- AKSHAY GLORY5.6 yr overdueSHREE DEVELOPMENT CORPORATION · Pune (M Corp.), PuneP52100006319· 81.8% built
- NYATI UNITREE II5.6 yr overdueNYATI BUILDERS PRIVATE LIMITED · Pune City, PuneP52100001629· 37.4% built
- Mayuri Optimum5.6 yr overdueVinesh Naresh Kumar Oswal · UNDRI, PuneP52100002131· filed Aug 2019 → now Jan 2021· 54.5% built
- JAI GANESH RESIDENCY C WING5.6 yr overdueYASH DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100005820· 59.5% built
- Shubhankar Classic5.6 yr overdueShiv Properties · Thergaon, PuneP52100001956· 32.7% built
- TRIMURTI5.5 yr overdueGruha Navnirman Developers · Pune (M Corp.), PuneP52100001969· filed Oct 2018 → now Feb 2021· 32.9% built
- Aabhas Phase I5.5 yr overdueVEDNIRMITEE REALITIES · medankarwadi, PuneP52100013811· 40.9% built
- SOLITAIRE PALMS C5.5 yr overdueRAJKUMARI GULAB CHOITHRAMANI · Borhadewadi, Moshi, PuneP52100002126· filed Aug 2019 → now Feb 2021· 27.3% built
- Gokul Residency5.5 yr overdueMEHTA BUILDERS · Suryanagari, PuneP52100016313· 90.9% built
- Shree Muktai Comlex5.5 yr overdueSAMARTH DEVELOPERS · Junnar, PuneP52100014225· 78.8% built
- INDRAPRASTHA5.5 yr overdueOMKAR DEVELOPERS · GAT NO 698/2/3, PuneP52100007400· filed Aug 2019 → now Feb 2021· 81.8% built
- GOKUL5.5 yr overdueHARICONSTRUCTION · rajland colony, PuneP52100017933· 81.8% built
- Tinsel County Phase II5.5 yr overdueGrow India Realcon LLP · HINJEWADI, PuneP52100008206· 80.8% built
- REGENT HILLS5.5 yr overdueRadheshyam Promoters and Builders · GHOTAWADE PHATA, PuneP52100003965· 90.9% built· 1 complaint
- Skyi Star Towers Phase II5.5 yr overdueEnerrgia Skyi Ventures · Bhukum, PuneP52100000690· 86.8% built· 1 complaint
- Rajashree Simandhar5.5 yr overdueRajashree Realty · Haveli, PuneP52100001297· 90.9% built
- SWOJAS VEDANT5.5 yr overdueASHISH RASIKLAL SHAH · ERANDVANA, PuneP52100017492· 8.2% built
- Divyatej5.5 yr overdueTejraj Promoters & Builders · Senapati Bapat Road, PuneP52100017295· 90.3% built
- SHIVAI 2 COOPERATIVE HOUSING SOCIETY5.5 yr overdueVISHWATAMAK ASSOCIATES · Parvati, PuneP52100003552· 51.8% built
- NIRANKA COOP HSG SOC5.5 yr overdueRAJESH DINESH VYAS · IDEAL COLONY KOTHRUD, PuneP52100006326· 81.8% built
- VISION ETERNITY5.5 yr overdueVISION DEVELOPERS · Marunji, PuneP52100002472· filed Aug 2019 → now Feb 2021· 90.9% built
- SHREE SADGURU AUDUMBAR5.5 yr overdueSUNIL BAPUSAHEB SHINDE · RASTA PETH, PuneP52100018627· 81.8% built
- SWAPNASHILP5.5 yr overdueKALAJE ASSOCIATES · KALAJEWADI, PuneP52100002380· filed Sept 2019 → now Feb 2021· 72.7% built
- SHRAVANDHARA5.5 yr overdueKIRTIVARDHAN DEVELOPERS AND BUILDERS · Kothrud, PuneP52100002928· 72.7% built
- Manjri Green woods phase 2 H1 building5.4 yr overdueMaloji Constructions · Manjari Budruk, PuneP52100000613· 90.9% built
- VENKATESH ORCHID5.4 yr overdueM/S SHREE SAI DEVELOPERS · AMBEGAON Bk, PuneP52100011026· 13.6% built
