec 2018 → now Dec 2021· 90.5% built
- Bella Casa4.8 yr overdueVEER REALITY · Haveli, PuneP52100002786· 90.9% built
Source: official MahaRERA registration filings. Construction progress and possession dates are promoter self-disclosure and are not independently audited. Figures update as new filings are synced.