- VERTICA5.4 yr overdueINFINITY CORP · Mulshi, PuneP52100000863· 52.3% built
- VENKATESH NANDANVAN D WING5.4 yr overdueSANJAY DNYANOBA JAGTAP · Sasvad (M Cl), PuneP52100009712· 44.5% built
- Unique Prospero5.4 yr overdueUnique Group Unit No. 4 · Haveli, PuneP52100013353· 86.8% built
- SAROJ CHSL5.4 yr overdueAssociated Recons LLP · DAHANUKAR COLONY, PuneP52100014747· 81.8% built
- CHRISHH FORTUNE5.4 yr overdueCHRISHH HOLDINGS · Talegaon Dabhade (M Cl), PuneP52100008612· 77.3% built
- SAISHRIYA SAMRUDDHI5.4 yr overdueSAI SHRIYA BUILDERS · WAGHOLI, PuneP52100005815· 24.8% built
- Beverly Hills - Building F5.4 yr overdueSheth Developers · Hinjewadi, PuneP52100008510· filed Mar 2020 → now Mar 2021· 38.2% built· 1 complaint
- RUNAL GATEWAY PHASE - II5.4 yr overdueRajendra Suresh Jain · Kiwale, PuneP52100019500· 90.9% built
- SILVER OAK5.4 yr overdueSHREE SIDDHIVINAYAK CONSTRUCTION · PUNE, PuneP52100019281· 6.8% built
- ROHAN LEHER 2 WING A5.4 yr overdueROHAN BUILDERS & DEVELOPERS PRIVATE LIMITED · Pune (M Corp.), PuneP52100000610· 86.4% built
- AKSHATA ANAND RESIDENCY5.4 yr overdueANAND CONTRACTORS AND DEVELOPERS · INDAPUR, PuneP52100016189· 90.9% built
- Nilaya5.4 yr overdueFour Seasons Holdings · Pune City, PuneP52100013216· 78.5% built
- GANESH GALAXY5.4 yr overdueV.N.D CONSTRUCTION · PUNE, PuneP52100004383· filed Sept 2019 → now Mar 2021· 42.7% built
- TruSpace Prima Domus Phase 25.4 yr overdueAtharva Enterprises · Balewadi, PuneP52100016331· 45.9% built
- La Montana Phase III5.4 yr overdueTata Value Homes Limited · Mawal, PuneP52100000145· filed Sept 2019 → now Mar 2021· 90.9% built· 1 complaint
- VISION INDRABHUMI5.4 yr overdueVISION INFRASTRUCTURE · DUDULGAON, PuneP52100018032· 90.9% built
- VENKATESH NANDANVAN C WING5.4 yr overdueSANJAY DNYANOBA JAGTAP · Sasvad (M Cl), PuneP52100011768· 41.8% built
- ROYAL RADIANCE5.4 yr overdueM/S.Five Star Shelters · RAHATANI, PuneP52100022253· 81.8% built
- ECSTASIA5.4 yr overdueA V BHAT BUILDERS PRIVATE LIMITED · Haveli, PuneP52100013096· filed Sept 2018 → now Mar 2021· 90.9% built
- SPLENDOUR GREENS SEETAI LAKE5.4 yr overdueJORI DAGADE ASSOCIAS · Bhugaon, PuneP52100005973· filed Aug 2019 → now Mar 2021· 99.1% built
- SHAGUN5.4 yr overdueSIDDHESH DEVELOPERS · Near Nal Stop , Karve Road , Erandwane, PuneP52100026627· 90.9% built
- SHIVNIL5.4 yr overdueSHIVKAILAS DEVELOPMENT CORPORATION · NEAR MOSHI TOLL PLAZA, PuneP52100023537· filed Dec 2020 → now Mar 2021· 81.8% built
- Arun Viva5.4 yr overduecelesta developers · Pune, PuneP52100013048· 90.9% built
- KRUPACHHATRA COMPLEX5.4 yr overdueMEHTA BUILDERS · Jalochi, PuneP52100013921· 90.9% built
- ECO SHOPPY5.4 yr overdueNAMRATA DEVELOPERS PVT. LTD · s, PuneP52100015225· 80% built
- PANCHAVATI NEST5.4 yr overduePANCHAVATI DEVELOPERS · chikhali, PuneP52100005358· 81.8% built
- Sanvi Marvel5.4 yr overdueMeghraj Spaces Private Limited · Khed, PuneP52100007075· filed Oct 2019 → now Apr 2021· 27.1% built· 3 complaints
- SINHGAD PLANET B WING5.4 yr overdueANANT NARAYAN GANDALE · NARHE, PuneP52100003473· filed Oct 2019 → now Apr 2021· 27.3% built
- VARDHAMAN PEARL-ABOLI5.4 yr overdueVardhman Pearl · Raghav nagar, PuneP52100000751· filed Oct 2019 → now Apr 2021· 90.9% built
- KATE VRUNDAVAN5.4 yr overdueVRUNDAVAN DEVELOPERS · Haveli, PuneP52100000189· 48% built
- 32 Pinewood Drive -Phase 15.1 yr overdueS S Properties · Hingewadi Phase 3, PuneP52100001171· 79.1% built
- Rajyog Royal5.1 yr overdueRajyog Builders and Developers · Haveli, PuneP52100013691· 80.5% built
- Courtyard One phase 25.1 yr overdueSIGMA ONE DHOOT VENTURES Previously Sigmaone Remonesa Ventures · WAKAD, PuneP52100004083· 87.3% built
- FUSION TOWERS PHASE I5.1 yr overdueRAMA SYNERGY SPACES · Hinjawadi - Phase III, PuneP52100018013· 95.5% built· 3 complaints
- GANESH EMERALD B WING5.1 yr overdueEKDANTA NEST LLP · CHIKHALI, PuneP52100019225· 72.3% built
- Silver Treasure Wing B5.1 yr overdueMark Bulidcon · Vadgaon Phata, PuneP52100013384· 61.8% built
- SIDDHESHWAR ARAMBHA5.1 yr overdueSIDDHESHWAR DEVELOPERS AND BUILDERS · MOSHI GAOTHAN, PuneP52100016365· 27.3% built
- NIRVANA BEYOND A WING5.1 yr overdueDiamond Nexus Properties · KATALE VASTI, PuneP52100015425· 90.5% built
- Sun Exotica Phase 25.1 yr overdueJindal Mittal Graha Nirman Pvt. Ltd. · S. No. 10/2/4, PuneP52100018347· 93.3% built
- Building D Voyage5.1 yr overdueKasturi Shelters · Borhadewadi, PuneP52100006188· 99.8% built
- Vistaara Residences5.1 yr overdueVistaara Lifespaces LLP · Gultekdi Pune, PuneP52100015297· 81.8% built
- VRUNDAVAN PARK4.9 yr overdueShree Saishraddha Developers & Builders · Shirur, PuneP52100018019· 18.2% built
- PRASANNA I SQUARE4.9 yr overduePRASANNA DEVELOPERS · Chakan (CT), PuneP52100011288· filed Dec 2017 → now Sept 2021· 90.9% built
- GREEN GLORY B WING4.9 yr overdueShree Mahalaxmi Group · Mawal, PuneP52100002374· filed Mar 2019 → now Sept 2021· 73.5% built
- MELANGE RESIDENCES - PHASE III4.9 yr overdueRAMA SYNERGY SPACES · Hinjawadi Phase III, PuneP52100017090· 94.5% built
- Sukhwani Coloronic Phase II4.9 yr overdueS. S. D. Construction · Ravet, PuneP52100019968· 88% built
- Shree Samarth Krupa4.9 yr overdueShri Labsons Builders and Developers Pvt Ltd · Vinayak nagar , Moshi, PuneP52100010272· filed Dec 2018 → now Oct 2021· 76.4% built
- SAIDHAM4.9 yr overdueRajmata Construction · Baramati (M Cl), PuneP52100003158· 90.9% built
- ANUSHRI KLASSIC4.8 yr overdueBalaji Developers · Kalas, PuneP52100015672· 81.8% built
- PARIJATAK, MADHUBAN PHASE 54.8 yr overdueSAHYADRI PROPERTIES · Haveli, PuneP52100010997· filed Sept 2019 → now Oct 2021· 50% built
- EKTARA4.8 yr overdueArtharaj Realtors · Haveli, PuneP52100006129· filed Oct 2019 → now Oct 2021· 90.9% built
- BHAGYASHREE4.8 yr overdueRANJEKAR REALTY · KOTHRUD, PuneP52100015709· 36.4% built
- K52 Building A4.8 yr overdueM/S Shri Sairaj Associates · Pune City, PuneP52100019093· 90.9% built
- ROYAL MYSTIC4.8 yr overdueFive Star Construction Company · RAHATANI,, PuneP52100016160· 81.8% built
- PARSHWA GOLD COUNTY WING A4.8 yr overduePARSHWA PROPERTIES · charohli, PuneP52100000180· 90.9% built
- PGD Pinnacle4.8 yr overduePGD Land LLP · Keshavnagar, PuneP52100002015· 90.9% built
- Zinnia Row Houses4.8 yr overdueMagarpatta Township Development & Construction Co. Ltd. · Haveli, PuneP52100018373· 87.1% built
- MANTRA CITY 360 PHASE034.8 yr overdueMANTRA ISLAND HOMES TALEGAON LLP · TALEGAON, PuneP52100002880· filed Oct 2019 → now Oct 2021· 88.2% built
- Dreams Avani C wing4.8 yr overdueDreams Corporation Pvt Ltd · Manjari, PuneP52100000157· filed Jun 2019 → now Oct 2021· 65.9% built· 8 complaints
- BALAJI VISHWA4.8 yr overdueBALAJI DEVELOPERS · NARHE, PuneP52100013310· 90.9% built
- Perfect 10 Phase III4.8 yr overdueShagun Manav Spaces LLP · Balewadi, PuneP52100001096· 90.9% built
- Hi Face4.8 yr overdueMBM Developers · Pimpale Saudagar, PuneP52100004321· filed Oct 2018 → now Oct 2021· 55.7% built· 7 complaints
- Skyways Esfera 14.8 yr overdueMoze Associates · Lohegaon, PuneP52100018128· 90.9% built
- GATHA HEIGHTS4.8 yr overdueOMGATHA BUILDERS AND DEVELOPERS PVT LTD · CHOVISAWADI, PuneP52100026233· filed Jan 2021 → now Oct 2021· 72.7% built
- SHIVAM GREENCOURT4.8 yr overdueSHIVAM DEVELOPERS PVT. LTD. · Mahalunge, PuneP52100010035· 90.9% built
- Gulmohar Apartment4.8 yr overdueM/S SHREERAM BUILDERS · OPP SHINDE HIGH SCHOOL, PuneP52100017155· 81.8% built
- The Legend4.8 yr overdueShree Sankalp Associates · Hinjawadi, PuneP52100007333· filed Dec 2020 → now Oct 2021· 18.2% built· 1 complaint
- Rajyog annexe4.8 yr overdueJhala and kodre associates · Wadgaon Khurd, PuneP52100000570· filed Oct 2019 → now Oct 2021· 90.9% built
- SAI SHIVAM4.8 yr overdueS.R. DEVELOPERS · Navlakh Umbre, PuneP52100012266· filed Apr 2019 → now Oct 2021· 81.8% built
- Audumber4.8 yr overdueOmChidanand · Haveli, PuneP52100014216· 17.6% built
- Kumar Sanctum - A1 and B14.8 yr overdueKumar Govind J V · Ivory Estate, PuneP52100004814· filed Nov 2019 → now Nov 2021· 82.6% built
- VINAYAK154.8 yr overdueBADHEKAR DEVELOPERS · Rambaug Colony, PuneP52100007478· 81.8% built
- VIVANTA LIFE VERONIKA4.7 yr overdueVIVANTA REALTY · Pimpale Saudagar, PuneP52100002206· 90.9% built
- VIDYA VILAS4.7 yr overdueRajyog Builders through its Proprietor Vinayak Alias Prakash Shankar Manohar · Mulshi, PuneP52100013901· 90.9% built
- Mantra Moments Phase 64.7 yr overdueMANTRA PROPERTIES · Pimpri Chinchawad (M Corp.), PuneP52100014375· 27.3% built· 2 complaints
- AXIS VERTIGA4.7 yr overdueAXIS LIFESPACES LLP · PUNE, PuneP52100003159· filed Nov 2019 → now Nov 2021· 90.9% built
- DB Commercial Phase I4.7 yr overduePune Buildtech Private Limited · Yerawada, PuneP52100004589· filed Dec 2019 → now Nov 2021· 62.3% built· 6 complaints
- SUYOG AMARDHAN4.7 yr overdueSUYOG STAR DEVELOPERS · Parvati, PuneP52100010912· filed Nov 2019 → now Nov 2021· 90.9% built
- SHIVSAGAR PLATINUM4.7 yr overdueSABLE ASSOCIATES · Haveli, PuneP52100003789· filed Mar 2018 → now Nov 2021· 89.5% built
- VINAYAKA BLISS4.7 yr overdueVinayaka Developers · Pimpri Chinchawad (M Corp.), PuneP52100014359· filed Jul 2019 → now Nov 2021· 95.5% built
- Shankeshwar Darshan4.7 yr overdueShankeshwar Developers · Haveli, PuneP52100000830· filed Dec 2019 → now Dec 2021· 81.8% built
- NEST4.7 yr overdueSKYLINE ENTERPRISES · NEAR ORCHID SCHOOL, PuneP52100026122· 72.7% built
- Westernhills V1 - V94.7 yr overdueHigh Seas Properties Private Limited · Sus, PuneP52100002728· filed Dec 2019 → now Dec 2021· 89.1% built
- BA IRIS4.7 yr overdueBhandari Patel Venture · Moze Engineering College, PuneP52100013967· 90.9% built
- BHAKTI MEERA4.7 yr overdueMEGHASWANA BHONGADE ASSOCIATES · Varale, PuneP52100003491· filed Dec 2019 → now Dec 2021· 9.3% built
- TROODOS HEIGHTS4.7 yr overdueSHIVGANGA DEVELOPERS · Shewalewadi, PuneP52100007606· filed Dec 2019 → now Dec 2021· 81.8% built
- PRIVIA 94.7 yr overduePRIVIA BUILDERS LLP · MOSHI, PuneP52100007271· 90.9% built
- Trade Park Phase14.6 yr overdueVTP Mohite Associates · UNDRI, PuneP52100000518· filed Dec 2019 → now Dec 2021· 90.9% built
- Runal Gateway Phase 14.6 yr overdueRajendra Suresh Jain · Kiwale, PuneP52100002021· filed Dec 2019 → now Dec 2021· 90.3% built· 2 complaints
- AUM TRIMURTI C BUILDING4.6 yr overdueM/S BUILT UP · Haveli, PuneP52100001581· filed Dec 2019 → now Dec 2021· 90% built
- Park Land - 1 - i4.6 yr overdueYashvastu Developers · Pune City, PuneP52100002945· filed Dec 2019 → now Dec 2021· 74.4% built
- SHIV ZEN WORLD - PHASE I4.6 yr overdueShubh Housing · MANJARI Bk, PuneP52100007579· 54.5% built
- Vaishnavi Park4.6 yr overdueKundnani Associates · Chakan (CT), PuneP52100005505· filed Dec 2019 → now Dec 2021· 90.9% built
- LOTUS - PHASE 1 B WING4.6 yr overdueRAVIKARAN CONSTRUCTION · Sus, PuneP52100007781· 69.1% built
- The Crown Greens4.6 yr overdueInternational Biotech Park Limited · Maan, Hinjawadi, PuneP52100001864· 99.9% built· 1 complaint
- SWARGANDHAR PHASE 1 A4,A5,A6,A7,B6,B74.6 yr overdueVAIBHAV CLASSIC BUILDERS AND DEVELOPERS · Uruli Kanchan, PuneP52100004071· filed Dec 2019 → now Dec 2021· 78.2% built
- AARAMBH4.6 yr overdueYashada Nivasa Associates · DUDULGAON, MOSHI, PuneP52100019333· 81.8% built
- SHIRKE AND PATIL ASSOCIATES4.6 yr overdueSHIRKE AND PATIL ASSOCIATES · PIMPLE SAUDAGAR, PuneP52100016444· 68.2% built
- Kiarah Terrazo4.6 yr overdueWellwisher Apartment · Haveli, PuneP52100002327· filed Dec 2019 → now Dec 2021· 57.7% built· 4 complaints
- ROHAN MADHUBAN II WINGS A B C4.6 yr overdueRohan Promoters & Developers · Pune City, PuneP52100002297· 90.9% built
- Irene4.6 yr overdueANGAL & CO · Erandwane, PuneP52100015640· 90.9% built
- Ganraya Mall phase1 wing B4.6 yr overduePrakash Realty · Daund (M Cl), PuneP52100005707· filed Dec 2019 → now Dec 2021· 72.7% built
- BRAMHA SKY ONE4.6 yr overdueB & G DEVELOPERS · UNDRI, PuneP52100012500· filed Dec 2019 → now Dec 2021· 90.9% built
- Majestique Venice4.6 yr overdueMajestique Nirman LLP · Dhayari Pune, PuneP52100000130· 95.5% built
- MULIK LUXURIA - E WING4.6 yr overdueTUKARAM SOPANRAO MULIK · WAGHOLI, PuneP52100017442· 41.8% built
- AMAR SERENITY4.6 yr overdueAMAR BUILDERS AND DEVELOPERS · PASHAN, PuneP52100001203· 90.9% built
- SWASTIK SHRUSHTI4.6 yr overdueSWASTIK ASSOCIATES · Pimpri Chinchawad (M Corp.), PuneP52100002248· filed Dec 2019 → now Dec 2021· 14.7% built· 1 complaint
- 212 RIVERWALK4.6 yr overdueRAMESH BUILDERS (INDIA) · Haveli, PuneP52100001010· filed Dec 2019 → now Dec 2021· 85.5% built
- SANTOSH DREAMS4.6 yr overdueMANAS PROMOTERS & DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100006993· filed Dec 2019 → now Dec 2021· 81.6% built
- SPLENDID COUNTY4.6 yr overdueYASHADA BUILDERS · LOHGAON, PuneP52100001057· 90.9% built
- GANGA GLITZ F. BLDG4.6 yr overdueLegends County Landmark Pvt Ltd · Pune City, PuneP52100000259· 88.4% built
- Saarrthi Savvy Homes4.6 yr overdueSiddharth Value Homes Limited Liability partnership · Hinjavadi (CT), PuneP52100001288· filed Dec 2019 → now Dec 2021· 90.9% built· 3 complaints
- SKY POINT-PHASE I-A WING4.6 yr overdueShubh Enterprises · KESHAVNAGAR, PuneP52100009213· 69.1% built
- VISTAS CENTREPOINT4.6 yr overdueCavalcade Properties Private Limited · MOHAMMADWADI, PuneP52100016359· 81.8% built· 1 complaint
- SUYOG ABHILASHA4.6 yr overdueSUYOG ADINATH · Jalochi, PuneP52100012264· filed Dec 2019 → now Dec 2021· 74.1% built
- 24K ATRIA4.6 yr overdueKOLTE-PATIL DEVELOPERS LIMITED · Haveli, PuneP52100000428· 45.5% built
- Westen Tower4.6 yr overdueKalbhor and Lanke Birje Associates · Wakad, PuneP52100016419· 90.9% built
- ARADHYAM B WING4.6 yr overdueDHANESHWAR VISION DEVELOPERS · Pimpri Chinchawad (M Corp.), PuneP52100014371· 90.9% built
- KESHAV VATIKA4.6 yr overdueUDAY INFRA · MAVAL, PuneP52100007032· filed Mar 2019 → now Dec 2021· 78.8% built
- ETASHA4.6 yr overdueKRISALA LIMAN LANDMARKS LIMITED LIABILITY PARTNERSHIP · Pimpri Chinchawad (M Corp.), PuneP52100012581· 90.9% built
- Aarohi H4.6 yr overdueTeirth Developers and Suyojit Infrastructure Ltd · -, PuneP52100007298· 0% built
- Soham Residency A Wing4.6 yr overdueKhushbu Realties Pvt. Ltd. · Haveli, PuneP52100019635· 81.8% built
- Omega Paradise Wing L Phase 24.6 yr overdueGarve Buildcon · WAKAD, PuneP52100004943· filed Dec 2019 → now Dec 2021· 90.9% built
- Grande View 7 Phase III Building K4.6 yr overdueChirag Developers · AMBEGAON bk, PuneP52100013947· 90.9% built
- SAI PARADISE4.6 yr overdueHaresh Premchand Chandwani · Baner, PuneP52100002660· 72.6% built
- Bella Casa4.6 yr overdueVEER REALITY · Haveli, PuneP52100002786· 90.9% built
- AVALON CITY C-34.6 yr overdueClassic Promoters and Builders Private Limited · Haveli, PuneP52100003105· filed Dec 2019 → now Dec 2021· 81.8% built· 1 complaint
- Apostrophe, Moshi4.6 yr overdueApex Builders · Moshi, PuneP52100000905· 81.8% built
- Sara Metroville C phase III4.6 yr overdueSara Infrastructures · Punawale, PuneP52100004198· 89.1% built
- DHRUVA4.6 yr overdueSANJEEVANI LANDSCAPE DHRUVA · PUNAWALE, PuneP52100000555· 42.5% built
- Bramha Exuberance C4.6 yr overdueBramhacorp Limited · KONDHWA, PuneP52100001076· 90.9% built· 1 complaint
- GANGA KINGSTON BUILDING G4.6 yr overdueVEDANT CONSTRUCTION · Mohammadwadi, PuneP52100015357· 23.6% built
- VALENCIA4.6 yr overdueBMC GROUP · Mulshi, PuneP52100008024· filed Dec 2019 → now Dec 2021· 81.8% built
- Nakshatra4.6 yr overdueAshwini Anil Lokhande · Baner, Pune, PuneP52100016234· 90.9% built· 1 complaint
- PARITOSH A,B,C4.6 yr overdueSHARADA ALLIANCE SHELTERS · Balewadi, PuneP52100004530· 76.1% built
- GOLDEN WINDS Building A Phase 44.6 yr overdueGOLDEN BRICKS DEVELOPERS · Lohegaon, PuneP52100003838· filed Dec 2019 → now Dec 2021· 76.8% built
- Bhagyoday Residency - A4.6 yr overduePrashant Developers (Mumbai) · Pimpri Chinchawad (M Corp.), PuneP52100010887· filed Dec 2019 → now Dec 2021· 63.2% built
- Mount Castel4.6 yr overdueSancheti Space · WAGHOLI, PuneP52100003062· 90.9% built
- Shlok - Phase 14.6 yr overdueDhankawade Patil Construction · NARHE, PuneP52100001466· filed Dec 2019 → now Dec 2021· 44.2% built
- EPIC PHASE II4.6 yr overdueSHIVSAGAR PROMOTERS & DEVELOPERS · Wagholi, PuneP52100005410· 73% built
- Vrindavan4.6 yr overdueGiriraj Associates · Pimpri Chinchawad (M Corp.), PuneP52100004464· filed Dec 2019 → now Dec 2021· 45.5% built
- NOTTING HILL PHASE I4.6 yr overdueJaikul Associates · CHARHOLI, PuneP52100001939· 81.8% built· 4 complaints
- Golden Treasures Wing A4.6 yr overdueVINAYAK KISHOR GARVE · Punawale, PuneP52100001868· filed Dec 2019 → now Dec 2021· 90.9% built
- TWIN TOWER4.6 yr overdueShraddha Spaces · Wakad, PuneP52100003875· 90.9% built
- MILLENNIUM PARAMOUNT4.6 yr overdueMillennium Superstructures LLP · CHIKHALI, PuneP52100018086· 81.8% built
- YUTHIKA ENCLAVE4.6 yr overdueAJIT DEVELOPERS AND COMPANY · Haveli, PuneP52100024706· 81.8% built
- EMPIRE ETERNITY4.6 yr overdueEMPIRE CONSTRUCTION · KHONDWA KHURD, PuneP52100015310· 90.9% built· 2 complaints
- SONIGARA PRATIK4.6 yr overdueSHANKHESHWAR CONSTRUCTIONS AND DEVELOPERS · KIWALE, PuneP52100013672· 90.9% built
- PARAS-VISTA4.6 yr overduePARAS DEVELOPERS · WAKAD, PuneP52100010721· 81.4% built
- INDRAA PARK4.6 yr overdueS K BUILDCON · AADARSH NAGAR, PuneP52100004605· 90.9% built
- STKANWARRAMPALACIOPHASE24.6 yr overdueVINOD PREMCHAND CHANDWANI · chikhli, PuneP52100000386· 90% built
- Market Place4.6 yr overdueVTP Mohite Associates · UNDRI, PuneP52100000587· filed Dec 2019 → now Dec 2021· 90.9% built
- PALM NEST-PHASE I4.6 yr overdueNG RATHI PROPERTIES LLP · WAGHOLI, PuneP52100013717· 27.3% built
- Crystal Tower4.6 yr overdueKSHITIJ PROMOTERS AND DEVELOPERS · Pashan, PuneP52100000082· filed Dec 2019 → now Dec 2021· 90.8% built· 1 complaint
- Geras Isle Royale Tower 2 and 34.6 yr overdueGera Developments Private Limited · Bavdhan, PuneP52100009870· 77.7% built
- RICH COUNTY- C & D WING4.6 yr overdueSWASTIK PROMOTERS & BUILDERS · PUNE, PuneP52100006337· filed Jun 2019 → now Dec 2021· 92.1% built
- POWER BOULEVARD4.6 yr overdueSAPRA PROPERTIES & INVESTMENTS · GANESH BAUG, PuneP52100002004· 81.8% built
- DB Commercial Phase II4.6 yr overduePune Buildtech Private Limited · Yerawada, PuneP52100003455· filed Dec 2019 → now Dec 2021· 60.9% built· 2 complaints
- PRIME BUSINESS CENTER4.6 yr overdueTHE PRIME PROPERTIES · MAWAL, PuneP52100015422· 72.7% built
- LALBAG PRESTIGE BUILDING B4.6 yr overdueRELIABLE CONSTRUCTION · Ambegaon, PuneP52100010952· filed Dec 2019 → now Dec 2021· 81.8% built
- SAHIL VIGHNESH RESIDENCY4.6 yr overdueVAISHNAVI PROMOTERS AND DEVELOPERS · Wakad, PuneP52100005542· filed Dec 2019 → now Dec 2021· 90.9% built
- SHREE SADGURU KRUPA4.6 yr overdueMAA PRANAAM VENTURE · Katraj, PuneP52100007899· filed Dec 2019 → now Dec 2021· 60.9% built
- Suvan Cresta - Phase B4.6 yr overdueL M Bafna · BIBVEWADI, PuneP52100000453· filed Dec 2019 → now Dec 2021· 90.9% built
- Suyog Aura Phase II4.6 yr overdueShivram Developers · Haveli, PuneP52100003242· 81.8% built
- PHASE I VISION CITY4.6 yr overdueSHUBBAN PROPERTIES VISION CITY · jambhul, PuneP52100011209· filed Dec 2018 → now Dec 2021· 89.1% built· 9 complaints
- Waves4.6 yr overdueGokhale Constructions · Wakad, PuneP52100003292· 60.6% built
- AMRUT PUSHP4.6 yr overdueMORAYA REALITY GROUP · DUDULGAON, PuneP52100011364· filed Dec 2019 → now Dec 2021· 65.7% built· 2 complaints
- Atmosphere - C Wing4.6 yr overdueJRS Associates · AMBEGAON, PuneP52100000821· filed Dec 2019 → now Dec 2021· 90.9% built· 23 complaints
- Suvan Forett4.6 yr overdueL M Bafna · Haveli, PuneP52100001907· filed Dec 2019 → now Dec 2021· 90.9% built
- Kamalraj Datta Vihar A Bldng4.6 yr overdueKAMALRAJ ESTATE · MOSHI, PuneP52100002971· filed Dec 2019 → now Dec 2021· 90.9% built
- Panache4.6 yr overdueTRIMURTI SAI NATH INFRAS LLP · KATRAJ, PuneP52100016181· 9.1% built
- ARV Newtown4.6 yr overdueVedant Infracon · Pisoli, PuneP52100002738· 90.9% built
- Devayani Residency4.6 yr overdueYashodhan Associates · Bibwewadi, PuneP52100002412· filed Dec 2019 → now Dec 2021· 90.9% built· 13 complaints
- Building D3 Eon Homes4.6 yr overdueHinjawadi Infradevelelopment Private Limited · Hinjwadi Ph-3, PuneP52100001860· 81.8% built